JPH09203060A - Last joint execution method of immersed tunnel - Google Patents

Last joint execution method of immersed tunnel

Info

Publication number
JPH09203060A
JPH09203060A JP8100398A JP10039896A JPH09203060A JP H09203060 A JPH09203060 A JP H09203060A JP 8100398 A JP8100398 A JP 8100398A JP 10039896 A JP10039896 A JP 10039896A JP H09203060 A JPH09203060 A JP H09203060A
Authority
JP
Japan
Prior art keywords
box
submerged
final joint
box body
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8100398A
Other languages
Japanese (ja)
Inventor
Takaharu Yoshikura
敬治 吉倉
Yoshio Ishibashi
由雄 石橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toa Corp
Original Assignee
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toa Corp filed Critical Toa Corp
Priority to JP8100398A priority Critical patent/JPH09203060A/en
Publication of JPH09203060A publication Critical patent/JPH09203060A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide the last-joint execution method capable of providing the last joint of an immersed tunnel in an optional position and easily following installation permissible deviation of the last joint part. SOLUTION: The last joint section 3 with double construction consisting of an inside box body 4 and an outside box body 5 sliding each other between the existing two immersed tubes 1 and 2 are installed through a temporary setting beam 7 temporarily fixing it. Then, after hydraulic pressure joint is made by drawing either the outside box body or the inside box body from one immersed tube 1, either the outside box body or the inside box body is separated from the beam 7, and after it is temporarily fixed to one immersed tube, neither the inside box body or the outside box body temporarily fixed to the other immersed tube is drawn up to make hydraulic pressure joint, and after both of them are fixed, a joint section between the outside box body and inside box body is filled with mortar, water inside the last joint section is discharged to fix after the cure, and then, all bulk heads are removed to release temporarily fixing to construct box bodies.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、海底などを掘って
予め陸上で製作しておいた沈埋函を現場に曳航し次々に
沈設し、連結して沈埋トンネルとする際の最終函体に内
側函体と外側函体とからなる二重函構造の最終継手部を
用いる沈埋トンネルの最終継手施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a submerged box which has been previously manufactured on land by digging the seabed and towed to the site and successively sunk. The present invention relates to a final joint construction method for a submerged tunnel using a final joint part having a double box structure including a box body and an outer box body.

【0002】[0002]

【従来の技術】従来、上記のごとく多数の沈埋函を連結
して沈設し、沈埋トンネルとする際の最終継手工法に
は、止水パネル工法、ターミナルブロック工法、Vブロ
ック工法、水中コンクリート式工法などがあり、それぞ
れ一長一短があった。一方、最終継手は大きな構造物で
あり、しかも予め陸上ヤードなどで製作しておくもので
あるが、設計時と施工時では多少の寸法の誤差はまぬか
れず、最終沈設時に発生する誤差を本来測定してから製
作すれば良いのであるが、実際の製作工程では実際の寸
法を計測する前に製作しておかなければ製作日数の関係
から工程上に問題が生じる。
2. Description of the Related Art Conventionally, as described above, when a large number of submerged boxes are connected and submerged to form a submerged tunnel, the final joint method includes a water stop panel method, a terminal block method, a V block method, and an underwater concrete method. There were pros and cons, respectively. On the other hand, the final joint is a large structure and is manufactured in advance on the land yard, etc.However, some dimensional error is not eliminated during designing and construction, and the error that occurs during final sunk is originally It suffices to manufacture after measuring, but in the actual manufacturing process, if it is not manufactured before measuring the actual dimensions, there will be a problem in the process due to the number of manufacturing days.

【0003】従って、既設の沈埋函の最終継手部分の設
置寸法に合わせた形状に製作し、発生する設置誤差に容
易に追従可能で、しかも沈埋トンネルの任意の位置に設
けることのできる最終継手の施工方法の実現が要望され
ることになる。
Therefore, a final joint which is manufactured to have a shape corresponding to the installation dimension of the final joint portion of the existing submerged box, can easily follow the generated installation error, and can be provided at any position of the submerged tunnel. Realization of the construction method will be required.

【0004】[0004]

【発明が解決しようとする課題】本発明は、複数の沈埋
函を次々と沈設し、連結して沈埋トンネルとする際の最
終継手を任意の位置に設けることができ、しかも最終継
手部分の設置寸法の誤差に容易に追従可能な沈埋トンネ
ルの最終継手施工方法を提供することをその解決課題と
している。
SUMMARY OF THE INVENTION According to the present invention, a final joint can be provided at an arbitrary position when a plurality of submerged boxes are successively sunk and connected to form a submerged tunnel, and the final joint is installed. The problem to be solved is to provide a final joint construction method for a submerged tunnel that can easily follow a dimensional error.

【0005】[0005]

【課題を解決するための手段】本発明は、既設の2つの
沈埋函の間に相互にスライドする内側函体と外側函体と
からなる二重函構造の最終継手部を、それを仮固定した
仮置用梁を介して設置し、一方の沈埋函から引寄せジャ
ッキで最終継手部全体を引寄せて水圧接合を行なった
後、内側函体または外側函体のいずれかを仮置用梁から
切り離し、かつ一方の沈埋函に固定した後、他方の沈埋
函に引寄せジャッキで固定されていない内側函体または
外側函体を引寄せて水圧接合を行い、かつ両者を仮固定
の上、上記外側函体と内側函体との連結部にモルタルを
注入し、養生の後、最終継手部内を固定の上排水し、全
てのバルクヘッドを撤去して仮固定を解除し、函体を構
築する沈埋トンネルの最終継手施工方法、ならびに既設
の2つの沈埋函の間に相互にスライドする内側函体と外
側函体とからなる二重函構造の最終継手部を、それを仮
固定した仮置用梁を介して設置し、一方の沈埋函から引
寄せジャッキで最終継手部全体を引寄せて水圧接合を行
なった後、内側函体または外側函体のいずれかを仮置用
梁から切り離し、かつ一方の沈埋函に固定した後、他方
の沈埋函に引寄せジャッキで固定されていない内側函体
または外側函体を引寄せて水圧接合を行い、かつ両者を
仮固定の上、上記外側函体と内側函体との連結部に剪断
モルタルを注入し、養生の後、最終継手部内を固定の上
排水し、全てのバルクヘッドを撤去して仮固定を解除
し、函体を構築する沈埋トンネルの最終継手施工方法か
らなる。また外側函体と内側函体との連結部に剪断モル
タルや圧縮モルタルを注入することをもその特徴とす
る。
SUMMARY OF THE INVENTION According to the present invention, a final joint portion of a double box structure consisting of an inner box body and an outer box body that slide between two existing submerged boxes is temporarily fixed. Installed through one of the submersible boxes, and after pulling the entire final joint with the pulling jack from one of the submerged boxes to perform hydraulic joining, either the inner box or the outer box is temporarily placed. After fixing it to one of the submerged boxes, pull it to the other submerged box by pulling the inner box or the outer box that is not fixed with a jack and perform hydraulic joining, and temporarily fix both. Mortar is injected into the connection between the outer and inner boxes, and after curing, the inside of the final joint is fixed and drained, all bulkheads are removed and temporary fixing is released to build the box. Final joint construction method for submerged tunnel and between two existing submerged boxes The final joint part of the double box structure consisting of the inner box and the outer box that slide with each other is installed via the temporary mounting beam that temporarily fixes them, and the final joint is pulled from one of the submerged boxes with a jack. After pulling the entire part and performing hydraulic joining, either the inner box or the outer box is separated from the temporary beam and fixed to one submerged box, and then pulled to the other submerged box with a jack. Hydraulically join by pulling the inner or outer box that is not fixed, and temporarily fixing both, then injecting shear mortar into the joint between the outer box and the inner box, and after curing. The final joint construction method of the submerged tunnel is to fix the inside of the final joint part, drain it, remove all bulkheads to release the temporary fixation, and construct a box body. It is also characterized in that shear mortar or compressed mortar is injected into the connecting portion between the outer box and the inner box.

【0006】[0006]

【発明の実施の形態】以下図面を参照して本発明の沈埋
トンネル最終継手施工方法を適用した一実施形態におけ
る施工工程について説明すると、まず、複数の沈埋函を
次々と沈設し、連結して沈埋トンネルとする際に、例え
ば図1にて(B)で示す一方の沈埋函1と、(A)で示
す他方の沈埋函2とを沈設し、これらの間に最終継手部
3を設置して連続した沈埋トンネルとするために、内側
函体4と相互にスライド可能な外側函体5とからなる二
重函構造の最終継手部3を製作しておき、その最終継手
部3を、図1の6のごとく仮固定した仮置用梁7と一体
として起重機船などで既設の沈埋函1と2の間に吊り降
し、仮置用梁7を介して各沈埋函1,2の上部に設けら
れた仮置用架台8上に仮置する。仮置用梁7と仮置用架
台8との摩擦抵抗はなるべく少なくなるようにする。
BEST MODE FOR CARRYING OUT THE INVENTION A construction process in an embodiment to which the method for constructing a submerged tunnel final joint of the present invention is applied will be described below with reference to the drawings. First, a plurality of submerged boxes are successively sunk and connected. When forming a submerged tunnel, for example, one submerged box 1 shown in (B) in FIG. 1 and the other submerged box 2 shown in (A) are submerged, and the final joint portion 3 is installed between them. In order to form a continuous buried tunnel, a final joint part 3 having a double box structure composed of an inner box 4 and an outer box 5 slidable with respect to each other has been manufactured. As shown in 6 of 1 above, it is suspended as a unit with the temporary placement beam 7 by means of a hoist ship between the existing submersion boxes 1 and 2, and the upper portion of each submersion box 1 or 2 is placed through the temporary placement beam 7. It is temporarily placed on the temporary placement stand 8 provided at. The frictional resistance between the temporary placement beam 7 and the temporary placement stand 8 is made as small as possible.

【0007】なお、図1の内側函体4の周端部には正規
ゴムガスケット9が、そして外側函体5の周端部には仮
ゴムガスケット10が設けられており、また沈埋函1,
2及び内側函体4及び外側函体5にはそれぞれバルクヘ
ッド11A,11B,11C,11Dが設けられてい
る。 次に、一方の沈埋函1から図2に示すごとく引寄
せジャッキ12で最終継手部3の全体を引寄せ、沈埋函
1のバルクヘッド11Dと最終継手部3の内側函体4の
バルクヘッド11Cとの間の水を排水装置15Bにより
排水して矢印P1 方向に水圧接合を行なった後、最終継
手部3の内側函体4と仮置用梁7との仮固定6を切り離
し、図3に示すごとく一方の沈埋函1に対し13で示す
仮固定を行なう。
A regular rubber gasket 9 is provided at the peripheral end of the inner casing 4 and a temporary rubber gasket 10 is provided at the peripheral end of the outer casing 5 in FIG.
The bulkheads 11A, 11B, 11C, and 11D are provided on the inner and outer boxes 2 and 5, respectively. Next, as shown in FIG. 2, the whole of the final joint portion 3 is pulled from one of the submerged boxes 1 by the pulling jack 12, and the bulkhead 11D of the submerged box 1 and the bulkhead 11C of the inner box 4 of the final joint section 3 are drawn. After the water between and is drained by the drainage device 15B and hydraulically joined in the direction of the arrow P 1 , the inner casing 4 of the final joint portion 3 and the temporary fixing 6 of the temporary placement beam 7 are separated, As shown in (1), one submerged box 1 is temporarily fixed as shown by 13.

【0008】しかる後、他方の沈埋函2に引寄せジャッ
キ12で最終継手部3の外側函体5を図3のごとく引寄
せて沈埋函2のバルクヘッド11Aと最終継手部3の外
側函体5のバルクヘッド11Bとの間の水を排水装置1
5Aにより排水して矢印P2方向に水圧接合を行ない、
沈埋函2と外側函体5とを図4にて14で示す溶接など
により固定し、仮置用梁7をクレーン等により撤去す
る。
Thereafter, the outer casing 5 of the final joint portion 3 is attracted to the other submerged casing 2 by the pulling jack 12 as shown in FIG. 3, and the bulkhead 11A of the submerged casing 2 and the outer casing of the final joint portion 3 are drawn. The water between the bulkhead 11B of 5 and the drainage device 1
Drain by 5A and perform hydraulic joining in the direction of arrow P 2 ,
The submerged box 2 and the outer box 5 are fixed by welding or the like shown by 14 in FIG. 4, and the temporary placement beam 7 is removed by a crane or the like.

【0009】次に、二重函構造の外側函体5と内側函体
4との連結部17に図4のごとく剪断モルタルMを注入
し、養生を行い、養生後にバルクヘッド11Bと11C
の間を排水装置15Cにより排水する。本実施形態で
は、連結部17内にモルタルMを注入し、モルタルMの
剪断力によって、内側函体4と外側函体3を連結する剪
断モルタルとしているが、連結部17内に注入されたモ
ルタルの圧縮力により内側函体4と外側函体3を連結す
る圧縮モルタルとすることもできる。
Next, as shown in FIG. 4, a shearing mortar M is injected into the connecting portion 17 between the outer box body 5 and the inner box body 4 of the double box structure for curing, and after curing, the bulkheads 11B and 11C.
The space is drained by the drainage device 15C. In this embodiment, the mortar M is injected into the connecting portion 17, and the shear force of the mortar M connects the inner box 4 and the outer box 3 to form a shearing mortar. It is also possible to use a compressed mortar that connects the inner box 4 and the outer box 3 by the compressive force of.

【0010】つづいて、図5のごとく外側函体5と内側
函体4とを14で示す溶接等で固定した後に、各バルク
ヘッド11A,11B,11C,11Dを撤去し、図6
に示すごとく、最終継手部3内の矢印20で示す凹部に
鉄筋組立及びコンクリート打設を行なって函体を構築
し、さらに、沈埋函1と最終継手部3との仮固定13を
撤去し、通常の継手と同様に二次止水ゴム21を取付
け、カプラー23で連結ケーブル22を取り付けて最終
継手の施工が完成する。
Subsequently, as shown in FIG. 5, the outer box body 5 and the inner box body 4 are fixed by welding or the like shown by 14, and then the bulkheads 11A, 11B, 11C and 11D are removed,
As shown in FIG. 5, a rebar assembly and concrete placement are carried out in the recess shown by the arrow 20 in the final joint part 3 to construct a box body, and further, the temporary fixing 13 between the submerged box 1 and the final joint part 3 is removed, The secondary water-stop rubber 21 is attached in the same manner as a normal joint, and the connecting cable 22 is attached by the coupler 23 to complete the construction of the final joint.

【0011】図7は、上記図1から図6までの沈埋トン
ネル最終継手施工の工程のフローチャートであり、二重
函構造の最終継手部3を便宜上二重函として説明してい
る。なお、上記の実施形態では内側函体4を右側に、外
側函体5を左側に設けているが、両者を左右反対に設け
ても上記と同様な施工ができる。また、上記の実施形態
では内側函体4を先に引き寄せて水圧接合を行っている
が、外側函体5側を先に引き寄せて水圧接合を行い、外
側函体5と沈埋函2とを溶接などで固定した後に、内側
函体4を引き寄せて水圧接合を行うという反対の手順で
も上記と同様に施工できる。
FIG. 7 is a flowchart of the steps for constructing the final joint of the submerged tunnel shown in FIGS. 1 to 6, and the final joint portion 3 of the double box structure is described as a double box for convenience. In the above embodiment, the inner box 4 is provided on the right side and the outer box 5 is provided on the left side. Further, in the above-described embodiment, the inner box 4 is drawn first to perform hydraulic joining, but the outer box 5 side is drawn first to perform hydraulic joining, and the outer box 5 and the submerged box 2 are welded. After fixing by, for example, the inner box body 4 is pulled to perform hydraulic joining, the reverse procedure can be performed in the same manner as above.

【0012】[0012]

【発明の効果】以上に説明した本発明の沈埋トンネルの
最終継手施工方法によれば、最終継手部だけを製作すれ
ばよいので、沈埋函の最終継手部の設置寸法に合わせた
形状に製作することができ、しかも沈埋函の設置誤差に
も容易に追従でき、施工を容易にし、施工コストの低減
をはかることができる。
According to the method for constructing the final joint of the submerged tunnel of the present invention described above, only the final joint portion needs to be manufactured. Therefore, the final joint portion of the submerged box is manufactured in a shape according to the installation dimension. Moreover, it is possible to easily follow the installation error of the submerged box, facilitate the construction, and reduce the construction cost.

【0013】また、沈埋トンネルの最終継手を任意の位
置に設けることができ、現場条件に柔軟に対応すること
ができる。
Further, the final joint of the submerged tunnel can be provided at an arbitrary position, so that it is possible to flexibly cope with site conditions.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の施工方法による工程の一実施形態にお
ける最終継手部を既設沈埋函の間に設置する状態を示す
概略の要部側断面図である。
FIG. 1 is a schematic side sectional view of an essential part showing a state in which a final joint part is installed between existing submerged boxes in one embodiment of a process according to a construction method of the present invention.

【図2】図1の工程に続く片面水圧接合の状態を示す概
略側断面図である。
FIG. 2 is a schematic side sectional view showing a state of single-sided hydraulic joining following the step of FIG.

【図3】図2の工程に続く反対面水圧接合の状態を示す
概略側断面図である。
FIG. 3 is a schematic side cross-sectional view showing a state of hydraulic joining on the opposite surface subsequent to the step of FIG.

【図4】図3の工程に続く剪断モルタル注入時の状態を
示す概略側断面図である。
FIG. 4 is a schematic side sectional view showing a state at the time of injecting shear mortar following the step of FIG.

【図5】図4の工程に続くバルクヘッド撤去状態を示す
概略側断面図である。
5 is a schematic side sectional view showing a state in which the bulkhead is removed following the step of FIG.

【図6】図5の工程に続く最終継手部の完成を示す概略
側断面図である。
6 is a schematic side sectional view showing the completion of the final joint portion following the step of FIG.

【図7】上記図1から図6までの工程のフローチャート
である。
FIG. 7 is a flowchart of the steps of FIGS. 1 to 6 described above.

【符号の説明】[Explanation of symbols]

1 沈埋函 2 沈埋函 3 最終継手部 4 内側函体 5 外側函体 6 仮固定 7 仮置用梁 11A バルクヘッド 11B バルクヘッド 11C バルクヘッ
ド 11D バルクヘッド 12 引寄せジャ
ッキ M 剪断モルタル
1 Submerged Box 2 Submerged Box 3 Final Joint Part 4 Inner Box 5 Outer Box 6 Temporary Fixation 7 Temporary Beam 11A Bulkhead 11B Bulkhead 11C Bulkhead 11D Bulkhead 12 Pulling Jack M Shear Mortar

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 既設の2つの沈埋函の間に相互にスライ
ドする内側函体と外側函体とからなる二重函構造の最終
継手部を、それを仮固定した仮置用梁を介して設置し、
一方の沈埋函から引寄せジャッキで最終継手部全体を引
寄せて水圧接合を行なった後、内側函体または外側函体
のいずれかを仮置用梁から切り離し、かつ一方の沈埋函
に仮固定した後、他方の沈埋函に引寄せジャッキで仮固
定されていない内側函体または外側函体を引寄せて水圧
接合を行い、かつ両者を固定の上、上記外側函体と内側
函体との連結部にモルタルを注入し、養生の後、最終継
手部内を排水の上固定し、全てのバルクヘッドを撤去し
て仮固定を解除し、函体を構築する沈埋トンネルの最終
継手施工方法。
1. A final joint part of a double box structure consisting of an inner box and an outer box that slide between two existing submerged boxes, and a temporary joint beam to which the final joint is temporarily fixed. Set up,
After pulling the entire final joint part from one submerged box with a pulling jack to perform hydraulic joining, either the inner box or the outer box is separated from the temporary placement beam and temporarily fixed to one submerged box. After that, the inner box or the outer box not temporarily fixed by the pulling jack to the other submerged box is drawn to perform hydraulic joining, and after fixing both, the outer box and the inner box are separated. A final joint construction method for a submerged tunnel in which mortar is injected into the connecting portion and after curing, the inside of the final joint portion is drained and fixed, all bulkheads are removed and temporary fixing is released, and a box is constructed.
【請求項2】 既設の2つの沈埋函の間に相互にスライ
ドする内側函体と外側函体とからなる二重函構造の最終
継手部を、それを仮固定した仮置用梁を介して設置し、
一方の沈埋函から引寄せジャッキで最終継手部全体を引
寄せて水圧接合を行なった後、内側函体または外側函体
のいずれかを仮置用梁から切り離し、かつ一方の沈埋函
に固定した後、他方の沈埋函に引寄せジャッキで固定さ
れていない内側函体または外側函体を引寄せて水圧接合
を行い、かつ両者を仮固定の上、上記外側函体と内側函
体との連結部にモルタルを注入し、養生の後、最終継手
部内を固定の上排水し、全てのバルクヘッドを撤去して
仮固定を解除し、函体を構築する沈埋トンネルの最終継
手施工方法。
2. A final joint part of a double box structure consisting of an inner box and an outer box that slide between two existing submerged boxes, and a temporary joint beam to which the final joint is temporarily fixed. Set up,
After pulling the entire final joint part from one submerged box with a pulling jack to perform hydraulic joining, either the inner box or the outer box was separated from the temporary beam and fixed to one submerged box. After that, the inner box or the outer box which is not fixed by the pulling jack is drawn to the other submerged box to perform hydraulic joining, and after temporarily fixing both, the outer box and the inner box are connected. The final joint construction method for the submerged tunnel in which mortar is injected into the section, after curing, the inside of the final joint section is fixed and then drained, all bulkheads are removed and temporary fixing is released, and a box is constructed.
【請求項3】 外側函体と内側函体との連結部に剪断モ
ルタルを注入する請求項1または2記載の沈埋トンネル
の最終継手施工方法。
3. The method for constructing a final joint for a submerged tunnel according to claim 1, wherein shear mortar is injected into a connecting portion between the outer casing and the inner casing.
【請求項4】 外側函体と内側函体との連結部に圧縮モ
ルタルを注入する請求項1または2記載の沈埋トンネル
の最終継手施工方法。
4. The method for constructing a final joint for a submerged tunnel according to claim 1, wherein compressed mortar is injected into a connecting portion between the outer casing and the inner casing.
JP8100398A 1995-11-24 1996-04-22 Last joint execution method of immersed tunnel Pending JPH09203060A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8100398A JPH09203060A (en) 1995-11-24 1996-04-22 Last joint execution method of immersed tunnel

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP7-305862 1995-11-24
JP30586295 1995-11-24
JP8100398A JPH09203060A (en) 1995-11-24 1996-04-22 Last joint execution method of immersed tunnel

Publications (1)

Publication Number Publication Date
JPH09203060A true JPH09203060A (en) 1997-08-05

Family

ID=26441429

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8100398A Pending JPH09203060A (en) 1995-11-24 1996-04-22 Last joint execution method of immersed tunnel

Country Status (1)

Country Link
JP (1) JPH09203060A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002364009A (en) * 2001-06-12 2002-12-18 Taisei Corp Jointing box body and connecting method for the box
CN103696441A (en) * 2013-11-29 2014-04-02 中交第四航务工程局有限公司 Automatic hydraulic steel template set and method for casting tube joint of immersed tube
CN103696434A (en) * 2014-01-09 2014-04-02 中国能源建设集团安徽省电力设计院 Flange type foundation for outgoing line framework of 500kV transformer substation
CN103774672A (en) * 2012-10-27 2014-05-07 山东港湾建设集团有限公司 Method for shipping caissons through ramp
CN107938709A (en) * 2017-12-26 2018-04-20 中交航局第二工程有限公司 Immersed tube tunnel final connector and its docking construction method
CN108385728A (en) * 2018-05-10 2018-08-10 中交第航务工程局有限公司 Immersed tube tunnel push mode FS final spice and its docking construction method
CN115162409A (en) * 2022-07-19 2022-10-11 深圳大学 Immersed tube tunnel final joint butt joint measuring method
WO2022213672A1 (en) * 2021-11-15 2022-10-13 中交第一航务工程局有限公司 Suspended-sliding-type water stop device and application thereof
CN115305957A (en) * 2022-08-04 2022-11-08 广州市市政工程设计研究总院有限公司 Final joint of immersed tunnel and construction method thereof
CN115538470A (en) * 2022-12-05 2022-12-30 中交第一航务工程局有限公司 Bidirectional pushing and pulling method for in-situ cast-in-place final joint of immersed tunnel

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002364009A (en) * 2001-06-12 2002-12-18 Taisei Corp Jointing box body and connecting method for the box
CN103774672A (en) * 2012-10-27 2014-05-07 山东港湾建设集团有限公司 Method for shipping caissons through ramp
CN103696441A (en) * 2013-11-29 2014-04-02 中交第四航务工程局有限公司 Automatic hydraulic steel template set and method for casting tube joint of immersed tube
CN103696441B (en) * 2013-11-29 2015-12-30 中交第四航务工程局有限公司 The method that automatic hydraulic steel form group and immersed tube tube coupling are built
CN103696434A (en) * 2014-01-09 2014-04-02 中国能源建设集团安徽省电力设计院 Flange type foundation for outgoing line framework of 500kV transformer substation
CN103696434B (en) * 2014-01-09 2016-06-15 中国能源建设集团安徽省电力设计院有限公司 A kind of formula basis, the edge of a wing for 500kV transformer station outlet structure
CN107938709A (en) * 2017-12-26 2018-04-20 中交航局第二工程有限公司 Immersed tube tunnel final connector and its docking construction method
CN108385728A (en) * 2018-05-10 2018-08-10 中交第航务工程局有限公司 Immersed tube tunnel push mode FS final spice and its docking construction method
WO2022213672A1 (en) * 2021-11-15 2022-10-13 中交第一航务工程局有限公司 Suspended-sliding-type water stop device and application thereof
US11655608B1 (en) 2021-11-15 2023-05-23 Cccc First Harbor Engineering Co., Ltd. Water stopping device of suspension and sliding type and an application thereof
CN115162409A (en) * 2022-07-19 2022-10-11 深圳大学 Immersed tube tunnel final joint butt joint measuring method
CN115305957A (en) * 2022-08-04 2022-11-08 广州市市政工程设计研究总院有限公司 Final joint of immersed tunnel and construction method thereof
CN115305957B (en) * 2022-08-04 2024-01-26 广州市市政工程设计研究总院有限公司 Final joint for immersed tube tunnel and its construction method
CN115538470A (en) * 2022-12-05 2022-12-30 中交第一航务工程局有限公司 Bidirectional pushing and pulling method for in-situ cast-in-place final joint of immersed tunnel
CN115538470B (en) * 2022-12-05 2023-03-10 中交第一航务工程局有限公司 Bidirectional pushing and pulling method for in-situ cast-in-place final joint of immersed tunnel

Similar Documents

Publication Publication Date Title
CN106988346B (en) Immersed tube tunnel final joint, prefabricating method and mounting method
JP6684838B2 (en) Prestressed submerged box structure and its construction method
CN107676104A (en) Integrated immersed tube tube coupling and its installation method, the installation closure method of immersed tube tube coupling
US4405260A (en) Method of constructing underpass across railway and highway without affecting normal traffic thereof
JPH09203060A (en) Last joint execution method of immersed tunnel
US3901038A (en) Method for joining submerged structures
CN108894250A (en) A kind of docking system of submarine pipeline
CN207538837U (en) Integrated immersed tube tube coupling
CN114508127A (en) Novel suspended tunnel pipe body joint form
JP3135833B2 (en) How to build underwater structures
JP2634381B2 (en) Split type box culvert and method of assembling the same
JP3715025B2 (en) Final joint construction method for submerged boxes
JP3470636B2 (en) Junction between shaft and shaft at the end of submerged tunnel and construction method
CN208870086U (en) A kind of docking system of submarine pipeline
JP3799106B2 (en) Final joint construction method for submerged boxes
JP3446640B2 (en) Flexible submerged tunnel and its construction method
JP2000240078A (en) Submerged caisson connecting method
JP2626441B2 (en) Connection box for submerged box connection
GB2101177A (en) Method of constructing underpass across railway and highway without affecting normal traffic thereof
JP2004285578A (en) The last tube of immersed tube and the last joining method
JP3404566B2 (en) How to build an underwater tunnel
JPH07305319A (en) Installating method for caison for breakwater
JPH0544396A (en) Flexible connection method of final connection part of submerged box
JPH0373717B2 (en)
JP2000257091A (en) Flexible structure type submersed caisson and its manufacture and launching method