- CN207063176U CN207063176U CN201720329982.8U CN201720329982U CN207063176U CN 207063176 U CN207063176 U CN 207063176U CN 201720329982 U CN201720329982 U CN 201720329982U CN 207063176 U CN207063176 U CN 207063176U
- Authority
- CN
- China
- Prior art keywords
- wall block
- attachment structure
- wall
- connector
- assembled architecture
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000007789 sealing Methods 0.000 claims abstract description 23
- 239000006260 foam Substances 0.000 claims description 19
- 239000003292 glue Substances 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- 239000000945 filler Substances 0.000 claims description 8
- 238000005187 foaming Methods 0.000 claims description 7
- 238000010276 construction Methods 0.000 abstract description 12
- 230000000712 assembly Effects 0.000 abstract description 5
- 238000000429 assembly Methods 0.000 abstract description 5
- 238000000034 method Methods 0.000 abstract description 2
- 230000002262 irrigation Effects 0.000 abstract 1
- 238000003973 irrigation Methods 0.000 abstract 1
- 230000000694 effects Effects 0.000 description 5
- 230000005489 elastic deformation Effects 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 238000009413 insulation Methods 0.000 description 3
- 230000001151 other effect Effects 0.000 description 3
- 238000012856 packing Methods 0.000 description 3
- 230000032683 aging Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 230000007797 corrosion Effects 0.000 description 2
- 239000003063 flame retardant Substances 0.000 description 2
- 238000007667 floating Methods 0.000 description 2
- 238000007373 indentation Methods 0.000 description 2
- 238000011084 recovery Methods 0.000 description 2
- 240000002853 Nelumbo nucifera Species 0.000 description 1
- 235000006508 Nelumbo nucifera Nutrition 0.000 description 1
- 235000006510 Nelumbo pentapetala Nutrition 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 238000013016 damping Methods 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000002277 temperature effect Effects 0.000 description 1
Landscapes
- Building Environments (AREA)
Abstract
The utility model discloses a kind of attachment structure of assembled architecture wall block, its drip irrigation device is:Including the first wall block and the second wall block, the first pre-buried connector is fixed with the first wall block, the second pre-buried connector is fixed with the second wall block, the first connector and the second connector are fixedly connected by fastening screw.First wall block and the second wall block are processed in processing factory respectively, are transported to job site afterwards and are carried out Assembling composition attachment structure, several attachment structures form construction wall, both facilitate and process wall block respectively, and can quickly assembles, shortens the duration.When two walls are assembled, all kinds of seals are provided between assem-bly facing, the gap between the first wall block and the second wall block is stuffed entirely with and sealed by seal, ensures the sealing of seam crossing.
Description
Technical field
Building material field is the utility model is related to, more particularly to a kind of construction wall.
Background technology
The wall of existing residential building is to build to complete at the construction field (site) mostly, and worker is first at the construction field (site)
Frame structure is set up, integrated poured building packing material completes construction again afterwards.
But the frame structure is needed to set up in order successively at the construction field (site), and wall pouring could be carried out after the completion of setting up,
Make the duration long, building can not come into operation as early as possible.
Utility model content
The purpose of this utility model is to provide a kind of attachment structure of assembled architecture wall block, and its advantage is can be with piecemeal
Wall block is processed, then carries out quick assembling to job site and fixes, effectively shortens the duration.
Above-mentioned technical purpose of the present utility model technical scheme is that:
A kind of attachment structure of assembled architecture wall block, it is characterized in that:Including the first wall block and the second wall block, institute
State and built-in fitting is respectively fixed with the first wall block and second wall block, two built-in fittings are fixed by fixed mechanism
Connection.
Pass through above-mentioned technical proposal, the first wall block and the second wall block can be processed in processing factory respectively, it
After be transported to job site carry out Assembling form attachment structure, several attachment structures form construction wall, both facilitate point
Wall block is not processed, and and can quickly assembles, shortens the duration.
The utility model is further arranged to:First wall block includes the first lateral keel, second wall block
Including the second lateral keel, first lateral keel and the second lateral keel are lightgage steel joist.
Pass through above-mentioned technical proposal, the first lateral keel and the second lateral keel play support to respective wall block respectively
Effect.Lightgage steel joist is a kind of new construction material, light steel(Baking vanish)Keel have that in light weight, intensity is high, adapts to waterproof, be anti-
Shake, dust-proof, sound insulation, sound-absorbing, constant temperature and other effects, while also there is short time limit, easy construction.On the other hand, using light
The also convenient recovery of steel joist and progress secondary use, have more preferably effects of energy conservation and environmental protection.
The utility model is further arranged to:Built-in fitting on first wall block is the first connector, described first
Connector includes the first fixed part and first connecting portion, and first fixed part is fixedly arranged on described first laterally by some stripped threads
Among keel, the first connecting portion is parallel with first lateral keel.
Pass through above-mentioned technical proposal, the first connector are fixed among the first lateral keel, and then are fixed on the first wall
On block.
The utility model is further arranged to:Built-in fitting on second wall block is the second connector, described second
Connector includes the second fixed part and second connecting portion, and second fixed part is fixedly arranged on described second laterally by some stripped threads
Among keel, the second connecting portion is parallel with second lateral keel.
Pass through above-mentioned technical proposal, the first connector are fixed among the first lateral keel, and then are fixed on the first wall
On block.
The utility model is further arranged to:The fixed mechanism is fastening screw, the first connecting portion and described
Two connecting portions are fixedly connected by the fastening screw.
Pass through above-mentioned technical proposal, fastening screw are successively screwed into first connecting portion and second connecting portion, and the two fixation is connected
Connect, and then the first wall block and the second wall block are fixedly connected.
The utility model is further arranged to:Sealing strip is provided between the first connecting portion and second connecting portion.
Pass through above-mentioned technical proposal, sealing strip are arranged on first connecting portion and second connecting portion before fastening screw is screwed
Between.Worker screws fastening screw, makes screwed hole, seal and second connecting portion of the fastening screw successively by first connecting portion
Screwed hole, and then fixed first connecting portion and second connecting portion.Now sealing strip is squeezed power and elastic deformation, and first is connected
Gap filling sealing between socket part and second connecting portion, sealing strip also act as damping, waterproof and other effects.
The utility model is further arranged to:Set between the connection gap of first wall block and second wall block
It is equipped with the foam rods close to surface of wall.
Pass through above-mentioned technical proposal, in spliced wall block, foam rods are squeezed power and produce elastic deformation, by seam
The space filling sealing at place, improve the sealing effectiveness of wall block seam crossing.
The utility model is further arranged to:Foaming gap filler is provided between the foam rods and the sealing strip.
Pass through above-mentioned technical proposal, foaming gap filler seal the gap filling between foam rods and sealing strip.Foaming is filled out
Seam agent have waterproof, it is resistance to expand with heat and contract with cold, be heat-insulated, sound insulation and fire-retardant effect.
The utility model is further arranged to:Structure glue is provided between the foam rods and the surface of wall.
Structure glue is used for the gap filling between foam rods and surface of wall and floating.Structure glue can bear larger lotus
Carry, and ageing-resistant, endurance, corrosion-resistant, stable performance.The profile pattern of attachment structure was both ensure that using structure glue, again
Wall bulk strength, rigidity and stability, and easy construction, short time limit are improved, engineering time and fund cost can be saved.
In summary, the utility model has the advantages that:
(1)First wall block and the second wall block are processed in processing factory respectively, are transported to job site afterwards and are entered
Row Assembling forms attachment structure, and several attachment structures form construction wall, has both facilitated and has processed wall block respectively, and can is fast
Speed assembling, shorten the duration.
(2)Sealing strip, foaming gap filler, foam rods and structure glue are connected, by the first wall block and the second wall block
Between gap be stuffed entirely with and seal, ensure the sealing of the seam crossing of attachment structure.
(3)First lateral keel and the second lateral keel are made by lightgage steel joist, and lightgage steel joist is used as one kind is new to build
Build material, have it is in light weight, be easy to construct, convenient recovery, the effect of energy-conserving and environment-protective.
Brief description of the drawings
Fig. 1 is the structural representation of the present embodiment.
In figure, the 1, first wall block;11st, the first lateral keel;12nd, the first wall;13rd, the first connector;131st, first
Fixed part;132nd, first connecting portion;2nd, the second wall block;21st, the second lateral keel;22nd, the second wall;23rd, the second connector;
231st, the second fixed part;232nd, second connecting portion;3rd, fastening screw;4th, sealing strip;5th, foam gap filler;6th, foam rods;7th, tie
Structure glue;8th, stripped thread.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
Embodiment:A kind of attachment structure of assembled architecture wall block, as shown in figure 1, including the first wall block 1 and second
Built-in fitting is respectively fixed with wall block 2, the first wall block 1 and the second wall block 2, two built-in fittings are solid by fastening screw 3
Fixed connection.
First wall block 1 and the second wall block 2 can be processed in processing factory respectively, be transported to job site afterwards
Carry out Assembling and form attachment structure, several attachment structures form construction wall, have both facilitated and have processed wall block, and can respectively
Quick assembling, shorten the duration.
First wall block 1 includes the first lateral keel 11, and the first lateral keel 11 is for lightgage steel joist and to the first wall block 1
Play a supporting role.Built-in fitting on first wall block 1 is the first connector 13, and the first connector 13 includes the first fixed part
131 and first connecting portion 132.The C-shaped indentations in cross section of first fixed part 131, the first fixed part 131 are slided by several
Silk 8 is fixed on the end of the first lateral keel 11, and then the first connector 13 is fixed on the first wall block 1.First connection
Portion 132 is fixed on the side of the first fixed part 131 and deviates from C-shaped recess, and first connecting portion 132 and the first lateral keel 11 are flat
OK, the screwed hole for extending vertically through its upper and lower surface is provided among first connecting portion 132.First wall 12 is poured with building packing material
Note inside and outside, the 1 overall knot of the first wall block of the first wall 12 guarantee in the first lateral keel 11 and the first connector 13
The integrality of structure.
Second wall block 2 includes the second lateral keel 21, and the second lateral keel 21 is for lightgage steel joist and to the second wall block 2
Play a supporting role.Built-in fitting on second wall block 2 is the second connector 23, and the second connector 23 includes the second fixed part
231 and second connecting portion 232.The C-shaped indentations in cross section of second fixed part 231, the second fixed part 231 are slided by several
Silk 8 is fixed on the end of the second lateral keel 21, and then the second connector 23 is fixed on the second wall block 2.Second connection
Portion 232 is fixed on the side of the second fixed part 231 and deviates from C-shaped recess, and second connecting portion 232 and the second lateral keel 21 are flat
OK, the screwed hole for extending vertically through its upper and lower surface is provided among second connecting portion 232.Second wall 22 is poured with building packing material
Note inside and outside, the 2 overall knot of the second wall block of the second wall 22 guarantee in the second lateral keel 21 and the second connector 23
The integrality of structure.
Second wall block 2 and the relative side of the first wall block 1 to assem-bly face, the assem-bly facing of two wall blocks protrude above and
The body fit of depression.
During the first wall block 1 and the second wall block 2 to be assembled to fixation, worker is relative with assem-bly facing for the two
Two wall blocks are spliced in direction, and the upper and lower surface of two wall blocks is respectively at same plane, ensure the planarization of wall.
The screwed hole allowed simultaneously on the screwed hole in first connecting portion 132 and the second connector 23 is concentric, and in first connecting portion 132
Sealing strip 4 is set between second connecting portion 232, fastening screw 3 is screwed afterwards and is fixed.
Worker screws fastening screw 3, the priority of fastening screw 3 is passed through the screwed hole of first connecting portion 132, seal and
The screwed hole of two connecting portions 232, and then fixed first connecting portion 132 and second connecting portion 232.Now sealing strip 4 is squeezed power
And elastic deformation, the gap filling between first connecting portion 132 and second connecting portion 232 is sealed, sealing strip 4, which also acts as, to be subtracted
Shake, waterproof and other effects.
Two foam rods 6 are provided between the assem-bly facing of first wall block 1 and second wall block 2, foam rods 6 are distinguished
Close to the upper and lower surface of wall.In spliced wall block, foam rods 6 are squeezed power and produce elastic deformation, will connect
Space filling sealing at seam, improve the sealing effectiveness of wall block seam crossing.
Filled with foaming gap filler 5 in gap between foam rods 6 and sealing strip 4.The gap filler 5 that foams has waterproof, resistance to
Expand with heat and contract with cold, be heat-insulated, sound insulation and fire-retardant effect.
Structure glue 7 is filled with gap between foam rods 6 and surface of wall, structure glue 7 is used for wall block junction
Surface it is floating.Structure glue 7 can bear larger load, and ageing-resistant, endurance, corrosion-resistant, stable performance.Use structure glue
7 both ensure that the profile pattern of attachment structure, improve wall bulk strength, rigidity and stability, and easy construction, work again
Phase is short, can save engineering time and fund cost.
Sealing strip 4, foaming gap filler 5, foam rods 6 and structure glue 7 are connected, by the first wall block 1 and the second wall
Gap between block 2 is stuffed entirely with and sealed, and ensures the sealing of the seam crossing of attachment structure.
This specific embodiment is only that it is not to limitation of the present utility model, ability to explanation of the present utility model
Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but
As long as all protected in right of the present utility model by Patent Law.
Claims (9)
1. a kind of attachment structure of assembled architecture wall block, it is characterized in that:Including the first wall block(1)With the second wall block
(2), first wall block(1)With second wall block(2)On be respectively fixed with built-in fitting, two built-in fittings pass through
Fixed mechanism is fixedly connected.
2. a kind of attachment structure of assembled architecture wall block according to claim 1, it is characterized in that:First wall
Block(1)Including the first lateral keel(11), second wall block(2)Including the second lateral keel(21), described first laterally
Keel(11)With the second lateral keel(21)It is lightgage steel joist.
3. a kind of attachment structure of assembled architecture wall block according to claim 2, it is characterized in that:First wall
Block(1)On built-in fitting be the first connector(13), first connector(13)Including the first fixed part(131)Connect with first
Socket part(132), first fixed part(131)Pass through some stripped threads(8)It is fixedly arranged on first lateral keel(11)Centre, institute
State first connecting portion(132)With first lateral keel(11)It is parallel.
4. a kind of attachment structure of assembled architecture wall block according to claim 3, it is characterized in that:Second wall
Block(2)On built-in fitting be the second connector(23), second connector(23)Including the second fixed part(231)Connect with second
Socket part(232), second fixed part(231)Pass through some stripped threads(8)It is fixedly arranged on second lateral keel(21)Centre, institute
State second connecting portion(232)With second lateral keel(21)It is parallel.
5. a kind of attachment structure of assembled architecture wall block according to claim 4, it is characterized in that:The fixed mechanism
For fastening screw(3), the first connecting portion(132)With the second connecting portion(232)Pass through the fastening screw(3)It is fixed
Connection.
6. a kind of attachment structure of assembled architecture wall block according to claim 5, it is characterized in that:First connection
Portion(132)And second connecting portion(232)Between be provided with sealing strip(4).
7. a kind of attachment structure of assembled architecture wall block according to claim 6, it is characterized in that:First wall
Block(1)With second wall block(2)Connection gap between be provided with foam rods close to surface of wall(6).
8. a kind of attachment structure of assembled architecture wall block according to claim 7, it is characterized in that:The foam rods
(6)With the sealing strip(4)Between be provided with foaming gap filler(5).
9. a kind of attachment structure of assembled architecture wall block according to claim 7, it is characterized in that:The foam rods
(6)Structure glue is provided between the surface of wall(7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720329982.8U CN207063176U (en) | 2017-03-30 | 2017-03-30 | A kind of attachment structure of assembled architecture wall block |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720329982.8U CN207063176U (en) | 2017-03-30 | 2017-03-30 | A kind of attachment structure of assembled architecture wall block |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207063176U true CN207063176U (en) | 2018-03-02 |
Family
ID=61501135
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720329982.8U Expired - Fee Related CN207063176U (en) | 2017-03-30 | 2017-03-30 | A kind of attachment structure of assembled architecture wall block |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207063176U (en) |
-
2017
- 2017-03-30 CN CN201720329982.8U patent/CN207063176U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108797847A (en) | A kind of assembled steel frame wall filled with masonry structural system and its construction method | |
CN208934197U (en) | The plug-in filling wall construction system of steel frame and assembled filled-in panel | |
CN207063176U (en) | A kind of attachment structure of assembled architecture wall block | |
CN206873716U (en) | A kind of antidetonation type unitized curtain wall | |
CN203769090U (en) | Structural frame and connection structure of lapping position of beam column frame | |
CN105421615A (en) | Prefabricated type shear wall horizontal bolt connecting structure | |
CN206143933U (en) | Assembled steel core concrete column H shaped steel roof beam is from power consumption connected node that restores to throne | |
CN203514531U (en) | Square steel tube concrete column and steel beam node connecting structure with internal diaphragms | |
CN205712705U (en) | The assembled cell cube of a kind of ALC external wall | |
CN202064488U (en) | Steel beam-reinforced concrete floor system | |
CN206769085U (en) | A kind of wall connecting point structure of assembled architecture | |
CN204059840U (en) | A kind of dry-hang keel installation structure | |
CN207739478U (en) | A kind of assembled architecture attachment device | |
CN206467883U (en) | Insulation wallboard and heat-preserving heat-insulating wall | |
CN210798003U (en) | Stone curtain wall wrapping column structure | |
CN211949549U (en) | Building scaffold wall connecting component | |
CN206015960U (en) | A kind of fixed structure of wall element | |
CN205617605U (en) | Compound interior wall structure of light gauge steel | |
CN203878779U (en) | Rectangular concrete-filled steel tube column and I-steel beam rebar penetrating type joint | |
CN205669284U (en) | The cast-in-place Integral Steel frame wall filled with masonry system that a kind of spring connects | |
CN214220710U (en) | Maintenance structure of building steel roofing | |
CN203625776U (en) | Arch spring anchoring structure for concrete-filled steel tube arch bridge | |
CN211200728U (en) | Connecting node structure of precast concrete externally-hung wallboard | |
CN207567989U (en) | Component is stitched in prefabricated reinforced concrete wall panel horizontal connection | |
CN202731037U (en) | Curtain wall framework structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180302 |