CN206956728U - A kind of civil engineering is lifted from sagging piling machine - Google Patents

A kind of civil engineering is lifted from sagging piling machine Download PDF

Info

Publication number
CN206956728U
CN206956728U CN201720591080.1U CN201720591080U CN206956728U CN 206956728 U CN206956728 U CN 206956728U CN 201720591080 U CN201720591080 U CN 201720591080U CN 206956728 U CN206956728 U CN 206956728U
Authority
CN
China
Prior art keywords
sagging
pull rope
substrate
fixed
pile monkey
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720591080.1U
Other languages
Chinese (zh)
Inventor
张公正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720591080.1U priority Critical patent/CN206956728U/en
Application granted granted Critical
Publication of CN206956728U publication Critical patent/CN206956728U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

A kind of civil engineering is lifted from sagging piling machine, including pull rope locating slot, pull rope, fixed plate and pulley;The pull rope locating slot is fixed on substrate top and the left side of supporting plate by locating rod support;One end of the pull rope is connected with hoist engine, and the other end coils through pulley and is connected to a fixed with pile monkey;The pile monkey is placed in the top of positioning tube;The fixed plate is fixedly welded on the bottom of top support plate;The pulley is fixed at two between fixed plate by rotating shaft.Civil engineering lifting is provided with positioning tube from sagging piling machine, array is provided with spin on the inwall of positioning tube, positioning tube is able to ensure that the sagging track of pile monkey is straight, the impulsive force of pile monkey is set to act perpendicularly in stake, and spin can reduce resistance to sliding of the pile monkey inside positioning tube, the loss of pile monkey impulsive force is reduced.

Description

A kind of civil engineering is lifted from sagging piling machine
Technical field
It the utility model is related to and plant equipment, civil engineering corollary equipment technical field, more particularly to a kind of building work Journey is lifted from sagging piling machine.
Background technology
Because if above ground structure will be built on the ground, ground will bear very big pressure, it is necessary that ground has Enough renitent intensity, this is difficult often to accomplish, thus the ground for bearing building must just be reinforced or Mode is born on person's improvement ground, so just expecting driving piles on ground, allows most of weight of building to pass to ground by stake Very deep position below face, because the ground of this position is more much bigger than ground ability to bear.
The inventors discovered that existing piling machine when in use its pull rope be present and easily thread off, the positioner of pile monkey track, Resistance to sliding to pile monkey is excessive, the impulsive force of pile monkey is lost the problem of serious.
Then, inventor in view of this, adhere to the relevant industries for many years it is abundant design and develop and the experience of actual fabrication, Improvement is studied for existing structure and missing, there is provided a kind of civil engineering lifting is from sagging piling machine, to reach With more the purpose of more practical value.
Utility model content
The purpose of this utility model is to provide a kind of civil engineering lifting from sagging piling machine, to solve above-mentioned background The pull rope proposed in technology is easily threaded off, and the positioner of pile monkey track, the resistance to sliding to pile monkey is excessive, makes rushing for pile monkey Hit the problem of power loss is serious.
The utility model civil engineering lifts the purpose and effect from sagging piling machine, by the institute of technological means in detail below Reach:
A kind of civil engineering is lifted from sagging piling machine, wherein, civil engineering lifting includes from sagging piling machine Have:
Substrate, roller, hydraulic top, positioning tube, support frame, supporting plate, limit switch, top supporting rod, top support plate, Push rod, hoist engine, pull rope locating slot, pull rope, pile monkey, fixed plate and pulley;
The bottom of the substrate is fixedly installed hydraulic top;The hydraulic pressure top/bottom part is fixedly installed roller;The positioning Cylinder extends through substrate and supporting plate, is fixed between substrate and supporting plate;Support frame as described above is fixedly supported to the top of substrate; Support frame as described above top is fixedly installed supporting plate;The limit switch is fixedly supported to the top of supporting plate;The top branch Strut supports the top for being arranged at supporting plate;The top support plate is fixedly installed on the top of top supporting rod;The push rod The top of substrate is fixedly welded on, and eaves is distributed outside its left side close to substrate;The hoist engine is screwed to substrate Top, and it is located at the left side of support frame;The pull rope locating slot is fixed on substrate top and support by locating rod support The left side of plate;One end of the pull rope is connected with hoist engine, and the other end coils through pulley and is connected to a fixed with pile monkey;Institute State the top that pile monkey is placed in positioning tube;The fixed plate is fixedly welded on the bottom of top support plate;The pulley is by turning Axle is fixed at two between fixed plate.
Further, array is provided with spin on the inwall of the positioning tube.
Further, the control pull rope is placed in the inside of pull rope locating slot.
Further, the hydraulic top is provided with everywhere altogether.
Further, the spacing contact of the limit switch is located at the top of pile monkey.
With existing structure in comparison, the utility model has the following advantages that:
1. the setting of the utility model loudspeaker, array is provided with spin on the inwall of positioning tube, and positioning tube is able to ensure that The sagging track of pile monkey is straight, the impulsive force of pile monkey is acted perpendicularly in stake, and spin can reduce pile monkey in positioning tube The resistance to sliding in portion, reduce the loss of pile monkey impulsive force.
2. the setting of the pressure-sensitive controlling switch of the utility model, pull rope are placed in the inside of pull rope locating slot, can avoid The motion of the big intensity of pull rope is driven when pile monkey is acutely sagging so as to causing pull rope to be threaded off.
3. the setting of the utility model microphone, hydraulic top is provided with everywhere altogether, and hydraulic top can lift the bottom of piling machine Disk, it is improved by performance, facilitates the transfer of piling machine at the construction field (site), while hydraulic top can lift the height of positioning tube, Its overhead is facilitated to be positioned at the top of stake.
4. the setting of the utility model microphone, the spacing contact of limit switch is located at the top of pile monkey, limit switch Normally-closed contact series winding is connected on the latching circuit of hoist engine, can realize the semi-automation of piling machine.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is the utility model positive structure diagram;
Fig. 3 is the utility model positioning tube three dimensional structure diagram
Fig. 4 is the utility model hoist engine control circuit schematic diagram.
In figure:1- substrates, 2- rollers, 3- hydraulic tops, 4- positioning tubes, 5- support frames, 6- supporting plates, 7- limit switches, 8- Top supporting rod, 9- top support plates, 10- push rods, 11- hoist engines, 12- pull rope locating slots, 13- pull ropes, 14- pile monkeys, 15- fixed plates, 16- pulleys.
Embodiment
Below, embodiment of the present utility model is will be explained in, the example is shown in the accompanying drawings and the description below.Although will The utility model is described with reference to exemplary embodiment, it is to be understood that the description does not really want the utility model to be limited to this to show The embodiment of example property.On the contrary, the utility model will not only cover the exemplary embodiment, but also cover various replacements, Change, equivalent and other embodiment, it can be included in spirit of the present utility model and the model that appended claims are limited In enclosing.
Referring to Fig. 1 to accompanying drawing 4, a kind of civil engineering lifting includes from sagging piling machine:
Substrate 1, roller 2, hydraulic top 3, positioning tube 4, support frame 5, supporting plate 6, limit switch 7, top supporting rod 8, top Portion's supporting plate 9, push rod 10, hoist engine 11, pull rope locating slot 12, pull rope 13, pile monkey 14, fixed plate 15 and pulley 16;
The bottom of substrate 1 is fixedly installed hydraulic top 3;The bottom of hydraulic top 3 is fixedly installed roller 2;Positioning tube 4 is through logical Substrate 1 and supporting plate 6 are crossed, is fixed between substrate 1 and supporting plate 6;Support frame 5 is fixedly supported to the top of substrate 1;Support frame 5 tops are fixedly installed supporting plate 6;Limit switch 7 is fixedly supported to the top of supporting plate 6;The support of top supporting rod 8 is arranged at The top of supporting plate 6;Top support plate 9 is fixedly installed on the top of top supporting rod 8;Push rod 10 is fixedly welded on substrate 1 Top, and it is distributed close to eaves outside the left side of substrate 1;Hoist engine 11 is screwed to the top of substrate 1, and it is located at support The left side of frame 5;Pull rope locating slot 12 is fixed on the top of substrate 1 and the left side of supporting plate 6 by locating rod support;Pull rope 13 One end be connected with hoist engine 11, the other end coils through pulley 16 and is connected to a fixed with pile monkey 14;Pile monkey 14 is placed in fixed The top of position cylinder 4;Fixed plate 15 is fixedly welded on the bottom of top support plate 9;Pulley 16 is fixed at two by rotating shaft to be fixed Between plate 15.
Civil engineering as described above lifts the preferred embodiment from sagging piling machine, wherein, the inwall of positioning tube 4 Upper array is provided with spin, and positioning tube 4 is able to ensure that the sagging track of pile monkey 14 is straight, makes the impulsive force perpendicular acting of pile monkey 14 In in stake, and spin can reduce resistance to sliding of the pile monkey 14 inside positioning tube 4, reduce the loss of the impulsive force of pile monkey 14;
Civil engineering as described above lifts the preferred embodiment from sagging piling machine, wherein, pull rope 13 is placed in The inside of pull rope locating slot 12, it can avoid driving the motion of 13 big intensity of pull rope when pile monkey 14 is acutely sagging so as to leading Pull rope 13 is caused to thread off;
Civil engineering as described above lifts the preferred embodiment from sagging piling machine, wherein, hydraulic top 3 is set altogether Having everywhere, hydraulic top 3 can lift the chassis of piling machine, improve it by performance, facilitate the transfer of piling machine at the construction field (site), Hydraulic top 3 can lift the height of positioning tube 4 simultaneously, facilitate its overhead to be positioned at the top of stake;
Civil engineering as described above lifts the preferred embodiment from sagging piling machine, wherein, the limit of limit switch 7 Position contact is located at the top of pile monkey 14, and the normally-closed contact series winding of limit switch 7 is connected on the latching circuit of hoist engine 11, Neng Goushi The semi-automation of existing piling machine.
The operation principle of the present embodiment:
Hydraulic pressure raises hydraulic top 3, lifting substrate 1 and the road clearance on ground, piling machine volume is passed through most obstacle Thing, and then piling machine is promoted and is transferred to piling work position, continuing rise hydraulic top 3 is higher than the end height of positioning tube 3 The height of stake simultaneously finely tunes the top completion installation that mobile piling machine makes positioning tube 3 be placed in stake, presses the start button of hoist engine 11 Self-locking is realized in switch, contactor adhesive, can now unclamp start button switch, and contactor adhesive hoist engine 11 obtains electric rotation, will Pull rope 13 is provided on the coiling rod of hoist engine 11, and then shrinks the winding of pull rope 13, under the slip transition of pulley 16 The linkage pile monkey 14 of pull rope 13 rises along positioning tube 4, and pile monkey 14 rises the spacing contact up to touching limit switch 7, spacing The normally-closed contact of switch 7 disconnects, and then hoist engine 11 is that dead electricity is stopped, now pile monkey 14 in the presence of gravitional force from By falling bodies, along the vertical direction toward impact of positioning tube 4 in stake, complete a piling work, start second and drive piles, press again The start button switch of hoist engine 11, repeats the above steps, and circulation piling work is until piling is qualified.
It should be noted that the standardized element that uses of the utility model can commercially, shaped piece according to Specification and accompanying drawing record can carry out customized, and the specific connected mode of each part is using ripe in the prior art Bolt, rivet, the conventional meanses such as welding, machinery, part and equipment are using in the prior art, conventional model, inventor It will not be described in detail herein.
In summary, although the utility model is described in detail with reference to the foregoing embodiments, for this area For technical staff, it can still modify to the technical scheme described in foregoing embodiments, or to which part Technical characteristic carries out equivalent substitution, all within the spirit and principles of the utility model, any modification for being made, equivalent substitution, Improve etc., it should be included within the scope of protection of the utility model.

Claims (5)

1. a kind of civil engineering is lifted from sagging piling machine, it is characterised in that:Described civil engineering lifting is beaten from sagging Stake machine includes:
Substrate, roller, hydraulic top, positioning tube, support frame, supporting plate, limit switch, top supporting rod, top support plate, push away Bar, hoist engine, pull rope locating slot, pull rope, pile monkey, fixed plate and pulley;
The bottom of the substrate is fixedly installed hydraulic top;The hydraulic pressure top/bottom part is fixedly installed roller;The positioning tube passes through Substrate and supporting plate are crossed in break-through, are fixed between substrate and supporting plate;Support frame as described above is fixedly supported to the top of substrate;It is described Support frame top is fixedly installed supporting plate;The limit switch is fixedly supported to the top of supporting plate;The top supporting rod Support is arranged at the top of supporting plate;The top support plate is fixedly installed on the top of top supporting rod;The push rod welding The top of substrate is fixed on, and eaves is distributed outside its left side close to substrate;The hoist engine is screwed to the top of substrate, And it is located at the left side of support frame;The pull rope locating slot is fixed on substrate top and a left side for supporting plate by locating rod support Side;One end of the pull rope is connected with hoist engine, and the other end coils through pulley and is connected to a fixed with pile monkey;The pile monkey It is placed in the top of positioning tube;The fixed plate is fixedly welded on the bottom of top support plate;The pulley is fixed by rotating shaft Between fixed plate at two.
2. civil engineering according to claim 1 is lifted from sagging piling machine, it is characterised in that:The positioning tube it is interior Array is provided with spin on wall.
3. civil engineering according to claim 1 is lifted from sagging piling machine, it is characterised in that:The pull rope is placed in The inside of pull rope locating slot.
4. civil engineering according to claim 1 is lifted from sagging piling machine, it is characterised in that:The hydraulic top is set altogether It is equipped with everywhere.
5. civil engineering according to claim 1 is lifted from sagging piling machine, it is characterised in that:The limit switch Spacing contact is located at the top of pile monkey.
CN201720591080.1U 2017-05-25 2017-05-25 A kind of civil engineering is lifted from sagging piling machine Expired - Fee Related CN206956728U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720591080.1U CN206956728U (en) 2017-05-25 2017-05-25 A kind of civil engineering is lifted from sagging piling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720591080.1U CN206956728U (en) 2017-05-25 2017-05-25 A kind of civil engineering is lifted from sagging piling machine

Publications (1)

Publication Number Publication Date
CN206956728U true CN206956728U (en) 2018-02-02

Family

ID=61375449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720591080.1U Expired - Fee Related CN206956728U (en) 2017-05-25 2017-05-25 A kind of civil engineering is lifted from sagging piling machine

Country Status (1)

Country Link
CN (1) CN206956728U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284502A (en) * 2019-05-27 2019-09-27 浙江天姥建设发展有限公司 Civil engineering piling machine
CN114892661A (en) * 2022-04-24 2022-08-12 江苏科技大学 Pile driver pile frame pile reversing device and method
CN115247422A (en) * 2021-04-26 2022-10-28 东台市巨力机械制造有限公司 Winding mechanism for crawler-type telescopic pile driver

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284502A (en) * 2019-05-27 2019-09-27 浙江天姥建设发展有限公司 Civil engineering piling machine
CN115247422A (en) * 2021-04-26 2022-10-28 东台市巨力机械制造有限公司 Winding mechanism for crawler-type telescopic pile driver
CN115247422B (en) * 2021-04-26 2023-09-15 东台市巨力机械制造有限公司 Hoisting mechanism for crawler-type telescopic pile driver
CN114892661A (en) * 2022-04-24 2022-08-12 江苏科技大学 Pile driver pile frame pile reversing device and method
CN114892661B (en) * 2022-04-24 2024-02-27 江苏科技大学 Pile frame pile backing device and pile backing method for pile driving ship

Similar Documents

Publication Publication Date Title
CN206956728U (en) A kind of civil engineering is lifted from sagging piling machine
CN206513037U (en) A kind of precast concrete wall panel position regulator
CN206328055U (en) A kind of portal frame
CN117071560A (en) Positioning and supporting device for construction of prefabricated pipe piles
CN208150864U (en) A kind of construction material lifting apparatus
CN212222240U (en) Energy-concerving and environment-protective type construction gallows
CN215052745U (en) Water conservancy water and electricity gate headstock gear
CN208415256U (en) A kind of hydraulic engineering pile pulling device
CN212336023U (en) Civil engineering is with small-size building pile driver
CN209276035U (en) A kind of self-supporting superelevation Lift-on/Lift-off System
CN216130679U (en) Energy-saving windproof dust suppression net capable of being conveniently moved
CN215888371U (en) Pile foundation resistance to plucking detection device
CN220888756U (en) Foundation pile bearing capacity test device for municipal works
CN219991030U (en) Foundation pit unearthing truss
CN215886185U (en) Construction elevator for intermediate frequency goods
CN211813118U (en) Material handling device is used in construction
CN219730420U (en) Liftable formula crane
CN218862388U (en) Lifting cover plate device
CN221093462U (en) Equipment installation promotes removes frock
CN213976663U (en) Lifting device for installing water conservancy gate
CN110778201B (en) Installation and erection method of high-pressure tower
CN208135763U (en) Assembled architecture equipment boom hoisting
CN212613836U (en) Installation device for construction of assembled wallboard
CN108328491A (en) A kind of Mobile hoisting equipment of Super High Core Walls Structure
CN209887817U (en) Auxiliary tool for high-speed rail box beam tube drawing

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180202

Termination date: 20190525

CF01 Termination of patent right due to non-payment of annual fee