CN207048152U - Composite beam is connected system with superimposed sheet - Google Patents

Composite beam is connected system with superimposed sheet Download PDF

Info

Publication number
CN207048152U
CN207048152U CN201720755622.4U CN201720755622U CN207048152U CN 207048152 U CN207048152 U CN 207048152U CN 201720755622 U CN201720755622 U CN 201720755622U CN 207048152 U CN207048152 U CN 207048152U
Authority
CN
China
Prior art keywords
superimposed sheet
positive stop
stress bar
principal rod
stirrup
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720755622.4U
Other languages
Chinese (zh)
Inventor
徐国军
王晓涛
刘新华
李瑞锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Green Building Integration Technology Co Ltd
Original Assignee
Zhejiang Green Building Integration Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Green Building Integration Technology Co Ltd filed Critical Zhejiang Green Building Integration Technology Co Ltd
Priority to CN201720755622.4U priority Critical patent/CN207048152U/en
Application granted granted Critical
Publication of CN207048152U publication Critical patent/CN207048152U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

It the utility model is related to a kind of composite beam and be connected system with superimposed sheet, belong to building member technical field.Including combination beam, superimposed sheet and beam stirrup, described beam stirrup is U-shaped structure, and two free end is fixed with combination beam respectively, and beam stirrup is distributed along combination beam length direction, and several positive stop strips are worn in beam stirrup;Some groups of principal rods are set on superimposed sheet, and each principal rod is connected by stress bar;Stress bar is fixedly connected through positive stop strip lower section with positive stop strip.Utility model is applied in assembling type steel structure dwelling house system, has the advantages that top surface of the beam is smooth, good with girder steel compactness.

Description

Composite beam is connected system with superimposed sheet
Technical field
It the utility model is related to a kind of composite beam and be connected system with superimposed sheet, belong to building member technical field.
Background technology
Common steel structure body ties up in residential housing the defects of having one clearly, i.e. conventional assembled architecture In, part combined girder steel is connected with prefabricated superimposed sheet using globality, and girder steel is combined frequently with peg with the concrete of plate, easily There is the defects of spillage and surface irregularity.
Based on this, the application is made.
Utility model content
For existing existing drawbacks described above, a kind of stability under loading of the application offer, surfacing, spillage rate are low to fold Close beam and be connected system with superimposed sheet.
To achieve the above object, the technical scheme that the application takes is as follows:
Composite beam is connected system, including combination beam, superimposed sheet and beam stirrup with superimposed sheet, and described beam stirrup is U-shaped knot Structure, two free end are fixed with combination beam respectively, and beam stirrup is distributed along combination beam length direction, and several are worn in beam stirrup Positive stop strip;Some groups of principal rods are set on superimposed sheet, and each principal rod is connected by stress bar;Stress bar is passed through below positive stop strip, and It is fixedly connected with positive stop strip.
Further, as preferred:
Described principal rod is X-shape, and its four free ends are separately fixed on superimposed sheet, center be then fixed on by On power bar.The distribution it is furthermore preferred that described principal rod is embarked on journey, a stress bar, Mei Geshou are set on corresponding often row principal rod Power bar is fixed with positive stop strip.
Described positive stop strip is provided with two, and two positive stop strips are mutually horizontal, and is set along the length direction of combination beam.
Described stress bar is arranged in pairs, and one is located at the top of principal rod, and one is arranged in below principal rod.More preferably , the public stress bar of principal rod of described beam stirrup both sides.A public stress bar, its one end are located at a beam stirrup left side Below the principal rod of side, the other end is located at below the principal rod on the right side of beam stirrup, and three stress bars shift to install, and realize strength Balance.
Combination beam through its top flange and pre-installs longitudinal direction using local combination section steel beam using U-shaped beam stirrup in the application (That is the longitudinal direction of combination beam)Reinforcing bar, the prefabricated superimposed sheet of laying after combination beam installation is in place, then lays plate face reinforcing bar, carries out recently Concrete is whole to be poured.
Possessed advantage and effect compared with prior art:
1st, combination beam uses part built-up steel plate girders, and top surface of the beam is smooth, is easy to lay superimposed sheet;
2nd, prefabricated superimposed sheet it is smooth bright and clean, can be preferably bonded with girder steel, simple process can prevent dew from starching, can be with Without using template;
3rd, girder steel adopts beam stirrup, and in the prior art, girder steel frequently with peg compared with the concrete of plate combines, using hoop Muscle can preferably combine concrete, form compound section.
The application is applied in assembling type steel structure dwelling house system, common steel structure body can be obviously improved and tie up to house The defects of building, the assembling interconnection technique of wherein floor and beam is the key point that the system realizes assembling.The skill Art will ensure floor and composite beam can form preferable closed space, can accomplish to exempt from template construction in work progress;Plate with Beam globality connects.
Brief description of the drawings
The side that Fig. 1 is the application is intended to;
Fig. 2 is the perspective representation of the application.
Wherein label:1. combination beam;2. superimposed sheet;3. beam stirrup;31. beam stirrup free end;4. positive stop strip;5. Principal rod;51. principal rod free end;52. center;6. stress bar;6a. stress bar one;6b. stress bar two;6c. Stress bar three.
Embodiment
Embodiment 1
The present embodiment composite beam is connected system with superimposed sheet, with reference to Fig. 1 and Fig. 2, including combination beam 1, superimposed sheet 2 and beam hoop Muscle 3, beam stirrup 3 are U-shaped structure, and two beam stirrup free end 31 is fixed with combination beam 1 respectively, and beam stirrup 3 is grown along combination beam 1 Directional spreding is spent, several positive stop strips 4 are worn in beam stirrup 3;Some groups of principal rods 5 are set on superimposed sheet 2, each principal rod 5 by Stress bar 6 is connected;Stress bar 6 is fixedly connected through the lower section of positive stop strip 4 with positive stop strip 4.
Embodiment 2
Setting and operation principle of the present embodiment with embodiment 1 are identical, and difference is:With reference to Fig. 1, principal rod 5 is X-shaped Shape, its four principal rod free ends 51 are separately fixed on superimposed sheet 2, and center 52 is then fixed on stress bar 6.To realize More preferable using effect, principal rod 3 are embarked on journey distribution, and a stress bar 6, each stress bar 6 are set on corresponding often row principal rod 5 Fixed with positive stop strip 4.
Embodiment 3
Setting and operation principle of the present embodiment with embodiment 1 are identical, and difference is:Positive stop strip 4 is provided with two, two Positive stop strip 4 is mutually horizontal, and is set along the length direction of combination beam 1.
Embodiment 4
Setting and operation principle of the present embodiment with embodiment 1 are identical, and difference is:Stress bar 6 is arranged in pairs, i.e. stress The 6a of bar one, the 6b of stress bar two or the 6b of stress bar two, the 6c of stress bar three, stress bar 6b are located at the top of principal rod 5, stress bar one The 6c of 6a/ stress bar three is arranged in the lower section of principal rod 5.To realize more preferable using effect, the principal rod public one of beam stirrup both sides Root stress bar.The public 6b of stress bar two, its one end are located at below the principal rod in the left side of beam stirrup 3, and the other end is located at beam stirrup 3 The lower section of principal rod 5 on right side, three stress bars shift to install, and realize the balance of strength.
Combination beam 1 through its top flange and is pre-installed vertical using local combination section steel beam using U-shaped beam stirrup 3 in the application To(That is the longitudinal direction of combination beam)Reinforcing bar, combination beam 1 install the rear prefabricated superimposed sheet 2 of laying in place, then lay plate face principal rod 5, Carry out that concrete is whole pours recently.
The application is applied in assembling type steel structure dwelling house system, common steel structure body can be obviously improved and tie up to house The defects of building, the assembling interconnection technique of wherein floor and beam is the key point that the system realizes assembling.The skill Art will ensure floor and composite beam can form preferable closed space, can accomplish to exempt from template construction in work progress;Plate with Beam globality connects.
Above content be with reference to the invention preferred embodiment provided technical scheme is made it is further detailed Describe in detail bright, it is impossible to assert that the invention specific implementation is confined to these above-mentioned explanations, for the affiliated technology of the invention For the those of ordinary skill in field, without departing from the concept of the premise of the invention, some simple deductions can also be made Or replace, it should all be considered as belonging to the protection domain of the invention.

Claims (6)

1. composite beam is connected system with superimposed sheet, it is characterised in that:Including combination beam, superimposed sheet and beam stirrup, described beam hoop Muscle is U-shaped structure, and two free end is fixed with combination beam respectively, and beam stirrup is distributed along combination beam length direction, in beam stirrup Wear several positive stop strips;Some groups of principal rods are set on superimposed sheet, and each principal rod is connected by stress bar;Stress bar passes through spacing Below bar, and it is fixedly connected with positive stop strip.
2. composite beam as claimed in claim 1 is connected system with superimposed sheet, it is characterised in that:Described principal rod is X-shape, Its four free ends are separately fixed on superimposed sheet, and center is then fixed on stress bar.
3. composite beam as claimed in claim 1 or 2 is connected system with superimposed sheet, it is characterised in that:Described principal rod is embarked on journey It is distributed, a stress bar is set on corresponding often row principal rod, each stress bar is fixed with positive stop strip.
4. composite beam as claimed in claim 1 is connected system with superimposed sheet, it is characterised in that:Described positive stop strip is provided with two Individual, two positive stop strips are mutually horizontal, and are set along the length direction of combination beam.
5. composite beam as claimed in claim 1 is connected system with superimposed sheet, it is characterised in that:Described stress bar is set in pairs Put, one is located at the top of principal rod, and one is arranged in below principal rod.
6. the composite beam as described in claim 1 or 5 is connected system with superimposed sheet, it is characterised in that:Described beam stirrup both sides The public stress bar of principal rod.
CN201720755622.4U 2017-06-27 2017-06-27 Composite beam is connected system with superimposed sheet Active CN207048152U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720755622.4U CN207048152U (en) 2017-06-27 2017-06-27 Composite beam is connected system with superimposed sheet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720755622.4U CN207048152U (en) 2017-06-27 2017-06-27 Composite beam is connected system with superimposed sheet

Publications (1)

Publication Number Publication Date
CN207048152U true CN207048152U (en) 2018-02-27

Family

ID=61493621

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720755622.4U Active CN207048152U (en) 2017-06-27 2017-06-27 Composite beam is connected system with superimposed sheet

Country Status (1)

Country Link
CN (1) CN207048152U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177369A (en) * 2020-09-23 2021-01-05 中建二局第三建筑工程有限公司 Building floor hoist and mount mouthful seal structure
CN114508050A (en) * 2022-04-19 2022-05-17 中铁工程设计咨询集团有限公司 Straddle type single-rail steel-concrete combined track beam and erection method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177369A (en) * 2020-09-23 2021-01-05 中建二局第三建筑工程有限公司 Building floor hoist and mount mouthful seal structure
CN114508050A (en) * 2022-04-19 2022-05-17 中铁工程设计咨询集团有限公司 Straddle type single-rail steel-concrete combined track beam and erection method

Similar Documents

Publication Publication Date Title
CN104389261B (en) Prefabricated ultra-high performance concrete π ellbeam unit, bridge structure and construction method thereof
CN101845871A (en) Cast-in-place steel-concrete composite beam
CN110067185A (en) A kind of steel pipe-steel plate combination web steel reinforced concrete combined box beam
CN207048152U (en) Composite beam is connected system with superimposed sheet
CN208685437U (en) A kind of wet seam construction of prefabricated assembled concrete floorings
CN103711255B (en) Truss concrete superposed beam
CN103882797B (en) A kind of corrugated steel web plate composite box girder and construction technology thereof
CN212128810U (en) UHPC corrugated steel web narrow steel box type composite beam
CN208717744U (en) A kind of assembled steel reinforced concrete combination prefabricated bridge
CN103643625A (en) Steel truss-concrete plate combined beam based on shear-resisting connecting structure
CN207686092U (en) A kind of assembled overlapped hollow floor system
CN203807928U (en) Corrugated-steel-web combined box girder
CN205999769U (en) A kind of high-speed railway steel reinforced concrete combines only tower section cable-stayed bridge
CN205259072U (en) Hollow mound of railway formwork support system that binds
CN104532733B (en) Partial cable-stayed bridge of fish bone beam structure
CN103866684B (en) A kind of Wavelike steel webplate combination girt strip and construction technology thereof
CN203807954U (en) Box girder strengthening structure based on steel plate-concrete and unbonded pre-stressing tendons
CN106088470B (en) Assembly concrete complex case shape beam and its construction method
CN207619818U (en) A kind of shearing resistance composite structure of the concrete of bridge
CN109853873A (en) Overlap concrete bidirectional stress insulation roof slab
CN106436553A (en) Bridge and shear resistant combined structure thereof
CN210420839U (en) Ramp bridge steel bar structure
CN104652267B (en) Band edge of a wing grooved FRP plate material-concrete combined bridge deck
TW200517561A (en) Floor support structure for building
CN203639805U (en) Steel truss-concrete slab composite beam based on shear-resistant connecting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Ningxia Green Building Integrated Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2019330000014

Denomination of utility model: Composite beam and superimposed sheet connected system

Granted publication date: 20180227

License type: Common License

Record date: 20190917

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Shandong Tianyuan Jinggong Green Integrated Building Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2020330000115

Denomination of utility model: Connection system of composite beam and composite plate

Granted publication date: 20180227

License type: Common License

Record date: 20201216

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Anhui Zhihong Precision Construction Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023990000037

Denomination of utility model: Composite beam and composite plate connection system

Granted publication date: 20180227

License type: Common License

Record date: 20230113

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangxi Huahong Jinggong Steel Structure Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023980034645

Denomination of utility model: Composite beam and composite plate connection system

Granted publication date: 20180227

License type: Common License

Record date: 20230413

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangsu Lvjian Jinggong Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023980034833

Denomination of utility model: Composite beam and composite plate connection system

Granted publication date: 20180227

License type: Common License

Record date: 20230421

EE01 Entry into force of recordation of patent licensing contract