CN207056237U - Tower for purifying waste gas - Google Patents

Tower for purifying waste gas Download PDF

Info

Publication number
CN207056237U
CN207056237U CN201720976346.4U CN201720976346U CN207056237U CN 207056237 U CN207056237 U CN 207056237U CN 201720976346 U CN201720976346 U CN 201720976346U CN 207056237 U CN207056237 U CN 207056237U
Authority
CN
China
Prior art keywords
tower
purification tower
cleaning
waste gas
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720976346.4U
Other languages
Chinese (zh)
Inventor
黄文伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meizhou Kexing Electronic Co Ltd
Original Assignee
Meizhou Kexing Electronic Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meizhou Kexing Electronic Co Ltd filed Critical Meizhou Kexing Electronic Co Ltd
Priority to CN201720976346.4U priority Critical patent/CN207056237U/en
Application granted granted Critical
Publication of CN207056237U publication Critical patent/CN207056237U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses Tower for purifying waste gas,Including purification tower,Shower nozzle regulating valve is provided with the left of the purification tower,And outtake tube is provided with the right side of purification tower,The preceding surface of the purification tower is provided with waste gas inlet,Cleaning water intaking valve is provided with below the shower nozzle regulating valve,The described one end of cleaning water intaking valve away from purification tower is provided with water circulating pump,The lower end of the water circulating pump is provided with cyclic water tank,Side of the cyclic water tank away from purification tower is provided with drainpipe,The one end of the outtake tube away from purification tower is provided with centrifugal blower,Purification tower bottom of the present utility model, which is provided with, rotates clean frame and cleaning brush,It can be rotated under the water slug of cleaning delivery port and purification body bottom is scrubbed,It ensure that the cleaning of purifying column bottom,Air inlet upper end of the present utility model, which is provided with uniform supply fan, can allow waste gas uniformly to be contacted with the packing layer of upper end,It is more preferable to absorb waste gas effect.

Description

Tower for purifying waste gas
Technical field
The utility model belongs to environmental technology field, and in particular to Tower for purifying waste gas.
Background technology
Tower for purifying waste gas is that the waste gas that factory, laboratory etc. give off is carried out into absorbing and filtering pernicious gas therein and had The equipment of evil material.
It is existing but existing Tower for purifying waste gas still has some irrational factors during absorption waste gas is carried out Some Tower for purifying waste gas are when in use:The impurity that the storage of waste water room of purification tower bottom is easily accumulated in waste gas and water body, can not Cleaning, influences whether the recovery of waste gas after impurities accumulation is excessive;When in use, gas and steam can not for existing Tower for purifying waste gas Uniformly preferably contact, causes waste gas to fully absorb, is discharged into air, pollutes air.
Utility model content
The purpose of this utility model is to provide Tower for purifying waste gas, to solve to propose purification tower bottom in above-mentioned background technology The impurity that easily accumulates in waste gas and water body of storage of waste water room, can not clean, waste gas is influenced whether after impurities accumulation is excessive Recovery;When in use, gas and steam uniformly can not be contacted preferably existing Tower for purifying waste gas, cause waste gas to inhale completely Receive, be discharged into air, pollute air the problem of.
To achieve the above object, the utility model provides following technical scheme:Tower for purifying waste gas, including purification tower, institute State and shower nozzle regulating valve is provided with the left of purification tower, and outtake tube is provided with the right side of purification tower, the purification tower Preceding surface be provided with waste gas inlet, cleaning water intaking valve, the cleaning water intaking valve are provided with below the shower nozzle regulating valve One end away from purification tower is provided with water circulating pump, and the lower end of the water circulating pump is provided with cyclic water tank, the recirculated water Side of the case away from purification tower is provided with drainpipe, and the upper end of the drainpipe is provided with draining valve, and the outtake tube is remote One end from purification tower is provided with centrifugal blower, and the upper end of the centrifugal blower is provided with discharge pipe, and the discharge pipe is remote One end of centrifugal blower is provided with rainhat, and the purification tower is internally provided with except steam layer, water spray pipe, packing layer, uniformly Supply fan, cleaning water inlet pipe, clean frame and cleaning brush are rotated, wherein the inside that the water removal vapour layer is arranged on purification tower is close The position on top, and except the lower end of steam layer is provided with water spray pipe, the water spray pipe is provided with away from the side except steam layer and filled out The bed of material, side of the described filler layer away from water spray pipe are provided with uniform supply fan, the uniformly supply fan away from packing layer one Side is provided with cleaning water inlet pipe, and the described one end of cleaning water inlet pipe away from uniform supply fan is provided with rotation clean frame, and cleans Water inlet pipe bottom is provided with cleaning delivery port, and the described one end of clean frame away from cleaning water inlet pipe that rotates is provided with cleaning brush, phase Catch bar is provided between the adjacent cleaning brush, one end of the close cleaning delivery port of the catch bar is provided with arc-shaped and pushed away Dynamic plate.
Preferably, the rotation clean frame is connected with cleaning water inlet pipe by axis of rotation.
Preferably, the catch bar is provided with eight altogether, and eight catch bars are evenly distributed on the adjacent cleaning brush Between.
Preferably, the arc-shaped pushing plate and catch bar are integral type structure.
Preferably, the purification tower is screwed with outtake tube by drive screw is fixedly connected.
Preferably, the water circulating pump is screwed with cyclic water tank by drive screw is fixedly connected.
Compared with prior art, the beneficial effects of the utility model are:
1st, purification tower bottom of the present utility model, which is provided with, rotates clean frame and cleaning brush, can be in cleaning delivery port Rotated under water slug and purification body bottom is scrubbed, ensure that the cleaning of purifying column bottom.
2nd, air inlet upper end of the present utility model, which is provided with uniform supply fan, can allow packing layer of the waste gas uniformly with upper end Contact, it is more preferable to absorb waste gas effect.
Brief description of the drawings
Fig. 1 is front view of the present utility model;
Fig. 2 is elevation cross-sectional view of the present utility model;
Fig. 3 is rotation clean frame partial structural diagram of the present utility model;
Fig. 4 is rotation clean frame top view of the present utility model;
Fig. 5 is rotation clean frame bottom surface structure schematic diagram of the present utility model;
Fig. 6 is rotation clean frame front view of the present utility model;
Fig. 7 is uniformly supply fan front view of the present utility model;
In figure:1- purification towers, 2- shower nozzles regulating valve, 3- waste gas inlets, 4- cleanings water intaking valve, 5- water circulating pumps, 6- Cyclic water tank, 7- draining valves, 8- drainpipes, 9- outtake tubes, 10- rainhats, 11- discharge pipes, 12- centrifugal blowers, 13- are removed Steam layer, 14- water spray pipes, 15- packing layers, the uniform supply fans of 16-, 17- cleanings water inlet pipe, 18- rotate clean frame, 19- cleanings Brush, 20- cleanings delivery port, 21- arc-shapeds pushing plate, 22- catch bars.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6 and Fig. 7 are referred to, the utility model provides following technical scheme:Waste gas is net Change tower, including purification tower 1, the left side of purification tower 1 is provided with shower nozzle regulating valve 2, and the right side of purification tower 1 is provided with out Airway 9, the preceding surface of purification tower 1 are provided with waste gas inlet 3, and the lower section of shower nozzle regulating valve 2 is provided with cleaning water intaking valve 4, the one end of cleaning water intaking valve 4 away from purification tower 1 is provided with water circulating pump 5, and the lower end of water circulating pump 5 is provided with cyclic water tank 6, side of the cyclic water tank 6 away from purification tower 1 is provided with drainpipe 8, and the upper end of drainpipe 8 is provided with draining valve 7, goes out conductance The one end of pipe 9 away from purification tower 1 is provided with centrifugal blower 12, and the upper end of centrifugal blower 12 is provided with discharge pipe 11, discharge pipe 11 one end away from centrifugal blower 12 are provided with rainhat 10, purification tower 1 be internally provided with except steam layer 13, water spray pipe 14, Packing layer 15, uniform supply fan 16, cleaning water inlet pipe 17, rotation clean frame 18 and cleaning brush 19, wherein except steam layer 13 is installed In the inside of purification tower 1 close to the position on top, and except the lower end of steam layer 13 is provided with water spray pipe 14, water spray pipe 14 is remote Side except steam layer 13 is provided with packing layer 15, side of the packing layer 15 away from water spray pipe 14 is provided with uniform supply fan 16, uniform side of the supply fan 16 away from packing layer 15 is provided with cleaning water inlet pipe 17, and cleaning water inlet pipe 17 is away from uniform air inlet One end of fan 16, which is provided with, rotates clean frame 18, and cleans the bottom of water inlet pipe 17 and be provided with cleaning delivery port 20, rotates clean frame 18 one end away from cleaning water inlet pipe 17 are provided with cleaning brush 19, and catch bar 22 is provided between adjacent cleaning brush 19, is promoted One end of the close cleaning delivery port 20 of bar 22 is provided with arc-shaped pushing plate 21.
In the present embodiment, it is preferred that rotate clean frame 18 and connected with cleaning water inlet pipe 17 by axis of rotation.
In the present embodiment, it is preferred that catch bar 22 is provided with eight altogether, and eight catch bars 22 be evenly distributed on it is adjacent Between cleaning brush 19.
In the present embodiment, it is preferred that arc-shaped pushing plate 21 and catch bar 22 are integral type structure.
In the present embodiment, it is preferred that purification tower 1 is screwed by drive screw with outtake tube 9 and is fixedly connected.
In the present embodiment, it is preferred that water circulating pump 5 is screwed by drive screw with cyclic water tank 6 and is fixedly connected.
Operation principle and process for using of the present utility model:After the utility model installs, it is new to first check for this practicality The installation fixation and security protection of type, then can uses, in use, clean frame 18 and cleaning water inlet pipe 17 will be rotated Connected by axis of rotation, purification tower 1 is screwed with outtake tube 9 by drive screw and is fixedly connected, by water circulating pump 5 are screwed by drive screw with cyclic water tank 6 and are fixedly connected.
Then, when needing to clean cleaning tower body 1 bottom, shower nozzle regulating valve 2 is closed, opens cleaning water intaking valve 4 With draining valve 7, the power switch of water circulating pump 5 is then opened, now cleans the water outlet of delivery port 20, and impact arc-shaped promotion Plate 21, arc-shaped pushing plate 21 drives and catch bar 22 rotates with clean frame 18 is rotated, and rotates clean frame 18 and drives cleaning brush 19 Rotation, cleaning brush 19 are scrubbed to cleaning bottom of towe end when rotated, when waste gas enters cleaning tower body by waste gas inlet 3 After 1, uniformly contacted under the intensive flabellum effect of uniform supply fan 16 with packing layer 15.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art, It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from principle of the present utility model and spirit, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (6)

1. Tower for purifying waste gas, including purification tower (1), it is characterised in that:Shower nozzle tune is provided with the left of the purification tower (1) Valve (2) is saved, and outtake tube (9) is provided with the right side of purification tower (1), the preceding surface of the purification tower (1) is provided with useless Gas air inlet (3), cleaning water intaking valve (4) is provided with below the shower nozzle regulating valve (2), and the cleaning water intaking valve (4) is remote One end of purification tower (1) is provided with water circulating pump (5), and the lower end of the water circulating pump (5) is provided with cyclic water tank (6), institute State side of the cyclic water tank (6) away from purification tower (1) and be provided with drainpipe (8), the upper end of the drainpipe (8) is provided with row Water valve (7), the one end of the outtake tube (9) away from purification tower (1) are provided with centrifugal blower (12), the centrifugal blower (12) upper end is provided with discharge pipe (11), and the one end of the discharge pipe (11) away from centrifugal blower (12) is provided with rainhat (10), the purification tower (1) is internally provided with except steam layer (13), water spray pipe (14), packing layer (15), uniform supply fan (16), clean water inlet pipe (17), rotate clean frame (18) and cleaning brush (19), wherein the water removal vapour layer (13) is arranged on purification The inside of tower body (1) is close to the position on top, and the lower end for removing steam layer (13) is provided with water spray pipe (14), the water spray pipe (14) side except steam layer (13) is provided with packing layer (15), side of the described filler layer (15) away from water spray pipe (14) Uniform supply fan (16) is provided with, the side of the uniformly supply fan (16) away from packing layer (15) is provided with cleaning water inlet pipe (17), it is described cleaning water inlet pipe (17) away from uniform supply fan (16) one end be provided with rotate clean frame (18), and clean into Water pipe (17) bottom is provided with cleaning delivery port (20), and the described one end of clean frame (18) away from cleaning water inlet pipe (17) that rotates is set Be equipped with cleaning brush (19), be provided with catch bar (22) between the adjacent cleaning brush (19), the catch bar (22) it is close One end of cleaning delivery port (20) is provided with arc-shaped pushing plate (21).
2. Tower for purifying waste gas according to claim 1, it is characterised in that:The rotation clean frame (18) and cleaning water inlet pipe (17) connected by axis of rotation.
3. Tower for purifying waste gas according to claim 1, it is characterised in that:The catch bar (22) is provided with eight altogether, and Eight catch bars (22) are evenly distributed between the adjacent cleaning brush (19).
4. Tower for purifying waste gas according to claim 1, it is characterised in that:The arc-shaped pushing plate (21) and catch bar (22) it is integral type structure.
5. Tower for purifying waste gas according to claim 1, it is characterised in that:The purification tower (1) and outtake tube (9) are logical Cross drive screw and screw and be fixedly connected.
6. Tower for purifying waste gas according to claim 1, it is characterised in that:The water circulating pump (5) and cyclic water tank (6) are logical Cross drive screw and screw and be fixedly connected.
CN201720976346.4U 2017-08-07 2017-08-07 Tower for purifying waste gas Expired - Fee Related CN207056237U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720976346.4U CN207056237U (en) 2017-08-07 2017-08-07 Tower for purifying waste gas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720976346.4U CN207056237U (en) 2017-08-07 2017-08-07 Tower for purifying waste gas

Publications (1)

Publication Number Publication Date
CN207056237U true CN207056237U (en) 2018-03-02

Family

ID=61519587

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720976346.4U Expired - Fee Related CN207056237U (en) 2017-08-07 2017-08-07 Tower for purifying waste gas

Country Status (1)

Country Link
CN (1) CN207056237U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110201479A (en) * 2019-07-01 2019-09-06 杭州路成环保科技有限公司 A kind of spray column and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110201479A (en) * 2019-07-01 2019-09-06 杭州路成环保科技有限公司 A kind of spray column and its construction method

Similar Documents

Publication Publication Date Title
CN207056237U (en) Tower for purifying waste gas
CN206273325U (en) A kind of dust filter unit
CN205461502U (en) Cross deduster of filter cylinder
CN208727065U (en) A kind of dust separation spray column
CN212142052U (en) Volatile gas energy-saving treatment equipment
CN207815550U (en) Self-cleaning fresh air machine
CN109621609A (en) A kind of coating cloud collection device
CN113731084A (en) Ventilation dust removal device, dust removal method thereof and purification and dehumidification method
CN112370949A (en) Industrial waste gas high concentration acid mist purifying tower
CN209423311U (en) A kind of industrial waste gas purifying scrubbing tower
CN207893877U (en) A kind of Household Air Purifier having moistening function
CN215692983U (en) Activated carbon adsorption device for waste gas
CN216092875U (en) Dust collecting equipment is used in production of tiling dry-mixed mortar
CN216259988U (en) Anti-blocking device for desulfurizing tower of desulfurizing system
CN212720442U (en) Circulating water system with energy-saving, efficiency-increasing and emission-reducing functions
CN107174901A (en) A kind of water spray type dust removal by ventilation takes off mist tower and technique
CN209696560U (en) A kind of spray column with packing layer
CN208852633U (en) A kind of exhaust-gas treatment recyclable device
CN209302485U (en) A kind of active carbon carbon dust adsorption tower
CN207576059U (en) A kind of chemical plant spraying dedusting device
CN208275193U (en) The cleaner in polyester resin workshop
CN219308282U (en) Waste gas purifying tower
CN212778556U (en) Hot air dryer with dust removal function
CN217041885U (en) Square pneumatic cyclone tower
CN219023876U (en) Tail gas treatment equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180302

Termination date: 20200807