- CN207062740U CN207062740U CN201720722253.9U CN201720722253U CN207062740U CN 207062740 U CN207062740 U CN 207062740U CN 201720722253 U CN201720722253 U CN 201720722253U CN 207062740 U CN207062740 U CN 207062740U
- Authority
- CN
- China
- Prior art keywords
- buoyancy tank
- locating rod
- sleeve pipe
- tank body
- combined
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of novel bridge floating box structure,Including columnar buoyancy tank body,The inside of the buoyancy tank body has the inner chamber for providing buoyancy,There is the plane of an assembling pedal at the top of the buoyancy tank body,The bottom symmetrical of the buoyancy tank body is provided with two connecting poles,The outer ring opening position of the connecting pole is provided with through hole,Steel cable is combined between two connecting poles,Knotting is fixed after the both ends of the steel cable pass through the through hole,A concrete column has been poured in riverbed,A ring body has been poured at the top of the concrete column,The ring body is combined with drawstring,That one end of the drawstring away from the ring body is provided with a slip ring,Sleeve pipe is vertically provided with the both sides opening position of the buoyancy tank body,Locating rod is combined with described sleeve pipe,In the lower end insertion riverbed of the locating rod,The upper end of the locating rod is extended to outside described sleeve pipe;Present apparatus Stability Analysis of Structures, gentle support can be formed.
Description
Technical field
It the utility model is related to a kind of novel bridge floating box structure.
Background technology
Pontoon bridge, refer to and replace bridge pier with ship or buoyancy tank, the bridge kept afloat.Army is using the military floating of standard equipment spelling group
Bridge, then claim the bridge of boats.
Pontoon bridge of the prior art, the structure of the buoyancy tank of its support is relatively simple, in the case of by water impact,
Irregular motion by a relatively large margin can occur for buoyancy tank, cause bed rearrangement pontoon bridge to rock, and walking is more difficult, there is overboard risk.
Based on above mentioned problem, it is desirable to provide a kind of Stability Analysis of Structures, the novel bridge floating box structure of gentle support can be formed.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of Stability Analysis of Structures, can form the new of gentle support
Bridge floating box structure.
The utility model is achieved through the following technical solutions:
A kind of novel bridge floating box structure, including columnar buoyancy tank body, the inside of the buoyancy tank body, which has, to be provided
The inner chamber of buoyancy, there is the plane of an assembling pedal at the top of the buoyancy tank body, in the buoyancy tank body
Bottom symmetrical is provided with two connecting poles, and the outer ring opening position of the connecting pole is provided with through hole, two connecting poles it
Between be combined with steel cable, the both ends of the steel cable are passed through to knot after the through hole and fixed, and a concrete column has been poured in riverbed,
A ring body is poured at the top of the concrete column, the ring body is combined with drawstring, that away from the ring body of the drawstring
One end is provided with a slip ring, and the steel cable passes through the slip ring, and set is vertically provided with the both sides opening position of the buoyancy tank body
Pipe, locating rod is combined with described sleeve pipe, the lower end of the locating rod is inserted in riverbed, and the upper end of the locating rod extends to
Outside described sleeve pipe.
Preferably, armrest assembly is combined between two adjacent locating rods, the armrest assembly includes two sets
Pipe, and welding are arranged on the bar between two described sleeve pipes, and described sleeve pipe is set in the outside of the locating rod, the set
Screw is combined between pipe and the locating rod, protection can be provided in the both sides of pontoon bridge by set armrest assembly, subtract
Few overboard accident.
Preferably, a spacing ball is connected with the threaded upper ends of the locating rod, the sphere diameter of the spacing ball is more than described
The internal diameter of sleeve pipe.
Preferably, the length that the concrete column is cast in riverbed is not less than 100cm.
Preferably, the capacity of the inner chamber is 1-3m3.
The beneficial effects of the utility model are:, can be in buoyancy tank body by the cooperation of steel cable and drawstring in the present apparatus
A lower limit formed below, when the support failure of locating rod, buoyancy tank can be held by drawstring, avoid buoyancy tank from floaing, really
The reliability of whole pontoon structure is protected, by setting locating rod so that buoyancy tank can only move up and down, even if stormy waves is larger, buoyancy tank
Floating action also more rule, convenient walking, reduce overboard probability, the structure of the present apparatus is relatively simple, and cost is more low
It is honest and clean, it is adapted to promote the use of.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art
Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are only
It is some embodiments of the utility model, for those of ordinary skill in the art, is not paying the premise of creative work
Under, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is structural representation of the present utility model;
Fig. 2 is sectional view at A-A of the present utility model;
Fig. 3 is the top view of armrest assembly.
Embodiment
All features disclosed in this specification, or disclosed all methods or during the step of, except mutually exclusive
Feature and/or step beyond, can combine in any way.
This specification(Including any accessory claim, summary and accompanying drawing)Disclosed in any feature, except non-specifically chatting
State, can alternative features equivalent by other or with similar purpose replaced.I.e., unless specifically stated otherwise, each feature
It is an example in a series of equivalent or similar characteristics.
A kind of novel bridge floating box structure as shown in Figure 1, Figure 2 and Figure 3, including columnar buoyancy tank body 1, it is described floating
The inside of case body 1 has the inner chamber 101 for providing buoyancy, has an assembling pedal at the top of the buoyancy tank body 1
Plane 102, the bottom symmetrical of the buoyancy tank body 1 is provided with two connecting poles 3, the outer ring position of the connecting pole 3
Place is provided with through hole 301, and steel cable 4 is combined between two connecting poles 3, and the both ends of the steel cable 4 pass through the through hole
Knotting and fix after 301, a concrete column 5 has been poured in riverbed, the top of the concrete column 5 has poured a ring body 6,
The ring body 6 is combined with drawstring 7, and that one end of the drawstring 7 away from the ring body 6 is provided with a slip ring 8, and the steel cable 4 is worn
The slip ring 8 is crossed, sleeve pipe 9 is vertically provided with the both sides opening position of the buoyancy tank body 1, it is fixed to be combined with described sleeve pipe 9
Position bar 10, the lower end of the locating rod 10 are inserted in riverbed, and the upper end of the locating rod 10 is extended to outside described sleeve pipe 9.
A preferred embodiment in the utility model, armrest assembly is combined between two adjacent locating rods 10
11, the armrest assembly 11 includes two sleeve pipes 12, and welding is arranged on the bar 13 between two described sleeve pipes 12, described
Sleeve pipe 12 is set in the outside of the locating rod 13, and screw 14 is combined between described sleeve pipe 12 and the locating rod 10, is passed through
Set armrest assembly can provide protection in the both sides of pontoon bridge, reduce overboard accident.
A preferred embodiment in the utility model, a spacing ball is connected with the threaded upper ends of the locating rod 10
15, the sphere diameter of the spacing ball 15 is more than the internal diameter of described sleeve pipe 12.
A preferred embodiment in the utility model, the length that the concrete column 5 is cast in riverbed are not less than
100cm。
A preferred embodiment in the utility model, the capacity of the inner chamber 101 is 1-3m3.
The beneficial effects of the utility model are:, can be in buoyancy tank body by the cooperation of steel cable and drawstring in the present apparatus
A lower limit formed below, when the support failure of locating rod, buoyancy tank can be held by drawstring, avoid buoyancy tank from floaing, really
The reliability of whole pontoon structure is protected, by setting locating rod so that buoyancy tank can only move up and down, even if stormy waves is larger, buoyancy tank
Floating action also more rule, convenient walking, reduce overboard probability, the structure of the present apparatus is relatively simple, and cost is more low
It is honest and clean, it is adapted to promote the use of.
It is described above, only specific embodiment of the present utility model, but the scope of protection of the utility model is not limited to
In this, any change or replacement expected without creative work, should all cover within the scope of protection of the utility model.
Therefore, the scope of protection of the utility model should be determined by the scope of protection defined in the claims.
Claims (5)
- A kind of 1. novel bridge floating box structure, it is characterised in that:Including columnar buoyancy tank body, the inside of the buoyancy tank body With the inner chamber for providing buoyancy, there is the plane of an assembling pedal at the top of the buoyancy tank body, floated described The bottom symmetrical of case body is provided with two connecting poles, and the outer ring opening position of the connecting pole is provided with through hole, described in two Steel cable is combined between connecting pole, the both ends of the steel cable pass through knotting fixation after the through hole, it is mixed that one has been poured in riverbed Native column is coagulated, a ring body has been poured at the top of the concrete column, the ring body is combined with drawstring, and the drawstring is away from described That one end of ring body is provided with a slip ring, and the steel cable passes through the slip ring, vertical in the both sides opening position of the buoyancy tank body Be provided with sleeve pipe, be combined with locating rod in described sleeve pipe, in the lower end insertion riverbed of the locating rod, the locating rod it is upper End is extended to outside described sleeve pipe.
- 2. novel bridge floating box structure according to claim 1, it is characterised in that:Between two adjacent locating rods Armrest assembly is combined with, the armrest assembly includes two sleeve pipes, and welding is arranged on the bar between two described sleeve pipes, Described sleeve pipe is set in the outside of the locating rod, and screw is combined between described sleeve pipe and the locating rod.
- 3. novel bridge floating box structure according to claim 2, it is characterised in that:Connect in the threaded upper ends of the locating rod A spacing ball is connected to, the sphere diameter of the spacing ball is more than the internal diameter of described sleeve pipe.
- 4. novel bridge floating box structure according to claim 1, it is characterised in that:The concrete column is cast in riverbed Interior length is not less than 100cm.
- 5. novel bridge floating box structure according to claim 1, it is characterised in that:The capacity of the inner chamber is 1-3m3.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720722253.9U CN207062740U (en) | 2017-06-21 | 2017-06-21 | A kind of novel bridge floating box structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720722253.9U CN207062740U (en) | 2017-06-21 | 2017-06-21 | A kind of novel bridge floating box structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207062740U true CN207062740U (en) | 2018-03-02 |
Family
ID=61509048
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720722253.9U Active CN207062740U (en) | 2017-06-21 | 2017-06-21 | A kind of novel bridge floating box structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207062740U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112853921A (en) * | 2021-03-24 | 2021-05-28 | 广州隆盛景观建设有限公司 | Landscape bridge structure and construction method |
-
2017
- 2017-06-21 CN CN201720722253.9U patent/CN207062740U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112853921A (en) * | 2021-03-24 | 2021-05-28 | 广州隆盛景观建设有限公司 | Landscape bridge structure and construction method |
CN112853921B (en) * | 2021-03-24 | 2022-08-05 | 广州隆盛景观建设有限公司 | Landscape bridge structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204527559U (en) | Semi-submersible offshore platform | |
CN202063242U (en) | Box type truss four-spar deep water platform system by using unsymmetrical soft cabins | |
CN203420289U (en) | Anti-icing structure of offshore wind turbine foundation | |
CN106759445A (en) | A kind of combined type bucket foundation with skirtboard and its construction method | |
CN103224016A (en) | Escape cabin of submersible | |
CN207062740U (en) | A kind of novel bridge floating box structure | |
US8146970B2 (en) | Recovery net | |
CN106428447A (en) | Ultra-large type multi-floating-body semi-submersible floating platform | |
CN103770914A (en) | Movable type marine tourism resort hotel | |
CN207843237U (en) | A kind of Hydrometeorology stabilizer | |
CN207607614U (en) | Marine floating facility stabilizer | |
CN206024883U (en) | Deep water net cage and double -barrelled reducing I -shaped frame thereof | |
CN202958466U (en) | Deepwater net cage H-shaped frame | |
US20120263543A1 (en) | Fully Constraint Platform in Deepwater | |
CN102991646A (en) | Gravity anchor and manufacturing methods thereof | |
CN205524857U (en) | Take how much truss -like stand platforms in oil storage tank | |
CN209686386U (en) | A kind of intectate waters steel-pipe pile can pull out anchor structure | |
CN214648910U (en) | Floating wind power platform | |
CN206928176U (en) | A kind of river surface pontoon bridge suspension support structure | |
CN204443640U (en) | The anti-string data buoyancy post flexible ecological environment-friendly type net cage swinging many case series connection of plate of band | |
CN107700450A (en) | A kind of mounting process of floating-supported type offshore wind farm mounting platform | |
CN206374934U (en) | A kind of oceanographic buoy | |
CN203452061U (en) | Large-sized ocean platform | |
CN207646703U (en) | A kind of Oil sucking device with support construction | |
CN207328757U (en) | A kind of gravity foundation of marine stretching anode system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180807 Address after: 223800 Suqian Suqian economic and Technological Development Zone, Jiangsu Province, 101 weeks ago, the office building of the neighborhood committee Patentee after: Jiangsu golden Yutong Construction Technology Group Co., Ltd. Address before: 311811 Mei Yuan village, Feng Qiao Town, Zhuji City, Shaoxing, Zhejiang Patentee before: Ye Meng |