Well formula hardening and tempering furnace pedestal frock Download PDFInfo
- Publication number
- CN207031502U CN207031502U CN201720796028.XU CN201720796028U CN207031502U CN 207031502 U CN207031502 U CN 207031502U CN 201720796028 U CN201720796028 U CN 201720796028U CN 207031502 U CN207031502 U CN 207031502U
- Authority
- CN
- China
- Prior art keywords
- link slot
- support
- hanger
- tempering furnace
- well formula
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Heat Treatment Of Articles (AREA)
Abstract
The utility model discloses a kind of well formula hardening and tempering furnace pedestal frock, including:Support meanss, described support meanss include:Collet, uniform welding has four the first support blocks on collet, and uniform welding is gone back on collet some support bases, and support base is provided with the second support block;The support meanss are provided with pendant device, and the pendant device includes:Base, uniform welding has four the first hangers on base outer wall, and some link slots are also symmetrically provided with base outer wall, and link slot is provided with the second hanger, and connecting rod is provided with the left of the second hanger, and connecting rod left side is provided with pillar;The pendant device is provided with suspension rod;The utility model is removably set by the second support block and the second hanger, so that this well formula hardening and tempering furnace pedestal frock can adapt to process while the axle of varying number, reduce the loss of frock, increase the utilization rate of equipment, raise labour efficiency, manufacturing schedule is accelerated, while also greatlys save cost.
Description
Technical field
The utility model belongs to field of machining, is related to a kind of well formula hardening and tempering furnace, specifically well formula hardening and tempering furnace pedestal work
Dress.
Background technology
Hardening and tempering furnace refers to the stove carried out steel or steel part used in the composite heat treating process of quenching and tempering.After modifier treatment
Steel be referred to as quenched and tempered steel, generally refer to medium carbon steel of the phosphorus content in 0.3-0.6%.The part requirements typically made of this kind of steel have
There is good comprehensive mechanical performance, i.e., there is good plasticity and toughness again while higher intensity is kept, people are often
Reach this purpose using modifier treatment, so this kind of steel is traditionally just referred to as quenched and tempered steel by people.On all kinds of machines
Constitutional detail largely uses quenched and tempered steel, is most popular a kind of steel in structural steel.
Currently, factory carries out modifier treatment to workpiece using well formula hardening and tempering furnace mostly, but enterprise is in the tune used at present
The supporting pedestal bearing capacity of matter furnace apparatus is limited, and a stove is quenched can only at most to adjust 12 axles (shaft diameter≤φ 210), and efficiency is low
Under, the manpower and materials of serious waste company.Unresolved drawbacks described above, it is proposed that a solution.
Utility model content
The purpose of this utility model is to provide well formula hardening and tempering furnace pedestal frock.
The purpose of this utility model can be achieved through the following technical solutions:
Well formula hardening and tempering furnace pedestal frock, including:Support meanss, described support meanss include:Collet, uniformly weld on collet
Four the first support blocks are connected to, uniform welding is gone back on collet there are some support bases, and support base is provided with the second support block;The branch
Support arrangement is provided with pendant device, and the pendant device includes:Base, uniform welding has four the first hangers on base outer wall,
Some link slots are also symmetrically provided with base outer wall, link slot is provided with the second hanger, connecting rod is provided with the left of the second hanger,
Pillar is provided with the left of connecting rod;The pendant device is provided with suspension rod;
Further, second support block is provided with the first bolt, and the second support block passes through the first bolt
It is fixedly connected on collet, the second support block is detachable;
Further, the link slot includes the first link slot, and the second link slot, the first link slot are opened in base appearance
On face, the second link slot is on the left of the first link slot, and the second link slot is than the first connection groove width;
Further, the pillar is wider than connecting rod;
Further, second hanger is connected by connecting rod, pillar and link slot, pillar and the second link slot gap
Coordinate, connecting rod coordinates with the first link slot gap.
The beneficial effects of the utility model:The utility model is removably set by the second support block and the second hanger,
So that this well formula hardening and tempering furnace pedestal frock can adapt to process while the axle of varying number, reduce the loss of frock, increase
The utilization rate of equipment, raises labour efficiency, and accelerates manufacturing schedule, while also greatly save cost.
Brief description of the drawings
For the ease of it will be appreciated by those skilled in the art that being further described below in conjunction with the accompanying drawings to the utility model.
Fig. 1 is the utility model front view;
Fig. 2 is the utility model top view;
Fig. 3 is the utility model collet top partial view diagram;
Fig. 4 is the utility model collet fragmentary front view;
Fig. 5 is the utility model base portion sectional view;
Fig. 6 is the utility model hanger part-structure schematic diagram.
Embodiment
As shown in figures 1 to 6, well formula hardening and tempering furnace pedestal frock, including:Support meanss 1, described support meanss 1 include:Bottom
Support 2, uniform welding has four the first support blocks 3 on collet 2, and uniform welding is gone back on collet 2 four support bases 4, on support base 4
Provided with the second support block 5, the second support block 5 is provided with the first bolt 6, and the second support block 5 is solid by the first bolt 6
Surely it is connected on collet 2, the second support block 5 is detachable;It is convenient to add or reduce the second support block 5 according to load-carrying, adapt to
The processing of varying number axle.The support meanss 1 are provided with pendant device 7, and the pendant device 7 includes:Base 8, outside base 8
Uniform welding has four the first hangers 9 on wall, and four link slots 10, the link slot 10 are also symmetrically provided with the outer wall of base 8
Including the first link slot 11, and the second link slot 12, the first link slot 11 is opened on the outer surface of base 8, and the second link slot 12 exists
The left side of first link slot 11, the link slot 11 of the second link slot 12 to the first are wide.Link slot 10 is provided with four second hangers 16, the
Two hangers 16 are arranged at intervals with the first hanger 9, and the left side of the second hanger 16 is provided with connecting rod 13, and the left side of connecting rod 13 is provided with pillar
14, pillar 14 is wider than connecting rod 13, and the second hanger 16 is connected by connecting rod 13, pillar 14 with link slot 10, pillar 14 and
The gap of two link slot 12 coordinates, and the link slot gap of connecting rod 13 and first coordinates.Second hanger 16 can be dismantled freely, be adapted to
The processing of varying number axle;The pendant device 7 is provided with suspension rod 15.
Well formula hardening and tempering furnace pedestal frock is corresponding to add according to the quantity of the axle of required processing when carrying out quenched work
The second support block and the second hanger, then processed according to normal flow.The utility model passes through the second support block and
Two hangers are removably set so that this well formula hardening and tempering furnace pedestal frock can adapt to process while the axle of varying number, subtract
Lack the loss of frock, increased the utilization rate of equipment, raise labour efficiency, accelerate manufacturing schedule, while also greatly save
Cost.
Above content is only to the utility model structure example and explanation, the technology people of affiliated the art
Member is made various modifications or supplement to described specific embodiment or substituted using similar mode, without departing from reality
With new structure or surmount scope defined in the claims, the scope of protection of the utility model all should be belonged to.
Claims (5)
1. well formula hardening and tempering furnace pedestal frock, it is characterised in that:Including support meanss (1), described support meanss (1) include:Bottom
Hold in the palm (2), uniform welding there are four the first support blocks (3) on collet (2), and going back uniform welding on collet (2) there are some support bases
(4), support base (4) is provided with the second support block (5);The support meanss (1) are provided with pendant device (7), the suspension member dress
Putting (7) includes:Base (8), uniform welding has four the first hangers (9) on base (8) outer wall, also symmetrical on base (8) outer wall
Be provided with some link slots (10), link slot (10) is provided with the second hanger (16), and connecting rod is provided with the left of the second hanger (16)
(13), it is provided with pillar (14) on the left of connecting rod (13);The pendant device (7) is provided with suspension rod (15).
2. well formula hardening and tempering furnace pedestal frock according to claim 1, it is characterised in that:Set on second support block (5)
There is the first bolt (6), the second support block (5) is fixedly connected on collet (2) by the first bolt (6), second
Bracer (5) is detachable.
3. well formula hardening and tempering furnace pedestal frock according to claim 1, it is characterised in that:The link slot (10) includes first
Link slot (11), and the second link slot (12), the first link slot (11) are opened on base (8) outer surface, the second link slot (12)
On the left of the first link slot (11), the second link slot (12) is wider than the first link slot (11).
4. well formula hardening and tempering furnace pedestal frock according to claim 1, it is characterised in that:The pillar (14) compares connecting rod
(13) it is wide.
5. well formula hardening and tempering furnace pedestal frock according to claim 1, it is characterised in that:Second hanger (16) and first
Hanger (9) is arranged at intervals, and the second hanger (16) is connected by connecting rod (13), pillar (14) with link slot (10), pillar (14)
Coordinate with the second link slot (12) gap, connecting rod (13) coordinates with the first link slot gap.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720796028.XU CN207031502U (en) | 2017-07-04 | 2017-07-04 | Well formula hardening and tempering furnace pedestal frock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720796028.XU CN207031502U (en) | 2017-07-04 | 2017-07-04 | Well formula hardening and tempering furnace pedestal frock |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207031502U true CN207031502U (en) | 2018-02-23 |
Family
ID=61466645
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720796028.XU Expired - Fee Related CN207031502U (en) | 2017-07-04 | 2017-07-04 | Well formula hardening and tempering furnace pedestal frock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207031502U (en) |
-
2017
- 2017-07-04 CN CN201720796028.XU patent/CN207031502U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203700474U (en) | Hot-dip galvanizing ring-type production line | |
CN206486569U (en) | Axial workpiece quenching for material rack | |
CN202878283U (en) | Rotating tool frame | |
CN207031502U (en) | Well formula hardening and tempering furnace pedestal frock | |
CN101417384A (en) | Production method of low-carbon free-cutting steel | |
CN209411003U (en) | A kind of conveyer of adjustable delivery board angled conveyor | |
CN208575101U (en) | A kind of wear-resisting conveying roller on the steel rolling line bushing using iron-based ceramics | |
CN213113582U (en) | Adjustable general electroplating rack for shaft parts | |
CN2908525Y (en) | Pin shaft hardening device | |
CN208913405U (en) | A kind of ring flange welding electronic pneumatic hammer easy to remove | |
CN202766088U (en) | Lifting device during shot blasting of large workpiece | |
CN211916576U (en) | Fixing device for metal box processing | |
CN206279259U (en) | A kind of fixture of ring-shaped work pieces nitridation | |
CN206029674U (en) | Take frock of L type mounting | |
CN208544721U (en) | One kind removing iron conveyer | |
CN209291764U (en) | A kind of heat treatment hanging apparatus for piston rod | |
CN109607184A (en) | A kind of numerically-controlled machine tool processing clamping transfer device | |
CN204450242U (en) | A kind of shot-blasting machine suspender | |
CN203033634U (en) | Novel multipurpose lifting tool for pit furnace | |
CN212100527U (en) | A continuous-flow type transmission structure for production of malleable cast iron pipe fitting | |
CN204508043U (en) | A kind of steel pipe conveyer frames with rust removing function | |
CN216473331U (en) | Simple tool for thermal treatment tempering of casting ledge | |
CN208104483U (en) | Heating device is used in a kind of quenching of bolt | |
CN204779698U (en) | Large -scale rotary part high frequency quenching equipment | |
CN207418811U (en) | A kind of runner heat treatment of workpieces special frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180223 Termination date: 20180704 |