Pushing tow power set available for Large-span Steel Box Beam construction
Technical field
A kind of corollary apparatus of bridge construction is the utility model is related to, in particular, the utility model relates generally to one
Kind can be used for the pushing tow power set of Large-span Steel Box Beam construction.
Background technology
Steel box girder incremental launching method construction is so that its construction cost is low, speed of application is fast, construction stationarity is good, construction period controllability
By force, in constructing need not in obtain more and more extensive application many advantages, such as traffic under bridge cut-off, be particularly suitable for use in across busy
The bridge of traffic route, shipping river.But with the development of Bridges in Our Country cause, due to being influenceed and design form by landform
Variation, part steel box girder bridge beam span is larger, across road or river because traffic or geology, hydrologic condition reason can not be set
Put Temporary Piers.Bridge linear of this kind of steel box-girder in work progress controls, the reaction of supports controls, steel box-girder itself Stress Control
Very high requirement is proposed etc. many aspects.Thus it is necessary for the push construction method of Large-span Steel Box Beam and with being arranged
The structure applied further is studied and improved.
Utility model content
One of the purpose of this utility model is to be directed to above-mentioned deficiency, there is provided a kind of to can be used for what Large-span Steel Box Beam was constructed
Pushing tow power set, it is larger it is expected to solve steel box girder bridge beam span in the prior art, it is difficult for bridge linear and the reaction of supports
With technical problems such as controls.
To solve above-mentioned technical problem, the utility model uses following technical scheme:
A kind of pushing tow power set available for Large-span Steel Box Beam construction provided by the utility model, including pushing tow oil
Cylinder, one end of the pipe bending cylinder are arranged on the end of steel box-girder, and the other end is arranged on oil cylinder counter-force seat, and the oil cylinder is anti-
Power seat is arranged on slipway beam, and the steel box-girder is placed in the top of slipway beam.
Preferably, further technical scheme is:The slipway beam is provided with multiple pin shaft holes, and multiple pin shaft hole phases
The distance between mutual equal, the oil cylinder counter-force seat is arranged on slipway beam by pin shaft hole.
Further technical scheme is:Multiple pin shaft holes arrange when slipway beam is horizontal positioned along horizontal line.
Further technical scheme is:The end of the pipe bending cylinder is arranged on oil cylinder counter-force seat, clutch end
Installed in the end of steel box-girder.
Further technical scheme is:It is also equipped with leading between the output end of the pipe bending cylinder and the end of steel box-girder
To seat, the output end with pipe bending cylinder, the end of steel box-girder are fixedly connected the guide holder respectively.
Further technical scheme is:Power transmission bearing beam is also equipped between guide holder and the end of steel box-girder.
Further technical scheme is:The pipe bending cylinder two, the slipway beam are two, and two slipway beams point
The both sides of steel box-girder are not placed in, and two pipe bending cylinders are respectively placed in respective slipway beam top.
Compared with prior art, one of the beneficial effects of the utility model are:By the way that oil cylinder counter-force seat is arranged on into slideway
Liang Shang so that pipe bending cylinder obtains counter-force backward after power is exported from slipway beam, and steel is promoted using the counter-force backward
Box beam moves forward on slipway beam, and by changing position of the oil cylinder counter-force seat on slipway beam, you can make pipe bending cylinder pushing tow
Steel box-girder constantly moves forward on slipway beam, is advantageous to lift the convenience to move forward in steel box girder construction, without the other liftings of peripheral hardware
Equipment is aided in, and Temporary Piers are set up without because steel box-girder moves forward, at the same it is provided by the utility model it is a kind of can be used for greatly across
The pushing tow powerplant configuration of degree steel box girder construction is simple, and suitable for being installed and used in all kinds of places, application is wide.
Brief description of the drawings
Fig. 1 is the structural representation for illustrating the utility model one embodiment;
Fig. 2 is Fig. 1 A to schematic diagram;
In figure, 1 it is pipe bending cylinder, 2 is steel box-girder, 3 is oil cylinder counter-force seat, 4 is slipway beam, 5 is pin shaft hole, 6 is guiding
Seat, 7 are power transmission bearing beam.
Embodiment
The utility model is further elaborated below in conjunction with the accompanying drawings.
With reference to shown in figure 1, one embodiment of the present utility model is a kind of pushing tow available for Large-span Steel Box Beam construction
Power set, including pipe bending cylinder 1, one end of the pipe bending cylinder 1 are arranged on the end of steel box-girder 2, and the other end is arranged on oil
On cylinder counter-force seat 3, the oil cylinder counter-force seat 3 need to be arranged on slipway beam 4, and steel box-girder 2 is placed in the top of slipway beam 4.And then make steel
Box beam 2 is slided in the presence of jacking force in the top of slipway beam 4.
In the present embodiment, by the way that oil cylinder counter-force seat 3 is arranged on slipway beam 4 so that pipe bending cylinder 1 is in output power
Afterwards, counter-force backward is obtained from slipway beam 4, promotes steel box-girder 2 to be moved forward on slipway beam 4 using the counter-force backward, and
By changing 3 position on slipway beam 4 of oil cylinder counter-force seat, you can make the pushing steel box girder 2 of pipe bending cylinder 1 on slipway beam 4 not
Move forward disconnectedly, be advantageous to lift the convenience to move forward during steel box-girder 2 is constructed, aided in without the other crane gears of peripheral hardware, without
Temporary Piers are set up because steel box-girder moves forward.
Go out as shown in Figure 1, in another embodiment of the present utility model, for ease of installation oil cylinder counter-force seat 3, go back
Multiple pin shaft holes 5 can be set on above-mentioned slipway beam 4, and the mutual distance of multiple pin shaft holes 5 is disposed as it is equal, so
Oil cylinder counter-force seat 3 is arranged on slipway beam 4 by pin shaft hole 5 afterwards.And then pipe bending cylinder 1 is set to be obtained every time from slipway beam 4
Counter-force, the distance for promoting steel box-girder 2 to move forward is all equal, contributes to pushing steel box girder 2 at the uniform velocity to move forward;Foregoing multiple pins
Axis hole 5 preferably arranges when slipway beam 4 is horizontal positioned along horizontal line, is conveniently adjusted the position of oil cylinder counter-force seat 3, ensures steel box-girder
The stability of 2 lateral displacements.And oil cylinder counter-force seat 3 is installed on slipway beam 4 by inserting the latch of pin shaft hole, can also be lifted
The convenience that oil cylinder counter-force seat 3 dismounts.And oil cylinder counter-force seat 3 is just played only at the end of pipe bending cylinder 1 portion mounted thereto and made
With, therefore the quantity of the oil cylinder counter-force seat 3 on slipway beam 4 can set one or more according to being actually needed, when being arranged to multiple,
The dismounting number of oil cylinder counter-force seat 3 in work progress can be reduced.
On the other hand, referring still to shown in Fig. 1, according to another embodiment of the present utility model, pushing tow is lifted to be further
The stability of the power output of oil cylinder 1, its end can be arranged on oil cylinder counter-force seat 3, and clutch end is then arranged on steel case
The end of beam 2.
Further, a guide holder 6 can be also installed again between the output end of pipe bending cylinder 1 and the end of steel box-girder 2,
The output end with pipe bending cylinder 1, the end of steel box-girder 2 are fixedly connected the guide holder 6 respectively;It is corresponding, can also be upper
State and a power transmission bearing beam 7 is installed again between the end of guide holder 6 and steel box-girder 2;By foregoing structure, steel box-girder can be lifted
The harmony of 2 end stress, i.e., the point of pipe bending cylinder 1 is exported by power by guide holder 6 and power transmission bearing beam 7 and be converted to face output
Power, the lifting surface area of steel box-girder 2 is expanded, when the weight of steel box-girder 2 is larger, steel box-girder 2 can be ensured in this way
It can smoothly be moved forward in slipway beam 4, avoid making the end of steel box-girder 2 that depression or curved occur because of the point output power of pipe bending cylinder
Folding.
It is suitable in the utility model is used to solve technical problem more preferably your one embodiment with reference to shown in Fig. 2
The width of steel box-girder 2 is answered, slipway beam 4 can be two, then puts two slipway beams 4 respectively by above-mentioned pipe bending cylinder 1 two
The respective top of slipway beam 4 is respectively placed in the both sides of steel box-girder 2, then by two pipe bending cylinders 1, is controlling pipe bending cylinder 1
In the presence of device, synchronization telescope is realized, i.e., both obtain counter-force on respective oil cylinder counter-force seat 3 simultaneously, synchronous to steel case
The power of the end output reach of beam 2, moves forward from the both sides synchronous drive steel box-girder 2 of steel box-girder 2.
Than that described above, it is also necessary to which explanation is " one embodiment ", " another implementation spoken of in this manual
Example ", " embodiment " etc., refer to that the specific features, structure or the feature that combine embodiment description are included in the application summary
Property description at least one embodiment in.It is not necessarily to refer to same reality that statement of the same race, which occur, in multiple places in the description
Apply example.Furthermore, it is understood that when describing a specific features, structure or feature with reference to any embodiment, what is advocated is knot
Other embodiment is closed to realize that this feature, structure or feature also fall in the scope of the utility model.
Although reference be made herein to the utility model is described multiple explanatory embodiments of the present utility model, still,
It should be understood that those skilled in the art can be designed that a lot of other modifications and embodiment, these modifications and embodiment
It will fall within spirit disclosed in the present application and spirit.More specifically, in disclosure, drawings and claims
In the range of, a variety of variations and modifications can be carried out to the building block and/or layout of theme combination layout.Except to building block
And/or outside the variations and modifications of layout progress, to those skilled in the art, other purposes also will be apparent.