CN206972383U - A kind of heated by natural gas system for Combined cycle gas-steam turbine - Google Patents
A kind of heated by natural gas system for Combined cycle gas-steam turbine Download PDFInfo
- Publication number
- CN206972383U CN206972383U CN201720947620.5U CN201720947620U CN206972383U CN 206972383 U CN206972383 U CN 206972383U CN 201720947620 U CN201720947620 U CN 201720947620U CN 206972383 U CN206972383 U CN 206972383U
- Authority
- CN
- China
- Prior art keywords
- gas
- turbine
- natural gas
- heated
- heater
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E20/00—Combustion technologies with mitigation potential
- Y02E20/16—Combined cycle power plant [CCPP], or combined cycle gas turbine [CCGT]
Landscapes
- Engine Equipment That Uses Special Cycles (AREA)
Abstract
A kind of heated by natural gas system for Combined cycle gas-steam turbine, including the gas turbine group being made up of gas turbine powered generator, gas turbine blower and gas turbine turbine, natural gas enters the acting of gas turbine turbine and generated electricity after being burnt in gas-turbine combustion chamber;Described gas-turbine combustion chamber is by performance heater connection natural gas pressure regulating station, the startup heater for being used for that dew point heating to be carried out to input natural gas is provided among natural gas pressure regulating station, the middle pressure economizer of described performance heater connection waste heat boiler, the delivery port of performance heater connect the condensate pump of Turbo-generator Set by pipeline.The utility model can make natural gas temperature enter gas-turbine combustion chamber after being lifted, and the middle pressure economizer of performance heater connection waste heat boiler, this causes the waste heat of middle pressure economizer to be fully used, and natural gas temperature gets a promotion, and effectively increases unit efficiency.
Description
Technical field
It the utility model is related to heated by natural gas system, specially a kind of natural gas for Gas-steam Combined Cycle
Heating system.
Background technology
Natural gas enters the air after compressor compresses by natural gas pressure regulating station and arrogant aspiration, with about 1:52 ratio
Example premix, produce high temperature and high pressure flue gas subsequently into gas-turbine combustion chamber and promote combustion engine acting to generate electricity.Natural gas temperature conduct
The performance of a pair of gas turbines of the characteristic of fuel has a certain impact.Natural gas by the separation of voltage regulating station, filtering, pressure regulation and
Start heating, after meeting combustion engine requirement, burnt into gas-turbine combustion chamber.Gas turbine on startup, natural temperature
Degree will meet requirement of the combustion engine to fuel.It is required that natural gas temperature is higher than the degree of superheat of 28 DEG C of hydrocarbon dew point in fuel,
Nytron is avoided to liquefy.Starting heater can meet to require, so starting heater is also referred to as dew point heater.
Combustion engine is very wide to the use range of natural gas temperature, and basic demand will ensure the degree of superheat higher than 28 DEG C of dew point, open
Dynamic heater can typically be heated to natural gas temperature 60 DEG C or so, the degree of superheat of 28 DEG C higher than dew-point temperature, fully meet combustion
Requirement of the machine to natural gas.It is rare and expensive due to natural gas, the initial outlay cost increase of fuel, cause per kilowatt to make
Valency is high, so seeking how effectively to improve unit performance, to compensate the loss that the high price of natural gas is brought, while can also carry
High unit efficiency, turn into technically need improve the problem of, the raising of natural gas temperature can increase combustion engine entrance heat, from
And natural gas gas consumption is reduced, reach raising unit output and put forward efficient purpose.
Utility model content
The purpose of this utility model is to be directed to above-mentioned the problems of the prior art, there is provided one kind is used for fuel gas-steam and joined
The heated by natural gas system of circulation is closed, by being equipped with performance heater, effectively improves unit performance.
To achieve these goals, the technical solution adopted in the utility model is:
Including the gas turbine group being made up of gas turbine powered generator, gas turbine blower and gas turbine turbine,
The air that natural gas and compressor come enters the acting of gas turbine turbine after gas-turbine combustion chamber burning and generated electricity;Described
Gas-turbine combustion chamber is used for inputting day by performance heater connection natural gas pressure regulating station, central be provided with natural gas pressure regulating station
Right gas carries out the startup heater of dew point heating, and described performance heater connects the middle pressure economizer of waste heat boiler, and performance adds
The delivery port of hot device connects the condensate pipe of Turbo-generator Set by pipeline.
It is additionally provided among described natural gas pressure regulating station for being separated, being filtered, the unit of pressure regulation to input natural gas.
Pressed in the performance heater connection and be provided with out water regulating valve on the pipeline of economizer water outlet.
The described water regulating valve that goes out includes being arranged on performance heater outlet side.
The Turbo-generator Set is by turbine generator, steam turbine high-pressure cylinder, Steam Turbine Through IP Admission, turbine low pressure cylinder
Composition;Turbine low pressure cylinder connects condenser, and condenser connects waste heat boiler and performance heater by condensate pump.
The feed temperature that described middle pressure economizer is passed through performance heater is 220 DEG C~230 DEG C.
The output natural gas temperature for starting heater is heated to 185 DEG C by described performance heater by 60 DEG C.
Described performance heater uses shell-and-tube heat exchanger, including housing and by some molecular tube banks of pipe.
Compared with prior art, the utility model has following beneficial effect:Gas turbine group initial start stage, by opening
Dynamic heater carries out heating to natural gas and is allowed to be higher than more than 28 DEG C of dew-point temperature, when set grid-connection input combined-cycle operation and
When the middle pressure economizer exit feed temperature of waste heat boiler is more than 50 DEG C, performance heater is put into, by performance heater to day
Right gas is reheated, and due to the setting of performance heater, enters gas-turbine combustion chamber after natural gas temperature lifting, and performance
Heater connects the middle pressure economizer of waste heat boiler, and the delivery port of performance heater connects the solidifying of Turbo-generator Set by pipeline
Pipe is born water, this causes the waste heat of middle pressure economizer to be fully used, and without outside vapour source, reduces natural gas dosage, simultaneously
Output is also add, reduces heat consumption, adds unit efficiency, solves that existing gas turbine group cost per kilowatt is high to ask
Topic.
Further, the pipeline of economizer water outlet is pressed to be adjusted provided with water outlet in the connection of the utility model performance heater
Valve, going out water regulating valve regulating water flow makes the natural gas temperature for being passed through gas-turbine combustion chamber reach 185 DEG C or so, meets combustion gas
Turbine combustion requirement.
Brief description of the drawings
Fig. 1 overall structure diagrams of the present utility model;
In accompanying drawing:1- gas-turbine combustion chambers;2- performance heaters;3- starts heater;4- waste heat boilers;Press and save in 5-
Coal device;6- condensers;7- condensate pumps;8- natural gas pressure regulatings station;9- goes out water regulating valve.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
Referring to Fig. 1, the utility model includes by gas turbine powered generator, gas turbine blower and combustion gas in structure
The gas turbine group of turbine turbine composition, natural gas are done after being burnt in gas-turbine combustion chamber 1 into gas turbine turbine
Work(generates electricity.Gas-turbine combustion chamber 1 connects natural gas pressure regulating station 8 by performance heater 2, is provided among natural gas pressure regulating station 8
For carrying out the startup heater 3 of dew point heating to input natural gas and for input natural gas to be separated, filters, adjusted
The unit of pressure.Performance heater 2 connects the middle pressure economizer 5 of waste heat boiler 4, is provided with the water outlet lateral line of performance heater 2
Go out water regulating valve 9.The delivery port of performance heater 2 connects the condensate pump 7 of Turbo-generator Set by pipeline.Waste heat boiler 4
On be provided with main chimney and chimney bypass, chimney bypass connection gas turbine turbine.
Turbo-generator Set is by turbine generator, steam turbine high-pressure cylinder, Steam Turbine Through IP Admission, turbine low pressure cylinder group
Into.Turbine low pressure cylinder connects condenser 6, and condenser 6 connects waste heat boiler 4 and performance heater 2 by condensate pump 7.
The feed temperature that middle pressure economizer 5 is passed through performance heater 2 is 220 DEG C~230 DEG C.Performance heater 2 can incite somebody to action
The output natural gas temperature for starting heater 3 is heated to 185 DEG C by 60 DEG C.The natural gas external from factory passes through natural gas pressure regulating station
Enter gas-turbine combustion chamber 1 and Combustion of Premixed after 8 separation, filtering, pressure regulation and heating.When unit starts to start, first
By starting the heated natural gas of heater 3 so that natural gas temperature is higher than the degree of superheat of 28 DEG C of hydrocarbon dew point in fuel,
Avoid nytron from liquefying, meet requirement of the gas turbine group to fuel.When set grid-connection puts into combined-cycle operation, and waste heat
When the middle exit water temperature of pressure economizer 5 of boiler 4 is more than 50 DEG C, performance heater 2 is put into, 3 are approximately passed through in Combined Cycle Unit
When individual hour reaches rated load, the outlet feed temperature of middle pressure economizer 5 reaches 220 DEG C.Performance heater 2 uses shell-and-tube
Heat exchanger, shell-and-tube heat exchanger are made up of a housing and the tube bank comprising many pipes, pass through pipe between cold and hot fluid
Wall is exchanged heat.Natural gas is flowed through from shell-side, and the middle pressure economizer 5 heating feedwater from waste heat boiler 4 is flowed through in pipe, hot and cold
Fluid obtains abundant heat convection.After the heated natural gas of performance heater 2, outlet condensate enters by going out water regulating valve 9
Enter the condensate pipe after condensate pump 7, the function of going out water regulating valve 9 is to reach regulation natural gas temperature by adjusting feedwater flow
Reach 185 DEG C or so, to meet the requirement of burning.The utility model makes feeding gas-turbine combustion chamber 1 using performance heater 2
Natural gas temperature reach 185 DEG C, add unit and integrally contribute, improve unit efficiency.
Particular embodiments described above, the purpose of this utility model, technical scheme and beneficial effect are entered
The detailed description of one step, above content are only specific embodiment of the utility model, it is impossible to assert tool of the present utility model
Body embodiment is only limitted to this, all within the spirit and principles of the utility model, some simple deduction or replace made,
The scope of patent protection that the utility model is determined by submitted claims should be all considered as belonging to.
Claims (8)
- A kind of 1. heated by natural gas system for Gas-steam Combined Cycle, it is characterised in that:Including by gas turbine power generation The air that the gas turbine generator group of machine, gas turbine blower and gas turbine turbine composition, natural gas and compressor come Enter the acting of gas turbine turbine after burning in gas-turbine combustion chamber (1) to generate electricity;Described gas-turbine combustion chamber (1) Natural gas pressure regulating station (8) are connected by performance heater (2), is provided with and is used for inputting natural gas among natural gas pressure regulating station (8) Carry out the startup heater (3) of dew point heating, the middle pressure economizer of described performance heater (2) connection waste heat boiler (4) (5), the delivery port of performance heater (2) connects the condensate pipe of Turbo-generator Set by pipeline.
- 2. it is used for the heated by natural gas system of Gas-steam Combined Cycle according to claim 1, it is characterised in that:It is described Natural gas pressure regulating station (8) among be additionally provided with for input natural gas to be separated, filtered, the unit of pressure regulation.
- 3. it is used for the heated by natural gas system of Gas-steam Combined Cycle according to claim 1, it is characterised in that:It is described Pressed in performance heater (2) connection and be provided with out water regulating valve (9) on the pipeline of economizer (5) water outlet.
- 4. it is used for the heated by natural gas system of Gas-steam Combined Cycle according to claim 3, it is characterised in that:It is described The water regulating valve (9) that goes out be arranged on performance heater (2) outlet side.
- 5. it is used for the heated by natural gas system of Gas-steam Combined Cycle according to claim 1, it is characterised in that:It is described Turbo-generator Set is made up of turbine generator, steam turbine high-pressure cylinder, Steam Turbine Through IP Admission, turbine low pressure cylinder;Steam turbine Low pressure (LP) cylinder connection condenser (6), condenser (6) connect waste heat boiler (4) and performance heater (2) by condensate pump (7).
- 6. it is used for the heated by natural gas system of Gas-steam Combined Cycle according to claim 1, it is characterised in that:It is described Middle pressure economizer (5) be passed through performance heater (2) feed temperature be 220 DEG C~230 DEG C.
- 7. it is used for the heated by natural gas system of Gas-steam Combined Cycle according to claim 1 or 6, it is characterised in that:Institute The output natural gas temperature for starting heater (3) is heated to 185 DEG C by the performance heater (2) stated by 60 DEG C.
- 8. it is used for the heated by natural gas system of Gas-steam Combined Cycle according to claim 1, it is characterised in that:It is described Performance heater (2) use shell-and-tube heat exchanger, including housing and by some molecular tube banks of pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720947620.5U CN206972383U (en) | 2017-07-31 | 2017-07-31 | A kind of heated by natural gas system for Combined cycle gas-steam turbine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720947620.5U CN206972383U (en) | 2017-07-31 | 2017-07-31 | A kind of heated by natural gas system for Combined cycle gas-steam turbine |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206972383U true CN206972383U (en) | 2018-02-06 |
Family
ID=61393653
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720947620.5U Active CN206972383U (en) | 2017-07-31 | 2017-07-31 | A kind of heated by natural gas system for Combined cycle gas-steam turbine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206972383U (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111852660A (en) * | 2020-06-16 | 2020-10-30 | 华电电力科学研究院有限公司 | Gas turbine performance heating system and operation method thereof |
CN113339093A (en) * | 2021-05-28 | 2021-09-03 | 上海申能临港燃机发电有限公司 | Flue gas waste heat effective utilization system of gas and steam combined cycle generator set |
IT202000022777A1 (en) * | 2020-09-28 | 2022-03-28 | Nuovo Pignone Tecnologie Srl | GAS TURBINE FUEL TREATMENT CIRCUIT AND METHOD FOR STARTING UP A GAS TURBINE. |
CN114687805A (en) * | 2020-12-30 | 2022-07-01 | 华能北京热电有限责任公司 | Turbine cooling and natural gas heating integrated gas turbine system |
CN114837818A (en) * | 2022-04-18 | 2022-08-02 | 中国联合重型燃气轮机技术有限公司 | Gas turbine system and power generation system |
CN114961906A (en) * | 2022-06-28 | 2022-08-30 | 西安热工研究院有限公司 | System for quickly starting gas-steam combined cycle unit and operation method |
GB2614839A (en) * | 2020-09-28 | 2023-07-19 | Nuovo Pignone Tecnologie Srl | Gas turbine fuel treatment circuit and method for starting up a gas turbine |
-
2017
- 2017-07-31 CN CN201720947620.5U patent/CN206972383U/en active Active
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111852660A (en) * | 2020-06-16 | 2020-10-30 | 华电电力科学研究院有限公司 | Gas turbine performance heating system and operation method thereof |
IT202000022777A1 (en) * | 2020-09-28 | 2022-03-28 | Nuovo Pignone Tecnologie Srl | GAS TURBINE FUEL TREATMENT CIRCUIT AND METHOD FOR STARTING UP A GAS TURBINE. |
WO2022063429A1 (en) * | 2020-09-28 | 2022-03-31 | Nuovo Pignone Tecnologie - S.R.L. | Gas turbine fuel treatment circuit and method for starting up a gas turbine |
GB2614839A (en) * | 2020-09-28 | 2023-07-19 | Nuovo Pignone Tecnologie Srl | Gas turbine fuel treatment circuit and method for starting up a gas turbine |
GB2614839B (en) * | 2020-09-28 | 2024-09-04 | Nuovo Pignone Tecnologie Srl | Gas turbine fuel treatment circuit and method for starting up a gas turbine |
CN114687805A (en) * | 2020-12-30 | 2022-07-01 | 华能北京热电有限责任公司 | Turbine cooling and natural gas heating integrated gas turbine system |
CN114687805B (en) * | 2020-12-30 | 2023-08-01 | 华能北京热电有限责任公司 | Turbine cooling and natural gas heating integrated gas turbine system |
CN113339093A (en) * | 2021-05-28 | 2021-09-03 | 上海申能临港燃机发电有限公司 | Flue gas waste heat effective utilization system of gas and steam combined cycle generator set |
CN114837818A (en) * | 2022-04-18 | 2022-08-02 | 中国联合重型燃气轮机技术有限公司 | Gas turbine system and power generation system |
CN114961906A (en) * | 2022-06-28 | 2022-08-30 | 西安热工研究院有限公司 | System for quickly starting gas-steam combined cycle unit and operation method |
CN114961906B (en) * | 2022-06-28 | 2024-05-17 | 西安热工研究院有限公司 | System for quickly starting gas-steam combined cycle unit and operation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206972383U (en) | A kind of heated by natural gas system for Combined cycle gas-steam turbine | |
CN109854313B (en) | Flexible coal-fired power generation system and operation method | |
CN103644004B (en) | The cogeneration system of a kind of pair of turbine, combined cycle | |
CN204402598U (en) | Join the double reheat supercharging steam turbine thermodynamic system of backpressure small turbine | |
CN103244944B (en) | Air preheating system and method performing steam extraction by utilizing steam turbine | |
CN107859538A (en) | It is a kind of to be used for the solidifying co-generation unit and its operation method for taking out back of the body heat supply | |
CN106499455A (en) | Combined-cycle power plant's soda pop backheat and fuel heating integrated put forward effect system | |
CN104675521A (en) | Novel gas-steam combined cycle cooling, heating and power generation system | |
CN207813667U (en) | Low pressure cylinder cooling system based on different steam ports | |
CN110344899A (en) | The system and method for high pressure industry steam supply ability is mentioned under a kind of power plant underload | |
CN207813675U (en) | A kind of co-generation unit for carrying on the back heat supply for solidifying pumping | |
CN106761982A (en) | A kind of new part backheating gas turbine combined cycle system | |
CN106437875B (en) | Fired power generating unit working medium bypassing circulation peak regulation system | |
CN104819054A (en) | Distributed energy resource waste heat utilization system | |
CN203249228U (en) | Air pre-heating system extracting steam through steam turbine | |
CN105443243A (en) | Gas-steam combined circulation system | |
CN206129338U (en) | Gas - steam combined cycle distributing type energy supply system | |
CN106523052A (en) | Combined-cycle power plant steam water back-heating and waste heat comprehensive utilization efficiency-improving system | |
CN103644032A (en) | System for heating natural gas through gradient utilization of water supplied at medium pressure from waste heat boiler of gas turbine power plant | |
CN105464731A (en) | Gas-steam combined system and operation control method thereof | |
CN105371267A (en) | Double-reheat steam turbine heat regenerative energy utilizing system for primary air and secondary air of heating boiler | |
CN102494329B (en) | Device for utilizing flue gas waste heat of boiler comprehensively | |
CN105042666B (en) | Wide-load heat supply energy-saving system of back pressure type small steam turbine driven draught fan | |
CN204704010U (en) | A kind of bootstrap system of distributed energy | |
CN204827562U (en) | Little steam turbine energy cascade utilization system of thermal power plant |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |