CN207047911U - A kind of poured band of outer wall of basement template - Google Patents
A kind of poured band of outer wall of basement template Download PDFInfo
- Publication number
- CN207047911U CN207047911U CN201720762895.1U CN201720762895U CN207047911U CN 207047911 U CN207047911 U CN 207047911U CN 201720762895 U CN201720762895 U CN 201720762895U CN 207047911 U CN207047911 U CN 207047911U
- Authority
- CN
- China
- Prior art keywords
- wall
- formwork
- post
- exterior wall
- exterior
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及地下室外墙后浇带相关技术领域,具体为一种地下室外墙后浇带模板。The utility model relates to the related technical field of post-cast strips of basement exterior walls, in particular to a formwork for post-cast strips of basement exterior walls.
背景技术Background technique
因地下室后浇带封闭按设计要求时间较长,地下外墙防水要提前施工,在地下外墙后浇带部位目前大多采用预制板与钢筋拉钩连接或砖墙作侧模的施工方式,缺点一是对后期后浇带混凝土浇筑的侧压力由于固定不牢或墙体拉结不理想,对外墙防水在后浇带部位造成破坏,产生渗漏现象;二是外墙内侧模板单侧支设造成困难,混凝土振捣不敢正常振捣,从而影响后浇带混凝土施工质量,为此我们提出一种地下室外墙后浇带模板来解决以上问题。Because the post-cast belt in the basement is sealed for a long time according to the design requirements, the waterproofing of the underground outer wall must be constructed in advance. At present, the construction method of prefabricated panels connected with steel bar hooks or brick walls as side forms is mostly used in the post-cast belt parts of the underground outer walls. The disadvantages are: It is the lateral pressure of the post-cast concrete pouring in the later stage due to poor fixation or unsatisfactory wall tie, which causes damage to the waterproofing of the outer wall at the post-cast belt, resulting in leakage; the second is caused by the unilateral support of the inner formwork of the outer wall Difficult, the concrete vibration is not dared to vibrate normally, which affects the construction quality of the post-cast concrete. Therefore, we propose a post-cast formwork for the basement exterior wall to solve the above problems.
实用新型内容Utility model content
本实用新型的目的在于提供一种地下室外墙后浇带模板,以解决上述背景技术中提出的问题。The purpose of this utility model is to provide a basement outdoor wall post-cast strip formwork to solve the problems raised in the above-mentioned background technology.
为实现上述目的,本实用新型提供如下技术方案:一种地下室外墙后浇带模板,包括外墙外模、外墙、外墙外侧以及找平防水层,所述外墙外侧以及找平防水层均设置于外墙左右两侧的外端,且外墙外模设置于外墙的中端,所述外墙内部的左右两侧设置有混凝土层,两混凝土层之间设置有后浇带,且后浇带的内部设置有止水对拉螺杆,所述止水对拉螺杆的一端焊接于外墙外模的内表面,该外墙外模的内侧还设置有支撑,基于支撑相应的设置有厚木模板,且止水对拉螺杆的一端与支撑交替设置于外墙外模上,该止水对拉螺杆的另一端贯穿厚木模板固定设置。In order to achieve the above object, the utility model provides the following technical solutions: a post-casting belt formwork for the basement exterior wall, including the exterior formwork of the exterior wall, the exterior wall, the outer side of the exterior wall and the leveling waterproof layer, and the outer side of the exterior wall and the leveling waterproof layer are both It is arranged at the outer ends of the left and right sides of the outer wall, and the outer mold of the outer wall is arranged at the middle end of the outer wall, and the left and right sides of the inner side of the outer wall are provided with concrete layers, and a post-casting strip is arranged between the two concrete layers, and The inside of the post-casting belt is provided with a water-stop anti-pull screw. One end of the water-stop anti-pull screw is welded to the inner surface of the outer mold of the outer wall. The inner side of the outer mold of the outer wall is also provided with a support. Based on the support, a corresponding A thick wood formwork, and one end of the water-stop anti-pull screw and the support are arranged alternately on the outer formwork of the outer wall, and the other end of the water-stop anti-pull screw runs through the thick wood formwork and is fixedly arranged.
优选的,所述外墙外模的侧边设置于后浇带的后侧三十毫米处,其模板底部固定在竖向内衬卡箍角钢上,且外墙外模的两侧与竖向钢板预埋件焊接固定。Preferably, the side of the external formwork for the external wall is set at 30 mm behind the post-casting belt, the bottom of the formwork is fixed on the vertical lining clip angle steel, and the two sides of the external formwork for the external wall are aligned with the vertical Steel plate embedded parts are welded and fixed.
优选的,所述止水对拉螺杆间距横向以及竖向均设置有三排,其间距均为四百毫米,其螺杆长度为外墙的宽度加一百五十毫米,且后浇带内部的锚筋与后浇带内部的钢筋拉结临时固定。Preferably, there are three rows of horizontal and vertical spacing between the water-stop tensioning screws, the spacing of which is 400 mm, the length of the screw is the width of the outer wall plus 150 mm, and the anchor inside the post-casting belt Temporary fixation of the ribs and the steel bars inside the post-casting strip.
优选的,所述外墙外模下端的左侧设置有第一嵌入块,右侧设置有第二嵌入块,而竖向内衬卡箍角钢与外墙外模的接触面上的左侧设置有第一嵌入槽,右侧设置有第二嵌入槽,第一嵌入块与第一嵌入槽相合,第二嵌入块与第二嵌入槽相合,且外墙外模与竖向内衬卡箍角钢相合的中端处设置有一呈菱形的空腔,该空腔与限位块相合。Preferably, the left side of the lower end of the outer mold of the outer wall is provided with a first embedded block, the right side is provided with a second embedded block, and the left side of the contact surface between the vertical lining clip angle steel and the outer mold of the outer wall is arranged There is a first embedding groove, the right side is provided with a second embedding groove, the first embedding block is matched with the first embedding groove, the second embedding block is matched with the second embedding groove, and the outer wall mold and the vertical inner lining clamp angle steel A rhombus-shaped cavity is arranged at the joint middle end, and the cavity is matched with the limit block.
与现有技术相比,本实用新型的有益效果是:本实用新型操作方便,设置合理;Compared with the prior art, the beneficial effects of the utility model are: the utility model is convenient to operate and reasonable in setting;
1、通过将外墙外模的侧边设置于后浇带的后侧三十毫米处,将模板底部固定在竖向内衬卡箍角钢上,且将外墙外模的两侧与竖向钢板预埋件焊接固定,使此新型结构方便固定安装;1. By setting the side of the external formwork of the external wall at the rear side of the post-casting belt 30 mm, the bottom of the formwork is fixed on the vertical lining clip angle steel, and the two sides of the external formwork of the external wall are aligned with the vertical The steel plate embedded parts are welded and fixed, making this new structure convenient for fixed installation;
2、通过将止水对拉螺杆间距横向以及竖向均设置有三排,其间距均为四百毫米,将螺杆长度设置为外墙的宽度加一百五十毫米,且后浇带内部的锚筋与后浇带内部的钢筋拉结临时固定,使此新型结构模板拉结稳固,不会造成后浇带的损坏;2. By setting the spacing of the water-stop anti-pull screws to three rows in both horizontal and vertical directions, the spacing is 400mm, and the length of the screw is set to the width of the outer wall plus 150mm, and the anchor inside the post-casting belt Temporary fixation of the ribs and the steel bars inside the post-casting belt, so that the new structural formwork is firmly tied and will not cause damage to the post-casting belt;
3、通过在外墙外模下端设置有第一嵌入块和第二嵌入块,在竖向内衬卡箍角钢上设置第一嵌入槽和第二嵌入槽,第一嵌入块与第一嵌入槽相合,第二嵌入块与第二嵌入槽相合,且外墙外模与竖向内衬卡箍角钢相合的中端处设置有一呈菱形的空腔,该空腔与限位块相合,使此新型结构定位方便,连接紧固。3. By setting the first inserting block and the second inserting block at the lower end of the outer mold of the outer wall, the first inserting groove and the second inserting groove are set on the vertical lining clamp angle steel, and the first inserting block fits the first inserting groove , the second embedding block fits the second embedding groove, and there is a diamond-shaped cavity at the middle end where the outer wall formwork and the vertical lining clamp angle steel fit together, and the cavity fits with the limit block, so that this new type The structure is convenient for positioning and the connection is tight.
附图说明Description of drawings
图1为本实用新型结构俯视图;Fig. 1 is a top view of the structure of the utility model;
图2为图1中A处横剖图;Figure 2 is a cross-sectional view at A in Figure 1;
图3为本实用新型钢筋拉结与锚筋结构俯视图;Fig. 3 is the top view of the utility model steel bar tie and anchor bar structure;
图4为本实用新型钢筋拉结与锚筋结构侧视图;Fig. 4 is a side view of the utility model steel tie and anchor bar structure;
图5为本实用新型外墙外模与竖向内衬卡箍角钢连接结构示意图。Fig. 5 is a schematic diagram of the connection structure between the outer formwork of the outer wall and the vertical lining clamp angle steel of the utility model.
图中:1外墙外模、2外墙外侧、3支撑、4找平防水层、5止水对拉螺杆、6后浇带、7厚木模板、8锚筋、9外墙、10竖向内衬卡箍角钢、11限位块、12第一嵌入块、13第二嵌入块、14第一嵌入槽、15第二嵌入槽、16混凝土层。In the figure: 1 external formwork of external wall, 2 external wall of external wall, 3 support, 4 leveling and waterproof layer, 5 water-stop tensioning screw, 6 post-pouring belt, 7 thick wood formwork, 8 anchor bar, 9 external wall, 10 vertical interior Lining clamp angle steel, 11 limit block, 12 first embedding block, 13 second embedding block, 14 first embedding groove, 15 second embedding groove, 16 concrete layer.
具体实施方式detailed description
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.
在本实用新型的描述中,需要理解的是,术语“上端”、“下端”、“中端”、“右侧”、“右侧”、“侧边”等指示的方位或位置关系为基于附图1-5所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置或结构必须具有的特定方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。In the description of the present utility model, it should be understood that the orientation or positional relationship indicated by the terms "upper end", "lower end", "middle end", "right side", "right side" and "side side" are based on The orientations or positional relationships shown in accompanying drawings 1-5 are only for the convenience of describing the utility model and simplifying the description, rather than indicating or implying that the referred device or structure must have a specific orientation, be constructed and operated in a specific orientation, Therefore, it cannot be understood as a limitation of the present utility model.
请参阅图1-5,本实用新型提供一种技术方案:一种地下室外墙后浇带模板,包括外墙外模1、外墙9、外墙外侧2以及找平防水层4,外墙外侧2以及找平防水层4均设置于外墙9左右两侧的外端,且外墙外模1设置于外墙9的中端,外墙外模1下端的左侧设置有第一嵌入块12,右侧设置有第二嵌入块13,而竖向内衬卡箍角钢10与外墙外模1的接触面上的左侧设置有第一嵌入槽14,右侧设置有第二嵌入槽15,第一嵌入块12与第一嵌入槽14相合,第二嵌入块13与第二嵌入槽15相合,且外墙外模1与竖向内衬卡箍角钢10相合的中端处设置有一呈菱形的空腔,该空腔与限位块11相合,使外墙外模1与竖向内衬卡箍角钢10定位方便,连接紧固。Please refer to Figures 1-5, the utility model provides a technical solution: a post-casting belt formwork for the exterior wall of the basement, including the exterior mold 1 of the exterior wall, the exterior wall 9, the exterior wall 2 and the leveling waterproof layer 4, the exterior wall exterior 2 and the leveling waterproof layer 4 are arranged at the outer ends of the left and right sides of the outer wall 9, and the outer wall mold 1 is arranged at the middle end of the outer wall 9, and the first embedded block 12 is arranged on the left side of the lower end of the outer wall mold 1 , the right side is provided with a second embedding block 13, and the left side of the contact surface between the vertical lining clip angle steel 10 and the outer wall mold 1 is provided with a first embedding groove 14, and the right side is provided with a second embedding groove 15 , the first embedding block 12 fits into the first embedding groove 14, the second embedding block 13 fits into the second embedding groove 15, and the middle end of the external wall formwork 1 and the vertical lining clip angle steel 10 is provided with a Rhombus-shaped cavity, the cavity is matched with the limit block 11, so that the outer wall outer mold 1 and the vertical lining clip angle steel 10 are positioned conveniently and connected tightly.
外墙9内部的左右两侧设置有混凝土层16,两混凝土层16之间设置有后浇带6,且后浇带6的内部设置有止水对拉螺杆5,外墙外模1的侧边设置于后浇带6的后侧三十毫米处,其模板底部固定在竖向内衬卡箍角钢10上,且外墙外模1的两侧与竖向钢板预埋件焊接固定,使外墙外模1方便固定安装。Concrete layers 16 are arranged on the left and right sides of the interior of the exterior wall 9, and post-casting belts 6 are arranged between the two concrete layers 16, and the interior of the post-casting strips 6 is provided with a water-stop pull screw 5, and the side of the outer wall mold 1 The side is set at the rear side of the post-casting belt 6 at 30 mm, the bottom of the formwork is fixed on the vertical lining clip angle steel 10, and the two sides of the outer wall mold 1 are welded and fixed with the vertical steel plate embedded parts, so that The external formwork 1 of the external wall is convenient for fixed installation.
止水对拉螺杆5的一端焊接于外墙外模1的内表面,该外墙外模1的内侧还设置有支撑3,基于支撑3相应的设置有厚木模板7,止水对拉螺杆5间距横向以及竖向均设置有三排,其间距均为四百毫米,其螺杆长度为外墙9的宽度加一百五十毫米,且后浇带6内部的锚筋8与后浇带6内部的钢筋拉结临时固定。且止水对拉螺杆5的一端与支撑3交替设置于外墙外模1上,该止水对拉螺杆5的另一端贯穿厚木模板7固定设置,使外墙外模1拉结稳固,不会造成后浇带6的损坏。One end of the water-stop anti-pull screw 5 is welded to the inner surface of the outer mold 1 of the exterior wall. A support 3 is also provided on the inside of the exterior mould. There are three rows of horizontal and vertical spacing, the spacing is 400 mm, the length of the screw is the width of the outer wall 9 plus 150 mm, and the anchor bars 8 inside the post-casting belt 6 are connected to the inside of the post-casting belt 6. Temporary fixation of steel bars. In addition, one end of the water-stop anti-tension screw 5 and the support 3 are alternately arranged on the outer wall mold 1, and the other end of the water-stop anti-tension screw 5 is fixedly installed through the thick wood formwork 7, so that the outer wall mold 1 is tied firmly and does not It will cause damage to the post-casting tape 6.
工作原理:所述外墙外模1采用钢板侧模,尺寸为厚10mm,宽860mm、高1200mm,所述支撑3采用木方40×70,钢管采用的直径为48.3mm。当需要进行外墙外模1的使用时,先定位放线,在基础底板外墙后浇带6的位置弹水平及竖向控制线,控制外墙外模1安装,而进行外墙外模1的安设时,外墙外模1宽度每侧超后浇带30mm,外墙外模1的底部支撑在竖向内衬卡箍角钢10上,其两侧与竖向钢板预埋件焊接固定,且外墙外模1的内部侧壁上焊接止水对拉螺杆5,止水对拉螺杆5间距横向以及竖向均设置有三排,其间距均为四百毫米,其螺杆长度为外墙9的宽度加一百五十毫米,且后浇带6内部的锚筋8与后浇带6内部的钢筋拉结临时固定,并且止水对拉螺杆5的一端与支撑3交替设置于外墙外模1上,该止水对拉螺杆5的另一端贯穿厚木模板7固定设置,外墙外模1组装完成。Working principle: the outer formwork 1 of the outer wall is made of steel plate side formwork, the size is 10mm thick, 860mm wide, and 1200mm high. The support 3 is made of wood 40×70, and the diameter of the steel pipe is 48.3mm. When it is necessary to use the external formwork 1 of the external wall, first position and set out the wires, and play the horizontal and vertical control lines at the position of the post-casting belt 6 on the external wall of the foundation base plate to control the installation of the external formwork 1 of the external wall, and then carry out the external formwork of the external wall. During the installation of 1, the width of each side of the outer wall formwork 1 is 30 mm longer than that of the post-casting tape, and the bottom of the outer wall formwork 1 is supported on the vertical lining clamp angle steel 10, and its two sides are welded with the vertical steel plate embedded parts It is fixed, and the inner side wall of the outer wall mold 1 is welded with water-stop anti-pull screw rods 5, and the distance between water-stop anti-pull screw rods 5 is arranged in three rows horizontally and vertically, and the distance between them is 400 mm. The width of the wall 9 is increased by 150 mm, and the anchor bar 8 inside the post-casting belt 6 is temporarily fixed with the reinforcement tie inside the post-casting belt 6, and one end of the water-stop anti-tensioning screw 5 and the support 3 are alternately arranged on the outside On the external formwork 1 of the wall, the other end of the water-stop anti-tension screw 5 is fixedly set through the thick wood formwork 7, and the assembly of the external formwork 1 of the external wall is completed.
尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes and modifications can be made to these embodiments without departing from the principle and spirit of the present invention , replacements and modifications, the scope of the present utility model is defined by the appended claims and their equivalents.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720762895.1U CN207047911U (en) | 2017-06-28 | 2017-06-28 | A kind of poured band of outer wall of basement template |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720762895.1U CN207047911U (en) | 2017-06-28 | 2017-06-28 | A kind of poured band of outer wall of basement template |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN207047911U true CN207047911U (en) | 2018-02-27 |
Family
ID=61492504
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720762895.1U Expired - Fee Related CN207047911U (en) | 2017-06-28 | 2017-06-28 | A kind of poured band of outer wall of basement template |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN207047911U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110043035A (en) * | 2019-02-25 | 2019-07-23 | 中天西北建设投资集团有限公司 | A kind of novel post empiricism method for supporting |
| CN110593320A (en) * | 2019-08-27 | 2019-12-20 | 中建四局第六建筑工程有限公司 | A pre-closed structure and construction method of post-pouring belt on exterior wall |
| CN111851595A (en) * | 2020-08-03 | 2020-10-30 | 中国建筑一局(集团)有限公司 | A kind of basement exterior wall back-casting with steel plate closed structure and construction method thereof |
-
2017
- 2017-06-28 CN CN201720762895.1U patent/CN207047911U/en not_active Expired - Fee Related
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110043035A (en) * | 2019-02-25 | 2019-07-23 | 中天西北建设投资集团有限公司 | A kind of novel post empiricism method for supporting |
| CN110043035B (en) * | 2019-02-25 | 2022-03-15 | 中天西北建设投资集团有限公司 | Post-cast strip construction supporting method |
| CN110593320A (en) * | 2019-08-27 | 2019-12-20 | 中建四局第六建筑工程有限公司 | A pre-closed structure and construction method of post-pouring belt on exterior wall |
| CN111851595A (en) * | 2020-08-03 | 2020-10-30 | 中国建筑一局(集团)有限公司 | A kind of basement exterior wall back-casting with steel plate closed structure and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104631512B (en) | Hang modulus method after-pouring band beam-slab construction method | |
| CN109736353A (en) | Construction method of composite single-side formwork deep foundation pit basement outer wall | |
| CN103410317A (en) | Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part | |
| CN102943530B (en) | Construction method of embedded type ultra-thin steel edge rubber water stop fixing device | |
| CN104652830A (en) | Construction method for building of prefabricated slab floor and prefabricated wall plate | |
| CN103195087A (en) | Mould support method of foundation pit basement haunch shearing wall | |
| CN105113706A (en) | Reinforced truss gypsum plate with insulation layer, novel dismantling-free formwork and their construction method | |
| CN103306463B (en) | Metal liner concrete air channel construction method | |
| CN109208816A (en) | A kind of external wall is cast-in-place with prefabricated thermal insulation integral system | |
| CN114687578A (en) | Construction method for reinforcing red brick outer wall of historical building | |
| CN114856181A (en) | Building pouring formwork support and construction method thereof | |
| CN211499326U (en) | A synchronous construction structure of concrete infill wall and cast-in-place structure | |
| CN201671323U (en) | Combination formwork for building walls | |
| CN111810193A (en) | A construction method for secondary lining of small-section tunnels | |
| CN103422515A (en) | Water stop belt and locating method thereof | |
| CN205713078U (en) | A kind of outer wall of basement vertical post-cast strip side mold device | |
| CN203452103U (en) | Waterstop | |
| CN206769180U (en) | A kind of shaped steel hole prefabricated section through walls | |
| CN214364434U (en) | Assembled constructional column suitable for prefabricated wallboard of frame construction | |
| CN211923020U (en) | A steel structure prefabricated building wall and steel beam connection structure | |
| CN109441099A (en) | Basement single side formwork system and the method for utilizing its outer wall of basement of constructing | |
| CN207376661U (en) | A kind of plugging structure of poured band of outer wall of basement | |
| CN206220132U (en) | A kind of base plate and exterior wall junction construction typified form support | |
| CN119466318A (en) | A PCF board single-side formwork construction technology | |
| CN217630810U (en) | Convenient assembled wallboard |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180227 |