CN206956747U - Arc double-row steel pipe pile cofferdam - Google Patents

Arc double-row steel pipe pile cofferdam Download PDF

Info

Publication number
CN206956747U
CN206956747U CN201720265336.XU CN201720265336U CN206956747U CN 206956747 U CN206956747 U CN 206956747U CN 201720265336 U CN201720265336 U CN 201720265336U CN 206956747 U CN206956747 U CN 206956747U
Authority
CN
China
Prior art keywords
steel
pipe pile
row
cofferdam
arc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720265336.XU
Other languages
Chinese (zh)
Inventor
张淑云
俞芳琴
刘薪莉
颜亚琴
陈振明
孙玉宇
张永杰
薛辉
张天琦
周兴虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Wisdom Water Science And Technology Co Ltd
Original Assignee
Nanjing Wisdom Water Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Wisdom Water Science And Technology Co Ltd filed Critical Nanjing Wisdom Water Science And Technology Co Ltd
Priority to CN201720265336.XU priority Critical patent/CN206956747U/en
Priority to CN201721299412.5U priority patent/CN207362859U/en
Priority to CN201721298781.2U priority patent/CN208009454U/en
Application granted granted Critical
Publication of CN206956747U publication Critical patent/CN206956747U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

It the utility model is related to construction of hydro project cofferdam, a kind of arc double-row steel pipe pile cofferdam more particularly in river course or in river bank hydraulic structure work progress, described cofferdam includes steel-pipe pile and canvas, the steel-pipe pile is two rows, and lower end insertion river bed, and it is distributed to outer arcuate, the horizontal steel tube of lateral connection is respectively equipped with the both sides of two row's arc-shaped steel pile tubes, canvas is respectively equipped with the inside of two row's arc-shaped steel pile tubes, soil is provided between described canvas and forms cofferdam, various engineering construction needs can be met.

Description

Arc double-row steel pipe pile cofferdam
Technical field
Construction of hydro project cofferdam is the utility model is related to, more particularly in river course or river bank hydraulic structure was constructed A kind of arc double-row steel pipe pile cofferdam in journey.
Background technology
Water conservancy structure all be unable to do without water, and a lot of hydraulic structures are all built in water or river bank, dry in order to create It is necessary to build construction cofferdam, conventional construction cofferdam has the condition of ground construction:Earth rock cofferdam, steel sheet-pile cofferdam, steel pipe pile cofferdam Deng.But some engineerings are influenceed by place, source of fetching earth, geology, soil permeability coefficient, SEA LEVEL VARIATION etc., and the cofferdam of the above can not Meet special construction requirement, several cofferdam will be carried out integrated application by this, meet Specific construction requirement.
Utility model content
In order to solve the above problems, the utility model provides a kind of arc double-row steel pipe pile cofferdam, and the utility model uses Double-row steel pipe stake is spaced apart to be squeezed into soil, horizontally disposed camber, and mud is put among two row's steel-pipe piles, in order to anti- Only mud is lost in, and waterproof canvas is put between mud and steel-pipe pile;In order that double-row steel pipe pile cofferdam is stable, in double steel Pile tube top outer adds two horizontal curved steel tubes, is integrally fixed with steel wire rope, can meet a variety of construction requirements.
To achieve the above object, the utility model provides following technical scheme:
A kind of arc double-row steel pipe pile cofferdam, including steel-pipe pile and canvas, the steel-pipe pile is two rows, and river is inserted in lower end Bottom, and be distributed to outer arcuate, the horizontal steel tube of lateral connection is respectively equipped with the both sides of two row's arc-shaped steel pile tubes, in two row's arcs Canvas is respectively equipped with the inside of steel-pipe pile, soil is provided between described canvas and forms cofferdam.
Further, described horizontal steel tube is located at the both sides of two row's steel-pipe piles, horizontal and suitable apart from top 20-50cm The arc for steel-pipe pile is set, a diameter of 5-10cm of horizontal steel tube.
Further, described canvas top is arranged on horizontal steel tube, and following pendant has fragment of brick and is placed in bed mud.
Further, two described row's arc-shaped steel pile tube upper ends are interconnected and fixed integrally provided with steel wire rope.
If being constructed in korneforos, then the upstream and downstream in construction area respectively sets described curved steel tube pile cofferdam, if in River bank is constructed, and can set curved steel tube pile cofferdam along semi-surrounding is applied at area, if in lake, korneforos construct, can be along applying Work zoned circular, which surrounds, sets round steel pipe pile cofferdam.
The beneficial effects of the utility model
1. steel pipe pile cofferdam can save space, the earthwork is saved, double-row steel pipe stake can increase the stability in cofferdam itself.
2. the cambered design in cofferdam adds the resistance to water;
3. gathering materials on the spot, fetch earth, restored to the original state after use nearby;
4. canvas reduces the seepage in cofferdam.
Brief description of the drawings
Fig. 1 is the arc double-row steel pipe pile cofferdam main structure diagram of the application;
Fig. 2 is the arc double-row steel pipe pile cofferdam overlooking the structure diagram of the application;
Fig. 3 is Fig. 2A-A sectional views;
The arc double-row steel pipe pile cofferdam that Fig. 4 is the application is used for the overlooking the structure diagram of construction area by the river.
Sequence number in figure:1- riverbanks, 2- steel-pipe piles, 3- horizontal steel tubes, 4- steel wire ropes, 5- canvas, 6- soil, 7- Construction area.
Embodiment
To make the purpose of the application and technical scheme clearer, the technical scheme of the application is carried out below in conjunction with accompanying drawing Clearly and completely describe.Described embodiment is the part of the embodiment of the application, rather than whole embodiments, is based on Described embodiments herein, those of ordinary skill in the art are obtained all on the premise of without creative work Other embodiment, belong to the scope of the application protection.
Embodiment:Refer to the attached drawing, a kind of arc double-row steel pipe pile cofferdam, including steel-pipe pile 2 and canvas 5, the steel-pipe pile 2 be two rows, and river bed certain depth is inserted in lower end, and is distributed to outer arcuate, is respectively equipped with the both sides of two row's arc-shaped steel pile tubes 2 Lateral connection horizontal steel tube 3, canvas 5 is respectively equipped with the inner side of two row's arc-shaped steel pile tubes 2, is provided between described canvas 5 Soil 6 forms cofferdam.
Further, described connection horizontal steel tube 3 is located at the both sides of two row's steel-pipe piles 2, apart from top 20-50cm, water Flat and along steel-pipe pile 2 arc is set, and connects a diameter of 5-10cm of horizontal steel tube 3.
Further, the described top of canvas 5 is arranged on connection horizontal steel tube 3, and following pendant has fragment of brick and is placed in river bed In mud.
Further, the described upper end of two row's arc-shaped steel pile tube 2 is interconnected and fixed integrally provided with steel wire rope 4.
If being constructed in korneforos, then the upstream and downstream in construction area 7 respectively sets described curved steel tube pile cofferdam, if in River bank construct, can along at construction area 7 semi-surrounding set curved steel tube pile cofferdam, if in lake, korneforos construct, Ke Yiyan Circular surround of construction area sets round steel pipe pile cofferdam.This arc double-row steel pipe pile cofferdam can meet various engineering construction need Will.
Disassemble steel wire rope after construction, extract steel-pipe pile, mud automatic levelling or can pull mud out.

Claims (5)

1. a kind of arc double-row steel pipe pile cofferdam, including steel-pipe pile (2) and canvas (5), it is characterised in that the steel-pipe pile (2) For two rows, and lower end insertion river bed, and be distributed to outer arcuate, it is respectively equipped with the both sides of two row's arc-shaped steel pile tubes (2) and laterally connects Horizontal steel tube (3) is connect, canvas (5) is respectively equipped with the inside of two row's arc-shaped steel pile tubes (2), is set between described canvas (5) There is soil (6) to form cofferdam.
2. arc double-row steel pipe pile cofferdam according to claim 1, it is characterised in that described horizontal steel tube (3) is located at two The both sides of steel-pipe pile (2) are arranged, apart from top 20-50cm, horizontal and along steel-pipe pile (2) arc is set, horizontal steel tube (3) A diameter of 5-10cm.
3. arc double-row steel pipe pile cofferdam according to claim 1 or 2, it is characterised in that described canvas (5) top is set Put on horizontal steel tube (3), following pendant has fragment of brick and is placed in bed mud.
4. arc double-row steel pipe pile cofferdam according to claim 1 or 2, it is characterised in that two described row's arc-shaped steel pile tubes (2) upper end is interconnected and fixed integrally provided with steel wire rope (4).
5. arc double-row steel pipe pile cofferdam according to claim 1 or 2, it is characterised in that the cofferdam is that twice are set respectively It is placed in the upstream and downstream of construction area (7).
CN201720265336.XU 2017-03-19 2017-03-19 Arc double-row steel pipe pile cofferdam Expired - Fee Related CN206956747U (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201720265336.XU CN206956747U (en) 2017-03-19 2017-03-19 Arc double-row steel pipe pile cofferdam
CN201721299412.5U CN207362859U (en) 2017-03-19 2017-03-19 Circular double-row steel pipe pile cofferdam
CN201721298781.2U CN208009454U (en) 2017-03-19 2017-03-19 A kind of arc double-row steel pipe pile cofferdam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720265336.XU CN206956747U (en) 2017-03-19 2017-03-19 Arc double-row steel pipe pile cofferdam

Related Child Applications (2)

Application Number Title Priority Date Filing Date
CN201721299412.5U Division CN207362859U (en) 2017-03-19 2017-03-19 Circular double-row steel pipe pile cofferdam
CN201721298781.2U Division CN208009454U (en) 2017-03-19 2017-03-19 A kind of arc double-row steel pipe pile cofferdam

Publications (1)

Publication Number Publication Date
CN206956747U true CN206956747U (en) 2018-02-02

Family

ID=61377360

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201721299412.5U Expired - Fee Related CN207362859U (en) 2017-03-19 2017-03-19 Circular double-row steel pipe pile cofferdam
CN201720265336.XU Expired - Fee Related CN206956747U (en) 2017-03-19 2017-03-19 Arc double-row steel pipe pile cofferdam
CN201721298781.2U Expired - Fee Related CN208009454U (en) 2017-03-19 2017-03-19 A kind of arc double-row steel pipe pile cofferdam

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201721299412.5U Expired - Fee Related CN207362859U (en) 2017-03-19 2017-03-19 Circular double-row steel pipe pile cofferdam

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201721298781.2U Expired - Fee Related CN208009454U (en) 2017-03-19 2017-03-19 A kind of arc double-row steel pipe pile cofferdam

Country Status (1)

Country Link
CN (3) CN207362859U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109024637A (en) * 2018-07-21 2018-12-18 四川启创建设工程有限公司 A kind of combined cofferdam and its build construction method
CN111576458A (en) * 2020-06-02 2020-08-25 浙江交工金筑交通建设有限公司 Inner support-free steel pipe pile cofferdam structure and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109024637A (en) * 2018-07-21 2018-12-18 四川启创建设工程有限公司 A kind of combined cofferdam and its build construction method
CN111576458A (en) * 2020-06-02 2020-08-25 浙江交工金筑交通建设有限公司 Inner support-free steel pipe pile cofferdam structure and construction method thereof

Also Published As

Publication number Publication date
CN208009454U (en) 2018-10-26
CN207362859U (en) 2018-05-15

Similar Documents

Publication Publication Date Title
CN104389318B (en) Reinforced concrete-steel structure hybrid gravity foundation for offshore wind power and construction method thereof
CN203429597U (en) Anti-underwashing protection slope structure for downstream river channel of hydropower plant
CN206815355U (en) A kind of river course pile foundation cofferdam
CN109418184A (en) Far-reaching sea aquaculture net cage
CN206956747U (en) Arc double-row steel pipe pile cofferdam
CN202559368U (en) Subsidence-reducing pile structure of capped steel pipe of immersed tunnel
CN203701123U (en) Shallow sea varying diameter single pile foundation
CN204780990U (en) Combined type retaining wall structure
CN207525758U (en) A kind of reinforced Structure About Soldier Pile
CN204662246U (en) steep slope bridge pier structure
CN204875811U (en) Combined type multirow stake underground structure
CN206015511U (en) One implant post steel pipe column
CN211571752U (en) Landscape garden design ecological slope protection
CN209779617U (en) Pile foundation structure with high-pressure jet grouting pile serving as side slope support pile
CN208844617U (en) Half floatation type immersed tube tunnel of underwater support
CN209308066U (en) A kind of pipe gallery foundation pit supporting construction
CN207405640U (en) Stake film is combined cofferdam with soil
CN206189428U (en) A steel sheet piling cofferdam for deep foundation construction
CN206438524U (en) A kind of geomembrane steel framework cofferdam structure
CN205116208U (en) Offshore wind farm fan single pile basis
CN205475276U (en) Strenghthened type double row pile cofferdam structure
CN205990619U (en) A kind of rich groundwater and geology bad deep pit digging supporting construction
CN109853651A (en) A kind of mill tailings library waterpower takes sand method
CN205839944U (en) A kind of Anti-floating reinforcing steel bar concrete basin
CN220394612U (en) Basic structure of waterfront archaizing pavilion

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhang Shuyun

Inventor after: Zhou Xinghu

Inventor after: Yu Fangqin

Inventor after: Liu Xingli

Inventor after: Yan Yaqin

Inventor after: Chen Zhenming

Inventor after: Sun Yuyu

Inventor after: Zhang Yongjie

Inventor after: Xue Hui

Inventor after: Zhang Tianqi

Inventor before: Zhang Shuyun

Inventor before: Zhou Xinghu

Inventor before: Yu Fangqin

Inventor before: Liu Xinli

Inventor before: Yan Yaqin

Inventor before: Chen Zhenming

Inventor before: Sun Yuyu

Inventor before: Zhang Yongjie

Inventor before: Xue Hui

Inventor before: Zhang Tianqi

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180202

Termination date: 20190319