CN206992495U - A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable - Google Patents

A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable Download PDF

Info

Publication number
CN206992495U
CN206992495U CN201720944331.XU CN201720944331U CN206992495U CN 206992495 U CN206992495 U CN 206992495U CN 201720944331 U CN201720944331 U CN 201720944331U CN 206992495 U CN206992495 U CN 206992495U
Authority
CN
China
Prior art keywords
cable
wiring
open ended
plug
gis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720944331.XU
Other languages
Chinese (zh)
Inventor
田俊强
李德强
吴蕾
邓大磊
李�远
王世泽
赵澄宇
黄永辉
梁尚坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Henan Energy Internet Electric Power Design Institute Co ltd
Original Assignee
China Electric Power Equipment and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Equipment and Technology Co Ltd filed Critical China Electric Power Equipment and Technology Co Ltd
Priority to CN201720944331.XU priority Critical patent/CN206992495U/en
Application granted granted Critical
Publication of CN206992495U publication Critical patent/CN206992495U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Installation Of Indoor Wiring (AREA)

Abstract

The utility model discloses a kind of wiring construction based on anti-open ended air plug and prefabricated branch cable, intelligent cabinet including GIS convergence control cabinets and with GIS convergence control cabinets by secondary cable wiring, described secondary cable wiring is by anti-open ended circle aviation plug and prefabricated branch cable combination wiring, leader cable line is drawn from GIS convergence control cabinets, and the cable of branch joint and the secondary device in intelligent cabinet is electrically connected by anti-open ended aviation plug;GIS converged into control wiring CT simplex winding three-phase current access secondary device using 46 cores anti-open ended circular configuration air plug with using, the corresponding device of a plug, does not influence other device during plug, in-site installation, wiring, debugging are convenient.By anti-open ended circle air plug and prefabricated branch cable connected applications, the different winding currents that same group of CT in wiring is controlled for GIS to be converged are connected to adjacent several cabinets by a cable, can significantly save cable dosage.

Description

A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable
Technical field
It the utility model is related to a kind of wiring construction based on anti-open ended air plug and prefabricated branch cable.
Background technology
With the continuous development of modern intelligent grid, one of important step of the intelligent substation as intelligent grid construction, It is the strong point of power network operation parameters collection point the most basic, management and control execution point and following intelligent grid, its development construction Level will directly influence the overall height of intelligent grid construction.To meet the requirement of intelligent grid, the intelligence of substation equipment It is melted into as a kind of new development trend, wherein in the intellectuality on the spot of control cabinet is also included within.
, it is necessary to which the intelligent apparatus such as combining unit, intelligent terminal, on-line monitoring is independent in the construction of GIS intelligent substations Intelligent cabinet is formed, is placed in substation secondary control room, intelligent cabinet and convergence control cabinet are apart from each other, it is necessary to live in intelligent cabinet Intelligent apparatus and convergence control cabinet carry out wiring by secondary cable so that cabinet inner terminal is arranged and wiring quantity is significantly increased therewith, just Cause wire to roll up, wire tail crimping process, risk be present, the pure armrest of connection procedure after conductor compression jointing with terminal block Work experience, efficiency is low and potential safety hazard be present.
Utility model content
To solve the deficiency of above-mentioned technical problem, there is provided a kind of wiring based on anti-open ended air plug and prefabricated branch cable Structure.
The utility model uses following technical scheme:
A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable, including GIS convergence control cabinets and and GIS Convergence control cabinet by the intelligent cabinet of secondary cable wiring, described secondary cable wiring be by anti-open ended circle aviation plug with it is pre- Branch cable combination wiring processed, leader cable line are drawn from GIS convergence control cabinets, the electricity of branch joint and the secondary device in intelligent cabinet Cable is electrically connected by anti-open ended aviation plug.
Described anti-open ended circle aviation plug can be with prefabricated branch cable combination wiring will be same in GIS convergence control cabinets One group of CT different winding currents are electrically connected into adjacent several intelligent cabinets by prefabricated branch cable and using aviation plug.
Two groups of different three-phase currents in GIS convergence control cabinets were connected into individual cable and two aviation plugs connect electrical connection Into same intelligent cabinet in different devices.
Using the utility model of above-mentioned technical proposal, there is advantages below:Using the anti-open ended circular configuration boat of 4-6 cores Insert and GIS is converged into control wiring CT simplex winding three-phase current access secondary device used, the corresponding device of a plug, during plug not Other device is influenceed, in-site installation, wiring, debugging are convenient.By anti-open ended circle air plug and prefabricated branch cable connected applications, The different winding currents that same group of CT in wiring is controlled for GIS to be converged are connected to adjacent several cabinets by a cable, can significantly save Save cable dosage.
Brief description of the drawings
Fig. 1 is the anti-open ended aviation plug of the utility model and prefabricated branch cable wiring schematic diagram.
Fig. 2 is the utility model unit cable and multiple aviation plug cable connection diagrams.
Wherein 1 is aviation plug, and 2 be prefabricated branch cable.
Embodiment
A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable, including GIS convergence control cabinets and and GIS Convergence control cabinet by the intelligent cabinet of secondary cable wiring, described secondary cable wiring be by anti-open ended circle aviation plug with it is pre- Branch cable combination wiring processed, leader cable line are drawn from GIS convergence control cabinets, the electricity of branch joint and the secondary device in intelligent cabinet Cable is electrically connected by anti-open ended aviation plug.
Such as Fig. 1:The different winding currents of same group of CT in GIS convergence control cabinets are inserted by prefabricated branch cable and using aviation Cable dosage can be greatly decreased into adjacent several intelligent cabinets in head electrical connection, and and can ensures the stability of wiring.
Such as Fig. 2:Two groups of different three-phase currents in GIS convergence control cabinets were connected into individual cable and two aviation plugs are electric It is connected in device different in same intelligent cabinet, cable dosage can be greatly decreased, also ensure that the stability of wiring.
Above-described is only preferred embodiment of the present utility model, it is noted that for those skilled in the art For, under the premise of the utility model general idea is not departed from, some changes and improvements can also be made, these should also be considered as The scope of protection of the utility model.

Claims (3)

1. a kind of wiring construction based on anti-open ended air plug and prefabricated branch cable, including GIS convergence control cabinets and converged with GIS Control intelligent cabinet of the cabinet by secondary cable wiring, it is characterised in that:Described secondary cable wiring is by the circular boat of anti-open ended Blind plug is drawn with prefabricated branch cable combination wiring, leader cable line from GIS convergence control cabinets, branch joint and two in intelligent cabinet The cable of secondary device is electrically connected by anti-open ended aviation plug.
2. a kind of wiring construction based on anti-open ended air plug and prefabricated branch cable as claimed in claim 1, its feature exist In:Described anti-open ended circle aviation plug can be by same group in GIS convergence control cabinets with prefabricated branch cable combination wiring CT different winding currents are electrically connected into adjacent several intelligent cabinets by prefabricated branch cable and using aviation plug.
3. a kind of wiring construction based on anti-open ended air plug and prefabricated branch cable as claimed in claim 1, its feature exist In:Two groups of different three-phase currents in GIS convergence control cabinets were connected into individual cable and two aviation plugs connect and are electrically connected to same In one intelligent cabinet in different devices.
CN201720944331.XU 2017-07-31 2017-07-31 A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable Expired - Fee Related CN206992495U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720944331.XU CN206992495U (en) 2017-07-31 2017-07-31 A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720944331.XU CN206992495U (en) 2017-07-31 2017-07-31 A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable

Publications (1)

Publication Number Publication Date
CN206992495U true CN206992495U (en) 2018-02-09

Family

ID=61417914

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720944331.XU Expired - Fee Related CN206992495U (en) 2017-07-31 2017-07-31 A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable

Country Status (1)

Country Link
CN (1) CN206992495U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113224649A (en) * 2021-05-19 2021-08-06 广东电网有限责任公司 Highly integrated modular protection device and switch cabinet

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113224649A (en) * 2021-05-19 2021-08-06 广东电网有限责任公司 Highly integrated modular protection device and switch cabinet

Similar Documents

Publication Publication Date Title
CN206098944U (en) Secondary circuit mistake proofing bayonet joint
CN206992495U (en) A kind of wiring construction based on anti-open ended air plug and prefabricated branch cable
CN210142847U (en) Join in marriage quick response access device of net side electrochemistry energy storage system
CN202949138U (en) Low-voltage cable branch box
CN203895633U (en) Short circuit grounding wire suitable for box transformer substation and electricity distribution room
CN208638279U (en) A kind of economic and reliable switching generator output device
CN204142947U (en) Secondary terminals shorting stub is used in mutual inductor test
CN204947516U (en) A kind of Intelligent Bus groove conversion equipment
CN206992441U (en) A kind of electric current concatenates pre-fabricated electric cables
CN206041016U (en) Practical earth connection in indoor GIS terminal
CN203895261U (en) Combined wire connector of secondary circuit short-circuiting wire of current/voltage transformer
CN206627574U (en) A kind of multidata transformer station's on-Line Monitor Device
CN201853820U (en) Miniature busbar connecting structure at top of metal armoured middle switch cabinet
CN206293812U (en) A kind of electric connection structure and Cubicle Gas-Insulated Switchgear
CN206208928U (en) Intelligent substation phase tests Special test line
CN203133149U (en) Detection device for grounding current of transformer core
CN208272368U (en) Electrical connection arrangement for the external DTU of high-tension switch cabinet
CN202503371U (en) Ultra-high voltage power transmission and transformation system
CN203398737U (en) Short-circuited terminal for short circuit of low-voltage cables
CN205304189U (en) Electric field high tension cable upper column system
CN203895640U (en) Grounding point switching device of voltage transformer secondary neutral grounding wire
CN211237877U (en) High-voltage electromagnetic induction electricity taking device
CN203166444U (en) Overhead transmission line with demarcation load switch
CN214176671U (en) Device for preventing reverse power supply of high-voltage line
CN203205548U (en) Multi-branch wiring board

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201123

Address after: 450000 9-18 / F, electric power building, 206 Zhongyuan West Road, Zhongyuan District, Zhengzhou City, Henan Province

Patentee after: State Grid Henan energy Internet Electric Power Design Institute Co.,Ltd.

Address before: Zhongyuan District Central Plains Road 450000 Henan city of Zhengzhou province No. 206

Patentee before: ZHENGZHOU ELECTRIC POWER DESIGN INSTITUTE OF CHINA ELECTRIC POWER EQUIPMENT AND TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180209

CF01 Termination of patent right due to non-payment of annual fee