CN207124455U - One kind metering rack electric power system - Google Patents

One kind metering rack electric power system Download PDF

Info

Publication number
CN207124455U
CN207124455U CN201721078403.3U CN201721078403U CN207124455U CN 207124455 U CN207124455 U CN 207124455U CN 201721078403 U CN201721078403 U CN 201721078403U CN 207124455 U CN207124455 U CN 207124455U
Authority
CN
China
Prior art keywords
power supply
output end
electric power
metering rack
switching power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721078403.3U
Other languages
Chinese (zh)
Inventor
闫国帅
张金伟
闫井超
杨峰
尹家文
李震宇
鞠海荣
李俊
杨文辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
China Oil and Gas Pipeline Network Corp
National Pipeline Network Group Sichuan to East Natural Gas Pipeline Co Ltd
Original Assignee
Sinopec Sichuan East Gas Pipeline Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Sichuan East Gas Pipeline Co Ltd filed Critical Sinopec Sichuan East Gas Pipeline Co Ltd
Priority to CN201721078403.3U priority Critical patent/CN207124455U/en
Application granted granted Critical
Publication of CN207124455U publication Critical patent/CN207124455U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/20Smart grids as enabling technology in buildings sector

Abstract

A kind of metering rack electric power system is the utility model is related to, including the ups power of alternating current is provided, alternating current is converted to multiple switch power supply, diode rectification device, DC voltage transmitter, slave computer and the host computer of direct current;The output end of the ups power electrically connects with the input of the multiple Switching Power Supply, the output end of the multiple Switching Power Supply electrically connects with the input of the diode rectification device, input of the output end of the multiple Switching Power Supply also with the DC voltage transmitter electrically connects, the output end of the DC voltage transmitter and the next mechatronics, the slave computer and the upper mechatronics.Metering rack electric power system provided by the utility model can provide the measuring equipment in station stable power supply by measuring rack, and when breaking down, failure situation can be known with the very first time, is handled in time, ensures station measuring equipment energy even running.

Description

One kind metering rack electric power system
Technical field
It the utility model is related to technical field of electricity, more particularly to a kind of metering rack electric power system.
Background technology
The station of Long-distance Transmission Pipeline is each equipped with measuring rack, and metering rack is mainly used in scene and rack room Equipment (such as flowmeter, flow computer, pressure transmitter and temperature transmitter) is powered, and the signal between transmission equipment. If during gas supply conduit, rack power supply sends failure, will cause the said equipment entirety power down, so as to measure in machine Air demand after cabinet power down, direct economic loss is caused to enterprise.Therefore, ensure that normal operation circuit is extremely important in rack.
Utility model content
, can be with order to provide the measuring equipment in station stable power supply by measuring rack, and when breaking down The very first time knows failure situation, is handled in time, ensures station measuring equipment energy even running, the utility model proposes one Kind metering rack electric power system.
The technical solution of the utility model is as follows:One kind metering rack electric power system, including the UPS electricity of alternating current is provided Source, the multiple switch power supply that alternating current is converted to direct current, diode rectification device, DC voltage transmitter, slave computer and Host computer;The output end of the ups power electrically connects with the input of the multiple Switching Power Supply, the multiple Switching Power Supply Output end electrically connects with the input of the diode rectification device, the output end of the multiple Switching Power Supply also with the direct current The input electrical connection of voltage transmitter, the output end of the DC voltage transmitter and the next mechatronics, under described Position machine and the upper mechatronics.
The beneficial effects of the utility model are:The ups power being arranged in rack can provide 220V alternating currents, and pass through Alternating current is converted to 24V direct currents by multiple switch power supply, so that the measuring equipment in station uses.Due to being provided with multiple open Powered-down source, wherein one other Switching Power Supplies can still provide stable DC voltage when breaking down, and due to setting There is diode rectification device, it is anti-that the Switching Power Supply not broken down will not carry out electric current to the Switching Power Supply to have broken down It is defeated, influence the performance of Switching Power Supply not broken down.In addition, DC voltage transmitter will monitor each switched power output Voltage, and by slave computer by monitoring result real-time Transmission to long-range host computer, if certain road output voltage occur it is abnormal, on Position machine will produce corresponding alarm signal.Not only make the power supply to measuring equipment more stable, and can occur in supply voltage When abnormal, and alarm and handle, improve the stability and security of equipment.
On the basis of above-mentioned technical proposal, the utility model can also do following improvement.
Further, the system also includes multiple power switch terminals, and the output end of the ups power is opened with the multiple The input in powered-down source electrically connects through the multiple power switch terminal.
It is using the above-mentioned further beneficial effect of scheme:Ups power output end and Switching Power Supply input it Between set power switch terminal, can a certain Switching Power Supply break down needs carry out change maintenance when be not required to cut off all electricity Road, and improve the security of operation.
Further, the system also includes multiple equipment switch terminal, the multiple facility switching terminal and two pole The output end electrical connection of pipe fairing.
It is using the above-mentioned further beneficial effect of scheme:The facility switching terminal of the output end of diode rectification device can So that the connection of electrical equipment and metering rack is more convenient, while it is easy to carry out corresponding inspection operation when breaking down.
Further, the slave computer is SCADA system slave computer, and the host computer is SCADA system host computer.
Further, the SCADA system slave computer is PLC.
It is using the above-mentioned further beneficial effect of scheme:SCADA system can be monitored to a wide range of multiple processes, So as to ensure that multiple metering racks of Long-distance Transmission Pipeline station can be monitored accurately, in addition using major control in station The PLC of other equipment can not only be formed with station other equipment and linked, moreover it is possible to be cost-effective as SCADA system slave computer.
Further, the system includes two Switching Power Supplies.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are Some embodiments of the utility model, for those of ordinary skill in the art, do not paying the premise of creative labor Under, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is a kind of metering rack electric power system block diagram of the utility model embodiment;
Fig. 2 is a kind of metering rack electric power system block diagram of the utility model embodiment.
Embodiment
Principle of the present utility model and feature are described below in conjunction with accompanying drawing, example is served only for explaining this practicality It is new, it is not intended to limit the scope of the utility model.
As shown in figure 1, a kind of rack electric power system of measuring provided by the utility model includes providing the UPS electricity of alternating current Source, the multiple switch power supply that alternating current is converted to direct current, diode rectification device, DC voltage transmitter, slave computer and Host computer;The output end of the ups power electrically connects with the input of the multiple Switching Power Supply, the multiple Switching Power Supply Output end electrically connects with the input of the diode rectification device, the output end of the multiple Switching Power Supply also with the direct current The input electrical connection of voltage transmitter, the output end of the DC voltage transmitter and the next mechatronics, under described Position machine and the upper mechatronics.
Specifically, ups power output is 220V alternating currents, and 220V alternating currents are converted into 24V direct currents, are by Switching Power Supply The equipment such as flowmeter, flow computer, pressure transmitter and temperature transmitter are powered.Order has two Switching Power Supplies, at it In one another can still export DC voltage and supply equipment even running when breaking down, and due to two switch electricity Source is in parallel with diode rectification device, and diode rectification device can block normal switch power supply to breakdown switch power supply Reverse current, to protect normal switch power supply.Meanwhile DC voltage transmitter is used for the direct current of monitoring switch power supply output Pressure, voltage signal is converted into 4-20mA signals, and is transmitted by being arranged on the slave computer of station in Background control room Host computer, the monitoring to power output signal is realized, when faulty or abnormal generation, host computer will generate corresponding alarm signal Number, remind relevant staff to arrange overhaul of the equipments in time.
In the present embodiment, the ups power being arranged in rack can provide 220V alternating currents, and pass through multiple switch electricity Alternating current is converted to 24V direct currents by source, so that the measuring equipment in station uses.Due to being provided with multiple switch power supply, When one of them breaks down, other Switching Power Supplies can still provide stable DC voltage, and due to being provided with diode Fairing, the Switching Power Supply not broken down will not carry out electric current reverse pumping to the Switching Power Supply to have broken down, influence not The performance of the Switching Power Supply to break down.In addition, DC voltage transmitter will monitor the voltage of each switched power output, and lead to Slave computer is crossed by monitoring result real-time Transmission to long-range host computer, if exception occurs for certain road output voltage, host computer will produce Raw corresponding alarm signal.Not only make power supply to measuring equipment more stable, and can when supply voltage occurs abnormal, and Alarm is simultaneously handled, and improves the stability and security of equipment.
Preferably, the system also includes multiple power switch terminals and multiple equipment switch terminal, the ups power Output end electrically connects with the input of the Switching Power Supply through the power switch terminal, the facility switching terminal and described two The output end electrical connection of pole pipe fairing.
Power switch terminal is set between the output end of ups power and the input of Switching Power Supply, can be opened a certain Closing power failure needs to carry out being not required to cut off all circuits when changing maintenance, and improves the security of operation.Diode The facility switching terminal of the output end of fairing can use the connection of electric equipment and metering rack more convenient, be easy to simultaneously Corresponding inspection operation is carried out when breaking down.
Preferably, the slave computer is SCADA system slave computer, and the host computer is SCADA system host computer.It is described SCADA system slave computer is PLC.
As shown in Fig. 2 make ups power that there is two FireWire port ports of L1, L2 and a N zero lines port, respectively by L1, L2 and N introduces two-way 220V alternating currents by two power switch terminals to two Switching Power Supplies, what two Switching Power Supplies were converted to DC voltage one diode rectification device of access, and multiple equipment switch terminals are set in diode rectification device output end side by side Son, to be powered to equipment, in addition, output end is provided with Surge Protector, reverse current is prevented, with protection switch power supply.Meanwhile The output voltage of two Switching Power Supplies of DC voltage transmitters monitor, after voltage signal is converted into current signal, by being used as The station PLC of SCADA system slave computer transmits voltage monitoring signal to SCADA system host computer, realizes and measuring equipment is supplied The remote monitoring of piezoelectric voltage, and when having exception and failure occurs, such as voltage is less than preset value, sends warning signal, in time Arrange maintenance.
The metering rack electric power system that the utility model embodiment provides, can be by measuring rack to the metering in station Equipment provides stable power supply, and when breaking down, failure situation can be known with the very first time, is handled in time, ensures Station measuring equipment energy even running.
Preferred embodiment of the present utility model is the foregoing is only, it is all in this practicality not to limit the utility model Within new spirit and principle, any modification, equivalent substitution and improvements made etc., guarantor of the present utility model should be included in Within the scope of shield.

Claims (6)

1. a kind of metering rack electric power system, it is characterised in that the system includes providing the ups power of alternating current, will exchanged Electricity is converted to multiple switch power supply, diode rectification device, DC voltage transmitter, slave computer and the host computer of direct current;Institute The output end for stating ups power electrically connects with the input of the multiple Switching Power Supply, the output end of the multiple Switching Power Supply with The input electrical connection of the diode rectification device, the output end of the multiple Switching Power Supply also with the DC voltage pick-up The input electrical connection of device, the output end of the DC voltage transmitter and the next mechatronics, the slave computer and institute State upper mechatronics.
2. metering rack electric power system according to claim 1, it is characterised in that the system is also opened including multiple power supplys Terminal is closed, the input of the output end of the ups power and the multiple Switching Power Supply is electric through the multiple power switch terminal Connection.
3. metering rack electric power system according to claim 2, it is characterised in that the system is also opened including multiple equipment Terminal is closed, the multiple facility switching terminal electrically connects with the output end of the diode rectification device.
4. metering rack electric power system according to claim 3, it is characterised in that the slave computer is under SCADA system Position machine, the host computer is SCADA system host computer.
5. metering rack electric power system according to claim 4, it is characterised in that the SCADA system slave computer is PLC。
6. the metering rack electric power system according to any one of claim 1 to 5, it is characterised in that the system includes two The individual Switching Power Supply.
CN201721078403.3U 2017-08-24 2017-08-24 One kind metering rack electric power system Active CN207124455U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721078403.3U CN207124455U (en) 2017-08-24 2017-08-24 One kind metering rack electric power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721078403.3U CN207124455U (en) 2017-08-24 2017-08-24 One kind metering rack electric power system

Publications (1)

Publication Number Publication Date
CN207124455U true CN207124455U (en) 2018-03-20

Family

ID=61611392

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721078403.3U Active CN207124455U (en) 2017-08-24 2017-08-24 One kind metering rack electric power system

Country Status (1)

Country Link
CN (1) CN207124455U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110504740A (en) * 2018-05-17 2019-11-26 中国石油天然气股份有限公司 A kind of power supply device of Gas Stations emergency stop (apparatus) system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110504740A (en) * 2018-05-17 2019-11-26 中国石油天然气股份有限公司 A kind of power supply device of Gas Stations emergency stop (apparatus) system

Similar Documents

Publication Publication Date Title
CN206628714U (en) Low voltage switch equipment
CN205067643U (en) Direct current system's of transformer substation distributed insulation monitoring and warning device
CN204758748U (en) Cubical switchboard intelligent integrated monitoring devices
CN203688090U (en) Online cable temperature monitoring system
CN104460614A (en) Hotel energy-consumption intelligent remote monitoring and managing system
CN207124455U (en) One kind metering rack electric power system
CN103151830B (en) Substation with internal bridge automatic throw-in equipment of emergency power supply
CN202351676U (en) Energy consumption metering and production safety monitoring system
CN204089348U (en) A kind of switchgear house remote online intelligent and safe operational system
CN202533787U (en) New type mine power supply monitoring system
CN104678756A (en) Novel intelligent comprehensive power transformation and distribution monitoring system
CN203967831U (en) A kind of intelligent multiloop first cabinet of each row
CN105119384A (en) High risk and important client remote monitoring system
CN205302580U (en) Leak water alarming system based on reactive power compensator
CN203339798U (en) Fire-fighting linkage power supply module
CN204290503U (en) Integral intelligent AC power case
CN205622329U (en) Power dispatching automation is network passageway warning device for system
CN202486585U (en) Transformer air cooling control device
CN202949283U (en) remote control power distribution cabinet for internet of things
CN204205612U (en) For the Powerless compensation control box of double power-supply system
CN203071653U (en) Power distribution equipment energy consumption monitoring device
CN205092446U (en) Rural power grids intelligent power distribution cabinet
CN204156376U (en) A kind of 10kV Zhu Shang transformer station of autonomous intelligence
CN208568968U (en) A kind of collection high voltage direct current insulating monitoring and integrated device of alarming
CN204304617U (en) Power monitoring circuit protective device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200914

Address after: 100728 Beijing, Chaoyangmen, North Street, No. 22, No.

Co-patentee after: SINOPEC CHUANQI DONGSONG NATURAL GAS PIPELINE Co.,Ltd.

Patentee after: China Petroleum & Chemical Corp.

Address before: 430223 Hubei Wuhan City, Wuhan City, East Lake New Technology Development Zone Optics Valley Avenue No. 126 Sichuan Gas East pipeline project, the 1-5 layer of the Wuhan control center

Patentee before: SINOPEC CHUANQI DONGSONG NATURAL GAS PIPELINE Co.,Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100728 No. 22 North Main Street, Chaoyang District, Beijing, Chaoyangmen

Patentee after: CHINA PETROLEUM & CHEMICAL Corp.

Patentee after: Sichuan East Natural Gas Pipeline Co.,Ltd.

Address before: 100728 No. 22 North Main Street, Chaoyang District, Beijing, Chaoyangmen

Patentee before: CHINA PETROLEUM & CHEMICAL Corp.

Patentee before: SINOPEC CHUANQI DONGSONG NATURAL GAS PIPELINE Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211115

Address after: Room 08-10, 6 / F, block a, No. 5, Dongtucheng Road, Chaoyang District, Beijing 100013

Patentee after: National Petroleum and natural gas pipeline network Group Co.,Ltd.

Patentee after: Sichuan East Natural Gas Pipeline Co.,Ltd.

Address before: 100728 No. 22 North Main Street, Chaoyang District, Beijing, Chaoyangmen

Patentee before: CHINA PETROLEUM & CHEMICAL Corp.