CN207062783U - It is easy to the job platform of storage for square or oval bridge pier assembled - Google Patents

It is easy to the job platform of storage for square or oval bridge pier assembled Download PDF

Info

Publication number
CN207062783U
CN207062783U CN201720995170.7U CN201720995170U CN207062783U CN 207062783 U CN207062783 U CN 207062783U CN 201720995170 U CN201720995170 U CN 201720995170U CN 207062783 U CN207062783 U CN 207062783U
Authority
CN
China
Prior art keywords
angle
axis
support
arm
anyhow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720995170.7U
Other languages
Chinese (zh)
Inventor
何华强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Teng Sheng Die Base Technology Co Ltd
Original Assignee
Guangdong Teng Sheng Die Base Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Teng Sheng Die Base Technology Co Ltd filed Critical Guangdong Teng Sheng Die Base Technology Co Ltd
Priority to CN201720995170.7U priority Critical patent/CN207062783U/en
Application granted granted Critical
Publication of CN207062783U publication Critical patent/CN207062783U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses the job platform for being easy to storage for square or oval bridge pier assembled, including platform panel;There is the bearing support perpendicular to the multi-point support face of Z axis;The bearing support includes perpendicular to y-axis, along the symmetrical a pair of planar frame of x-axis and is placed in the right angled triangle suspension scaffold at the plane rack both ends, right angled triangle suspension scaffold has first arm of angle and the first vertical arm of angle anyhow, plane rack includes rectangular frame, middle part support column of the affixed N bars parallel to z-axis in the rectangular frame, N >=1, the first vertical arm of angle and the removable ground connection in end face at the rectangular frame both ends fix as one;For right angle trigonometry support frame perpendicular to x-axis, the right angle trigonometry support frame has second arm of angle and the second vertical arm of angle anyhow, and the second vertical arm of angle fixes as one with the removable ground connection of the middle part support column;Connector adjustably fixes as one a pair of planar frame distance;The arm of angle and the horizontal top surface for choosing support rod form multi-point support face anyhow for the arm of angle, second anyhow for rectangular frame, first.

Description

It is easy to the job platform of storage for square or oval bridge pier assembled
Technical field
It the utility model is related to a kind of job platform for being easy to storage for square or oval bridge pier assembled.
Background technology
During the build of high ferro and urban rail, set supporting pier stud by two circumscribed circular diameters at 1.8~2.2 meters on the way In the range of column and be placed in middle part a connection beam and be placed in top a bent cap form, column cross-section for ellipse Or rectangle, there are multiple reserved through hole during pouring template column.Support after the completion of pier stud cast is built, it is necessary to carry out sandbag or water polo Precompressed checks whether column and bent cap are deformed shrinking or settling, the job platform of traditional detection column and bent cap, need to be Scaffold frame is built in ground upwards around column, and the height of column is higher, and scaffold frame level is more, required built expense It is bigger.Store and assemble and disassemble and be very inconvenient.
The content of the invention
Technical problem to be solved in the utility model, which is to provide a kind of arbitrary height in square or oval bridge pier, to be made With, the operation horizontal for being used for square or oval bridge pier assembled and being easy to storage saving cost, be easy to storage and transportation, be easy to assembling Platform.
Technical scheme is used by the utility model solves its technical problem:One kind is used for square or oval bridge pier dress The job platform for being easy to storage with formula includes platform panel, and the platform panel is perpendicular to Z axis;Bearing support, the bearing support have vertically In the multi-point support face of Z axis, the platform panel is laid on the multi-point support face;The bearing support is included perpendicular to y-axis, along x-axis Symmetrical a pair of planar frame and the right angled triangle suspension scaffold for being placed in the plane rack both ends, the right angled triangle suspension scaffold with The plane is placed on same plane, and the right angled triangle suspension scaffold has first arm of angle and the first vertical arm of angle anyhow, the plane rack Including rectangular frame, affixed N bars are parallel to the middle part support column of z-axis in the rectangular frame, and N >=1, the first vertical arm of angle is with being somebody's turn to do The removable ground connection in end face at rectangular frame both ends fixes as one;The bearing support also includes the right angle to be fixed as one with the plane rack Triangle support frame, for the right angle trigonometry support frame perpendicular to x-axis, the right angle trigonometry support frame has second arm of angle and second perpendicular anyhow Right-angle side, the second vertical arm of angle fix as one with the removable ground connection of the middle part support column;The bearing support also includes connector, should Connector adjustably fixes as one a pair of plane rack distances;Horizontal to choose support rod, the horizontal support rod of choosing is parallel to y-axis and this First anyhow the arm of angle fix as one;Second the arm of angle and horizontal support rod of choosing are directed to the direction away from the bearing support anyhow for this;Should The top surface of rectangular frame, first anyhow arm of angle top surface, second anyhow arm of angle top surface and it is horizontal choose support rod top surface form together it is described Multi-point support face.
Beneficial effect:In above-mentioned technical proposal, connector adjustably fixes as one a pair of planar frame distance so that one The square or oval column of bridge pier can be clipped to plane rack, and vacantly rests on the carrying for the reserved through hole for being fixed on column On outrigger, using original reserved through hole on column, arbitrary height can support and fix the job platform on column, take In generation, needs to build the mode of scaffold supporting platform upwardly from ground in the prior art, the height for solving prior art central post Degree it is higher, scaffold frame level is more, required built expense is bigger the problem of, therefore the technical program be used for it is square or ellipse Circular pier assembled is easy to the job platform of storage, and arbitrary height can be used, save cost on column;In storage and transportation When, after taking connector apart, the detachable two big parts into based on plane rack of job platform, will be straight on this two big part Angle triangle suspension scaffold and right angle trigonometry support frame are unloaded down, sort out stack respectively, be easy to store and transport time save space.Make Used time, affixed on plane rack can will be right angled triangle suspension scaffold and right angle trigonometry support frame are assembled on the ground in building site On big part, then the carrying outrigger for the reserved through hole that this two big part is lifted on into column, close up into job platform, assembling side Just.
As a concrete scheme of above-mentioned technical proposal, first method of the first vertical arm of angle welding one perpendicular to x-axis Blue plate, the rectangular frame both ends be respectively welded one perpendicular to x-axis second flange plate, the first flange plate and second flange plate Joint is connected through a screw thread to be integrated.Due to flange accurate positioning, high mechanical strength is connected, dismounting is convenient, makes job platform Dismounting more improve effect and intensity.
As a concrete scheme to above-mentioned technical proposal, the second vertical arm of angle connects with middle part supporting male screw Connect.
As a concrete scheme to above-mentioned technical proposal, connector is parallel to the screw thread reinforcing pull rod of y-axis.Screw-thread steel The characteristics of pull bar utilizes screw thread hardness of steel high, makes safety coefficient higher.
As the further improvement to above-mentioned technical proposal, in addition to guard rail, the guard rail by perpendicular railing and Horizontal bar bar is formed, and the perpendicular railing lower end is fixed on the multi-point support face.
Brief description of the drawings
Fig. 1 is the schematic diagram for supporting pier stud;
Fig. 2 is use state schematic perspective view of the bearing support of embodiment one on column;
Fig. 3 is use state schematic front view of the bearing support of embodiment one on column;
Fig. 4 is use state schematic top plan view of the bearing support of embodiment one on column;
Fig. 5 is one structure decomposition figure of the present utility model of embodiment;
Fig. 6 is the structure decomposition figure of the bearing support of embodiment one;
Fig. 7 is one stereogram of the present utility model of embodiment;
Fig. 8 is use state schematic top plan view of the bearing support of embodiment two on column.
Embodiment
The utility model is further illustrated with reference to the accompanying drawings and examples.
Embodiment one
Referring to Fig. 1, during the build of high ferro and urban rail, the supporting pier stud 3 set on the way is by two circumscribed circular diameters Column 2 in the range of 1.8~2.2 meters and it is placed in a connection beam 31 at middle part and is placed in the bent cap 32 at top and form, There is reserved through hole 21 during pouring template column 2.
Referring to Fig. 2, the oval bridge pier assembled that is used for of the present embodiment is easy to the job platform 1 of storage to be used to support pier stud Or the column 2 on construction site.
Referring to Fig. 3, Fig. 4, reserved through hole 21 is parallel to y-axis, and in reserved through hole 21, fixed carrying outrigger 22, installation makes Used time, it is easy to the job platform 1 of storage to be held on for oval bridge pier assembled on carrying outrigger 22 and fixed.This implementation The cross section of the column 2 of example is ellipse.
Referring to Fig. 5, the job platform 1 for being easy to storage for oval bridge pier assembled includes platform panel 11, flat surface Plate 11 is perpendicular to Z axis;Bearing support 12, bearing support 12 has to be laid on more perpendicular to the multi-point support face 121 of Z axis, platform panel 11 On dot point face 121;Bearing support 12 includes perpendicular to y-axis, along the symmetrical a pair of planar frame 13 of x-axis and is placed in plane rack 13 The right angled triangle suspension scaffold 14 at both ends, right angled triangle suspension scaffold 14 are placed in same plane with plane rack 13.Bearing support 12 is also Including connector 16, connector 16 is by a pair of planar frame 13 apart from adjustably fixing as one;Connector 16 is parallel to y-axis Screw thread reinforcing pull rod.Screw thread reinforcing pull rod utilizes the characteristics of screw-thread steel high mechanical strength, makes safety coefficient cost performance higher.Connector 16 By a pair of planar frame 13 apart from adjustably fixing as one, seen with reference to Fig. 3, Fig. 4 so that a pair of planar frame 13 can clip cross section It is the column 2 of ellipse, and vacantly rests on the carrying outrigger 22 being fixed in the reserved through hole 21 of column 2, utilizes column 2 Original reserved through hole 21, arbitrary height can support simultaneously fixed operation platform on column 2.Also include guard rail 18, Guard rail 18 is made up of perpendicular railing 181 and horizontal bar bar 182, and the perpendicular lower end of railing 181 is fixed on multi-point support face 121.
Referring to Fig. 6, right angled triangle suspension scaffold 14 has the first 141 and first vertical arm of angle 142 of the arm of angle anyhow, plane rack 13 Including rectangular frame 131, affixed N bars are parallel to the middle part support column 132 of z-axis, N >=1, the first vertical angle in rectangular frame 131 The removable ground connection in end face on side 142 and the both ends of rectangular frame 131 fixes as one, and the first vertical welding one of the arm of angle 142 is perpendicular to x-axis First flange plate 1421, the both ends of rectangular frame 131 be respectively welded one perpendicular to x-axis second flange plate 1311, first flange Plate 1421 is connected through a screw thread Joint with second flange plate 1311 and is integrated.Due to flange accurate positioning, mechanical strength is connected Height, dismounting is convenient, the first vertical arm of angle 142 and the dismounting of rectangular frame 131 is more improved effect and intensity.Bearing support 12 also wraps The right angled triangle support frame 15 to be fixed as one with plane rack 13 is included, right angle trigonometry support frame 15 is perpendicular to x-axis, right angle trigonometry Support frame 15 has second, and the 151 and second vertical arm of angle 152 of the arm of angle, the second vertical arm of angle 152 and middle part support column 132 are removable anyhow Ground connection fixes as one;The second vertical arm of angle 152 is threadedly coupled with middle part support column 132.It is horizontal choose support rod 17 parallel to y-axis with First anyhow the arm of angle 141 fix as one;Seen with reference to Fig. 5, second the arm of angle 151 and horizontal support rod 17 of choosing are directed to away from branch anyhow The direction of bolster 12;The top surface of the arm of angle 141, second top surface of the arm of angle 151 and horizontal are chosen anyhow anyhow for the top surface of rectangular frame 131, first The top surface of support rod 17 forms multi-point support face 121 together.
Fig. 5 is reviewed, in storage and transportation, after taking connector 16 apart, job platform is detachable into based on plane rack 13 Two big parts, review Fig. 6, unloaded by the right angled triangle suspension scaffold 14 on this two big part and right angle trigonometry support frame 15 Come, sort out stack respectively, be easy to store and transport time save space.In use, right angled triangle can be hanged on the ground in building site It is big part that builder's jack 14 and right angle trigonometry support frame 15, which are assembled in affixed on plane rack 13, then this two big part is lifted on into carrying On outrigger 22, close up into job platform, it is easy to assembly, as shown in Figure 7.
Embodiment two
The present embodiment and embodiment one are essentially identical, and its difference is:The cross section of column is rectangle.As shown in Figure 8.
Described is only preferred embodiment of the present utility model, is not limited to the utility model, although with reference to before State embodiment the utility model is described in detail, for those skilled in the art, it still can be to preceding State the technical scheme described in each embodiment to modify, or equivalent substitution is carried out to which part technical characteristic, it is all at this Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc., the utility model should be included in Protection domain within.

Claims (6)

1. a kind of job platform for being easy to storage for square or oval bridge pier assembled, including
Platform panel, the platform panel is perpendicular to Z axis;
Bearing support, the bearing support has is laid on the multi-point support face perpendicular to the multi-point support face of Z axis, the platform panel On;
Its feature is:
The bearing support includes perpendicular to y-axis, along the symmetrical a pair of planar frame of x-axis and is placed in the straight of the plane rack both ends Angle triangle suspension scaffold, the right angled triangle suspension scaffold are placed on same plane with the plane, and the right angled triangle hangs Builder's jack has first arm of angle and a first vertical arm of angle anyhow, and the plane rack includes rectangular frame, affixed N bars in the rectangular frame It is solid parallel to the middle part support column of z-axis, N >=1, the first vertical arm of angle and the removable ground connection in end face at the rectangular frame both ends It is connected in one;
The bearing support also includes the right angled triangle support frame to be fixed as one with the plane rack, the right angle trigonometry support For frame perpendicular to x-axis, the right angle trigonometry support frame has second arm of angle and a second vertical arm of angle anyhow, the second vertical arm of angle with The removable ground connection of middle part support column fixes as one;
The bearing support also includes connector, and the connector adjustably fixes as one a pair of plane rack distances;
It is horizontal to choose support rod, it is described it is horizontal choose support rod parallel to y-axis with described first anyhow the arm of angle fix as one;
Described second the arm of angle and horizontal support rod of choosing are directed to the direction away from the bearing support anyhow;
Arm of angle top surface and horizontal support rod top surface of choosing are formed anyhow for arm of angle top surface, second anyhow for the top surface of the rectangular frame, first The multi-point support face.
2. the job platform according to claim 1 for being easy to storage for square or oval bridge pier assembled, its feature It is:Perpendicular to the first flange plate of x-axis, the rectangular frame both ends are respectively welded one and hung down for the first vertical arm of angle welding one Directly it is connected through a screw thread Joint in the second flange plate of x-axis, the first flange plate with second flange plate and is integrated.
3. the job platform according to claim 1 for being easy to storage for square or oval bridge pier assembled, its feature It is:The second vertical arm of angle is threadedly coupled with the middle part support column.
4. the operation horizontal for being used for square or oval bridge pier assembled and being easy to storage according to any one of claims 1 to 3 Platform, it is characterised in that:The bearing support is made by rectangle section bar or steel angle profile.
5. the operation horizontal for being used for square or oval bridge pier assembled and being easy to storage according to any one of claims 1 to 3 Platform, it is characterised in that:The connector is parallel to the screw thread reinforcing pull rod of y-axis.
6. the operation horizontal for being used for square or oval bridge pier assembled and being easy to storage according to any one of claims 1 to 3 Platform, it is characterised in that:Also include guard rail, the guard rail is made up of perpendicular railing and horizontal bar bar, the perpendicular railing lower end It is fixed on the multi-point support face.
CN201720995170.7U 2017-08-09 2017-08-09 It is easy to the job platform of storage for square or oval bridge pier assembled Active CN207062783U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720995170.7U CN207062783U (en) 2017-08-09 2017-08-09 It is easy to the job platform of storage for square or oval bridge pier assembled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720995170.7U CN207062783U (en) 2017-08-09 2017-08-09 It is easy to the job platform of storage for square or oval bridge pier assembled

Publications (1)

Publication Number Publication Date
CN207062783U true CN207062783U (en) 2018-03-02

Family

ID=61520298

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720995170.7U Active CN207062783U (en) 2017-08-09 2017-08-09 It is easy to the job platform of storage for square or oval bridge pier assembled

Country Status (1)

Country Link
CN (1) CN207062783U (en)

Similar Documents

Publication Publication Date Title
CN207933894U (en) A kind of bridge double-limb Thin-Wall Piers pier stud reinforcing bar binding device
CN207062783U (en) It is easy to the job platform of storage for square or oval bridge pier assembled
CN103866692A (en) Novel assembling method for bent cap bearing frame
CN210918296U (en) Square steel pipe sleeve fixing device
CN205637119U (en) Connection structure of steel pipe concrete pillar and reinforced concrete girders
CN110076468B (en) Secondary truss installation method and temporary fixing device thereof
CN204040437U (en) Cantilever tripod and single protective frame system of encorbelmenting
CN104499435B (en) Bracket for mounting self-anchored cable-stayed bridge cable-stayed saddle base
CN107881914B (en) Wire-dividing tube type cable saddle back field assembly type positioning device and assembly method
CN207619847U (en) Column and Coping Construction assembled adjustable operating platform
CN202766974U (en) Bent cap bearing frame without full framing
CN213448902U (en) Pre-buried box steel bracket structure
CN203307733U (en) Construction platform system of concrete pier of viaduct
CN204418027U (en) A kind of bracket of the cable saddle floor installation that falls apart for self-anchored suspension bridge
CN211815625U (en) Accurate positioning device for connecting embedded steel bars between assembled bridge upright post and bearing platform
CN103628727A (en) Electric power supporting frame
CN208455656U (en) A kind of anchor ear support device
CN204645668U (en) The top support structure of shape steel support installed by a kind of rack
CN209367607U (en) A kind of mounting structure that people's goods elevator attached wall lengthening rods are fixed
CN202164547U (en) Bracket system for concrete pouring of bridge contact network platform
CN205421871U (en) On --spot elevation measuring tool of construction
CN112095464A (en) Anchoring connection device for precast concrete bridge deck of steel-concrete composite beam
CN110847011A (en) Steel trestle bailey sheet fixing device and fixing method thereof
CN112227681A (en) Novel socket key groove type formwork support, formwork system and building method thereof
CN205296397U (en) Huge node field weld construction platform of box steel truss polylinker

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant