CN206970057U CN201720694079.1U CN201720694079U CN206970057U CN 206970057 U CN206970057 U CN 206970057U CN 201720694079 U CN201720694079 U CN 201720694079U CN 206970057 U CN206970057 U CN 206970057U
Authority
CN
China
Prior art keywords
tower crane
crane base
foundation ditch
diaphram wall
cushion cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720694079.1U
Other languages
Chinese (zh)
Inventor
金国栋
陈新喜
王俊佚
郭绍华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201720694079.1U priority Critical patent/CN206970057U/en
Application granted granted Critical
Publication of CN206970057U publication Critical patent/CN206970057U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

It the utility model is related to building engineering field, more particularly to a kind of tower crane base in foundation pit construction stage installation tower crane.To reduce the construction cost of tower crane base, improve the economy of tower crane base, the utility model proposes a kind of tower crane base, the tower crane base is located above foundation ditch diaphram wall, the tower crane base includes the cushion cap bar-mat reinforcement being connected with the foundation ditch diaphram wall, and the online casting concrete of the cushion cap reinforcing bar forms cushion cap.Such tower crane base is located on foundation ditch diaphram wall, therefore, workmen is when building foundation ditch diaphram wall, the cushion cap bar-mat reinforcement being connected with foundation ditch diaphram wall can be laid above foundation ditch diaphram wall according to tower crane position, so as to which tower crane base and diaphram wall formed by integrally casting be completed, the construction cost of tower crane base is greatly reduced, improves the economy of tower crane base.

Description

A kind of tower crane base
Technical field
It the utility model is related to building engineering field, more particularly to a kind of tower crane in foundation pit construction stage installation tower crane Pedestal.
Background technology
In Building Construction, it is often necessary to the tower crane base for arrangement installation early stage tower crane of constructing, that is, pouring Tower crane base while building sole plate, in order to complete material transportation work in construction work.Pacify in the foundation pit construction stage The tower crane base of dress tower crane generally comprises foundation pile, lattice column and cushion cap, and cost is high.But in the foundation pit construction stage, by Not perfect enough in the construction drawing of architectural engineering, the tower crane for causing the installation of foundation pit construction stage is difficult to meet follow-up construction institute The movement requirement needed, usage time is short, less economical.
Utility model content
To reduce the construction cost of tower crane base, the economy of tower crane base is improved, the utility model proposes a kind of tower crane Pedestal, the tower crane base are located above foundation ditch diaphram wall, and the tower crane base includes being connected with the foundation ditch diaphram wall Cushion cap bar-mat reinforcement, and the online casting concrete of the cushion cap reinforcing bar forms cushion cap.Such tower crane base is located at foundation ditch underground On diaphragm wall, therefore, workmen, can be continuous in foundation ditch underground according to tower crane position when building foundation ditch diaphram wall The cushion cap bar-mat reinforcement being connected with foundation ditch diaphram wall is laid above wall, so that by tower crane base and diaphram wall formed by integrally casting Complete, greatly reduce the construction cost of tower crane base, improve the economy of tower crane base.
Preferably, the bracket for the hanging part for supporting the cushion cap is provided with the foundation ditch diaphram wall both sides.This Sample, using hanging part of the bracket on the cushion cap of foundation ditch diaphram wall supported on both sides tower crane base, it can avoid because of cushion cap two Side is hanging and influences the support performance of pedestal.Further, the bracket is in symmetrically to set in the foundation ditch diaphram wall both sides Put, further to improve the support performance of bracket.It is further preferred that the cross section of the bracket for it is suitable for reading it is wide, lower mouth is narrow Inverted trapezoidal.Preferably, the bracket includes corbels support bar-mat reinforcement, and has poured concrete on the corbels support bar-mat reinforcement. Such bracket structure is simple, can be completed formed by integrally casting when preparing cushion cap and foundation ditch diaphram wall, easy for construction, is built into This is low.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model tower crane base;
Fig. 2 is the schematic top plan view of the tower crane base shown in Fig. 1;
Fig. 3 is the process schematic that the utility model tower crane base is built after foundation ditch diaphram wall is built up.
Embodiment
Illustrate embodiment of the present utility model below by way of specific instantiation, those skilled in the art can be by this theory Content disclosed by bright book understands other advantages and effect of the present utility model easily.The utility model can also be by addition Different embodiments are embodied or practiced, and the various details in this specification can also be based on different viewpoints with answering With, without departing from it is of the present utility model spirit under carry out various modifications or alterations.
It should be noted that structure, ratio, size depicted in this specification institute accompanying drawings etc., only coordinating Content disclosed in bright book, so that those skilled in the art understands and reads, being not limited to the utility model can implement Qualifications, therefore do not have technical essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size, In the case where not influenceing the effect of the utility model can be generated and the purpose that can reach, all should still fall disclosed in the utility model Technology contents obtain and can cover in the range of.Meanwhile in this specification it is cited as " on ", " under ", "left", "right", " in Between " and " one " etc. term, be merely convenient to understanding for narration, and be not used to limit the enforceable scope of the utility model, its Relativeness is altered or modified, in the case where changing technology contents without essence, when being also considered as the enforceable category of the utility model.
As illustrated in fig. 1 and 2, the utility model tower crane base includes the cushion cap 2 of installation tower crane 1, and the cushion cap 2 is by positioned at base Cheat the cushion cap bar-mat reinforcement (not shown) being connected above diaphram wall 3 and with foundation ditch diaphram wall 3 and be cast in cushion cap Concrete on bar-mat reinforcement is formed.To improve the bonding strength between cushion cap 2 and foundation ditch diaphram wall 3, ensure the branch of cushion cap 2 Intensity is supportted, when building foundation ditch diaphram wall 3, by the cushion cap reinforcing bar network arrangements of tower crane base on foundation ditch diaphram wall 3, And cushion cap bar-mat reinforcement is connected with the cage bar of foundation ditch diaphram wall by binding reinforcing bars, and by cushion cap 2 and foundation ditch diaphram wall 3 Concrete formed by integrally casting complete, cushion cap 2 is structure as a whole with foundation ditch diaphram wall 3.Preferably, it is continuous in foundation ditch underground The both sides of wall 3 are provided with the bracket 4 of the hanging part of support cushion cap 2, and the top surface of the bracket 4 is against on the bottom surface of cushion cap 2.This Sample, the hanging part of cushion cap 2 is supported using bracket 4, the bearing capacity of cushion cap 2 can be strengthened, prevent that cushion cap 2 from toppling or occurring inequality Even sedimentation, and then the steadiness that tower crane 1 is arranged in tower crane base is improved, it is easy to the handling material in subsequent construction of tower crane 1. To improve the support performance of bracket 4, these brackets 4 are symmetrical set in the both sides of foundation ditch diaphram wall 3, and bracket 4 is terraced to fall Shape structure, the i.e. cross section of bracket 4 are inverted trapezoidal wide, lower mouth is narrow suitable for reading.Preferably, bracket 4 includes corbels support bar-mat reinforcement (not shown), and poured concrete on corbels support bar-mat reinforcement.Such bracket 4 is by corbels support bar-mat reinforcement and pours Concrete on corbels support bar-mat reinforcement is formed, therefore, when building foundation ditch diaphram wall 3, by corbels support reinforcing bar screen cloth Put in foundation ditch diaphram wall both sides and be allowed to link together with cushion cap bar-mat reinforcement, by tower crane base, bracket 4 and foundation ditch underground The concrete formed by integrally casting of diaphragm wall 3 is completed, and tower crane base, bracket 4 and foundation ditch diaphram wall 3 is structure as a whole, so as to Strengthen the bonding strength between bracket 4 and cushion cap 2 and foundation ditch diaphram wall 3, while the construction cost of tower crane base can be reduced, Substantially increase the economy of tower crane base.
In addition, when building this practicality tower crane base after the completion of the construction of foundation ditch diaphram wall, as shown in figure 3, first The top of foundation ditch diaphram wall 3 is cut in the position for laying tower crane base, makes the collar joist steel on foundation ditch diaphram wall 3 Muscle 31 exposes;Then, rectangle formwork 5 is formed in top beam surrounding formwork, and lays bricks to form brick fetal membrane 6 in the surrounding of formwork 5;So Afterwards, cushion cap bar-mat reinforcement 21 is placed on formwork 5, and cushion cap bar-mat reinforcement 21 and collar beam steel 31 is tied up and be connected to one with reinforcing bar Rise;The finally casting concrete in formwork 5, treat that concrete setting is molded, tower crane base completes.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to described above.Thus, some details in embodiment should not be formed to this practicality New restriction, the utility model will be used as protection domain using the scope that appended claims define.

Claims (5)

1. a kind of tower crane base, it is characterised in that the tower crane base is located above foundation ditch diaphram wall, and the tower crane base includes The cushion cap bar-mat reinforcement being connected with the foundation ditch diaphram wall, and the online casting concrete of the cushion cap reinforcing bar forms cushion cap.
2. tower crane base according to claim 1, it is characterised in that the foundation ditch diaphram wall both sides are provided with branch Support the bracket of the hanging part of the cushion cap.
3. tower crane base according to claim 2, it is characterised in that the bracket is in the foundation ditch diaphram wall both sides It is symmetrical set.
4. the tower crane base according to Claims 2 or 3, it is characterised in that the cross section of the bracket is wide, lower mouth suitable for reading Narrow inverted trapezoidal.
5. tower crane base according to claim 4, it is characterised in that the bracket includes corbels support bar-mat reinforcement, and institute State and poured concrete on corbels support bar-mat reinforcement.
CN201720694079.1U 2017-06-15 2017-06-15 A kind of tower crane base Expired - Fee Related CN206970057U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720694079.1U CN206970057U (en) 2017-06-15 2017-06-15 A kind of tower crane base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720694079.1U CN206970057U (en) 2017-06-15 2017-06-15 A kind of tower crane base

Publications (1)

Publication Number Publication Date
CN206970057U true CN206970057U (en) 2018-02-06

Family

ID=61408849

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720694079.1U Expired - Fee Related CN206970057U (en) 2017-06-15 2017-06-15 A kind of tower crane base

Country Status (1)

Country Link
CN (1) CN206970057U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565676A (en) * 2019-08-01 2019-12-13 中交二公局第二工程有限公司 Cantilever type tower crane foundation structure and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565676A (en) * 2019-08-01 2019-12-13 中交二公局第二工程有限公司 Cantilever type tower crane foundation structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN107100290A (en) A kind of prefabricated shear wall and overlapping plate node
CN107447647A (en) Assembled bridge pier and its construction method
CN208486404U (en) A kind of concrete shear force wall of steel bar template integrative installation technology
CN206970057U (en) A kind of tower crane base
CN207436503U (en) Efficient construction of precast floorslab hangs membrane module
CN103722613A (en) Construction method for vertically casting and mounting four-foot hollow block in seawall wave resistance engineering
CN205889488U (en) Steel sleeve box's precast reinforced concrete back cover template and hoist device thereof
CN107327046A (en) A kind of steel pipe bundle combining structure
CN209652990U (en) The antiseepage plugging structure of the hole for hoist of basement computer room
CN208884808U (en) Combine prefabricated panel and laminated floor slab structure
CN204038860U (en) Tee girder formwork hoisting instrument
CN207296184U (en) A kind of beam steel positioner
CN206288849U (en) A kind of auto-split brick hoisting cage
CN109763658A (en) A kind of support device and its construction method for arrangement material distributing machine in elevator
CN208518076U (en) Support column suspension column anti-seismic structure
CN206359993U (en) Stud structure for main transformer fire wall
CN210477335U (en) Precast box culvert concreting equipment
CN208668745U (en) A kind of hollow floor large scale core mold structure
CN207846424U (en) Structure and device suitable for the cast of deep narrow structure inner concrete
CN209260730U (en) A kind of inclined-plane plain concrete construction
CN206829185U (en) A kind of concrete thin-wall wall and bottom plate formed by integrally casting device
CN207277545U (en) Fork-shaped steel reinforced concrete combining structure
CN106760189B (en) Tall building structure transfer beam construction method
CN206143914U (en) SC fabricated frame bearing structure system
CN206000020U (en) Docking structure at concrete frame structure prefabricated post and beam slab node

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180206

Termination date: 20200615

CF01 Termination of patent right due to non-payment of annual fee