CN207144000U - FS final spice outfititem - Google Patents

FS final spice outfititem Download PDF

Info

Publication number
CN207144000U
CN207144000U CN201721116856.0U CN201721116856U CN207144000U CN 207144000 U CN207144000 U CN 207144000U CN 201721116856 U CN201721116856 U CN 201721116856U CN 207144000 U CN207144000 U CN 207144000U
Authority
CN
China
Prior art keywords
final spice
final
spice
outfititem
monitoring system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721116856.0U
Other languages
Chinese (zh)
Inventor
林鸣
李勇
李一勇
刘德进
宿发强
岳远征
王强
王伟
朱岭
管泽旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201721116856.0U priority Critical patent/CN207144000U/en
Application granted granted Critical
Publication of CN207144000U publication Critical patent/CN207144000U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The utility model discloses a kind of FS final spice outfititem, including FS final spice, in addition to Lift-on/Lift-off System, and on FS final spice, equipment handling FS final spice sinking is installed for connecting;CAS, on two end faces of FS final spice, prevent the collision of FS final spice and immersed tube when FS final spice handling matches immersed tube from causing the displacement of FS final spice and/or immersed tube or structure to destroy;Position adjustment, on FS final spice and corresponding immersed tube, for position adjustment of the FS final spice in the plane of seabed;Temporary leaking water system, located at the both ends of FS final spice, completed for FS final spice position adjustment, FS final spice isolates seawater inside and outside tube coupling after being docked with immersed tube, prevents outside seawater from entering inside tube coupling;Umbilical cables system, including several pipelines, power supply, communication and the offer power that umbilical cables system is used to install between equipment and FS final spice;Monitoring system, on FS final spice and lifting appliance, for monitoring each system on FS final spice.

Description

FS final spice outfititem
Technical field
Immersed tube tunnel field is the utility model is related to, more particularly to a kind of FS final spice outfititem.
Background technology
Immersed tunnelling method constructing tunnel, exactly partly latent refute or dry-docking in prefabricated tunnel caisson difference transportation by driving to making a reservation for The docking of position sinking, is longer than the metric space of the pipeline section to make the sinking of final section pipeline section smoothly to leave, the remainder away from Pipeline section from the sinking docking of space institute is considered as the equal Immersed tunnel in both ends of FS final spice, i.e. tunnel connection, and in marine docking Close up, the last pipeline section that closes up is FS final spice.The immersed tube tunnel final joint is the key of immersed tube tunnel construction, particularly Off-lying sea overlength immersed tube tunnel construction, job site operating condition is difficult, is faced with the marine environment bars such as wave and the ocean current of complexity Part and meteorological condition.
How to ensure that FS final spice smoothly docks the immersed tube of both sides in seabed, realize that the insertion of seabed tunnel turns into and need solution badly Certainly the problem of.
Utility model content
The purpose of this utility model is that solve FS final spice smoothly docks the immersed tube of both sides in seabed, realizes seabed tunnel Insertion, there is provided a kind of FS final spice outfititem.
In order to realize above-mentioned purpose of utility model, the utility model provides following technical scheme:
A kind of FS final spice outfititem, including FS final spice, in addition to:
Lift-on/Lift-off System, on the FS final spice, for connecting FS final spice sinking described in installation equipment handling;
CAS, on two end faces of the FS final spice, when preventing the FS final spice handling matching immersed tube The collision of the FS final spice and the immersed tube causes the displacement of the FS final spice and/or the immersed tube or structure to destroy;
Position adjustment, on the FS final spice and the corresponding immersed tube, for the FS final spice in sea Position adjustment on baseplane;
Temporary leaking water system, located at the both ends of the FS final spice, completed for the FS final spice position adjustment, it is described FS final spice isolates seawater inside and outside tube coupling after being docked with the immersed tube, prevents outside seawater from entering inside tube coupling;
Umbilical cables system, including several pipelines, the umbilical cables system are used for the installation equipment and the most terminating Power supply, communication and offer power between head;
Monitoring system, it is each on the FS final spice for monitoring on the FS final spice and the lifting appliance Individual system.
Wherein, several pipelines include cable, signal cable and power cable, and the cable is used to power, and the signal cable is used In communications, the power cable is used to provide such as pressure oil power source.
Using a kind of FS final spice outfititem described in the utility model, by setting the Lift-on/Lift-off System, the anticollision System, the position adjustment, the temporary leaking water system, the umbilical cables system and the monitoring system integrated use one The immersed tube of both sides is smoothly docked in seabed with the guarantee FS final spice, realizes the insertion of seabed tunnel.
Preferably, the temporary leaking water system includes closed circular pushing tow girder, pushing tow part, the sealing of closed circular first Band and the waterstop of closed circular second, the pushing tow girder is in the mounting groove of the FS final spice end, the pushing tow part One end is connected to the mounting groove bottom land, and the other end is connected to the pushing tow girder, and first waterstop is located at the pushing tow Small beam end, described second waterstop one end are connected to the FS final spice end on the outside of the mounting groove, other end connection In the pushing tow girder, the end face of end face first waterstop of the CAS is high, and the CAS is used to protect Protect first waterstop not to be destroyed, the pushing tow part makes the pushing tow girder relatively described final in the mounting groove Joint moves, and first waterstop is used for the top by thrusting action in immersed tube end face sealing, second waterstop Push away the sealing between girder and the FS final spice.
Preferably, first waterstop is Gina waterstops, and the Gina waterstops are rubber product, and its effect is logical Cross the pushing tow girder pushing tow and compress the Gina waterstops and be brought into close contact and reach the effect of sealing in the immersed tube end face.
Preferably, second waterstop is with the flexible water stop that the pushing tow girder is mobile and stretches or collapses.
Preferably, the flexible water stop is M waterstops, i.e., section is the waterstop of M shapes, and it is to prevent seawater that it, which is acted on, Entered by the gap between the FS final spice and the pushing tow girder inside the FS final spice.
Preferably, the temporary leaking water system also includes the waterstop of closed circular the 3rd, and the 3rd waterstop is located at institute State on pushing tow girder, mounting groove cell wall described in the 3rd waterstop end thereof contacts, the 3rd waterstop is used for the pushing tow Secondary sealing between girder and the FS final spice.
Preferably, the 3rd waterstop is the waterstop of unidirectional water inflow.
Preferably, the 3rd waterstop is Lip waterstops, i.e., section is the waterstop of L shape, and it is as described second Secondary waterproof after waterstop, prevent seawater by between the FS final spice and the pushing tow girder gap enter described in most Inside terminating head.
Preferably, the CAS includes several anticollison blocks located at described two end faces of FS final spice, Mei Gesuo The end for stating anticollison block is provided with rubber blanket.
Preferably, the high 40-80mm in end face of the end face of the CAS first waterstop.
Preferably, the high 50mm in end face of the end face of the CAS first waterstop.
Preferably, the position adjustment includes being used for the longitudinally adjusted part of the FS final spice and laterally adjusts portion Part.
Preferably, the part that laterally adjusts is included located at the raised component of the FS final spice top ends and located at described The channel components of immersed tube top ends, the raised component are adapted to the channel components, and FS final spice described in handling makes the projection Component is put into the channel components, the FS final spice transverse direction coarse regulation.
Preferably, the width of the channel components is more than the width of the raised component, and two are arranged with the immersed tube Individual piston element, raised component described in each piston element pushing tow adjust the raised component in the channel components middle position Put, the FS final spice transverse direction accurate adjustment is whole.
Preferably, the longitudinally adjusted part includes several jack located at the FS final spice end, Suo Yousuo Jack is stated after the FS final spice laterally adjusts in place, free end stretch out contact corresponding to the immersed tube end, it is described most All jack pushing tows of the first side of terminating, the adaptable recovery of all jack of opposite side, make described final The distance of immersed tube described in joint to both sides is equal, so as to the sealing operation of the follow-up temporary leaking water system.
Preferably, the free end of each jack is spherical hinge structure, is easy to free end to be brought into close contact corresponding described heavy Tube end, uniform force.
Preferably, the monitoring system includes the measurement tower at the top of the FS final spice, and the measurement tower is provided with The manhole well of the FS final spice is connected, the umbilical cables system enters in the FS final spice pipe through the manhole well, institute The top for stating measurement tower is provided with I-shaped job platform, and the I-shaped job platform is provided with satellite positioning device.
Wherein, the top of the measurement tower is still located at more than the water surface after the FS final spice implantation.
Preferably, the monitoring system includes measurement early warning system, and the measurement early warning system is included in the most terminating The sonar altimeter set at the two corners of each end bottom of head, after FS final spice bottom surface sinking described in handling to certain depth, The sound wave of altimeter described in the immersed tube end face reflection, the altimeter are obtained between the FS final spice and the immersed tube end face Distance, handled by the data obtained to the altimeter, obtain the relative position of the FS final spice and the immersed tube Relation, prevent the collision with the immersed tube end face during the FS final spice sinking.
Preferably, the distance that the altimeter is obtained between the FS final spice and the immersed tube end face exceedes predetermined threshold value, The measurement early warning system alarm.
Preferably, the monitoring system includes the first waterstop opening and closing amount monitoring system, the first waterstop decrement Monitoring system, interim prestressing apparatus stress monitoring system, end seal door stress deformation monitoring system, the end seal door connection member Stress monitoring system, three-way locking device stress monitoring system, suspension centre stress monitoring system, bottom grouting pressure monitoring system, Pushing tow girder installation site gap monitoring system, the pushing tow girder temporary support stress monitoring system, FS final spice peace One or more in dress process attitude monitoring system and the FS final spice relative settlement monitoring system.
Preferably, the umbilical cables system also includes switch board and distribution box in the FS final spice, the control Cabinet processed connects the distribution box, and the switch board connects the installation equipment with the distribution box by the pipeline, described to match somebody with somebody Electronic box is used for the power supply of the position adjustment, the temporary leaking water system and the monitoring system, and the switch board is used for To control and the data transfer of the position adjustment, the temporary leaking water system and the monitoring system.
Preferably, the umbilical cables system connection CCTV (Closed Circuit Television, closed-circuit television), institute CCTV is stated to be used for the real-time monitoring inside the FS final spice and the immersed tube.
Preferably, the Lift-on/Lift-off System includes several equally distributed suspension centres, and each suspension centre includes hanger, bearing pin With rocker device, the rocker device connects the bearing pin, and the bearing pin connects the hanger, and lifting rope is socketed on the bearing pin.
The utility model additionally provides a kind of method for dismounting of FS final spice outfititem, is installed to for the FS final spice The dismounting of outfititem thereon, comprises the following steps behind position:
A, two ships of tower both sides anchoring are measured, form warning value defending zone, protects the measurement tower not collided, prevents described Measure tower and the FS final spice junction is destroyed and the caused final joints structure destroys;
B, all pipelines being connected between installation equipment and the FS final spice are removed and are reclaimed;
C, the measurement tower and manhole well are removed, handling appliance connects the measurement tower and manhole well in advance, and tightens institute The lifting rope of handling appliance is stated, prevents the measurement tower from toppling over collision and the manhole well after releasing connection with the FS final spice Topple over collision after releasing connection with the FS final spice;
D, the raised component positioned at the FS final spice top ends and the channel components located at the immersed tube top ends are removed, Complete Demolition Construction.
Using a kind of method for dismounting of FS final spice outfititem described in the utility model so that the outfititem of dismounting does not touch The FS final spice, including the final joints structure and the safety for dismounting personnel are hit, makes the FS final spice suitable in seabed The immersed tube of profit docking both sides, realizes the insertion of seabed tunnel.
In summary, by adopting the above-described technical solution, the beneficial effects of the utility model are:
1st, with a kind of FS final spice outfititem described in the utility model, by setting the Lift-on/Lift-off System, described anti- Hit system, the position adjustment, the temporary leaking water system, the umbilical cables system and the monitoring system integrated use Together ensure that the FS final spice smoothly docks the immersed tube of both sides in seabed, realize the insertion of seabed tunnel;
2nd, with a kind of method for dismounting of FS final spice outfititem described in the utility model so that the outfititem of dismounting is not The FS final spice, including the final joints structure and the safety for dismounting personnel are collided, makes the FS final spice in seabed The smoothly immersed tube of docking both sides, realizes the insertion of seabed tunnel.
Brief description of the drawings
Fig. 1 is the structural representation of FS final spice outfititem described in the utility model;
Fig. 2 is the structural representation that part is laterally adjusted in embodiment;
Fig. 3 is Fig. 1 longitudinal sectional view;
Fig. 4 is Fig. 3 partial enlarged drawing;
Fig. 5 is the schematic flow sheet of the method for dismounting of FS final spice outfititem described in the utility model.
Marked in figure:1- FS final spices, 11- pushing tow girders, 12- pushing tow parts, the waterstops of 13- first, 14- second stop Water band, the waterstops of 15- the 3rd, 16- mounting grooves, 2- immersed tube, 3- CAS, 41- projection components, 42- channel components, 43- live Plunger member, 44- jack, 5- measurement towers, 6- suspension centres.
Embodiment
The utility model is described in further detail with reference to test example and embodiment.But should not be by this The scope for being interpreted as the above-mentioned theme of the utility model is only limitted to following embodiment, all to be realized based on the utility model content Technology belongs to the scope of the utility model.
Embodiment 1
As shown in figure 1, a kind of FS final spice outfititem described in the utility model, including FS final spice 1, in addition to:
Lift-on/Lift-off System, on the FS final spice 1, for connecting the sinking of FS final spice 1 described in installation equipment handling;
CAS 3, on two end faces of the FS final spice 1, prevent the handling of the FS final spice 1 matching immersed tube The collision of the FS final spice 1 and the immersed tube 2 causes displacement or the knot of the FS final spice 1 and/or the immersed tube 2 when 2 Structure destroys;
Position adjustment, on the FS final spice 1 and the corresponding immersed tube 2, exist for the FS final spice 1 Position adjustment in the plane of seabed;
Temporary leaking water system, located at the both ends of the FS final spice 1, completed for the position adjustment of FS final spice 1, institute State after FS final spice 1 docks with the immersed tube 2 and isolate seawater inside and outside tube coupling, prevent outside seawater from entering inside tube coupling;
Umbilical cables system, including several pipelines, the umbilical cables system are used for the installation equipment and the most terminating Power supply, communication and offer power between first 1;
Monitoring system, on the FS final spice 1 and the lifting appliance, for monitoring on the FS final spice 1 Each system.
Wherein, several pipelines include cable, signal cable and power cable, and the cable is used to power, and the signal cable is used In communications, the power cable is used to provide such as pressure oil power source.
As a preferred scheme of the present embodiment, the temporary leaking water system includes closed circular pushing tow girder 11, top Push part 12, the first waterstop of closed circular 13 and the second waterstop of closed circular 14, the pushing tow girder 11 located at it is described most In the first 1 end mounting groove 16 of terminating, described one end of pushing tow part 12 is connected to the bottom land of mounting groove 16, and the other end is connected to institute Pushing tow girder 11 is stated, first waterstop 13 is located at the end of pushing tow girder 11, the one end of the second waterstop 14 connection In the end of the FS final spice 1 in the outside of mounting groove 16, the other end is connected to the pushing tow girder 11, the CAS The end face of 3 end face first waterstop 13 is high, the CAS 3 be used to protecting first waterstop 13 not by Destroy, the pushing tow part 12 makes the pushing tow girder 11 be moved in the mounting groove 16 relative to the FS final spice 1, described First waterstop 13 is used for the pushing tow girder 11 by thrusting action in the end face sealing of immersed tube 2, second waterstop 14 Sealing between the FS final spice 1.First waterstop 13 is Gina waterstops.Second waterstop 14 is with institute State the flexible water stop that pushing tow girder 11 moves and stretches or collapse.The flexible water stop is M waterstops.It is described interim Water-stopping system also includes the waterstop 15 of closed circular the 3rd, and the 3rd waterstop 15 is described on the pushing tow girder 11 The cell wall of mounting groove 16 described in the end thereof contacts of 3rd waterstop 15, the 3rd waterstop 15 are used for the pushing tow girder 11 and institute State the secondary sealing between FS final spice 1.3rd waterstop 15 is the waterstop of unidirectional water inflow.3rd waterstop 15 be Lip waterstops.
As a preferred scheme of the present embodiment, the CAS 3 is included located at described 1 two ends of FS final spice Several anticollison blocks in face, the end of each anticollison block are provided with rubber blanket.The end face more described of the CAS 3 The high 50mm in end face of one waterstop 13.The position adjustment include for the FS final spice 1 longitudinally adjusted part and Laterally adjust part.The part that laterally adjusts is included located at the raised component 41 of the top ends of FS final spice 1 and located at institute The channel components 42 of the top ends of immersed tube 2 are stated, the raised component 41 is adapted to the channel components 42, FS final spice 1 described in handling The raised component 41 is set to be put into the channel components 42, the 1 horizontal coarse regulation of FS final spice.The channel components 42 Width is more than the width of the raised component 41, and two piston elements 43 are arranged with the immersed tube 2, each piston portion Raised component 41 described in the pushing tow of part 43 adjusts the raised component 41 position in the channel components 42, the FS final spice 1 Horizontal accurate adjustment is whole.
As a preferred scheme of the present embodiment, the longitudinally adjusted part includes being located at the end of FS final spice 1 Several jack 44, all jack 44 after the FS final spice 1 laterally adjusts in place, free end stretch out contact The corresponding end of the immersed tube 2, all pushing tows of jack 44 of the side of FS final spice 1, opposite side it is all described The adaptable recovery of jack 44, makes the distance of FS final spice 1 to the immersed tube described in both sides 2 equal, faces so as to subsequently described When water-stopping system sealing operation.The free end of each jack 44 is spherical hinge structure, is easy to free end to be brought into close contact pair Answer the end of immersed tube 2, uniform force.
As a preferred scheme of the present embodiment, the monitoring system includes the survey located at the top of FS final spice 1 Tower 5 is measured, the manhole well of the FS final spice 1 is communicated with the measurement tower 5, the umbilical cables system passes through the manhole well In managing into the FS final spice 1, the top of the measurement tower 5 is provided with I-shaped job platform, the I-shaped job platform Be provided with satellite positioning device, wherein, it is described measurement tower 5 top after the implantation of FS final spice 1 still positioned at the water surface with On.The monitoring system includes measurement early warning system, and the measurement early warning system is included in each end face bottom of the FS final spice 1 The sonar altimeter set at the two corners in portion, after the bottom surface sinking of FS final spice 1 described in handling to certain depth, the end of immersed tube 2 The sound wave of the altimeter is reflected in face, and the altimeter obtains the distance between the FS final spice 1 and the end face of the immersed tube 2, leads to Cross the data for obtaining the altimeter to handle, obtain the relative position relation of the FS final spice 1 and the immersed tube 2, Prevent the collision with the end face of immersed tube 2 during the sinking of FS final spice 1.The altimeter obtains the FS final spice 1 Distance between the end face of immersed tube 2 exceedes predetermined threshold value, the measurement early warning system alarm.The monitoring system includes first The opening and closing amount monitoring system of waterstop 13, the decrement monitoring system of first waterstop 13, interim prestressing apparatus stress monitoring System, end seal door stress deformation monitoring system, the end seal door connection member stress monitoring system, three-way locking device stress prison Examining system, suspension centre stress monitoring system, bottom grouting pressure monitoring system, the installation site gap monitoring system of pushing tow girder 11, The temporary support stress monitoring system of pushing tow girder 11, the installation process attitude monitoring system of the FS final spice 1 and it is described most One or more in the first 1 relative settlement monitoring system of terminating.
As a preferred scheme of the present embodiment, the umbilical cables system also includes in the FS final spice 1 Switch board and distribution box, the switch board connect the distribution box, and the switch board and the distribution box are connected by the pipeline The installation equipment is connect, the distribution box is used for the position adjustment, the temporary leaking water system and the monitoring system Power supply, the switch board is used for control to the position adjustment, the temporary leaking water system and the monitoring system And data transfer.The umbilical cables system connects CCTV, and the CCTV is used in the FS final spice 1 and the immersed tube 2 The real-time monitoring in portion.The Lift-on/Lift-off System includes several equally distributed suspension centres 6, and each suspension centre 6 includes hanger, bearing pin With rocker device, the rocker device connects the bearing pin, and the bearing pin connects the hanger, and lifting rope is socketed on the bearing pin.
With a kind of FS final spice outfititem described in the utility model, by setting the Lift-on/Lift-off System, the anticollision System 3, the position adjustment, the temporary leaking water system, the umbilical cables system and the monitoring system integrated use Together ensure that the FS final spice 1 smoothly docks the immersed tube of both sides in seabed, realize the insertion of seabed tunnel.
Embodiment 2
As shown in figure 1, a kind of method for dismounting of FS final spice outfititem described in the utility model, for the most terminating First 1 be installed in place after outfititem thereon dismounting, comprise the following steps:
A, two ships of the both sides of tower 5 anchoring are measured, form warning value defending zone, protects the measurement tower 5 not collided, prevents institute State measurement tower 5 and the junction of the FS final spice 1 is destroyed and the caused structure of the FS final spice 1 is destroyed;
B, all pipelines being connected between installation equipment and the FS final spice 1 are removed and are reclaimed;
C, the measurement tower 5 and manhole well are removed, handling appliance connects the measurement tower 5 and manhole well in advance, and tightens The lifting rope of the handling appliance, prevent the measurement tower 5 from toppling over collision and the people after releasing connection with the FS final spice 1 FS final spice 1 described in Kong Jingyu topples over collision after releasing connection;
D, the raised component 41 positioned at the top ends of FS final spice 1 and the groove located at the top ends of immersed tube 2 are removed Component 42, complete Demolition Construction.
With a kind of method for dismounting of FS final spice outfititem described in the utility model so that the outfititem of dismounting does not touch The FS final spice 1, including the structure of the FS final spice 1 and the safety for dismounting personnel are hit, makes the FS final spice 1 in seabed The smoothly immersed tube of docking both sides, realizes the insertion of seabed tunnel.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model All any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (15)

1. a kind of FS final spice outfititem, including FS final spice (1), it is characterised in that also include:
Lift-on/Lift-off System, on the FS final spice (1), for connecting FS final spice (1) sinking described in installation equipment handling;
CAS (3), on two end faces of the FS final spice (1), prevent that the FS final spice (1) handling matching is heavy The FS final spice (1) and the collision of the immersed tube (2) cause the FS final spice (1) and/or the immersed tube (2) when managing (2) Displacement or structure destroy;
Position adjustment, on the FS final spice (1) and the corresponding immersed tube (2), for the FS final spice (1) Position adjustment in the plane of seabed;
Temporary leaking water system, located at the both ends of the FS final spice (1), completed for the FS final spice (1) position adjustment, institute State after FS final spice (1) docks with the immersed tube (2) and isolate seawater inside and outside tube coupling;
Umbilical cables system, including several pipelines, the umbilical cables system are used for the installation equipment and the FS final spice (1) Between power supply, communication and provide power;
Monitoring system, it is each on the FS final spice (1) for monitoring on the FS final spice (1) and lifting appliance System.
2. FS final spice outfititem according to claim 1, it is characterised in that the temporary leaking water system includes closed-loop Shape pushing tow girder (11), pushing tow part (12), the waterstop of closed circular first (13) and the waterstop of closed circular second (14), institute Pushing tow girder (11) is stated in the FS final spice (1) end mounting groove (16), described pushing tow part (12) one end is connected to Mounting groove (16) bottom land, the other end are connected to the pushing tow girder (11), and first waterstop (13) is located at the top Girder (11) end is pushed away, described second waterstop (14) one end is connected to the FS final spice on the outside of the mounting groove (16) (1) end, the other end are connected to the pushing tow girder (11), end face first waterstop of the CAS (3) (13) end face is high.
3. FS final spice outfititem according to claim 2, it is characterised in that second waterstop (14) is with described The flexible water stop that pushing tow girder (11) is mobile and stretches or collapses.
4. FS final spice outfititem according to claim 3, it is characterised in that the temporary leaking water system also includes closing The waterstop (15) of ring-type the 3rd, the 3rd waterstop (15) is on the pushing tow girder (11), the 3rd waterstop (15) mounting groove described in end thereof contacts (16) cell wall.
5. FS final spice outfititem according to claim 1, it is characterised in that the CAS (3) includes being located at institute Several anticollison blocks of (1) two end face of FS final spice are stated, the end of each anticollison block is provided with rubber blanket.
6. FS final spice outfititem according to claim 2, it is characterised in that the end face of the CAS (3) is compared with institute State the high 40-80mm in end face of the first waterstop (13).
7. FS final spice outfititem according to claim 1, it is characterised in that the position adjustment includes being used for institute State the longitudinally adjusted part of FS final spice (1) and laterally adjust part.
8. FS final spice outfititem according to claim 7, it is characterised in that the part that laterally adjusts includes being located at institute The raised component (41) of FS final spice (1) top ends and the channel components (42) located at the immersed tube (2) top ends are stated, it is described convex Play component (41) and be adapted to the channel components (42).
9. FS final spice outfititem according to claim 7, it is characterised in that the longitudinally adjusted part includes being located at institute State several jack (44) of FS final spice (1) end.
10. FS final spice outfititem according to claim 1, it is characterised in that the monitoring system is included located at described Measurement tower (5) at the top of FS final spice (1), it is described to measure the manhole well that the FS final spice (1) is communicated with tower (5), institute State umbilical cables system through the manhole well to enter in the FS final spice (1) pipe, the top of the measurement tower (5) is provided with I-shaped Type job platform, the I-shaped job platform are provided with satellite positioning device.
11. FS final spice outfititem according to claim 1, it is characterised in that the monitoring system includes measurement early warning System, the measurement early warning system are included in the sonar height set at the two corners of each end bottom of the FS final spice (1) Meter.
12. FS final spice outfititem according to claim 1, it is characterised in that the monitoring system includes the first sealing Band (13) opening and closing amount monitoring system, first waterstop (13) decrement monitoring system, end seal door stress deformation monitoring system, The end seal door connection member stress monitoring system, three-way locking device stress monitoring system, suspension centre stress monitoring system, bottom Grouting pressure monitoring system, pushing tow girder (11) installation site gap monitoring system, the pushing tow girder (11) temporary support should Power monitoring system, the FS final spice (1) installation process attitude monitoring system and the FS final spice (1) relative settlement monitoring system One or more in system.
13. FS final spice outfititem according to claim 1, it is characterised in that the umbilical cables system also includes being located at Switch board and distribution box in the FS final spice (1), the switch board connect the distribution box, the switch board and described match somebody with somebody Electronic box connects the installation equipment by the pipeline, and the distribution box is used for the position adjustment, the temporary leaking water The power supply of system and the monitoring system, the switch board be used for the position adjustment, the temporary leaking water system and The control of the monitoring system and data transfer.
14. FS final spice outfititem according to claim 13, it is characterised in that the umbilical cables system connects CCTV, The CCTV is used for the real-time monitoring internal to the FS final spice (1) and the immersed tube (2).
15. FS final spice outfititem according to claim 1, it is characterised in that it is equal that the Lift-on/Lift-off System includes several The suspension centre (6) of even distribution, each suspension centre (6) include hanger, bearing pin and rocker device, and the rocker device connects the pin Axle, the bearing pin connect the hanger, and lifting rope is socketed on the bearing pin.
CN201721116856.0U 2017-09-01 2017-09-01 FS final spice outfititem Active CN207144000U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721116856.0U CN207144000U (en) 2017-09-01 2017-09-01 FS final spice outfititem

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721116856.0U CN207144000U (en) 2017-09-01 2017-09-01 FS final spice outfititem

Publications (1)

Publication Number Publication Date
CN207144000U true CN207144000U (en) 2018-03-27

Family

ID=61676986

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721116856.0U Active CN207144000U (en) 2017-09-01 2017-09-01 FS final spice outfititem

Country Status (1)

Country Link
CN (1) CN207144000U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107524170A (en) * 2017-09-01 2017-12-29 中交第航务工程局有限公司 FS final spice outfititem and method for dismounting
CN108385728A (en) * 2018-05-10 2018-08-10 中交第航务工程局有限公司 Immersed tube tunnel push mode FS final spice and its docking construction method
CN113232797A (en) * 2021-06-23 2021-08-10 江苏骅通船舶工程设备有限公司 Connection structure of boats and ships fitting-out spare in advance

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107524170A (en) * 2017-09-01 2017-12-29 中交第航务工程局有限公司 FS final spice outfititem and method for dismounting
CN108385728A (en) * 2018-05-10 2018-08-10 中交第航务工程局有限公司 Immersed tube tunnel push mode FS final spice and its docking construction method
CN113232797A (en) * 2021-06-23 2021-08-10 江苏骅通船舶工程设备有限公司 Connection structure of boats and ships fitting-out spare in advance

Similar Documents

Publication Publication Date Title
CN207144000U (en) FS final spice outfititem
CN106988346B (en) Immersed tube tunnel final joint, prefabricating method and mounting method
US10253904B1 (en) Integrated immersed tube coupling and installation method thereof as well as installation closure method of immersed tube coupling
EP3140512B1 (en) Method for producing a construction element, in particular a tunnel element, having a watertight seal
CN107524170A (en) FS final spice outfititem and method for dismounting
CN107700544A (en) Off-lying sea immersed tube installation method
CN109386293B (en) Sealing type receiving construction method for rectangular jacking pipe with super-large section
CN207538837U (en) Integrated immersed tube tube coupling
CN114508127B (en) Novel suspension tunnel pipe body joint form
Liu et al. Engineering measures for preventing upheaval buckling of buried submarine pipelines
Ko et al. Full‐scale shaking table tests on soil liquefaction‐induced uplift of buried pipelines for buildings
JPH09203060A (en) Last joint execution method of immersed tunnel
Prevost et al. Basics of flexible pipe structural design
Agostoni et al. TSG-integrated storage platform for early production in the North Sea
CN111101947B (en) Hard tube system angle deviation compensation device for deep sea mining at different water depth levels
Poon Vitrified clay pipe joint behaviour under differential ground movement
CN114086533A (en) Buoyancy-free double-wall self-elevating platform pile leg
JP3470636B2 (en) Junction between shaft and shaft at the end of submerged tunnel and construction method
CN104483064A (en) In-situ calibration method for soft steel arm type mooring system stress monitoring device
CN212452555U (en) Buoyancy-free double-wall self-elevating platform pile leg
Wilson et al. Pull-out parameters for buried suction anchors
CN116815790B (en) Construction method of foundation pit supporting servo system with two sides adjacent to protection object
Solano et al. Design and installation of buried heated pipelines at the capixaba north terminal offshore brazil
Douglas et al. Design of seismic joint for San Francisco bay tunnel
Nelson Floating breakwater prototype test program

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant