CN206941414U - The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage - Google Patents

The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage Download PDF

Info

Publication number
CN206941414U
CN206941414U CN201720844433.4U CN201720844433U CN206941414U CN 206941414 U CN206941414 U CN 206941414U CN 201720844433 U CN201720844433 U CN 201720844433U CN 206941414 U CN206941414 U CN 206941414U
Authority
CN
China
Prior art keywords
horn
tonnage
bridge
hole
achievable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720844433.4U
Other languages
Chinese (zh)
Inventor
熊国辉
王心利
李珍西
李世龙
申超
袁宝成
向锐
胡勇
彭程
陈家乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Second Bureau Construction Co.,Ltd.
China Railway No 2 Engineering Group Co Ltd
China Railway Engineering Machinery Research and Design Institute Co Ltd
Xinyun Emgineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Original Assignee
China Railway No 2 Engineering Group Co Ltd
China Railway Engineering Machinery Research and Design Institute Co Ltd
Xinyun Emgineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 2 Engineering Group Co Ltd, China Railway Engineering Machinery Research and Design Institute Co Ltd, Xinyun Emgineering Co Ltd of China Railway No 2 Engineering Group Co Ltd filed Critical China Railway No 2 Engineering Group Co Ltd
Priority to CN201720844433.4U priority Critical patent/CN206941414U/en
Application granted granted Critical
Publication of CN206941414U publication Critical patent/CN206941414U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of Bridge Erector of the whole two-way erection in hole on achievable asymmetric framing prefabricated case beam beam of large-tonnage, including the horn along the equal symmetric design of vertical and horizontal, the front leg strut that the horn is provided with, middle supporting leg and rear support leg, the horn is provided with along before the traveling of girder longitudinal direction, rear spar car, before being moved left and right on the purlin car, trolley afterwards, and the elevator tractor structure for each supporting leg vertical shift walking, the front leg strut is removable and multi-stage expansion, suspender includes shoulder pole girder and multiple rod member components used by the trolley, the shoulder pole girder upper end is provided with horizontal balance device, both sides are respectively equipped with stepless regulator and longitudinal oscillation adjusting apparatus.Bridge Erector is three leg structures of unmatched auxiliary leg, become across when, corresponding span location arrive in front leg strut vertical shift walking, plug the i.e. achievable complete machine change of alignment pin across;Bridge Erector can reversely set a roof beam in place after the fast simple exchange of forward and backward supporting leg is carried out on bridge.

Description

The whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage Bridge Erector
Technical field
A kind of Bridge Erector is the utility model is related to, on particularly a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage The Bridge Erector of the whole two-way erection in hole.
Background technology
Using large-scale transportation rack device, realize and beam is transported on beam car beam, the construction method of Bridge Erector full span erection, there is quality Reliably, efficiency high, the advantages that smaller, is influenceed on traffic and environment.In existing railway engineering, on large-tonnage prefabricated case beam beam Fortune beam, the construction method of a piece of box beam of Bridge Erector full span erection are used widely.In highway engineering, only Hangzhou Gulf Great Bridge is carried out Cross on large-tonnage prefabricated case beam beam and transport the construction of beam, by a variety of auxiliary equipment, its Bridge Erector can the left and right width two panels of full span erection Box beam.
When Bridge Erector is reversely set a roof beam in place, transportation rack device u-turn need to be carried out, is generally lifted transportation rack device using lifting beam machine Lower bridge, packed by beam car after Bridge Erector reversed end for end on ground, then lift bridge and carry out reversely fortune and set a roof beam in place operation.
Traditional large-tonnage box beam bridge formation machine set up different spans box beam become across when, typically need auxiliary leg, become across program compared with It is less efficient to be cumbersome.
Traditional large-tonnage box beam bridge formation machine is complicated, and Bridge Erector need to typically carry out small disintegration, and needs to have under bridge Enough places, operation of reversely setting a roof beam in place is carried out after could reversing end for end, it is impossible to realize and directly reversed end for end on simple efficient bridge.
Traditional large-tonnage box beam bridge formation machine is generally a piece of box beam of full span erection single width or whole by more auxiliary equipment Aperture frame sets left and right double width two panels box beam, it is impossible to the left and right width two panels large-tonnage prefabricated case beam of direct full span erection.
Traditional large-tonnage box beam bridge formation machine Bridge Erector typically realizes the erection in first and last hole, it is necessary to carry out by front leg strut turnover Certain dismounting, operation procedure is relatively complicated, increases labor intensity.
In urban elevated bridge engineering, to make full use of space under bridge, reduce bridge pier as far as possible and take up an area width, gradually adopt The unsymmetric structure design that top prefabricated case beam structure both sides cantilevers does not wait.It is asymmetric prefabricated that traditional Bridge Erector sets up large-tonnage Box beam, box beam occur it is unstable and by turn round phenomenon, less can ensure that Bridge Erector security and stability.
Utility model content
Goal of the invention of the present utility model is:Existing frame when setting up large-tonnage prefabricated case beam for traditional Bridge Erector Bridge machine structure is complex, can not realize that u-turn, the erection in first and last hole inconvenience, full span erection large-tonnage are double on simple efficient bridge Width box beam auxiliary equipment is more, and the erection asymmetric box beam of large-tonnage is unstable and can not carry out a problems such as hole double width is set a roof beam in place, and carries For simple dismounting on a kind of bridge can be achieved it is two-way set a roof beam in place, first and last aperture frame set it is safe and efficient, become across convenient, the directly whole aperture frame of Liang Shangke If the Bridge Erector of the left and right asymmetric prefabricated case beam of width large-tonnage.
To achieve these goals, the technical solution adopted in the utility model is:
The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage, including along longitudinal direction With laterally the horn of symmetric design, front leg strut, middle supporting leg and the rear support leg that the horn is provided with are the front leg strut, described Middle supporting leg and the rear support leg are attached by bolt-locking device and the horn respectively, and the horn is provided with along master The forward and backward purlin car of beam longitudinal direction traveling, the forward and backward trolley that can be moved left and right on the purlin car, and indulged for each supporting leg The elevator tractor structure divided a word with a hyphen at the end of a line away, the front leg strut is removable and multi-stage expansion.Suspender includes flat used by the trolley Spreader beam and multiple rod member components, the shoulder pole girder upper end are provided with horizontal balance device, both sides be respectively equipped with stepless regulator and Longitudinal oscillation adjusting apparatus.
The Bridge Erector is three leg structures of unmatched auxiliary leg.Become across when, front leg strut vertical shift walking arrive corresponding span Position, plug alignment pin and complete machine change can be achieved across safe and efficient.
The crane's major girder horn is longitudinally, laterally symmetrical and the design of three leg structures of unmatched auxiliary leg, reduces Supporting leg changes the outfit workload, Bridge Erector u-turn only need on bridge by bale handle station straddle truck carry out forward and backward supporting leg it is fast simple mutually Can reversely it be set a roof beam in place after changing.
The forward and backward purlin car of Bridge Erector along the longitudinal direction traveling of girder horn, trolley along purlin car transverse shifting by building bridge The left and right width two panels large-tonnage prefabricated case beam of function full span erection.
The suspender that the trolley uses can the eccentric throw different to asymmetric box beam adjusted respectively, it is non-right to realize Claim box beam center of gravity and trolley center superposition, elevator each point stress is inconsistent when avoiding lifting asymmetric box beam, so as to protect Demonstrate,prove the stability of the lifting of asymmetric box beam.
The front leg strut is removable and multi-stage expansion structure, only needs a latch conversion to complete when first and last aperture frame is set, First and last aperture frame sets simple to operate, and efficiency is higher.
As preferred scheme of the present utility model, the front leg strut is inside and outside column structure, and is connected with telescopic and liter Oil cylinder drops.
The front leg strut of Bridge Erector includes upper horizontal-associate assembly, telescopic mast, conversion sleeve and lower support beam, the top of upper horizontal-associate assembly The horn is carried, is respectively equipped with telescopic inside its both sides, each telescopic slides setting telescopic mast respectively, under each telescopic mast End is hinged the lower support beam, and lower support beam is carried on pier;At least two liftings are provided between extrusome and upper horizontal-associate assembly Oil cylinder, the cylinder body of hoist cylinder are fixed on the upper horizontal-associate assembly, and expansion link is connected to the conversion sleeve affixed with telescopic mast, to drive The relatively upper horizontal-associate assembly of dynamic telescopic mast carries out sliding extension, and the achievable gradient is set a roof beam in place.Pass through telescopic, hoist cylinder, interior column jacket Body combines operation, realizes that the front leg strut multiple stage circulation stretches.Therefore, during first and last aperture frame beam, turned down without dismantling, it is simple high Effect.
As preferred scheme of the present utility model, the front leg strut is detachably connected on pier.
The adverse effect of wind-force is fully taken into account, the longitudinal stability of complete machine is ensured by the fulcrum width of supporting leg in increasing Property;By increasing the horizontal spacing between the column of front leg strut two, ensure the lateral stability of complete machine;In addition by middle supporting leg and frame If being attached between beam piece using lifting hole(eyelet) to increase complete machine security, so as to fully ensure that the stability of front leg strut, institute State front leg strut to be detachably connected on pier, it is not necessary to again by way of anchoring strengthened.Meet set up require and On the premise of security, equipment availability efficiency is improved, reduces time cost.
As preferred scheme of the present utility model, the front leg strut and middle supporting leg are multi-point support structure, i.e., using a variety of Support cylinder connects bridge floor and pier respectively.
As preferred scheme of the present utility model, the front leg strut and middle supporting leg are multi-point support structure, utilize multigroup Oil cylinder is supportted, uniform load is assigned on bridge floor and pier.Preferably, middle supporting leg is 8 fulcrum supports and front leg strut is 4 fulcrum branch Support, by the control of construction maximum load in design tolerance band.Rear support leg is designed as packaged type, can be according to different spans box beam It is supported the longitudinally adjusted of position.
As preferred scheme of the present utility model, the bolt-locking device includes the latch oil for being fixed on wheel holding mechanism Cylinder, and flexible latch is driven by plugging pin oil cylinder, the lower end of the horn is provided with the pin-and-hole for latch assembling.Latch Hydraulic oil cylinder driving bearing pin is horizontally inserted in the pin-and-hole of horn, and when preventing from subsequently setting a roof beam in place, horn is deformed to Relative sliding caused by supporting leg, Play a part of safeguard protection.
As preferred scheme of the present utility model, the front leg strut and the horn, and the middle supporting leg and the machine The connected mode of arm is be hinged for single pin.
As preferred scheme of the present utility model, the connected mode of the rear support leg and the horn is affixed for double-pin, shape Into firm leg structure, complete machine security performance is improved.
In summary, by adopting the above-described technical solution, the beneficial effects of the utility model are:
1st, Design of bridge-erecting machine be unmatched auxiliary leg three leg structures, become across when, front leg strut vertical shift walking to accordingly across Position is spent, alignment pin is plugged and complete machine change can be achieved across safe and efficient.
2nd, it is after Bridge Erector u-turn need to only be carried out the fast simple exchange of forward and backward supporting leg on bridge by bale handle station straddle truck Can, save u-turn under Bridge Erector bridge and take larger ground place, simplify Bridge Erector u-turn program, reduce supporting leg and change the outfit work Amount, ensure Bridge Erector u-turn safety, improve the efficiency that Bridge Erector is reversely set a roof beam in place.
3rd, pass through horizontal along purlin car along the longitudinal direction traveling of girder horn, trolley without auxiliary equipment, the forward and backward purlin car of Bridge Erector To movement, can full span erection double width two panels large-tonnage prefabricated case beam, the erection efficiency of large-tonnage box beam greatly improved.
4th, trolley use suspender can the eccentric throw different to asymmetric box beam adjusted respectively, realize precast box Beam center of gravity and trolley center superposition, the erection of the asymmetric box beam of large-tonnage can be carried out safely.
5th, front outrigger for bridge girder erection machine can vertical shift walking, and be multi-stage expansion structure, a latch only needed when first and last aperture frame is set Conversion can be completed, and first and last aperture frame sets simple to operate, and efficiency is higher.
6th, using front outrigger for bridge girder erection machine and multigroup support cylinder of middle supporting leg, before making, the multiple spot distribution loaded of middle supporting leg institute, Support bridge floor or pier single-point load smaller;Use vertical motion rear support leg simultaneously, it is not loaded in bridge span during Bridge Erector via, Ensure the safety of elevated bridge.
7th, by the horizontal spacing between the fulcrum width and the column of front leg strut two of supporting leg in increasing, the transverse direction of complete machine is ensured Stability;Middle supporting leg and the lifting hole(eyelet) for having set up beam piece are attached, increase complete machine security;Front leg strut no longer needs anchoring to add By force, Bridge Erector safety work efficiency is improved.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the structural representation of front leg strut.
Fig. 3 is the structural representation of middle supporting leg.
Fig. 4 is the structural representation of rear support leg.
Marked in figure:1- rear support legs, 11- rear support leg Pulley mechanisms, 12- outer cylindrical body assemblies, 13- inner cylinder assemblies, 14- stretch Contracting oil cylinder, 2- horns, 3- trolleys, supporting leg in 4-, supporting leg Pulley mechanism in 41-, 42- wheel holding mechanisms, 43- columns, 44- connect Connect beam assembly, 45- equalizer assemblies, 46- support cylinders, 47- transverse-moving mechanisms, the traversing platforms of 48-, 5- front leg struts, 51- stretches Post, support beam under 52-, the upper horizontal-associate assemblies of 53-, 54- hoist cylinders, 55- conversion sleeves, 6- elevator tractor structures, 7- latch lockings Device, 8- purlins car.
Embodiment
Below in conjunction with the accompanying drawings, the utility model is described in detail.
In order that the purpose of this utility model, technical scheme and advantage are more clearly understood, below in conjunction with accompanying drawing and implementation Example, the utility model is further elaborated.It should be appreciated that specific embodiment described herein is only explaining this Utility model, it is not used to limit the utility model.
As shown in Figure 1-2, on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage the whole two-way erection in hole bridge formation Machine, including the horn 2 along the equal symmetric design of vertical and horizontal, front leg strut 5, middle supporting leg 4 and the rear support leg that the horn 2 is provided with 1, the front leg strut 5, the middle supporting leg 4 and the rear support leg 1 are carried out by bolt-locking device 7 and the horn 2 respectively Connection, the forward and backward purlin car 8 along the traveling of girder longitudinal direction that the horn 2 is provided with, before being moved left and right on the purlin car 8, Trolley 3 afterwards, and the elevator tractor structure 6 for each supporting leg vertical shift walking, the front leg strut 5 is removable and multi-stage expansion.
The front leg strut 5 of the Bridge Erector includes upper horizontal-associate assembly 53, telescopic mast 51, conversion sleeve 55 and lower support beam 52, on The top of horizontal-associate assembly 53 carries the horn 2, is respectively equipped with telescopic inside its both sides, each telescopic slides setting and stretched respectively Contracting post 51, the lower end of each telescopic mast 51 are hinged the lower support beam 52, and lower support beam is carried on pier;Telescopic mast 51 and upper horizontal-associate At least two hoist cylinders 54 are provided between assembly 53, the cylinder body of hoist cylinder 54 is fixed on the upper horizontal-associate assembly 53, stretches Bar is connected to the conversion sleeve affixed with telescopic mast 51, can to drive the relatively upper horizontal-associate assembly 53 of telescopic mast 51 to carry out sliding extension Realize that the gradient is set a roof beam in place.By telescopic, hoist cylinder 54, interior outer cylindrical body combines operation, realizes that the multiple stage circulation of front leg strut 5 is stretched Contracting, last aperture frame beam can be achieved, turned down without dismantling, simply efficiently.
The front leg strut 5 is detachably connected on pier, without being anchored with pier, fully takes into account the unfavorable shadow of wind-force Ring, the longitudinal stability of complete machine is ensured by the fulcrum width of supporting leg in increasing 4;By increasing between 5 liang of columns of front leg strut Horizontal spacing, ensure the lateral stability of complete machine;In addition by middle supporting leg 4 and set up between beam piece using lifting hole(eyelet) be attached with Increase complete machine security, so as to fully ensure that the stability of front leg strut 5, it is not necessary to added again by way of anchoring By force.On the premise of meeting to set up requirement and security, equipment availability efficiency is improved, reduces time cost.
Referring to Fig. 3, supporting leg 4 includes column 43, tie-beam assembly 44, equalizer assembly 45 and transverse-moving mechanism in Bridge Erector 47, the top of two columns 43 carries the horn 2, and the lower end of column 43 is connected with tie-beam assembly 44, the lower end of tie-beam assembly 44 It is be hinged with the four groups of equalizer being arranged symmetrically assemblies 45 respectively;The beam-ends of equalizer assembly 45 is provided with two groups of support cylinders 46, eight groups Described support cylinder 46 is basically identical by hydraulic pressure balanced realization stress, is supported on frame box beam beam-ends.
Wherein:Bogey is additionally provided between column 43 and horn 2, bogey is respectively in both sides and comprising Pulley mechanism 41st, wheel holding mechanism 42 is fixed in wheel holding mechanism 42, traversing platform 48, the lower end of Pulley mechanism, and upper end is provided with and hangs over the side of horn 2 The change gear of change gear ear beam, the lower end of wheel holding mechanism 42 are fixedly arranged on the column 43, and upper end is provided with the multiple rollers for accepting horn, more The locking device 7 that vertical shift is driven by described winch dragging mechanism 6 is provided with the middle part of individual roller;Between column 43 and bogey Provided with transverse-moving mechanism 47, relatively traversing, the march coil holder beam of horn 2 and middle supporting leg 4 is realized by oil cylinder pushing.
Referring to Fig. 4, rear support leg 1 includes rear support leg Pulley mechanism 11, outer cylindrical body assembly 12 and inner cylinder assembly 13, change gear machine Structure 11 and outer cylindrical body assembly 12 are affixed, and inner cylinder assembly 13 and outer cylindrical body assembly 12 are slidably connected, and are driven by telescopic oil cylinder 14 Sliding extension is realized, height regulation is carried out and adapts to line slope.
The front leg strut 5 and middle supporting leg 4 are multi-point support structure, and using multigroup support cylinder, uniform load is assigned to On bridge floor and pier.Preferably, middle supporting leg 4 is 8 fulcrum supports and front leg strut 5 is 4 fulcrum supports, by construction maximum load control In design tolerance band.Rear support leg 1 is designed as packaged type, and the longitudinal direction tune of position can be supported according to different spans box beam It is whole.
The bolt-locking device 7 includes being fixed on the plugging pin oil cylinder of wheel holding mechanism, and is stretched by plugging pin oil cylinder driving The latch of contracting, the lower end of the horn 2 are provided with the pin-and-hole for latch assembling.Plugging pin oil cylinder driving bearing pin is horizontally inserted horn Pin-and-hole in, when preventing from subsequently setting a roof beam in place, horn 2 is deformed to Relative sliding caused by each supporting leg, plays a part of safeguard protection.
The front leg strut 5 and the horn 2, and the connected mode of the middle supporting leg 4 and the horn 2 are cut with scissors for single pin Connect.The connected mode of the rear support leg 1 and the horn 2 is that double-pin is affixed, forms firm leg structure, improves complete machine security performance.
The suspender suspender that the trolley 3 uses includes shoulder pole girder and multiple rod member components, and the shoulder pole girder upper end is set There is horizontal balance device, both sides are respectively equipped with stepless regulator and longitudinal oscillation adjusting apparatus, can be different to asymmetric box beam Eccentric throw adjusted respectively, so as to ensure the stability of the lifting of asymmetric box beam.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model All any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (7)

  1. A kind of 1. Bridge Erector of the whole two-way erection in hole on asymmetric framing prefabricated case beam beam of achievable large-tonnage, it is characterised in that Including the horn (2) along the equal symmetric design of vertical and horizontal, front leg strut (5) that the horn (2) is provided with, middle supporting leg (4) and Rear support leg (1), the front leg strut (5), the middle supporting leg (4) and the rear support leg (1) pass through bolt-locking device (7) respectively It is attached with the horn (2), the horn (2) is provided with the forward and backward purlin car (8) along the traveling of girder longitudinal direction, in the purlin The forward and backward trolley (3) that can be moved left and right on car (8), and the elevator tractor structure (6) for each supporting leg vertical shift walking, The front leg strut (5) is removable and multi-stage expansion, and suspender includes shoulder pole girder and multiple rod member groups used by the trolley (3) Part, the shoulder pole girder upper end are provided with horizontal balance device, and both sides are respectively equipped with stepless regulator and longitudinal oscillation adjusting apparatus.
  2. 2. the frame of the whole two-way erection in hole on a kind of achievable asymmetric framing prefabricated case beam beam of large-tonnage as claimed in claim 1 Bridge machine, it is characterised in that the front leg strut (5) is inside and outside column structure, and is connected with telescopic and hoist cylinder (54).
  3. 3. the frame of the whole two-way erection in hole on a kind of achievable asymmetric framing prefabricated case beam beam of large-tonnage as claimed in claim 1 Bridge machine, it is characterised in that the front leg strut (5) is detachably connected on pier.
  4. 4. the frame of the whole two-way erection in hole on a kind of achievable asymmetric framing prefabricated case beam beam of large-tonnage as claimed in claim 1 Bridge machine, it is characterised in that the front leg strut (5) and middle supporting leg (4) are multi-point support structure, i.e., are distinguished using a variety of support cylinders Connect bridge floor and pier.
  5. 5. the whole two-way frame in hole on a kind of achievable asymmetric framing prefabricated case beam beam of large-tonnage as described in claim 1-4 is any If Bridge Erector, it is characterised in that the bolt-locking device includes being fixed on the plugging pin oil cylinder of wheel holding mechanism, and by inserting The flexible latch of hydraulic oil cylinder driving is sold, the lower end of the horn (2) is provided with the pin-and-hole for latch assembling.
  6. 6. the frame of the whole two-way erection in hole on a kind of achievable asymmetric framing prefabricated case beam beam of large-tonnage as claimed in claim 5 Bridge machine, it is characterised in that the front leg strut (5) and the horn (2), and the company of the middle supporting leg (4) and the horn (2) It is be hinged for single pin to connect mode.
  7. 7. the frame of the whole two-way erection in hole on a kind of achievable asymmetric framing prefabricated case beam beam of large-tonnage as claimed in claim 5 Bridge machine, it is characterised in that the rear support leg (1) and the horn (2) connected mode are affixed for double-pin.
CN201720844433.4U 2017-07-12 2017-07-12 The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage Active CN206941414U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720844433.4U CN206941414U (en) 2017-07-12 2017-07-12 The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720844433.4U CN206941414U (en) 2017-07-12 2017-07-12 The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage

Publications (1)

Publication Number Publication Date
CN206941414U true CN206941414U (en) 2018-01-30

Family

ID=61369173

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720844433.4U Active CN206941414U (en) 2017-07-12 2017-07-12 The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage

Country Status (1)

Country Link
CN (1) CN206941414U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119578A (en) * 2017-07-12 2017-09-01 中铁二局集团有限公司 The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage
CN112095473A (en) * 2020-09-10 2020-12-18 中交第二航务工程局有限公司 Double-guide-beam bridge girder erection machine turning method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119578A (en) * 2017-07-12 2017-09-01 中铁二局集团有限公司 The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage
CN112095473A (en) * 2020-09-10 2020-12-18 中交第二航务工程局有限公司 Double-guide-beam bridge girder erection machine turning method

Similar Documents

Publication Publication Date Title
CN107119578A (en) The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage
CN104631335A (en) Novel large-tonnage bridge girder erection machine and construction method thereof
CN101462672B (en) Big elevating capacity and big elevating height hoisting crane
CN104762885A (en) Large-tonnage beam erection and transportation system in tunnel and beam erection span change procedure thereof
CN201338911Y (en) Lifting cane with large lifting capacity and great lifting height
CN101736703B (en) 3000t special bridge girder erection machine for integrally erecting 120m-span double-layer four-line steel beam bridge for highway and railway
CN204551283U (en) In tunnel, large-tonnage is set a roof beam in place fortune frame system
CN102071650A (en) Inside and outside general bridge girder erection machine for high speed railway tunnel and girder erecting technology thereof
CN106917360A (en) Lift leg formula frame plate machine and its frame plate method
CN207904782U (en) Large span crosses tunnel box beam bridge formation machine
CN106285020A (en) High-altitude precoated plate fitting machine
CN206941414U (en) The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage
CN103321156A (en) Foldable through-tunnel bridge girder erection machine rear support leg and application thereof
CN108149589B (en) Bridge girder erection machine with large span and tunnel box girder
CN201713767U (en) Bridge erecting machine for bridge erection
CN201746780U (en) Bridge girder erection machine capable of passing through tunnel and realizing girder erection at tunnel opening
CN103147398A (en) Bridge girder erection machine and method for enabling the bridge girder erection machine to transfer among bridges or pass through tunnels
CN210368663U (en) Wide-body double-width bridge girder erection machine
CN106320190A (en) Platform of bridge maintenance, consolidation and suspension construction
CN107747280A (en) The Bridge Erector of full span erection steel-pipe concrete truss
CN106087763B (en) It is a kind of to cross the double girder rubber-tyred railway T-girder bridge girder erections of tunnel type and bridging method
CN101487235B (en) Movable supporting legs of bridge erecting machine
CN203878478U (en) A bridge girder erection machine with a single arm box girder
CN103924523B (en) A kind of single armed box beam bridge formation machine
CN203890888U (en) Girder hoisting traveling crane of single-arm box girder bridge erecting machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee after: CHINA RAILWAY ENGINEERING MACHINERY RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Patentee after: China Railway Second Bureau Construction Co.,Ltd.

Co-patentee after: CHINA RAILWAY ERJU CORPORATION CHING ENGINEERING Co.,Ltd.

Address before: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee before: CHINA RAILWAY ENGINEERING MACHINERY RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Patentee before: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Co-patentee before: CHINA RAILWAY ERJU CORPORATION CHING ENGINEERING Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190813

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee after: CHINA RAILWAY ENGINEERING MACHINERY RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Patentee after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Co-patentee after: CHINA RAILWAY ERJU CORPORATION CHING ENGINEERING Co.,Ltd.

Address before: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee before: CHINA RAILWAY ENGINEERING MACHINERY RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Patentee before: China Railway Second Bureau Construction Co.,Ltd.

Co-patentee before: CHINA RAILWAY ERJU CORPORATION CHING ENGINEERING Co.,Ltd.