CN102535343B - Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge - Google Patents

Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge Download PDF

Info

Publication number
CN102535343B
CN102535343B CN201210023189.7A CN201210023189A CN102535343B CN 102535343 B CN102535343 B CN 102535343B CN 201210023189 A CN201210023189 A CN 201210023189A CN 102535343 B CN102535343 B CN 102535343B
Authority
CN
China
Prior art keywords
girder
erection crane
crane
steel
girder erection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210023189.7A
Other languages
Chinese (zh)
Other versions
CN102535343A (en
Inventor
代皓
李军堂
涂满明
张爱花
张瑞霞
姚发海
吕磊
张文斌
杜凤
吴方明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
8th Engineering Co Ltd of MBEC
Original Assignee
China Railway Major Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CN201210023189.7A priority Critical patent/CN102535343B/en
Publication of CN102535343A publication Critical patent/CN102535343A/en
Application granted granted Critical
Publication of CN102535343B publication Critical patent/CN102535343B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a method for erecting a girder on top of a main tower mound of a steel truss girder cable-stayed bridge, which includes the following steps: A10, an erection crane occupying support is erected beside the main tower mound, and a first erection crane is erected on the support; A20, a girder rod piece on top of a mound is hoisted from the surface of a river directly by using the first erection crane, and a third section of girder close to a position beside the erection crane occupying support is erected; and A30, the first erection crane is moved by using a walking device of the erection crane, erection of a second section of girder and a first section of girder is finished sequentially, a second erection crane is assembled on the first section of girder, and a fourth section of girder is erected by using the first erection crane. By means of the method, using time of a floating crane is shortened, a large number of slide girders, sliding cushion blocks and vertically-moving devices are not required to be arranged on a bracket beside the mound, work amount of temporary structures is saved, vertically-moving processes of the girders are reduced, working time is shortened, construction cost is saved, and effect of riverway water level is avoided.

Description

Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge
Technical field
The present invention relates to method for bridge construction, be specifically related to method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge, be specially adapted to the erection construction that river water level changes greatly, girder steel is higher apart from river surface steel truss girder cable-stayed bridge king-tower place pier pushes up four internode girder steels.
Background technology
Construction for steel truss girder cable-stayed bridge king-tower place pier top girder steel in water, conventional constructure scheme is that slipway beam and longitudinal-moving device are set on pier-side bracket, first utilize crane barge to stand in the girder steel girder steel of an internode of the assembled main span side pier of end bay side top outermost (or) of an internode of the assembled end bay side pier of main span side top outermost, between girder steel lower chord and pier-side bracket slipway beam, slip device is installed, this internode girder steel utilizes vertical shift jack by the distance of an internode of girder steel vertical shift after spelling, and then utilize the assembled girder steel being connected with this internode of crane barge, then by the two internode girder steels of the having spelled distance of an internode of vertical shift again, crane barge continues assembled next internode girder steel, again by the distance of an assembled good internode of three internode girder steel vertical shifts, assembled last the internode girder steel of crane barge, complete pier and push up the assembled of four internode girder steels, finally utilize the assembled two gantry beams loop wheel machines of crane barge.
This job practices: the one, need take for a long time crane barge resource, construction is affected by SEA LEVEL VARIATION, and equipment handover charge is expensive; The 2nd, be subject to the impact of girder steel vertical shift, each internode girder steel all needs slippage cushion block is set, the slipway beam while also needing on pier-side bracket heavy in section steel case beam is set as girder steel slippage, temporary structure quantity is huge; The 3rd, because girder steel bearing is identical in direction across bridge position with slipway beam, for guaranteeing the continuity of girder steel slippage, dress after girder steel bearing needs, increases difficulty of construction.
Therefore, be badly in need of a kind of life cycle that can shorten large-scale floating crane, reduce the assembled operation of pier top girder steel, and the steel beam lifting operation job practices that not affected by river water level.
Summary of the invention
Technical problem to be solved by this invention is to solve in erecting girder on top of main tower mound of steel truss girder cable-stayed bridge process, and the crane barge resource occupation time is long, construction is subject to river water level variable effect, temporary structure quantity is huge and the problem of girder steel working procedure complexity.
In order to solve the problems of the technologies described above, the technical solution adopted in the present invention is to provide a kind of method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge, comprises the following steps:
A10, on main pylon pier side, set up girder erection crane occupy-place support, and on this support, set up first beam loop wheel machine;
A20, utilize the first girder erection crane directly from the river surface dress pier top girder steel rod member of hanging oneself, set up the 3rd internode girder steel near girder erection crane occupy-place support side;
A30, utilize the running gear of girder erection crane to move the first girder erection crane, complete successively second and first segment between the setting up of girder steel, and on girder steel between first segment assembled the second girder erection crane, utilize first gantry of setting a roof beam in place to establish the 4th internode girder steel.
In said method, steps A 10 comprises the following steps:
A101, at the other pier-side bracket of installing of main pylon pier;
A102, utilize crane barge that girder erection crane occupy-place support is installed on pier-side bracket, between this support and pier-side bracket, utilize finish rolling deformed bar to be firmly connected;
A103, utilize crane barge and tower crane to be engaged on girder erection crane occupy-place support the first girder erection crane is installed, between the first girder erection crane and this support, by bearing pin, be fixedly connected with.
In said method, steps A 30 comprises the following steps:
A301, the first girder erection crane are walked to walk on the 3rd internode girder steel, then by the first girder erection crane, remove girder erection crane occupy-place support;
A302, by the first girder erection crane from main span side-draw beam, girder steel between assembled second section;
A303, the first girder erection crane are walked to walk between second section on girder steel, and from end bay side-draw beam, girder steel between assembled first segment;
A304, utilize the first girder erection crane and tower crane to be engaged between first segment assembled the second girder erection crane on girder steel;
A305, the first girder erection crane are walked to walk on the 3rd internode girder steel, utilize assembled the 4th internode girder steel of the first girder erection crane;
A306, the first girder erection crane is walked to walk on the 4th internode girder steel, then carry out pier and push up four internode girder steel Coordinate Adjustings.
The present invention, in river course, when high water level, utilize crane barge that girder erection crane occupy-place support and the first girder erection crane are installed, crane barge is deactivated, the first girder erection crane is directly got beam from river surface boats and ships and is carried out setting up of pier top girder steel, girder steel does not need vertical shift, traveling by girder erection crane completes assembled with the second girder erection crane of setting up that pier pushes up four internode girder steels, has following beneficial effect:
(1) girder erection crane is the necessary equipment of girder steel construction, in steel girder erection, need long-term use, and the non-girder steel construction of large-scale floating crane needs long-term use equipment, and its lease expenses is expensive, the present invention has shortened crane barge service time as far as possible, on saving construction costs, has positive impact.
(2) because river all exists dry season and flood period (the Changjiang river dry season water level and flood period water level differ nearly 15m) in 1 year, crane barge is hung high restriction, great changes have taken place in the crane barge model meeting that dry season and flood period, girder steel construction was selected, and in the present invention, adopting girder erection crane to carry out steel girder erection, lifting is not affected by water level.
(3) on pier-side bracket without the huge slipway beam of magnitude setting, slippage cushion block and longitudinal-moving device, saved temporary structure engineering quantity, reduce girder steel vertical shift operation, shorten the activity duration.
(4) in conventional construction, the slipway beam of girder steel vertical shift has taken the position of girder steel bearing, therefore bearing need be traversing to design attitude by bearing by newly-increased temporary structure again after pier pushes up the whole installations of four internode girder steels, and in the present invention, girder steel bearing can be installed before steel girder erection, did not need newly-increased temporary structure.
Accompanying drawing explanation
Fig. 1 is the composition structural representation of pier top girder steel;
Fig. 2 splices the schematic diagram of the first girder erection crane in the present invention;
Fig. 3 is the lateral view of Fig. 1;
Fig. 4~Fig. 7 splices the schematic diagram of the 3rd internode girder steel in the present invention, the lateral view that wherein Fig. 5 is Fig. 4, the lateral view that Fig. 7 is Fig. 6;
Fig. 8~Figure 10 is the first girder erection crane traveling schematic diagram in the present invention;
Figure 11 is the schematic diagram of running gear;
Figure 12 splices the schematic diagram of girder steel between second section in the present invention;
Figure 13 is the lateral view of Figure 12;
Figure 14 splices the schematic diagram of girder steel between first segment in the present invention;
Figure 15 is the lateral view of Figure 14;
Figure 16 splices the schematic diagram of the second girder erection crane in the present invention;
Figure 17 is the lateral view of Figure 16;
Figure 18 splices the schematic diagram of the 4th internode girder steel in the present invention;
Figure 19 is the lateral view of Figure 18.
The specific embodiment
Below in conjunction with accompanying drawing, the present invention is described in detail.
As shown in Figure 1, steel truss girder cable-stayed bridge main pylon pier top girder steel is linked in sequence and is formed by the first, second, third and the 4th internode girder steel 601,602,603 and 604, the second and the 3rd internode girder steel 602,603 be positioned at main pylon pier top directly over, the first and the 4th internode girder steel 601,604 lays respectively at both sides, during follow-up construction, successively from the first and the 4th internode girder steel 601,604Xiang both sides expansion.
Take Fig. 1 as example, and main pylon pier top girder steel forms successively E22, E23, E24, E25 and E26 node from left to right on bottom surface, forms successively A22, A23, A24, A25 and A26 node on end face.
Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge provided by the invention, comprises the following steps:
A10, in steel truss girder cable-stayed bridge king-tower 500 both sides, set up pier-side bracket 100, and on pier-side bracket 100, set up girder erection crane occupy-place support 200 and the first girder erection crane 400.As shown in Figure 2 and Figure 3, concrete steps are as follows:
A101, at the other pier-side bracket 100 of installing of the pier of steel truss girder cable-stayed bridge king-tower 500;
A102, utilize crane barge 300 that girder erection crane occupy-place support 200 is installed on pier-side bracket 100, between this support 200 and pier-side bracket 100, utilize finish rolling deformed bar to be firmly connected;
A103, utilize crane barge 300 and tower crane to be engaged in to install on falsework 200 the first girder erection crane 400 (main span side girder erection crane), between main span side girder erection crane 400 and girder erection crane occupy-place support 200, by bearing pin, be fixedly connected with.
A20, utilize main span side girder erection crane 400 to lift pier top girder steel rod member from river surface boats and ships, set up the 3rd internode girder steel 603 on girder erection crane occupy-place support 200 sides, as shown in Figure 4, Figure 5, Figure 6 and Figure 7.
Concrete steps are:
(1) the large node of assembled E24 and the internodal lower chord of E24~E25;
(2) the railway bridge panel of lifting E24~E25 internode;
(3) the internodal montant of assembled E24~A24, the internodal brace of E24~A25 and the internodal montant of E25~A25;
(4) lifting A25 node, the splicing internodal upper chord of A24~A25 and A24, A25 Nodes sway bracing;
(5) the road bridge panel of lifting A24~A25 internode.
A30, utilize the running gear of girder erection crane to complete successively the setting up of girder steel at king-tower 500 diverse location places, pier top.
Steps A 30 comprises the following steps:
A301, Fig. 8~Figure 10 shows the shifting process that girder erection crane utilizes running gear, Figure 11 is the schematic diagram of running gear, as shown in Fig. 8~Figure 11, utilize vertical shift jack 703 that girder erection crane rail beam 701 is drawn to girder steel A24 Nodes and with track bearing beam 702 and is connected, then remove being connected between main span side girder erection crane 400 and girder erection crane occupy-place support 200, vertical shift jack 703 is fixing with rail beam 701, pushing tow main span side girder erection crane 400 to girder steel A24 nodes, then by main span side girder erection crane 400 and 702 lockings of track bearing beam, repeating above-mentioned steps makes main span side girder erection crane 400 walk to walk between A24~A25 node.
As shown in Figure 12 and Figure 13.
A 302, utilize main span side girder erection crane 400 that girder erection crane occupy-place support 200 is removed, then main span side girder erection crane 400 is from main span side-draw beam, and the girder steel between assembled E23~E24 node forms girder steel 602 between second section;
As shown in Figure 14, Figure 15.
A303, main span side girder erection crane 400 are walked to walk between E23~E24 node, and from end bay side-draw beam, the girder steel between assembled E22~E23 node forms girder steel 601 between first segment.
As shown in Figure 16, Figure 17.
A304, utilize main span side girder erection crane 400 and tower crane to be engaged in assembled end bay side girder erection crane 800(the second girder erection crane on the girder steel between E22~E23 node).
As shown in Figure 18, Figure 19.
A305, main span side girder erection crane 400 is walked to walk on the girder steel between E25~E26 node, utilize the girder steel between the assembled E25~E26 node of main span side girder erection crane 400 to form the 4th internode girder steel 604, and pier top the first, second, third and the 4th internode girder steel 601,602,603 and 604 4 internode girder steels are carried out to Coordinate Adjusting.
Follow-up, utilize free cantilever erection construction main, that end bay side girder erection crane 400,800 symmetries are carried out girder steel.
In the present invention, pier top girder steel does not need vertical shift, by the traveling of girder erection crane, completes assembled with the second gantry beams loop wheel machine of setting up of diverse location place, pier top girder steel, and pier top girder steel bearing can be installed before steel girder erection.
The present invention is not limited to above-mentioned preferred forms, and anyone should learn the structural change of making under enlightenment of the present invention, and every have identical or close technical scheme with the present invention, within all falling into protection scope of the present invention.

Claims (2)

1. method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge, is characterized in that, comprises the following steps:
A10, on main pylon pier side, set up girder erection crane occupy-place support, and on this support, set up first beam loop wheel machine;
A20, utilize the first girder erection crane directly from the river surface dress pier top girder steel rod member of hanging oneself, set up the 3rd internode girder steel near girder erection crane occupy-place support side;
A30, utilize the running gear of girder erection crane to move the first girder erection crane, complete successively second and first segment between the setting up of girder steel, and on girder steel between first segment assembled the second girder erection crane, utilize first gantry of setting a roof beam in place to establish the 4th internode girder steel;
Steps A 30 comprises the following steps:
A301, the first girder erection crane are walked to walk on the 3rd internode girder steel, then by the first girder erection crane, remove girder erection crane occupy-place support;
A302, by the first girder erection crane from main span side-draw beam, girder steel between assembled second section;
A303, the first girder erection crane are walked to walk between second section on girder steel, and from end bay side-draw beam, girder steel between assembled first segment;
A304, utilize the first girder erection crane and tower crane to be engaged between first segment assembled the second girder erection crane on girder steel;
A305, the first girder erection crane are walked to walk on the 3rd internode girder steel, utilize assembled the 4th internode girder steel of the first girder erection crane;
A306, the first girder erection crane is walked to walk on the 4th internode girder steel, then carry out pier and push up four internode girder steel Coordinate Adjustings.
2. method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge as claimed in claim 1, is characterized in that, steps A 10 comprises the following steps:
A101, at the other pier-side bracket of installing of main pylon pier;
A102, utilize crane barge that girder erection crane occupy-place support is installed on pier-side bracket, between this support and pier-side bracket, utilize finish rolling deformed bar to be firmly connected;
A103, utilize crane barge and tower crane to be engaged on girder erection crane occupy-place support the first girder erection crane is installed, between the first girder erection crane and this support, by bearing pin, be fixedly connected with.
CN201210023189.7A 2012-02-02 2012-02-02 Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge Active CN102535343B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210023189.7A CN102535343B (en) 2012-02-02 2012-02-02 Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210023189.7A CN102535343B (en) 2012-02-02 2012-02-02 Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge

Publications (2)

Publication Number Publication Date
CN102535343A CN102535343A (en) 2012-07-04
CN102535343B true CN102535343B (en) 2014-01-15

Family

ID=46343249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210023189.7A Active CN102535343B (en) 2012-02-02 2012-02-02 Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge

Country Status (1)

Country Link
CN (1) CN102535343B (en)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103224198A (en) * 2013-05-21 2013-07-31 中铁九桥工程有限公司 Hydraulic travelling-pedrail type cable crane capable of travelling with load
CN104480862B (en) * 2014-12-03 2016-04-20 中铁大桥局集团有限公司 A kind of erection method of cable stayed bridge end bay steel truss girder
CN104594201B (en) * 2014-12-16 2016-04-20 中铁大桥局集团有限公司 A kind of method utilizing one-sided pier-side bracket to set up pier top girder steel
CN106192755A (en) * 2015-04-29 2016-12-07 江苏沪宁钢机股份有限公司 A kind of fish-bellied type shaped form cross a river double width steel box-girder steel bridge construction method of installation
CN105544405A (en) * 2016-01-25 2016-05-04 中交二公局第一工程有限公司 Construction method for erecting and installing bridge pier top block by adopting floating crane
CN105926457A (en) * 2016-05-30 2016-09-07 中国铁建大桥工程局集团有限公司 Method for mounting steel box girders in main tower area of cable-stayed bridge and auxiliary girder erection crane base
CN108411783A (en) * 2018-03-12 2018-08-17 中铁建大桥工程局集团第四工程有限公司 A kind of steel truss girder joint assembling and construction method
CN108824202B (en) * 2018-07-05 2023-06-09 中交第二航务工程局有限公司 Support system for concrete cable-stayed bridge hanging basket installation and tower area beam cast-in-situ construction
CN109653236A (en) * 2019-01-29 2019-04-19 中铁大桥局集团第四工程有限公司 Tower-crane foundation structure for restricted clearance
CN110374006B (en) * 2019-07-22 2021-08-10 中铁大桥局集团有限公司 Construction method for dismantling space anisotropic large-tonnage steel beam bracket
CN110565676A (en) * 2019-08-01 2019-12-13 中交二公局第二工程有限公司 Cantilever type tower crane foundation structure and construction method thereof
CN110863436A (en) * 2019-12-09 2020-03-06 中铁大桥局集团有限公司 Construction method for auxiliary pier and side pier top segment of cantilever-erected cable-stayed bridge
CN112523090B (en) * 2020-11-11 2022-11-18 中交二航局第二工程有限公司 Initial internode installation mode of steel truss girder cable-stayed bridge
CN112609578B (en) * 2020-11-24 2022-07-22 中铁二局集团有限公司 Method for mounting steel truss girder at top section of bridge pier of cable-stayed bridge
CN112663499A (en) * 2020-12-01 2021-04-16 中铁二局集团有限公司 Positioning and mounting method for lower chord of steel truss girder of cable-stayed bridge
CN113718658B (en) * 2021-09-18 2023-03-14 中铁大桥局集团第五工程有限公司 Butt joint method for steel trussed beams of cable-stayed bridge
CN113818356A (en) * 2021-10-25 2021-12-21 中交二公局第五工程有限公司 Cable-stayed bridge tower area steel plate beam and bridge deck installation method
CN114016422B (en) * 2021-11-23 2023-11-03 中铁大桥局集团有限公司 Steel girder erection method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3940211B2 (en) * 1997-12-22 2007-07-04 前田建設工業株式会社 Construction method of horizontal beams for concrete main tower.
CN1900423A (en) * 2006-07-10 2007-01-24 中铁大桥局股份有限公司 Integrate section frame building method for steel truss
CN101210415A (en) * 2007-12-20 2008-07-02 中铁大桥局股份有限公司 Method for mounting bridge main tower cross beam top steel box girder segment
CN101476294B (en) * 2009-01-22 2010-10-27 四川公路桥梁建设集团有限公司 Mounting method for underbeam segment of large-stride steel box girder stayed-cable bridge
CN101649604B (en) * 2009-08-28 2011-04-13 中铁八局集团第一工程有限公司 Construction bracket of 1# block of inclined pull bridge and constructing method thereof

Also Published As

Publication number Publication date
CN102535343A (en) 2012-07-04

Similar Documents

Publication Publication Date Title
CN102535343B (en) Method for erecting girder on top of main tower mound of steel truss girder cable-stayed bridge
CN102121234B (en) Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN104929373B (en) Large span Square Steel Tubes Truss and its accumulation slippage construction method
CN102108676B (en) Arch bridge construction method for combined beam-steel arch combined system
CN102535348B (en) Method for tensioning stayed cables of hinged tower cable stayed bridge
CN104532748B (en) The floating jacking of a kind of super kiloton steel truss girder pushes away erection construction method
CN103882812B (en) Across the construction method of girder in stayed-cable bridge
CN102953343A (en) Descending bracket self-mobile model framework bridge fabrication machine
CN105648924A (en) Construction method of multi-span simply-supported steel truss girder bridge
CN104652283A (en) Asynchronous splicing construction method for symmetrically splicing main steel girder erection cranes of cable-stayed bridge
CN104594201B (en) A kind of method utilizing one-sided pier-side bracket to set up pier top girder steel
CN201106155Y (en) Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN103669226A (en) River-crossing prestressed concrete continuous beam bridge box girder 0# block support construction method
CN105926457A (en) Method for mounting steel box girders in main tower area of cable-stayed bridge and auxiliary girder erection crane base
CN101324054B (en) Incremental launching positioning construction method of bridge subsection girder temporary pier
CN102582786A (en) Building process for deep sea spar platform
CN102587293A (en) System and method for cradle cantilever construction of variable-width section concrete girder
CN103806374B (en) The overall track erection supplying system of assembly type steel bridge on highway and erection push technique
CN110093862A (en) Vertically and horizontally assembled three working face Bridge Erectors and bent cap can be achieved without sidewalk section assembling engineering method
CN105970822B (en) A kind of 50m double width upstroke movable framework and its corresponding beam-making construction method
CN102587280B (en) Main tower area steel truss girder erection method of base support auxiliary frame beam crane and base support
CN102587292B (en) System and method for cradle cantilever construction
CN105155418A (en) Construction method for bridge horizontal movement
CN113026563A (en) Suspension bridge high-low displacement girder trestle girder hoisting facility and construction method thereof
CN105696470A (en) Synchronous quick steel box girder in-situ incremental launching and tower column construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150226

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430074 WUHAN, HUBEI PROVINCE TO: 430050 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20150226

Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No.

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: 430074 Hubei province Wuhan Dongxin East Lake New Technology Development Zone Road SBI Venture Street No. 6 Building 12 layer

Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd.

TR01 Transfer of patent right

Effective date of registration: 20190410

Address after: 400020 No.1-1, No.2-1, No.3-1, No.4-1, No.6 East Ring Road, Gangcheng City, Jiangbei District, Chongqing

Patentee after: The 8th Engineering Co., MBEC

Address before: 430050 Hanyang Avenue, Hanyang District, Wuhan, Hubei Province, No. 38

Patentee before: Group Co., Ltd., Zhongtie Daqiao Bureau

TR01 Transfer of patent right