CN207159929U - A kind of rubber dam water filling and draining device - Google Patents

A kind of rubber dam water filling and draining device Download PDF

Info

Publication number
CN207159929U
CN207159929U CN201721108137.4U CN201721108137U CN207159929U CN 207159929 U CN207159929 U CN 207159929U CN 201721108137 U CN201721108137 U CN 201721108137U CN 207159929 U CN207159929 U CN 207159929U
Authority
CN
China
Prior art keywords
valve
dam
filling
water
rubber dam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721108137.4U
Other languages
Chinese (zh)
Inventor
雷雨
夏瑞英
申明
吕小光
蒋拴拴
汪淩雁
李丽峰
温宗然
陈亚男
刘鑫
李少哲
阮博文
马千
白景
陈兆昆
王旭光
赵亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANYANG DESIGN INSTITUTE OF WATER CONSERVANCY CONSTRUCTION AND SURVEY
AGILE WATER CONSERVANCY RECONNAISSANCE DESIGN RESEARCH Co Ltd
Original Assignee
NANYANG DESIGN INSTITUTE OF WATER CONSERVANCY CONSTRUCTION AND SURVEY
AGILE WATER CONSERVANCY RECONNAISSANCE DESIGN RESEARCH Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANYANG DESIGN INSTITUTE OF WATER CONSERVANCY CONSTRUCTION AND SURVEY, AGILE WATER CONSERVANCY RECONNAISSANCE DESIGN RESEARCH Co Ltd filed Critical NANYANG DESIGN INSTITUTE OF WATER CONSERVANCY CONSTRUCTION AND SURVEY
Priority to CN201721108137.4U priority Critical patent/CN207159929U/en
Application granted granted Critical
Publication of CN207159929U publication Critical patent/CN207159929U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Barrages (AREA)

Abstract

The utility model discloses a kind of rubber dam water filling and draining device, it is related to hydraulic engineering operational management field, including sump, water pump and pipeline, described pipeline includes main line and valve group, described main line includes filling valve and check valve since the water pump backward successively, and finally injects dam sack of rubber dam;Blowoff line and blowoff valve are set before described filling valve;Overflow passage and overflow valve are set after described check valve;Discharge water pipeline and discharging valve are set after described overflow passage;Described filling valve, blowoff valve and overflow valve and its associated ping are positioned above the earth's surface above dam bag, and described discharging valve is arranged below in the piping shaft below dam bag.The utility model utilizes simple structure, fills drain operation with regard to that can complete rubber dam, and because itself possesses filter, makes requirement of the whole device to water quality also not high, can use compared with complex environment.

Description

A kind of rubber dam water filling and draining device
Technical field
The utility model belongs to hydraulic engineering operational management field, more particularly, to a kind of rubber dam water filling and draining device.
Background technology
Rubber dam is a kind of new hydraulic structure occurred with the development of high molecular synthetic material, by filling comb Road water is inflated the pocket type checkdam formed.Dam crest can be safe, and can adjust height of dam as needed, controls upper water Position, to play the benefits such as irrigation, flood control.Therefore, rubber dam is very universal in the application of water conservancy.And in order to prevent dam bag from surpassing Pressure, water filling rubber dam must set superpressure bursting tube to be connected with dam bag on two sides abutment wall or middle pier, nozzle position palpus and dam Bag internal design pressure level flushes.In practice, the safe operation to dam sack of rubber dam really of safe superpressure bursting tube is set Serve protective effect.But some problems are also encountered, exactly when running into compared with great flood, because central water is anxious, wave Greatly, manpower can not reach, and flood can produce from the mouth of pipe pour in down a chimney water phenomenon, raise dam bag, it is excessively big vast to influence dam bag, or even can be by dam bag Tear, destroy.Based on above mentioned problem, propose to be changed to draw from side wall by all superpressure bursting tubes of rubber dam, when meeting great flood Ensure manually from the timely closed conduct in both sides, prevent flood from irrigating inside, but the method is still thin due to being added in dam bag opening Weakness.
Existing rubber dam mainly includes civil engineering part, dam bag and anchoring piece, fills the parts such as pumping equipment and control system Composition.Fill pumping equipment and control system is generally mounted in control room, control room is broadly divided into three layers:One layer is mechanical floor, Located underground, main place fills draining water pump, fills drainpipe and control valve and pressure instrumentataion etc.;Two layers are electricity generating layer, are mainly put Put the equipment such as power distribution cabinet;Three layers are management level, to manipulate and nursing the residence of rubber dam personnel.
Chinese patent(Application number 2014202538692)A kind of rubber dam water filling and draining device is disclosed, belongs to a kind of rubber Dam bag water-filling, drainage equipment, including water-supply-pipe are carried, water-supply-pipe one end connects rubber dam, the other end connects water leg, on water-supply-pipe Provided with the first valve, it is characterized in that, three loops in parallel are also included on the water-supply-pipe, series connection is provided with first on the first loop Water pump, the first non-return valve, the second valve, series connection is provided with the second water pump, the second non-return valve, the 3rd valve on second servo loop, and the 3rd Loop is provided with the 4th valve, and tertiary circuit connects with the first loop between the first non-return valve and the second valve, tertiary circuit Connected with second servo loop between the second non-return valve and the 3rd valve, the end in the tertiary circuit and the first loop is provided with the 5th Valve;The beneficial effect of the utility model is:Cheap, compact-sized, simple structure, water pump alternatively use, maintenance letter It is single, reduce pump house cost.
But the system of the rubber dam water filling and draining device in small-sized dam in use, still slightly aobvious too fat to move;And due to rubber Dam bag water-filling in dam needs to there are certain requirements water quality, it is necessary to establish special water purification installation.
Utility model content
In view of this, the purpose of this utility model is in view of the shortcomings of the prior art, there is provided a kind of rubber dam fills draining dress Put, using simple structure, fill drain operation with regard to rubber dam can be completed, and because itself possesses filter, make whole device Requirement to water quality is not also high, can use compared with complex environment.
To reach above-mentioned purpose, the utility model uses following technical scheme:
A kind of rubber dam water filling and draining device, including sump, water pump and pipeline, described pipeline include main line and valve Group, described main line includes filling valve and check valve since the water pump backward successively, and finally injects dam sack of rubber dam;It is described Filling valve before blowoff line and blowoff valve are set;Overflow passage and overflow valve are set after described check valve;Described Discharge water pipeline and discharging valve are set after overflow passage;Described filling valve, blowoff valve and overflow valve and its associated ping are set Earth's surface on higher than dam bag, described discharging valve are arranged below in the piping shaft below dam bag.
As further improvement of the utility model, described water pump includes submersible sewage pump.
As further improvement of the utility model, described filling valve, blowoff valve, overflow valve and discharging valve are lock Valve.
As further improvement of the utility model, described discharging valve, which is set, lengthens handle control.
As further improvement of the utility model, described sump sets filter layer.
The beneficial effects of the utility model are:
The utility model uses simple structure, you can that completes dam sack of rubber dam fills drainage works, has low cost, dimension Repair conveniently, operate the characteristics of succinct, there is prominent advantage in the use of the complex small-sized rubber dam of condition.
Due to needing to use electric pump when its water-filling only operates, mechanical valve can be used in remaining operation, therefore need not Computer room is built in addition, and the operation of described water-filling can switch the unlatching of control water pump, the operation of remaining water-filling by simple electric brake It can be realized in near-end using manually-operated gate, its dam that collapses of discharging water is operated with the piping shaft being arranged below below dam bag Discharging valve presses realization certainly using the gravity of water.
In order to further improve the water-filling efficiency of dam sack of rubber dam, set filter layer to improve filter efficiency in sump, subtract Less due to limitation of the filter efficiency to water filling and draining device operating rate.
Brief description of the drawings
Fig. 1 is the pipeline arranging structure schematic diagram of embodiment one of the present utility model.
Fig. 2 is the cross-sectional view of the sump of embodiment two of the present utility model.
In figure:1- sumps, 2- water pumps, 3- main lines, 4- filling valves, 5- check valves, 6- blowoff lines, 7- blowoff valves, 8- overflow valves, 9- overflow passages, 10- dams bag, 11- discharging valves, 12- lengthen handle, and 13- discharges water pipeline, 14- filter layers.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples.
Embodiment one
As shown in figure 1, a kind of rubber dam water filling and draining device, including sump 1, water pump 2 and pipeline, described pipeline include Main line 3 and valve group, described main line 3 includes filling valve 4 and check valve 5 since the water pump 2 backward successively, and finally injects Dam sack of rubber dam 10;Blowoff line 6 and blowoff valve 7 are set before described filling valve 4;Set and overflow after described check valve 5 Flow tube road 9 and overflow valve 8;Discharge water pipeline 13 and discharging valve 11 are set after described overflow passage 9;Described filling valve 4, row Dirty valve 7 and overflow valve 8 and its associated ping are positioned above the earth's surface above dam bag 10, and the wherein outlet of overflow passage 9 is higher than it Remaining pipeline, described discharging valve 11 are arranged below in the piping shaft below dam bag 10.
Described water pump 2 includes submersible sewage pump, and submersible sewage pump is the sewage pump 2 of submersible type, can by sewage medium-length fibre, bag, band, The tear of the materials such as grass, cloth, cut-out, then smooth discharge, particularly suitable for liquid of the conveying containing rigid solid, fibre object with And especially dirty, viscous, sliding liquid.
Described filling valve 4, blowoff valve 7, overflow valve 8 and discharging valve 11 is gate valve.Gate valve, which is that one kind is most common, to be opened Valve closing, utilize flashboard(That is opening and closing element, opening and closing element is referred to as flashboard or gate in flashboard, and lock seat is referred to as flashboard seat)To connect(Entirely Open)Or block(It is fully closed)Medium in pipeline.It does not allow to use as damming, and should be avoided the micro unlatching of flashboard in use, because The erosion of swiftly flowing medium can accelerate the damage of sealing surface.Flashboard is in the unilateral conduct perpendicular to gate seat channel centerline Elevating movement, the medium blocked as gate in pipeline, therefore referred to as gate valve.
Described discharging valve 11 sets lengthening handle 12 to control.
Rise dam operating process:Filling valve 4 is closed, opens blowoff valve 7, starts water pump 2, the bottom sludge of sump 1 and sewage It is extracted, is discharged by blowoff valve 7 and blowoff line 6, band mud and sewage pumps, and the water that blowoff line 6 flows out is after clear water; Discharging valve 11 remains turned-off, and opens filling valve 4 and overflow valve 8, and closes blowoff valve 7, and current flow into dam bag by main line 3 10, the water-filling of band dam bag 10 is completed, and superfluous water flows out from overflow valve 8 and overflow passage 9, closes filling valve 4 and overflow valve 8, dam bag 10 water-fillings are completed.
Dam operating process is dropped:Discharging valve 11 is operated using the lengthening handle 12 that is arranged in piping shaft, the water in dam bag 10 Body is discharged by the pipeline 13 that discharges water, flat, the completion drop dam operation until dam bag 10 collapses, closing discharging valve 11.
Embodiment two
The present embodiment is similar to the general structure of embodiment one, and its difference is:As shown in Fig. 2 described sump 1 is set Filter layer 14, filter layer 14 can filter to current in advance, further improve the water into the current in dam bag 10 Matter.
Finally illustrate, above example only to illustrate the technical solution of the utility model and unrestricted, this area Other modifications or equivalent substitution that those of ordinary skill is made to the technical solution of the utility model, without departing from this practicality The spirit and scope of new technique scheme, it all should cover among right of the present utility model.

Claims (5)

1. a kind of rubber dam water filling and draining device, including sump, water pump and pipeline, it is characterised in that:Described pipeline includes master Pipeline and valve group, described main line includes filling valve and check valve since the water pump backward successively, and finally injects rubber dam Dam bag;Blowoff line and blowoff valve are set before described filling valve;Overflow passage and overflow are set after described check valve Valve;Discharge water pipeline and discharging valve are set after described overflow passage;Described filling valve, blowoff valve and overflow valve and its attached Pipeline is positioned above the earth's surface above dam bag, and described discharging valve is arranged below in the piping shaft below dam bag.
A kind of 2. rubber dam water filling and draining device according to claim 1, it is characterised in that:Described water pump includes latent dirt Pump.
A kind of 3. rubber dam water filling and draining device according to claim 1, it is characterised in that:Described filling valve, blowoff valve, Overflow valve and discharging valve are gate valve.
A kind of 4. rubber dam water filling and draining device according to claim 1, it is characterised in that:Described discharging valve, which is set, to be lengthened Handle controls.
A kind of 5. rubber dam water filling and draining device according to claim 1, it is characterised in that:Described sump sets filtering Layer.
CN201721108137.4U 2017-08-31 2017-08-31 A kind of rubber dam water filling and draining device Active CN207159929U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721108137.4U CN207159929U (en) 2017-08-31 2017-08-31 A kind of rubber dam water filling and draining device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721108137.4U CN207159929U (en) 2017-08-31 2017-08-31 A kind of rubber dam water filling and draining device

Publications (1)

Publication Number Publication Date
CN207159929U true CN207159929U (en) 2018-03-30

Family

ID=61719941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721108137.4U Active CN207159929U (en) 2017-08-31 2017-08-31 A kind of rubber dam water filling and draining device

Country Status (1)

Country Link
CN (1) CN207159929U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984077A (en) * 2019-11-25 2020-04-10 中水淮河规划设计研究有限公司 Novel dam bag full display device for rubber dam
CN111005352A (en) * 2019-11-25 2020-04-14 中水淮河规划设计研究有限公司 Intelligent automatic water filling and draining system for rubber dam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984077A (en) * 2019-11-25 2020-04-10 中水淮河规划设计研究有限公司 Novel dam bag full display device for rubber dam
CN111005352A (en) * 2019-11-25 2020-04-14 中水淮河规划设计研究有限公司 Intelligent automatic water filling and draining system for rubber dam

Similar Documents

Publication Publication Date Title
CN100590323C (en) Controllable siphon discharging device and operation method for reservoir drainage or flood discharge
CN105625483B (en) A kind of underground engineering hydraulic pressure control method
CN207159929U (en) A kind of rubber dam water filling and draining device
CN112854416B (en) Backflow-preventing intercepting well and operation method thereof
CN104499463A (en) Multi-stage telescopic type steel dam
CN206206294U (en) A kind of the siphon priming device
CN104963322A (en) Hydraulic junction facility
CN202688943U (en) Self-suction drainage system for barrier lake
CN205557464U (en) Type of can decontaminating intelligence flood control dam
CN104775402A (en) Hydraulic lifting weir
CN107130620A (en) Channel steel cofferdam method for arranging with the flow-compensated function of section
CN204326026U (en) A kind of multi-stage telescopic steel dam
CN216108848U (en) A energy-conserving integration sewage pump station for crossing a river
CN206607654U (en) The vacuum collecting and processing unit of a kind of house refuse
CN204059578U (en) Water tank turnover panel rinses door
CN216999572U (en) Self-draining, pumping and dirt-flushing cleaning device for rubber dam
CN208395840U (en) Basement sump pit preventive drainage device
CN208395947U (en) A kind of draining of unit maintenance and seepage from powerhouse drainage system
CN2266269Y (en) Agricultural water absorption pipe
CN207419414U (en) Cushion pool draining, water filling system
CN206299575U (en) A kind of water supply system
CN212452499U (en) Water filling and draining device for rubber dam
CN111321714A (en) A overhaul drainage system for V style of calligraphy tailwater tunnel crowd
CN115679884B (en) Automatic sand discharging device for pond and reservoir
CN111287149B (en) Realize hollow dam of channel irrigation and ecological moisturizing in river course

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Lei Yu

Inventor after: Liu Xin

Inventor after: Li Shaozhe

Inventor after: Ruan Bowen

Inventor after: Ma Qian

Inventor after: Bai Jing

Inventor after: Chen Zhaokun

Inventor after: Wang Xuguang

Inventor after: Zhao Liang

Inventor after: Xia Ruiying

Inventor after: Shen Ming

Inventor after: Lv Xiaoguang

Inventor after: Jiang Shuanshuan

Inventor after: Wang Lingyan

Inventor after: Li Lifeng

Inventor after: Wen Zongran

Inventor after: Chen Yanan

Inventor before: Lei Yu

Inventor before: Liu Xin

Inventor before: Li Shaozhe

Inventor before: Ruan Bowen

Inventor before: Ma Qian

Inventor before: Bai Jing

Inventor before: Chen Zhaokun

Inventor before: Wang Xuguang

Inventor before: Zhao Liang

Inventor before: Xia Ruiying

Inventor before: Shen Ming

Inventor before: Lv Xiaoguang

Inventor before: Jiang Shuanshuan

Inventor before: Wang Lingyan

Inventor before: Li Lifeng

Inventor before: Wen Zongran

Inventor before: Chen Yanan