CN207105697U - A kind of construction waste metal processing unit - Google Patents

A kind of construction waste metal processing unit Download PDF

Info

Publication number
CN207105697U
CN207105697U CN201720739482.1U CN201720739482U CN207105697U CN 207105697 U CN207105697 U CN 207105697U CN 201720739482 U CN201720739482 U CN 201720739482U CN 207105697 U CN207105697 U CN 207105697U
Authority
CN
China
Prior art keywords
plate
processing unit
construction waste
metal processing
waste metal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720739482.1U
Other languages
Chinese (zh)
Inventor
王则鉴
余悦之
卢子言
姚欣妍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720739482.1U priority Critical patent/CN207105697U/en
Application granted granted Critical
Publication of CN207105697U publication Critical patent/CN207105697U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of construction waste metal processing unit, including installing plate, the installing plate fixes two pairs of support columns, the support column fixes loading plate, the loading plate is provided with the first opening, the first opening first bogie of installation, and first bogie installs first hydraulic cylinder, the loading plate fixes bottom plate, and the bottom plate is provided with embedding slot.The utility model can focus on to metal garbage at random, make garbage-compressing at random into regular shape, to facilitate management and transport.

Description

A kind of construction waste metal processing unit
Technical field
Building field is the utility model is related to, particularly a kind of construction waste metal processing unit.
Background technology
When construction, substantial amounts of metal garbage can be produced, for example reinforcing bar can not be used because of outer force deformation, or Metallic plate deformation can not use, and these metal garbages need staff to entruck and carry away after stacking, because metal is irregular, are filling During be possible to that staff can be damaged, and some large scale equipments can not carry out entrucking, in consideration of it, to above-mentioned Problem is furtherd investigate, and obtains this case then.
Utility model content
The purpose of this utility model is to solve the above problems, and devises a kind of construction waste metal processing dress Put.
To achieve the above object, the utility model provides following technical scheme:A kind of construction waste metal processing dress Put, including installing plate, the installing plate fixes two pairs of support columns, and the support column fixes loading plate, and the loading plate is provided with the One opening, the first opening first bogie of installation, first bogie install first hydraulic cylinder, and the loading plate is fixed Bottom plate, the bottom plate are provided with embedding slot, and the embedding slot is provided with the second opening, and the embedding slot installs the first portable plate, described Loading plate installs a pair of first baffles, and the installing plate installs a pair of second baffles, the first baffle fixed support, the branch Frame, the support install the second bogie, and installing plate described in the second bogie installation second hydraulic cylinder is provided with the second activity Plate, second portable plate install infrared sensor.
Preferably, first opening is corresponding with the second opening, and first portable plate installs the first fitting, described First hydraulic cylinder connects the first fitting.
Preferably, second portable plate installs the second fitting, and the second hydraulic cylinder connects the second fitting.
Preferably, the first baffle fixes the first reinforcing plate, and the second baffle fixes the second reinforcing plate.
Preferably, the loading plate is provided with mounting hole, and the mounting hole fixes suspension ring.
Preferably, the second baffle Fixing clamp-seat, the deck install stripper.
A kind of construction waste metal processing unit made using the technical solution of the utility model, the present apparatus can be with Metal garbage at random is focused on, makes garbage-compressing at random into regular shape, to facilitate management and transport.
Brief description of the drawings
Fig. 1 is a kind of structural representation of construction waste metal processing unit described in the utility model;
Fig. 2 is a kind of top view of construction waste metal processing unit described in the utility model;
Fig. 3 is a kind of side view of construction waste metal processing unit described in the utility model;
In figure:1st, installing plate;2nd, support column;3rd, loading plate;4th, the first bogie;5th, first hydraulic cylinder;6th, bottom plate;7th, One portable plate;8th, first baffle;9th, second baffle;10th, support;11st, the second bogie;12nd, the second portable plate;13rd, infrared biography Sensor;14th, the first fitting;15th, the second fitting;16th, second hydraulic cylinder;17th, the first reinforcing plate;18th, the second reinforcing plate; 19th, suspension ring;20th, deck;21st, stripper.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
In description of the present utility model, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " on ", " under ", The orientation or position relationship of the instruction such as "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", " outer " are Based on orientation shown in the drawings or position relationship, merely to make sub- description the utility model and simplify to describe, rather than instruction Or imply that signified device or element must have specific orientation, with specific azimuth configuration and operation, therefore be not understood that For to limitation of the present utility model.In addition, term " first ", " second " are only used for describing purpose, and it is not intended that instruction or Imply relative importance or the implicit quantity for indicating indicated technical characteristic.Thus, define " first ", " second " is only used In description purpose, and it is not intended that indicating or implying relative importance or implicitly include one or more spy Sign.In description of the present utility model, unless otherwise indicated, " multiple " are meant that two or more.
The utility model provides a kind of construction waste metal processing unit as Figure 1-3, including installing plate 1, the installing plate 1 fixes two pairs of support columns 2, and the support column 2 fixes loading plate 3, and the loading plate 3 is provided with the first opening, First opening, first bogie 4 of installation, first bogie 4 install first hydraulic cylinder 5, and the loading plate 3 fixes bottom Plate 6, the bottom plate 6 are provided with embedding slot, and the embedding slot is provided with the second opening, and the embedding slot installs the first portable plate 7, described Loading plate 3 installs a pair of first baffles 8, and the installing plate 1 installs a pair of second baffles 9, the fixed support of first baffle 8 10, the support 10, the support 10 installs the second bogie 11, and second bogie 11 is installed described in second hydraulic cylinder 16 Installing plate 1 is provided with the second portable plate 12, and second portable plate 12 installs infrared sensor 13;First opening is opened with second Mouth is corresponding, and first portable plate 7 installs the first fitting 14, and the first hydraulic cylinder 5 connects the first fitting 14;It is described Second portable plate 12 installs the second fitting 15, and the second hydraulic cylinder 16 connects the second fitting 15;The first baffle 8 is solid Fixed first reinforcing plate 17, the second baffle 9 fix the second reinforcing plate 18;The loading plate 3 is provided with mounting hole, the mounting hole Fixed suspension ring 19;The Fixing clamp-seat 20 of second baffle 9, the deck 20 install stripper 21.
When specifically used:Programmable Series Controller and 2 relays are installed first at the present apparatus free time,
By taking MAM-200 controller as an example, by the output end of the model controller by wire respectively with XXX platforms 2 after Electrical equipment connects with the input of infrared sensor, at the same by 2 relays by wire respectively with first hydraulic cylinder and the second liquid The magnetic valve connection that cylinder pressure carries.After those skilled in the art are by controller programming, the work of the fully controllable each electrical part of system is suitable Sequence, concrete operating principle are as follows:Correct position is moved to by suspension ring 19 first, when there is metal garbage, is thrown to first gear In plate 8 and second baffle 9, when accumulating to a certain degree, start second hydraulic cylinder 16, the drive end of second hydraulic cylinder 16 promotes Second fitting 15, the second portable plate 12 is moved down, the first portable plate 14 is applied pressure initiation rule to metal at random Shape then, risen by the first portable plate 14, while start first hydraulic cylinder 5, the drive end of first hydraulic cylinder 5 promotes first to match somebody with somebody Piece installing 14, the first portable plate 7 is moved upwards, the metal derby after compression is ejected upwards, when the first portable plate 7 and second When baffle plate 9 is horizontal, stop movement, metal derby is released, slid by stripper 21 to other carriers, by red by staff Outer sensor 13 prevents staff's device in operation from starting, and concrete operating principle demonstration finishes.
Finally it should be noted that:Preferred embodiment of the present utility model is the foregoing is only, is not limited to this Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art For, it can still modify to the technical scheme described in foregoing embodiments, or to which part technical characteristic Progress equivalent substitution, all within the spirit and principles of the utility model, any modification, equivalent substitution and improvements made etc., It should be included within the scope of protection of the utility model.

Claims (6)

1. a kind of construction waste metal processing unit, including installing plate (1), it is characterised in that the installing plate (1) is fixed Two pairs of support columns (2), the fixed loading plate (3) of the support column (2), the loading plate (3) are provided with the first opening, and described first opens Mouth the first bogie of installation (4), the first bogie (4) installation first hydraulic cylinder (5), the loading plate (3) fix bottom plate (6), the bottom plate (6) is provided with embedding slot, and the embedding slot is provided with the second opening, and the embedding slot installs the first portable plate (7), The loading plate (3) installs a pair of first baffles (8), and the installing plate (1) installs a pair of second baffles (9), the first gear Plate (8) fixed support (10), the support (10), the support (10) install the second bogie (11), second bogie (11) second hydraulic cylinder (16) installing plate (1) is installed and is provided with the second portable plate (12), the second portable plate (12) installation Infrared sensor (13).
A kind of 2. construction waste metal processing unit according to claim 1, it is characterised in that first opening Corresponding with the second opening, first portable plate (7) installs the first fitting (14), first hydraulic cylinder (5) connection the One fitting (14).
A kind of 3. construction waste metal processing unit according to claim 1, it is characterised in that second activity Plate (12) installs the second fitting (15), and the second hydraulic cylinder (16) connects the second fitting (15).
A kind of 4. construction waste metal processing unit according to claim 1, it is characterised in that the first baffle (8) the first reinforcing plate (17) is fixed, the second baffle (9) fixes the second reinforcing plate (18).
A kind of 5. construction waste metal processing unit according to claim 1, it is characterised in that the loading plate (3) mounting hole is provided with, the mounting hole fixes suspension ring (19).
A kind of 6. construction waste metal processing unit according to claim 1, it is characterised in that the second baffle (9) Fixing clamp-seat (20), deck (20) the installation stripper (21).
CN201720739482.1U 2017-06-23 2017-06-23 A kind of construction waste metal processing unit Expired - Fee Related CN207105697U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720739482.1U CN207105697U (en) 2017-06-23 2017-06-23 A kind of construction waste metal processing unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720739482.1U CN207105697U (en) 2017-06-23 2017-06-23 A kind of construction waste metal processing unit

Publications (1)

Publication Number Publication Date
CN207105697U true CN207105697U (en) 2018-03-16

Family

ID=61588971

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720739482.1U Expired - Fee Related CN207105697U (en) 2017-06-23 2017-06-23 A kind of construction waste metal processing unit

Country Status (1)

Country Link
CN (1) CN207105697U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108673927A (en) * 2018-05-21 2018-10-19 芜湖牧羿自动化科技有限公司 A kind of metal waste rolls retracting device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108673927A (en) * 2018-05-21 2018-10-19 芜湖牧羿自动化科技有限公司 A kind of metal waste rolls retracting device

Similar Documents

Publication Publication Date Title
CN207105697U (en) A kind of construction waste metal processing unit
CN206139766U (en) Automatic formula construction steel muscle aligning forming device
CN208996201U (en) Construction steel structure support device
CN105545059B (en) A kind of modularization tower device and its construction transportation resources
CN203568222U (en) Side wall reinforcing structure of rectangular coal scuttle
CN106609601B (en) Container modular architectural
CN202031309U (en) Suspending operation platform for structural concrete constructions
CN201924532U (en) Standard stair guard rail capable of being repeatedly used
CN208933417U (en) Well formula tempering furnace tempering frame
CN207485005U (en) Construction steel construction fixing device
CN207144533U (en) The horizontal protective of building hoist basis conversion
CN104612166A (en) Combined supporting device and method for hole wall supporting
CN106065712B (en) Hanging rack system Fast Installation construction method for low level jacking formwork system
CN203212007U (en) Waste printed circuit board loading device and processing device
CN207066886U (en) A kind of road and bridge concrete NDT device
CN207045856U (en) A kind of miberal powder canning equipment
CN206278823U (en) The photovoltaic module transporter used in the photovoltaic plant work progress of mountain region
CN206908020U (en) A kind of multi-row-type electronic communication equipment
CN209396484U (en) A kind of fuel cell is framed up transportation system with pole plate
CN202731414U (en) Safety fence net support
CN209430226U (en) A kind of electromechanical installation construction safety protection device
CN203047381U (en) Top board of caravan
CN210914264U (en) Plate conveying device for brick machine production
CN201489845U (en) Combined operation platform of underwater inversed source
CN206997614U (en) A kind of building iron apparatus for bending

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180316