CN206971638U - A kind of marble dried hanging hang structure - Google Patents

A kind of marble dried hanging hang structure Download PDF

Info

Publication number
CN206971638U
CN206971638U CN201720907923.4U CN201720907923U CN206971638U CN 206971638 U CN206971638 U CN 206971638U CN 201720907923 U CN201720907923 U CN 201720907923U CN 206971638 U CN206971638 U CN 206971638U
Authority
CN
China
Prior art keywords
marble
main body
angle steel
wall
aluminium alloy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720907923.4U
Other languages
Chinese (zh)
Inventor
路春波
管作为
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA NATIONAL DECORATION Co Ltd
Original Assignee
CHINA NATIONAL DECORATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA NATIONAL DECORATION Co Ltd filed Critical CHINA NATIONAL DECORATION Co Ltd
Priority to CN201720907923.4U priority Critical patent/CN206971638U/en
Application granted granted Critical
Publication of CN206971638U publication Critical patent/CN206971638U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of marble dried hanging hang structure, including wall, ear type aluminium alloy suspension member, second angle steel and marble main body, the side of the wall is uniformly provided with stainless steel back of the body bolt, and the one end of stainless steel back of the body bolt away from wall is fixed with ear type aluminium alloy suspension member by the second fixing bolt, the top of the ear type aluminium alloy suspension member is respectively and fixedly provided with regulating bolt, and the both ends inside the ear type aluminium alloy suspension member below regulating bolt are mounted on the first clip, the sliding block to be cooperated with chute is evenly arranged with the marble main body, and the top of marble main body is provided with fixture block, the bottom of the marble main body is provided with neck.The utility model is cooperated by being provided with chute, chute with the sliding block in marble main body so that marble main body can be fixed on angle steel, and chute and sliding block are easily installed and dismantled.

Description

A kind of marble dried hanging hang structure
Technical field
Decorating outer wall of building technical field is the utility model is related to, specially a kind of marble dried hanging hang structure.
Background technology
With the continuous development of society, the living standard of people quickly improves, and while development, people are outer to building The requirement more and more higher of incrustation, cladding Dali Stone technique come into vogue, and stone material dry-hanging method also known as hang-in-air method, are current A kind of new construction technology in wall decoration, ornamental stone is directly hung on into metope with metal hanger for this method or sky is hung on On steelframe, stickup of being in the milk again is not required to, its principle is to set main stress point on the body construction, consolidates stone material by metal hanger It is scheduled on building, forms stone decoration curtain wall, but marble dry hanging construction at this stage is sufficiently complex, installation and removal are all Inconvenience, so raw material and construction cost are very high, and it is heavier plus marble itself, hang again on the wall, by self gravitation shadow Ring, it is easy to come off, cause danger, and most marble dried hanging hang structure when being collided, is also easy at this stage Breakage, can not also be connected between marble blocks in place, produce gap, in the course of time between stone material can hollowing, tilt even fragmentation, Therefore, it is badly in need of a kind of marble dried hanging hang structure to meet the needs of people.
Utility model content
The purpose of this utility model is to provide a kind of marble dried hanging hang structure, to solve what is proposed in above-mentioned background technology Problem.
To achieve the above object, the utility model provides following technical scheme:A kind of marble dried hanging hang structure, including wall Body, ear type aluminium alloy suspension member, the second angle steel and marble main body, the side of the wall are uniformly provided with stainless steel back of the body bolt, and The one end of stainless steel back of the body bolt away from wall is fixed with ear type aluminium alloy suspension member, the ear type aluminium alloy by the second fixing bolt The top of suspension member is respectively and fixedly provided with regulating bolt, and the both ends inside the ear type aluminium alloy suspension member below regulating bolt are mounted on One clip, the first angle steel is respectively and fixedly provided between first clip, and the bottom of the first angle steel side is solid by second Fixed button is connected with bottom of the ear type aluminium alloy suspension member away from wall side, and spiral shell is fixed in the bottom of first angle steel by first Bolt is fixed with the second angle steel, and the side of second angle steel away from wall is mounted on chute, and chute is away from the second angle steel Side is mounted on marble main body, and the sliding block to be cooperated with chute, and Dali are evenly arranged with the marble main body The top of stone main body is provided with fixture block, and the bottom of the marble main body is provided with neck.
Preferably, it is provided with plastic cement pad between the ear type aluminium alloy suspension member and wall.
Preferably, it is provided with damping spring between first angle steel and marble main body.
Preferably, the marble main body is provided with heat-insulation layer close to the side of wall.
Preferably, one end of the chute is provided with limited block.
Compared with prior art, the beneficial effects of the utility model are:The marble dried hanging hang structure by being provided with chute, Chute is cooperated with the sliding block in marble main body so that marble main body can be fixed on angle steel, chute It is easily installed and dismantles with sliding block, while device avoids, in construction, damaging device by friction by being provided with plastic cement pad It is bad, while device passes through the draw runner and slide rail in marble main body so that it can also be held in the mouth well between marble main body Fixation is connect, avoids producing gap between generation marble main body, hollowing or cracking, while device is caused into dust and moisture By being provided with damping spring, when marble main body is collided or extruded, damping, buffering can be played a part of, avoided big Reason stone main body directly contacts angle steel, and extruding is damaged, while device, by being provided with heat-insulation layer, preventing from expanding with heat and contract with cold causes marble Bulk deformation.
Brief description of the drawings
Fig. 1 is structure schematic side view of the present utility model;
Fig. 2 is marble main body schematic diagram of the present utility model;
Fig. 3 is partial schematic diagram of the present utility model;
In figure:1- walls;2- stainless steel back of the body bolt;The clips of 3- first;The clips of 4- second;5- plastic cement pads;6- is adjusted Bolt;7- ear type aluminium alloy suspension members;The angle steel of 8- first;9- fixture blocks;10- damping springs;The angle steel of 11- second;12- marble masters Body;The fixing bolts of 13- first;14- sliding blocks;The fixing bolts of 15- second;16- chutes;17- necks.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Refer to Fig. 1-3, a kind of embodiment provided by the utility model:A kind of marble dried hanging hang structure, including wall 1, Ear type aluminium alloy suspension member 7, the second angle steel 11 and marble main body 12, the side of wall 1 are uniformly provided with stainless steel back of the body bolt 2, and The one end of stainless steel back of the body bolt 2 away from wall 1 is fixed with ear type aluminium alloy suspension member 7 by the second fixing bolt 15, and ear type aluminium closes Plastic cement pad 5 is provided between golden suspension member 7 and wall 1, is avoided in construction, device directly contacts metope and is damaged, and ear type aluminium closes The top of golden suspension member 7 is respectively and fixedly provided with regulating bolt 6, and the both ends inside the ear type aluminium alloy suspension member 7 of the lower section of regulating bolt 6 are pacified Equipped with the first clip 3, the first angle steel 8 is respectively and fixedly provided between the first clip 3, between the first angle steel 8 and marble main body 12 It is provided with damping spring 10 so that when marble main body 12 is collided extruding, play a part of damping, and the first angle steel 8 The bottom of side is connected by the second clip 4 with bottom of the ear type aluminium alloy suspension member 7 away from the side of wall 1, the first angle steel 8 Bottom the second angle steel 11 is fixed with by the first fixing bolt 13, the second side of the angle steel 11 away from wall 1 is mounted on Chute 16, one end of chute 16 are provided with limited block, play a part of positioning, and side of the chute 16 away from the second angle steel 11 is equal Marble main body 12 is installed, marble main body 12 is provided with heat-insulation layer close to the side of wall 1, and avoiding expanding with heat and contract with cold, it is big to cause The deformation of reason stone main body 12 is impaired, and the sliding block 14 to be cooperated with chute 16, and marble are evenly arranged with marble main body 12 The top of main body 12 is provided with fixture block 9, and the bottom of marble main body 12 is provided with neck 17.
Operation principle:In use, stainless steel back of the body bolt 2 is fixed in wall 1 first, afterwards by ear type aluminium alloy suspension member 7 It is connected with the stainless steel back of the body bolt 2 inside wall 1 by the second fixing bolt, is provided between ear type aluminium alloy suspension member 7 and wall 1 Plastic spacer 5, avoid that device is caused to damage in construction, the top installation and adjustment bolt 6 of ear type aluminium alloy suspension member 7, ear type Both ends inside aluminium alloy suspension member 7 are respectively mounted the first clip 3, and the first angle steel 8 is fixed between the first clip 3, passes through tune Section bolt 6 can adjust the position of the first angle steel 8, and the side of the close wall 1 of the first angle steel 8 passes through the second clip 4 and ear Type aluminium alloy suspension member connects so that the fixation of the first angle steel 8 is more firm, and the bottom of the first angle steel 8 is fixed by first afterwards Bolt 13 fixes the second angle steel 11, and the second side of the angle steel 11 away from wall 1 is provided with chute 16, installed in marble main body 12 There is sliding block 14, chute 16 and sliding block 14 are cooperated afterwards so that marble main body 12 is installed on wall 1, is easily installed And dismounting, meanwhile, be provided with damping spring between the angle steel 8 of marble main body 12 and first, ensure marble main body 12 by To when extruding or collision, play a part of damping compression-resistant, protect marble main body 12 not to be damaged, meanwhile, in marble main body 12 Top be provided with fixture block 9, the bottom of marble main body 12 is provided with neck 17 so that can be by very between marble main body 12 It is connected fixation well, avoids producing gap and cause hollowing to ftracture, the side of last marble main body 12 is provided with heat-insulation layer, can be with Prevent from expanding with heat and contract with cold and cause marble main body 12 to damage.
It is obvious to a person skilled in the art that the utility model is not limited to the details of above-mentioned one exemplary embodiment, and And in the case of without departing substantially from spirit or essential attributes of the present utility model, it can realize that this practicality is new in other specific forms Type.Therefore, no matter from the point of view of which point, embodiment all should be regarded as exemplary, and is nonrestrictive, this practicality is new The scope of type limits by appended claims rather than described above, it is intended that the equivalency fallen in claim is contained All changes in justice and scope are included in the utility model.Any reference in claim should not be considered as limitation Involved claim.

Claims (5)

1. a kind of marble dried hanging hang structure, including wall (1), ear type aluminium alloy suspension member (7), the second angle steel (11) and marble master Body (12), it is characterised in that:The side of the wall (1) is uniformly provided with stainless steel back of the body bolt (2), and stainless steel back of the body bolt (2) is remote One end from wall (1) is fixed with ear type aluminium alloy suspension member (7) by the second fixing bolt (15), and the ear type aluminium alloy is hung The top of part (7) is respectively and fixedly provided with regulating bolt (6), and the both ends of ear type aluminium alloy suspension member (7) inside below regulating bolt (6) The first clip (3) is mounted on, the first angle steel (8), and the first angle steel (8) are respectively and fixedly provided between first clip (3) The bottom of side is connected by the second clip (4) with bottom of the ear type aluminium alloy suspension member (7) away from wall (1) side, institute The bottom for stating the first angle steel (8) is fixed with the second angle steel (11), second angle steel (11) by the first fixing bolt (13) Side away from wall (1) is mounted on chute (16), and side of the chute (16) away from the second angle steel (11) is mounted on greatly Reason stone main body (12), the sliding block (14) to be cooperated with chute (16) is evenly arranged with the marble main body (12), and greatly The top of reason stone main body (12) is provided with fixture block (9), and the bottom of the marble main body (12) is provided with neck (17).
A kind of 2. marble dried hanging hang structure according to claim 1, it is characterised in that:The ear type aluminium alloy suspension member (7) Plastic cement pad (5) is provided between wall (1).
A kind of 3. marble dried hanging hang structure according to claim 1, it is characterised in that:First angle steel (8) and Dali Damping spring (10) is provided between stone main body (12).
A kind of 4. marble dried hanging hang structure according to claim 1, it is characterised in that:The marble main body (12) is close The side of wall (1) is provided with heat-insulation layer.
A kind of 5. marble dried hanging hang structure according to claim 1, it is characterised in that:One end of the chute (16) is set Limited location block.
CN201720907923.4U 2017-07-25 2017-07-25 A kind of marble dried hanging hang structure Active CN206971638U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720907923.4U CN206971638U (en) 2017-07-25 2017-07-25 A kind of marble dried hanging hang structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720907923.4U CN206971638U (en) 2017-07-25 2017-07-25 A kind of marble dried hanging hang structure

Publications (1)

Publication Number Publication Date
CN206971638U true CN206971638U (en) 2018-02-06

Family

ID=61397073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720907923.4U Active CN206971638U (en) 2017-07-25 2017-07-25 A kind of marble dried hanging hang structure

Country Status (1)

Country Link
CN (1) CN206971638U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108571101A (en) * 2018-04-28 2018-09-25 浙江中南建设集团有限公司 A kind of back-bolt type stone curtain wall connector
CN109057114A (en) * 2018-09-26 2018-12-21 苏州市鑫泰建筑装璜有限公司 A kind of dry-hang stone curtain wall that anti-seismic performance is high
CN110295718A (en) * 2019-06-25 2019-10-01 何艳 It is a kind of for marble slab in architectural engineering or the dry hanging article device of ceramic tiles
CN110295717A (en) * 2019-06-25 2019-10-01 何艳 A kind of dried hanging method of marble slab
CN111719800A (en) * 2020-07-07 2020-09-29 宁波中腾建筑科技有限公司 Connection structure of green energy-conserving precast concrete outer wall and shear force wall
CN112647634A (en) * 2020-12-18 2021-04-13 苏州广林建设有限责任公司 Nested formula back of body is tied stone material furred ceiling structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108571101A (en) * 2018-04-28 2018-09-25 浙江中南建设集团有限公司 A kind of back-bolt type stone curtain wall connector
CN109057114A (en) * 2018-09-26 2018-12-21 苏州市鑫泰建筑装璜有限公司 A kind of dry-hang stone curtain wall that anti-seismic performance is high
CN110295718A (en) * 2019-06-25 2019-10-01 何艳 It is a kind of for marble slab in architectural engineering or the dry hanging article device of ceramic tiles
CN110295717A (en) * 2019-06-25 2019-10-01 何艳 A kind of dried hanging method of marble slab
CN111719800A (en) * 2020-07-07 2020-09-29 宁波中腾建筑科技有限公司 Connection structure of green energy-conserving precast concrete outer wall and shear force wall
CN112647634A (en) * 2020-12-18 2021-04-13 苏州广林建设有限责任公司 Nested formula back of body is tied stone material furred ceiling structure
CN112647634B (en) * 2020-12-18 2021-12-31 苏州广林建设有限责任公司 Nested formula back of body is tied stone material furred ceiling structure

Similar Documents

Publication Publication Date Title
CN206971638U (en) A kind of marble dried hanging hang structure
CN102305002B (en) Damper-including sliding wheel assembly under wall cabinet door
CN103423566A (en) Television wall hanging support with adjustable installment gap
CN206299004U (en) A kind of stone curtain wall with buffering coupling assembly
CN210134522U (en) Keel connecting structure based on assembly type building
CN203925061U (en) A kind of extension type door-inhale
CN107191444A (en) Automatic locking is fixed in a kind of new installation
CN201772226U (en) Hanging board for mounting panel TV set
CN106121121A (en) A kind of Combined type suspended ceiling
CN206789253U (en) KT plate Display Racks
CN202298930U (en) Building deformation joint
CN107795076A (en) One kind can hang thing skirting
CN205529114U (en) Electroplate product stores pylon
CN206090986U (en) Installation of stone material curtain fixed knot construct
CN203716443U (en) Ultrathin heat insulation decoration integrated plate installation system
CN207162195U (en) A kind of new side luminous lamp
CN207584572U (en) A kind of pendent lamp being easily installed
CN206205252U (en) ceiling fixing device
CN109989513A (en) A kind of novel building finishing furred ceiling
CN2842040Y (en) Inner hexagonal flat expansion bolt
CN203400816U (en) Connection structure of ceiling-mounted shower head
CN209245980U (en) A kind of easy-to-mount lamp casing component
CN203186170U (en) Base of fixed rod of bus
CN103758317B (en) A kind of ultra-thin heat insulation decoration integrated plate installation system
CN216305049U (en) Energy-saving environment-friendly curtain wall structure for decoration

Legal Events

Date Code Title Description
GR01 Patent grant