CN206986729U - A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow - Google Patents

A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow Download PDF

Info

Publication number
CN206986729U
CN206986729U CN201720667963.6U CN201720667963U CN206986729U CN 206986729 U CN206986729 U CN 206986729U CN 201720667963 U CN201720667963 U CN 201720667963U CN 206986729 U CN206986729 U CN 206986729U
Authority
CN
China
Prior art keywords
box beam
pushing tow
steel
support frame
rectifying bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720667963.6U
Other languages
Chinese (zh)
Inventor
苏春生
林羽
武晓英
梁朋刚
宋连东
何十美
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dianchi College of Yunnan University
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
5th Engineering Co Ltd of MBEC
Original Assignee
Dianchi College of Yunnan University
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dianchi College of Yunnan University, Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical Dianchi College of Yunnan University
Priority to CN201720667963.6U priority Critical patent/CN206986729U/en
Application granted granted Critical
Publication of CN206986729U publication Critical patent/CN206986729U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow provided by the utility model, including multiple bolts, correction support frame, rolling wheel support frame and the roller being connected by sliding bearing with rolling wheel support frame;The correction support frame is fixedly connected on below rolling wheel support frame and is fastenedly connected with interim pier stud;Described rolling wheel support frame one end is fastenedly connected with interim pier stud, and the other end is connected by roller and box girder body;The bolt one side contacts with roller, and the tetrafluoro slide plate that another side moves together with pushing tow box beam contacts.The utility model can accurately be guided, limited, correcting box beam horizontal swing, skew, it is ensured that box beam moves along set direction.Meanwhile the utility model simple structure, operation facility is reusable, has wide applicability for incremental launching construction.Further, in engineering is implemented, the utility model can carry out that box beam is spacing and correction in multiple orientation, and guard box back pushes through the continuity of journey.

Description

A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow
Technical field
It the utility model is related to building engineering field, and in particular to a kind of spacing correction branch for the control of box beam pushing tow Frame.
Background technology
The construction of box beam method is one of construction method conventional and important in bridge construction, and its principle is to pass through jack Apply horizontal thrust, by slideway or sliding block by piecewise or whole section of beam pushing tow forward, fall beam after in place, change formal bearing.Top Pushing manipulation instead of hoist engine and coaster with level jack.Incremental launching method is to make on the A Geer bridges of Austria nineteen fifty-nine earliest With being characterized in:Because Work places limit within the specific limits, can ceiling be set above operation field and makes construction not by day Gas influences, all-weather construction.
In bridge incremental launching construction, when girder lateral deviation pushing tow route is larger, bridge need to be made using deviation correcting device Return on predetermined pushing tow route.In theory, pushing tow design advance track is continuous, along the continuous cloth in planned course line both sides Put stopping means pushing tow girder can be completely secured and advance along planned course, will not deviate, that is, not need deviation correcting device.
In Practical Project, due to construction error on Temporary Piers, box beam and slideway, so as to cause box beam in each slideway Upper friction will not be definitely identical, and some engineering designs are not symmetrical structures, therefore can offset axis during pushing tow Line position, thus for ensure box beam can accurately pushing tow to design attitude, it is necessary to correction control is carried out during pushing tow.
During actual pushing tow, generally use fixed idler whell is straight using the jack laterally set as stopping means Pick up top and carry out dynamic correcting to girder, it is spacing with correction often it is synchronous alternately, rectifying a deviation will when returning to designed path Be converted to it is spacing, such as deviate during spacing it is larger will enable correction, and frequently changing two kinds of equipment necessarily makes the company of pushing tow Continuous property substantially reduces.
Utility model content
The purpose of this utility model is to provide for a kind of simple to operation integrating spacing with deviation-correcting function use In the spacing deviation-rectifying bracket of box beam pushing tow control.
In order to solve the above technical problems, the utility model provides a kind of spacing deviation-rectifying bracket for the control of box beam pushing tow: Multiple bolts, correction support frame, rolling wheel support frame and the roller being connected by sliding bearing with rolling wheel support frame;It is described to entangle Inclined support frame is fixedly connected on below rolling wheel support frame and is fastenedly connected with interim pier stud;Described rolling wheel support frame one end with it is interim Pier stud is fastenedly connected, and the other end is connected by roller and box girder body;The bolt one side contacts with roller, another The tetrafluoro slide plate that face is moved together with pushing tow box beam contacts.
The rolling wheel support frame includes horizontally disposed channel-section steel and is vertically arranged in the 32a I-steel of channel-section steel one end, described Channel-section steel one end is provided with the first anchor ear being fastenedly connected with interim pier stud, is vertically arranged on the other end away from interim pier stud 32a I-steel is connected by sliding bearing with roller.
The triangular steel plate for reinforcing is welded in the channel-section steel and 32a I-steel connection, away from interim on the channel-section steel One end of pier stud is welded with strengthening steel slab.
The correction support frame includes the I-steel being welded on below channel-section steel and is fixedly connected on the second of I-steel one end Anchor ear;The I-steel is welded by two section 14a I-steel into obtuse angle.
The spacing deviation-rectifying bracket is symmetricly set on pushing tow box beam both sides.
Further, the spacing deviation-rectifying bracket is arranged on the rear and front end of pushing tow box beam.
A kind of described spacing deviation-rectifying bracket for the control of box beam pushing tow is realized by following construction procedure:
(1) spacing deviation-rectifying bracket is fixed on by the first anchor ear, the second anchor ear connected by channel-section steel with I-steel one end to be faced When pier stud on, make that there is between the beam body of roller and pushing tow box beam distance and the gap for being put into tetrafluoro slide plate;
(2) tetrafluoro slide plate is put between the beam body of roller and pushing tow box beam, on the contact surface of tetrafluoro slide plate and roller Smear lubricant;
(3) wedge-shaped wood is continuously fed in the side of pushing tow box beam or both sides according to the skew of pushing tow box beam when pushing tow advances Block, and ensure to be filled up by bolt between the beam body of pushing tow box beam and tetrafluoro slide plate;
(4) when overall offset axis is occurring during pushing tow for box beam, spacing deviation-rectifying bracket is fixed on pushing tow box beam Rear and front end, and the rear and front end of pushing tow box beam side simultaneously feed bolt so that integrally entangled before and after pushing tow box beam Partially.
When beam body pushing tow goes out spacing deviation-rectifying bracket, spacing deviation-rectifying bracket is removed, moves to the interim pier stud of next needs, Repeat step (1)~(4).
Beneficial effect:A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow provided by the utility model, including it is multiple Bolt, correction support frame, rolling wheel support frame and the roller being connected by sliding bearing with rolling wheel support frame, can be accurate Guiding, the box beam horizontal swing of limitation pushing tow, it is ensured that pushing tow box beam moves along set direction.When pushing tow box beam shifts, It can be rectified a deviation by the device, meanwhile, the utility model simple structure, operation facility is reusable, is applied for pushing tow Work has wide applicability simultaneously in engineering is implemented.Further, the utility model can carry out pushing tow case in multiple orientation Beam is spacing and correction, guard box back push through the continuity of journey.
Brief description of the drawings
Fig. 1 is a kind of schematic diagram of spacing deviation-rectifying bracket for the control of box beam pushing tow of the utility model;
Fig. 2 is the schematic top plan view that the anchor ear of the utility model first is fastenedly connected with interim pier stud;
Fig. 3 is the schematic top plan view that the anchor ear of the utility model second is fastenedly connected with interim pier stud;
Brief description of the drawings:1-roller;2-bolt;3-tetrafluoro slide plate;4-rolling wheel support frame;5-triangular steel plate; 6-strengthening steel slab;7-correction support frame, 8-I-steel;10-interim pier stud;11-channel-section steel;12-pushing tow box beam;13-the One anchor ear;14-32a I-steel;15-the second anchor ear.
Embodiment
Embodiment 1:
Below in conjunction with accompanying drawing, the present invention is further described.
As shown in figure 1, the utility model is a kind of bracket type inner form support system construction method, including multiple bolts 2nd, correction support frame 7, rolling wheel support frame 4 and the roller 1 being connected by sliding bearing with rolling wheel support frame.The correction support frame 7 are fixedly connected on the lower section of rolling wheel support frame 4;The rolling wheel support frame 4 includes horizontally disposed channel-section steel 11 and is vertically arranged in groove The 32a I-steel 14 of the one end of steel 11.As shown in Fig. 2 described one end of channel-section steel 11 is provided be fastenedly connected with interim pier stud 10 One anchor ear 13, the 32a I-steel 14 that is vertically arranged is connected by sliding bearing and roller 1 on the other end away from interim pier stud 10 Connect.The triangular steel plate 5 for reinforcing is welded in the channel-section steel 11 and the connection of 32a I-steel 14, away from facing on the channel-section steel 11 When pier stud 10 one end be welded with strengthening steel slab 6, for it is spacing correction support frame reinforcing, avoid spacing correction process due to Spacing deviation-rectifying bracket insufficient strength causes to damage, and then causes rectifying effect bad.Triangular steel plate 5 selects the processing of 4cm steel plates Form, strengthening steel slab 6 selects 2cm steel plates.As shown in figure 3, the correction support frame 7 includes being welded on the work of the lower section of channel-section steel 11 Word steel 8 and the second anchor ear 15 for being fixedly connected on the one end of I-steel 8;The I-shaped being welded by two section 14a I-steel into obtuse angle Steel 8 leaves the connection end being fixedly connected with channel-section steel and anchor ear.The one side of bolt 2 contacts with roller 1, another side with The tetrafluoro slide plate 3 that pushing tow box beam 12 moves together contacts, and during box beam pushing tow, bolt 2 is with the shifting of tetrafluoro slide plate 3 It is dynamic to be embedded between the beam body of pushing tow box beam 12 and tetrafluoro slide plate, complete the correction of pushing tow box beam 12.
The utility model is embodied as in work progress:
(1) by the second anchor ear 15 for being connected on the first anchor ear 13 and I-steel 8 that are connected on channel-section steel 11 by spacing correction Support is fixed on interim pier stud 10, roller 1 is had the distance and the gap that are put into tetrafluoro slide plate 3 with the beam body of pushing tow box beam 12. According to pushing tow box beam 12 and the size of the size design of interim pier stud 10 correction support frame 7 when prepared by spacing deviation-rectifying bracket, according to top Push away box beam 12 quality and pushing tow during spacing deviation-rectifying bracket need the pressure born, adjust the quantity of strengthening steel slab 6, reached To good consolidation effect.
(2) tetrafluoro slide plate 3 is put between the beam body of roller 1 and pushing tow box beam 12, in connecing for tetrafluoro slide plate 3 and roller 1 Lubricant is smeared in contacting surface, to reduce the frictional force between tetrafluoro slide plate 3 and roller 1, while also enables bolt 2 more preferable Between embedded tetrafluoro slide plate 3 and roller 1.Tetrafluoro slide plate 3 is smooth when being put between the beam body of roller 1 and pushing tow box beam 12 Simultaneously contacted with beam body, the one side of hole contacts with roller 1.With the continuous push of pushing tow box beam 12, tetrafluoro slide plate 3 is preceding End is constantly skidded off, it is necessary to from being continuously fed to tetrafluoro slide plate 3 below.
(3) when box beam pushing tow advances, wedge is continuously fed in the side of pushing tow box beam 12 according to the offset direction of pushing tow box beam 12 Shape wooden unit 2, and ensure to be filled up by bolt 2 between beam body and tetrafluoro slide plate 3, as box beam pushing tow moves ahead, constantly amendment skew, Return on axis.
(4) when beam body pushing tow goes out spacing deviation-rectifying bracket, spacing deviation-rectifying bracket is removed, moves to the Temporary Piers of next needs Post, repeat step (1)~(4).
Embodiment 2:
The present embodiment is improved on the basis of above-described embodiment, is theed improvement is that:If box beam is in pushing tow process In, the beam body overall offset pushing tow axis of pushing tow box beam 12 then can be in the rear and front end peace of the same side that pushing tow box beam 12 is inclined to Spacing deviation-rectifying bracket is filled, the spacing deviation-rectifying bracket of opposite side of pushing tow box beam 12 is same as Example 1, and is synchronously fed in the same side Bolt 2, corrected with reaching the overall of the skew of pushing tow box beam 12.If the overall offset of pushing tow box beam 12 and front and back end offset distance From it is different when, then frequency can be fed according to the front and back end offset distance adjustment bolt 2 of pushing tow box beam 12, make pushing tow box beam 12 In overall offset makeover process, while take into account the left and right skew of pushing tow box beam 12.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 3:
The utility model can be arranged on pushing tow box beam 12 all around in four orientation, and in pushing tow box beam in work progress After 12 rear ends remove the spacing deviation-rectifying bracket of rear end, the spacing deviation-rectifying bracket of rear end is removed, moves to the correction of pushing tow box beam front end Next interim pier stud 10 of interim pier stud 10 where support, pushing tow box beam 12 is set to be maintained at four orientation upper limit corrections.
To reach more preferable spacing and rectifying effect, its Specific construction is embodied as:
(1) in all around the first anchor ear 13 and I-steel in four orientation by being connected on channel-section steel 11 of pushing tow box beam 12 Spacing deviation-rectifying bracket is symmetrically installed by the second anchor ear 15 connected on 8 to be fixed on interim pier stud 10, and with pushing tow box beam 12 Push process be constantly put into the tetrafluoro slide plate 3 for scribbling lubricant between beam body and roller 1, complete the spacing top of pushing tow box beam Push away.
(2) when pushing tow box beam 12 shifts, suitable bolt 2 is put on the direction that pushing tow box beam 12 is offset, Realize the correction during box beam pushing tow.When the push route of pushing tow box beam 12 returns to axis, stopping is put into bolt 2, continue box beam pushing tow.
(3) after the rear end of pushing tow box beam 12 removes the spacing deviation-rectifying bracket of rear end, the spacing deviation-rectifying bracket of rear end is removed, is moved to Next interim pier stud 10 of interim pier stud 10 where the deviation-rectifying bracket of pushing tow box beam front end, continues to complete the control of box beam pushing tow Spacing and correction.
Using this embodiment, box beam pushing tow process can be limited in four orientation, reaches good limit effect, simultaneously The installation of spacing deviation-rectifying bracket is carried out simultaneously with dismantling with box beam pushing tow process, it is not necessary to after box beam pushing tow process is stopped The installation and dismounting of spacing deviation-rectifying bracket are carried out again, are reached continuous pushing tow process, have been saved duration and the energy.Meanwhile four Carry out spacing in individual orientation, the offset distance of box beam is smaller, and correction process is simple to operation.
The other parts of the present embodiment are identical with above-described embodiment 1, therefore repeat no more.
The utility model is not limited to above-mentioned preferred forms, and anyone can draw other under the enlightenment of the present invention Various forms of products, however, make any change in its shape or structure, it is every with identical or similar to the present application Technical scheme, be within the scope of the present invention.

Claims (6)

  1. A kind of 1. spacing deviation-rectifying bracket for the control of box beam pushing tow, it is characterised in that:Including multiple bolts (2), correction Support frame (7), rolling wheel support frame (4) and the roller (1) being connected by sliding bearing with rolling wheel support frame (4);The correction branch Support (7) is fixedly connected on below rolling wheel support frame (4) and is fastenedly connected with interim pier stud (10);Described rolling wheel support frame one end It is fastenedly connected with interim pier stud (10), the other end is connected by roller (1) and box girder body;The bolt (2) one Face contacts with roller (1), tetrafluoro slide plate (3) contact that another side moves together with pushing tow box beam (12).
  2. A kind of 2. spacing deviation-rectifying bracket for the control of box beam pushing tow according to claim 1, it is characterised in that:The rolling Wheeling supporting frame (4) includes horizontally disposed channel-section steel (11) and is vertically arranged in the 32a I-steel (14) of channel-section steel (11) one end, described Channel-section steel (11) one end is provided with the first anchor ear (13) being fastenedly connected with interim pier stud (10), on the other end away from interim pier stud The 32a I-steel (14) being vertically arranged is connected by sliding bearing with roller (1).
  3. A kind of 3. spacing deviation-rectifying bracket for the control of box beam pushing tow according to claim 2, it is characterised in that:The groove The triangular steel plate (5) for reinforcing is welded in steel (11) and 32a I-steel (14) connection, away from interim pier stud on the channel-section steel One end be welded with strengthening steel slab (6).
  4. A kind of 4. spacing deviation-rectifying bracket for the control of box beam pushing tow according to claim 1, it is characterised in that:It is described to entangle Inclined support frame (7) includes I-steel (8) and the second anchor ear (15);Described I-steel (8) one end is fixedly connected on channel-section steel (11) bottom Portion, the other end are fixedly connected with the second anchor ear (15) being fastenedly connected with interim pier stud (10);The I-steel (8) is by two section 14a I-steel is welded into obtuse angle.
  5. A kind of 5. spacing deviation-rectifying bracket for the control of box beam pushing tow according to claim 1, it is characterised in that:The limit Position deviation-rectifying bracket is symmetricly set on pushing tow box beam (12) both sides.
  6. A kind of 6. spacing deviation-rectifying bracket for the control of box beam pushing tow according to claim 2, it is characterised in that:The limit Position deviation-rectifying bracket is arranged on pushing tow box beam (12) rear and front end.
CN201720667963.6U 2017-06-09 2017-06-09 A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow Active CN206986729U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720667963.6U CN206986729U (en) 2017-06-09 2017-06-09 A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720667963.6U CN206986729U (en) 2017-06-09 2017-06-09 A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow

Publications (1)

Publication Number Publication Date
CN206986729U true CN206986729U (en) 2018-02-09

Family

ID=61395171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720667963.6U Active CN206986729U (en) 2017-06-09 2017-06-09 A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow

Country Status (1)

Country Link
CN (1) CN206986729U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643595A (en) * 2018-06-29 2018-10-12 浙江省二建钢结构有限公司 The full-automatic aligning apparatus and its construction method of cantilever steel girder
CN111926685A (en) * 2020-08-19 2020-11-13 中铁二院工程集团有限责任公司 Shear force conversion component for transversely moving high-speed railway continuous beam and conversion method
CN112627065A (en) * 2020-12-31 2021-04-09 陕西铁路工程职业技术学院 Bridge pier stud resetting means that rectifies
CN114892539A (en) * 2022-05-15 2022-08-12 中建七局第四建筑有限公司 Steel box girder pushing construction support with settlement monitoring function and use method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643595A (en) * 2018-06-29 2018-10-12 浙江省二建钢结构有限公司 The full-automatic aligning apparatus and its construction method of cantilever steel girder
CN108643595B (en) * 2018-06-29 2023-04-28 浙江省二建钢结构有限公司 Full-automatic correcting device for cantilever steel beam and construction method thereof
CN111926685A (en) * 2020-08-19 2020-11-13 中铁二院工程集团有限责任公司 Shear force conversion component for transversely moving high-speed railway continuous beam and conversion method
CN111926685B (en) * 2020-08-19 2022-02-22 中铁二院工程集团有限责任公司 Shear force conversion component for transversely moving high-speed railway continuous beam and conversion method
CN112627065A (en) * 2020-12-31 2021-04-09 陕西铁路工程职业技术学院 Bridge pier stud resetting means that rectifies
CN114892539A (en) * 2022-05-15 2022-08-12 中建七局第四建筑有限公司 Steel box girder pushing construction support with settlement monitoring function and use method thereof
CN114892539B (en) * 2022-05-15 2023-07-25 中建七局第四建筑有限公司 Steel box girder pushing construction support with sedimentation monitoring function and application method thereof

Similar Documents

Publication Publication Date Title
CN206986729U (en) A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow
CN103266573B (en) Steel Box Girder of Self-Anchored Suspension beam unidirectional single-point three slideway synchronous push construction method
CN202899016U (en) Arched steel truss bridge with slide rails
CN102587229B (en) Joint for track panel and manufacturing and installing method
CN103452018B (en) Track gauge correction method for double-block type ballastless track construction
CN214271732U (en) Bridge construction that stridees across railway line is with dilatory device
CN216864864U (en) A direction stop device for steel case roof beam pushes away construction
CN205369009U (en) Three -dimensional adjustment prestressing force support of PC roof beam
CN201671064U (en) Roller row slideway
CN107725066B (en) Prefabricated box culvert and layout method thereof
CN106270953B (en) Large-scale I-shaped crane beam field assembly, welding method
CN202705924U (en) Assembling platform arranged in the middle of bridge span
CN201420241Y (en) Dynamic hydraulic correcting system of steel box girder
CN117182461A (en) Manufacturing and construction control method for small-curvature high-pier continuous steel box girder
CN110172878B (en) Ground transportation rail installation method
CN203282598U (en) Movable steel pedestal with adjustable jacking
CN103273567B (en) Movable steel pedestal with adjustable jacking and construction method thereof
CN207242759U (en) Conveying device for large-scale heavy duty hardware
CN104947600A (en) Incremental launching construction platform
CN212925783U (en) Channel beam supporting device for crossing two railway business lines
CN211772922U (en) Translation thrustor for rush repair of railway pier
CN209907227U (en) Girder steel high altitude long distance top pushes away slide device
CN203021922U (en) Sliding support point assembly
CN213358352U (en) Support for bridge construction crossing railway line
CN213571836U (en) Special box track fixing device of synchronous lining cutting steel mould platform truck of inclined shaft

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant