CN207079474U - The assembling type steel tubing string temporary rest pier Bailey beam support of the high cast-in-place turnout junction girder of pier stud - Google Patents

The assembling type steel tubing string temporary rest pier Bailey beam support of the high cast-in-place turnout junction girder of pier stud Download PDF

Info

Publication number
CN207079474U
CN207079474U CN201720620786.6U CN201720620786U CN207079474U CN 207079474 U CN207079474 U CN 207079474U CN 201720620786 U CN201720620786 U CN 201720620786U CN 207079474 U CN207079474 U CN 207079474U
Authority
CN
China
Prior art keywords
steel
cushion cap
pipe column
steel pipe
sandbox
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720620786.6U
Other languages
Chinese (zh)
Inventor
李树彬
史保真
苏伟业
王亮
盛文治
周小平
邹卫东
任江波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Original Assignee
Sixth Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd filed Critical Sixth Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority to CN201720620786.6U priority Critical patent/CN207079474U/en
Application granted granted Critical
Publication of CN207079474U publication Critical patent/CN207079474U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of assembling type steel tubing string temporary rest pier Bailey beam support of high cast-in-place turnout junction girder of pier stud, solve the problems, such as that falsework security risk is big in railway super-high pier cast-in-place construction under the conditions of complicated landform landforms soft foundation.In left cushion cap(1)With right cushion cap(2)Between be provided with middle Temporary Piers pile foundation(3), middle Temporary Piers cushion cap(22)With middle steel pipe column(13), the top of middle steel pipe column is provided with middle sandbox(14), the top of middle sandbox is provided with intermediate lateral steel I-beam(21), left and right steel pipe column is respectively arranged with left and right cushion cap, in left steel pipe column(5)Top be provided with left sandbox(8), in right steel pipe column(16)Top be provided with right sandbox(19), in left horizontal steel I-beam(9), intermediate lateral steel I-beam(21)With right horizontal steel I-beam(20)On be provided with Bailey beam(10).The utility model has that construction cost is low, practical.

Description

The assembling type steel tubing string temporary rest pier Bailey beam support of the high cast-in-place turnout junction girder of pier stud
Technical field
It the utility model is related to a kind of support, the falsework in more particularly to a kind of Railway Bridges And Piers cast-in-place construction.
Background technology
With high ferro and the fast development of urban track traffic, AT STATION in bridge type selecting, cast-in-place track switch continuous beam is set Meter scheme by through frequently with.When constructing cast-in-place track switch continuous beam, it is necessary to falsework system be used, to cast-in-place track switch continuous beam Template is supported, this falsework system generally use full framing support system.But some topography and geomorphologies it is complicated, The poor area of matter condition, especially in geologic feature to impact the low mountains and hills landforms proluvial layer strip based on silty clay, Construction is supported according to full framing system, because its bearing capacity and flatness requirement to ground is high, particularly when full After hall support scaffolding height is higher, once the local differential settlement of ground occurs, easily cause whole full framing system Cave in, the problem of security risk is big, long and material installation input of setting up the time is big be present.
The content of the invention
The utility model provides a kind of cast-in-place turnout junction girder assembling type steel tubing string temporary rest pier Bailey beam support of high pier stud, solution The big technology of falsework security risk in railway super-high pier cast-in-place construction under the conditions of complicated landform of having determined landforms soft foundation Problem.
The utility model is that solve above technical problem by the following technical programs:
A kind of assembling type steel tubing string temporary rest pier Bailey beam support of cast-in-place turnout junction girder of high pier stud, including left cushion cap and the right side are held Platform, left pier shaft is provided with left cushion cap, right pier shaft is provided with right cushion cap, in being provided between left cushion cap and right cushion cap Between Temporary Piers pile foundation, middle Temporary Piers cushion cap is provided with middle Temporary Piers pile foundation, is set on middle Temporary Piers cushion cap Middle steel pipe column is equipped with, middle sandbox is provided with middle steel pipe column, intermediate lateral I-steel is provided with middle sandbox Beam, left steel pipe column is provided with left cushion cap, left pre-buried junction steel plate is arranged at intervals with the side wall of left pier shaft, left pre-buried Left fixed angle steel is welded between junction steel plate and left steel pipe column, the top of left steel pipe column is provided with left sandbox, in left sandbox On be provided with left horizontal steel I-beam, right steel pipe column is provided with right cushion cap, the right side is arranged at intervals with the side wall of right pier shaft Pre-buried junction steel plate, right fixed angle steel is welded between right pre-buried junction steel plate and right steel pipe column, on the top of right steel pipe column Right sandbox is provided with, right horizontal steel I-beam is provided with right sandbox, in left horizontal steel I-beam, intermediate lateral steel I-beam Bailey beam is provided with right horizontal steel I-beam, cross direction profiles steel I-beam is provided with Bailey beam, in cross direction profiles work Cast-in-situ Beam template system is provided with word girder steel.
The support frame 23 of Cast-in-situ Beam template system is provided with cross direction profiles steel I-beam.
The utility model has that construction cost is low, and efficiency of construction is high, easy to operate, the practical and excellent spy of technique effect Point, it is with the obvious advantage in general safety stability, it can be widelyd popularize in the engineering constructions such as railway, highway, municipal administration.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is A-A in Fig. 1 to sectional view.
Embodiment
The utility model is described in detail below in conjunction with the accompanying drawings:
A kind of assembling type steel tubing string temporary rest pier Bailey beam support of cast-in-place turnout junction girder of high pier stud, including left cushion cap 1 and the right side Cushion cap 2, left pier shaft 4 is provided with left cushion cap 1, right pier shaft 15 is provided with right cushion cap 2, left cushion cap 1 and right cushion cap 2 it Between be provided with middle Temporary Piers pile foundation 3, middle Temporary Piers cushion cap 22 is provided with middle Temporary Piers pile foundation 3, in centre Middle steel pipe column 13 is provided with Temporary Piers cushion cap 22, the top of middle steel pipe column 13 is provided with middle sandbox 14, in centre The top of sandbox 14 is provided with intermediate lateral steel I-beam 21, and left steel pipe column 5 is provided with left cushion cap 1, in the side of left pier shaft 4 Left pre-buried junction steel plate 6 is arranged at intervals with wall, left fixed angles are welded between left pre-buried junction steel plate 6 and left steel pipe column 5 Steel 7, the top of left steel pipe column 5 is provided with left sandbox 8, left horizontal steel I-beam 9 is provided with left sandbox 8, in right cushion cap 2 On be provided with right steel pipe column 16, right pre-buried junction steel plate 17 is arranged at intervals with the side wall of right pier shaft 15, in right pre-buried connection Right fixed angle steel 18 is welded between steel plate 17 and right steel pipe column 16, the top of right steel pipe column 16 is provided with right sandbox 19, Right horizontal steel I-beam 20 is provided with right sandbox 19, in left horizontal steel I-beam 9, intermediate lateral steel I-beam 21 and right transverse direction Bailey beam 10 is provided with steel I-beam 20, cross direction profiles steel I-beam 11 is provided with Bailey beam 10, in cross direction profiles work Cast-in-situ Beam template system 12 is provided with word girder steel 11.
The support frame 23 of Cast-in-situ Beam template system 12 is provided with cross direction profiles steel I-beam 11.
The utility model is applied to setting up for the falsework of the high pier stud Cast-in-situ Beam of low mountains and hills landforms proluvial layer strip, special The high pier stud in-situ beam casting not being suitable under complicated geological, landform, landforms, technical scheme, which has, implements convenient, strutting system Rigidity is good, and support basement process is simple, and support is set up the advantages that light quick, while using customization steel pipe post after-poppet system In modular operation, can freely arrange in pairs or groups regulation buttress height in construction according to pier shaft height.

Claims (2)

1. a kind of assembling type steel tubing string temporary rest pier Bailey beam support of cast-in-place turnout junction girder of high pier stud, including left cushion cap(1)And the right side Cushion cap(2), in left cushion cap(1)On be provided with left pier shaft(4), in right cushion cap(2)On be provided with right pier shaft(15), its feature exists In in left cushion cap(1)With right cushion cap(2)Between be provided with middle Temporary Piers pile foundation(3), in middle Temporary Piers pile foundation(3) On be provided with middle Temporary Piers cushion cap(22), in middle Temporary Piers cushion cap(22)On be provided with middle steel pipe column(13), in centre Steel pipe column(13)Top be provided with middle sandbox(14), in middle sandbox(14)Top be provided with intermediate lateral steel I-beam (21), in left cushion cap(1)On be provided with left steel pipe column(5), in left pier shaft(4)Side wall on be arranged at intervals with left pre-buried connection steel Plate(6), in left pre-buried junction steel plate(6)With left steel pipe column(5)Between be welded with left fixed angle steel(7), in left steel pipe column(5)'s Top is provided with left sandbox(8), in left sandbox(8)On be provided with left horizontal steel I-beam(9), in right cushion cap(2)On be provided with Right steel pipe column(16), in right pier shaft(15)Side wall on be arranged at intervals with right pre-buried junction steel plate(17), in right pre-buried connection steel Plate(17)With right steel pipe column(16)Between be welded with right fixed angle steel(18), in right steel pipe column(16)Top be provided with right sandbox (19), in right sandbox(19)On be provided with right horizontal steel I-beam(20), in left horizontal steel I-beam(9), intermediate lateral I-shaped Girder steel(21)With right horizontal steel I-beam(20)On be provided with Bailey beam(10), in Bailey beam(10)On be provided with cross direction profiles work Word girder steel(11), in cross direction profiles steel I-beam(11)On be provided with Cast-in-situ Beam template system(12).
A kind of 2. assembling type steel tubing string temporary rest pier Bailey beam branch of high cast-in-place turnout junction girder of pier stud according to claim 1 Frame, it is characterised in that in cross direction profiles steel I-beam(11)On be provided with Cast-in-situ Beam template system(12)Support frame(23).
CN201720620786.6U 2017-05-31 2017-05-31 The assembling type steel tubing string temporary rest pier Bailey beam support of the high cast-in-place turnout junction girder of pier stud Active CN207079474U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720620786.6U CN207079474U (en) 2017-05-31 2017-05-31 The assembling type steel tubing string temporary rest pier Bailey beam support of the high cast-in-place turnout junction girder of pier stud

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720620786.6U CN207079474U (en) 2017-05-31 2017-05-31 The assembling type steel tubing string temporary rest pier Bailey beam support of the high cast-in-place turnout junction girder of pier stud

Publications (1)

Publication Number Publication Date
CN207079474U true CN207079474U (en) 2018-03-09

Family

ID=61436730

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720620786.6U Active CN207079474U (en) 2017-05-31 2017-05-31 The assembling type steel tubing string temporary rest pier Bailey beam support of the high cast-in-place turnout junction girder of pier stud

Country Status (1)

Country Link
CN (1) CN207079474U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593102A (en) * 2019-08-22 2019-12-20 中铁十六局集团第四工程有限公司 High mound continuous beam construction support

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593102A (en) * 2019-08-22 2019-12-20 中铁十六局集团第四工程有限公司 High mound continuous beam construction support

Similar Documents

Publication Publication Date Title
CN105568866B (en) Across the large-span steel box beam push construction method of existing road
CN101831873B (en) Temporary bridge covered excavation method for constructing box culvert below traffic ground line of operating track
CN202577157U (en) Simple support arch bridge straining beam construction support system
CN110424274A (en) The construction method of simple-supported thencontinuous PC track girder
CN102146676A (en) High-steep side slope subgrade structure for mountain area
CN108149712A (en) Partly inverse for road tunnel makees underground structure and its construction method
CN207079474U (en) The assembling type steel tubing string temporary rest pier Bailey beam support of the high cast-in-place turnout junction girder of pier stud
CN112983493A (en) Reinforcing structure for shield to closely penetrate large-section bridge and culvert downwards and construction method
CN205369043U (en) Long span steel case back pushes away construction and uses interim bearing structure
CN202369930U (en) Door opening type bearing framed bent device for multiplayer concrete box girder
CN217078829U (en) Position structure of bridge pile foundation and subway tunnel
CN207846471U (en) Partly inverse for road tunnel makees underground structure
CN208346838U (en) Viaduct beam bridge pier structure and grade separation bridge above subway
CN211228039U (en) One-span type buttress-free large-span Bailey beam steel temporary bridge
CN204151662U (en) A kind of one across the temporary trestle bridge crossing over river valley
CN210482000U (en) Limiting device for jacking construction of large-span steel pipe concrete tied arch bridge
CN203588579U (en) Teaching simulation structural body of simply supported beam bridge
CN102677563A (en) Modularized direct-moving fast channel system for crossroads of urban main road and construction method
JP4263935B2 (en) Construction method and elevated detour
CN206486798U (en) The bridgehead structures of overpass above underground rail
CN204676556U (en) One is encorbelmented People's Bank of China's packway
CN109826231A (en) A kind of novel super-high U-type groove structure and its setting method
CN211524190U (en) Foundation pit packway ladder cage fixing base
CN217758292U (en) Transition bridge between tunnels under gully landform
CN214656263U (en) Exposed rock stratum flood steel trestle structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant