CN206937660U - A kind of building block drilling transposition - Google Patents

A kind of building block drilling transposition Download PDF

Info

Publication number
CN206937660U
CN206937660U CN201720594140.5U CN201720594140U CN206937660U CN 206937660 U CN206937660 U CN 206937660U CN 201720594140 U CN201720594140 U CN 201720594140U CN 206937660 U CN206937660 U CN 206937660U
Authority
CN
China
Prior art keywords
building block
rig
vertically movable
transposition
movable mechanism
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720594140.5U
Other languages
Chinese (zh)
Inventor
顾洪锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
North China Metallurgical Construction Engineering Construction Co Ltd
Original Assignee
China Huaye Group Co Ltd
North China Metallurgical Construction Engineering Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd, North China Metallurgical Construction Engineering Construction Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201720594140.5U priority Critical patent/CN206937660U/en
Application granted granted Critical
Publication of CN206937660U publication Critical patent/CN206937660U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Processing Of Stones Or Stones Resemblance Materials (AREA)

Abstract

A kind of building block drilling transposition, including:Building block fixed mount, for fixing building block;Drill fixing support, the neighbouring building block fixed mount are arranged;Vertically movable mechanism, vertically movable mechanism is arranged on drill fixing support, and vertically movable mechanism is horizontally slidable on drill fixing support;Rig, rig is arranged in vertically movable mechanism, and can vertically be slided in vertically movable mechanism, and rig is used to drill to building block fixed on building block fixed mount.Using the building block drilling equipment, building block, rig fixation, damage of the building block in boring procedure will not be caused.Drilling efficiency is improved, size is accurate, and perpendicularity deviation is small.Supreme hypodermis building block faulting of slab ends phenomenon, no obstructed phenomenon of hole.Horizontal, longitudinal, the vertical displacement of rig can be adjusted so that rig walking path is accurate, is not in the security incident of rig injury operating personnel in operating process.Building block keeps certain distance with ground, had both ensured that pore-forming was penetrating, and will not destroy the finished products such as floor again.

Description

A kind of building block drilling transposition
Technical field
Building field is the utility model is related to, specifically, is related to a kind of building block drilling transposition.
Background technology
The building enclosure of the engineering such as industry and civil buildings, municipal administration, bridge, tunnel is, it is necessary to largely use air entrained concrete Building block, each specialized engineering such as plumbing, electric, HVAC, air-conditioning are both needed to slot in building block, drilled.
Bore mode universal at present is that building block is positioned over to the ground at scene, and operator fixes building block, hand with bipod Water holding bores or other rigs, is drilled.Because bipod clamping may not consolidate, and hand-held drill is also easily shaken, tilted, It easily causes following defect:
1) in boring procedure, building block destruction is more serious, and the ratio for causing building block to damage in boring procedure according to statistics is up to 2%, though being unlikely to discarded, the ratio for impacting total quality is up to 5%.
2) building block is easily toppled over, and rig sideslip, operating efficiency is low, and normal operations worker's day pore-forming is less than 40 meters.
3) pore-forming dimensional discrepancy is big, and epithelium building block and hypodermis building block hole location are inconsistent, and threading is difficult or can not thread, Secondary fluting is needed, it is time-consuming.
4) because building block is fixed loosely, in boring procedure, rig injury operating personnel leg, the security incident of pin easily occurs.
5) because building block is placed on the spot, building block ground proximity during drilling operation, pore-forming is not penetrating, and is easily caused in boring procedure The finished products such as floor destroy.
Utility model content
To solve the above problems, the utility model has made this building block drilling equipment.The present apparatus can firmly fix building block And rig, while rig can transversely, vertically, longitudinal direction it is flexibly mobile, building block is drilled, crosshead has drawn from shaped steel corner Material, cost is cheap, simple to operate, safe and efficient, greatly improves hole quality, has practiced people-oriented, green Theory.
A kind of building block drilling transposition, including:Building block fixed mount, for fixing building block;Drill fixing support, the neighbouring building block Fixed mount is arranged;Vertically movable mechanism, the vertically movable mechanism are arranged on the drill fixing support, and described vertically movable Mechanism is horizontally slidable on the drill fixing support;Rig, the rig are arranged in vertically movable mechanism, and can be described Vertically slided in vertically movable mechanism, the rig is used to drill to building block fixed on the building block fixed mount.
Preferably, the longitudinal slide rail extended longitudinally is provided with the drill fixing support, in the longitudinal slide rail Slide plate is provided with, the slide plate is connected with the vertically movable mechanism, and the slide plate is provided with the longitudinal rack extended longitudinally, The first gear engaged with the longitudinal rack is provided with the drill fixing support, the axis of the first gear extends Crank is vertically moved, with the shake for vertically moving crank, the slide plate moves along longitudinal direction in longitudinal slide rail, described perpendicular to drive Longitudinally slided to travel mechanism.
Preferably, the vertically movable mechanism includes connecting plate, and the connecting plate is arranged on the slide plate, from connecting plate Upwardly extended vertical rack, be also arranged with adapter sleeve in the vertical rack, have in the adapter sleeve with it is described vertical The second gear of rack engagement, the axis of the second gear extend vertically movable crank, and the rig is arranged on the company In female connector, with the shake of vertically movable crank, the rig vertically slides.
Preferably, horizontal slide rail is additionally provided with the drill fixing support, the longitudinal slide rail is installed in horizontal slide rail On, there is the horizontal tooth bar extended transversely on the drill fixing support, be provided with the longitudinal slide rail and the horizontal stroke The 3rd gear engaged to rack, the axis of the 3rd gear extends transverse shifting crank, with shaking for transverse shifting crank Dynamic, the longitudinal slide rail is laterally slided in horizontal slide rail.
Preferably, grip block is provided with the width of the building block fixed mount, for clamping the building block.
Preferably, the building block locating piece for determining building block placement location is additionally provided with the building block fixed mount.
Preferably, the building block fixed mount connects as one with the drill fixing support.
Preferably, the bottom surface of the building block fixed mount and ground separation setpoint distance.
Preferably, the longitudinal slide rail is the parallel track of two or more pieces.
Preferably, the adapter sleeve has installation card to the rig installing plate that extends sideways out in the end of rig installing plate, Rig is fixed on rig installing plate by installation card.
Brief description of the drawings
By the way that embodiment is described with reference to accompanying drawings below, features described above of the present utility model and technological merit will Become more fully apparent and be readily appreciated that.
Fig. 1 is the schematic perspective view for the building block drilling transposition for representing the utility model embodiment;
Fig. 2 is the schematic perspective view for the vertically movable mechanism for representing the utility model embodiment;
Fig. 3 is the schematic diagram of the horizontal slide rail for the building block drilling transposition for representing the utility model embodiment.
Embodiment
The embodiment of building block described in the utility model drilling transposition described below with reference to the accompanying drawings.This area it is common Technical staff will recognize, in the case of without departing from spirit and scope of the present utility model, can use a variety of sides Formula or its combination are modified to described embodiment.Therefore, accompanying drawing and description are inherently illustrative, rather than use In limitation scope of the claims.In addition, in this manual, accompanying drawing is drawn not in scale, and identical accompanying drawing mark Note represents identical part.
Hereinafter, longitudinally refer to the width of drill fixing support, laterally refer to the length direction of drill fixing support.
In the utility model, building block drilling transposition includes building block fixed mount, drill fixing support, rig, vertically movable machine Structure, rig 5 are arranged in vertically movable mechanism 4, and the position of rig can be adjusted in transverse direction, longitudinal direction and vertical direction.Tie below Close Fig. 1 and illustrate its structure.Building block fixed mount 2 and drill fixing support 1 are all tower structure.Angle steel can be used to make, For example, drill fixing support is welded using 50*50 angle steel (or 400*600 square steel), long 700mm, wide 600mm, high 520mm. Building block fixed mount 2 can also use 50*50 angle steel welding productions, and the width of building block fixed mount 2 determines according to building block width, is building The both sides of the width of block fixed mount 2 have upward grip block, and building block can be then placed between two pieces of grip blocks.Can To be used as grip block by the use of two sides of angle steel.As shown in figure 1, building block 21 is clamped in the side of two angle steel of building block fixed mount 2 In side.The width of building block fixed mount 2 is wider 2mm than the width of building block to be advisable to 4mm.It can be made not according to the building block of different size Same building block fixed mount.The width of building block fixed mount 2 can also determine according to the length of building block.
The longitudinal slide rail 31 extended longitudinally is fixed with the top of drill fixing support 1, is pacified in the longitudinal slide rail 31 Slide plate 32 is placed with, the slide plate 32 can slide along longitudinal slide rail 31.Two longitudinal slide rails 31, longitudinal slide rail are used in Fig. 1 and Fig. 3 31 can use that two channel-section steels are parallel and compartment of terrain is welded on the top of drill fixing support 1, and slide plate 32 is inserted in the recessed of two channel-section steels In groove.The vertically movable mechanism 4 includes connecting plate 41, and the connecting plate 41 is arranged on the slide plate 32, in the slide plate 32 bottom is provided with the longitudinal rack extended longitudinally, is provided with the drill fixing support 1 and is nibbled with the longitudinal rack The first gear 33 of conjunction, the axis of first gear 33, which extends, vertically moves crank 34.Shake vertically moves crank 34, and first The rotation driving slide plate 32 of gear 33 slides along longitudinal slide rail 31.Because vertically movable mechanism 4 is connected on slide plate 32, therefore rig 5 also just can be along vertically moving.
After building block is fixed on building block fixed mount 2, crank 34 is vertically moved by regulation, rig can be adjusted from building block Distance, by adjusting vertically movable mechanism 4, height of the rig apart from building block can be adjusted.
The building block drilling transposition of the present embodiment uses building block fixed mount by the firm fixation of building block, and rig is movably solid It is scheduled on drill fixing support.Can transversely, the position of longitudinal direction and vertical adjustment rig, enable to drill bit easily to reach area to be drilled Domain.Building block, rig fixation, damage of the building block in boring procedure will not be caused.Hole quality is good, and size is accurate, perpendicularity Deviation is small, and general building block hole perpendicularity deviation is no more than 1mm.Upper and lower building block is without faulting of slab ends phenomenon, no obstructed phenomenon of hole.Side Convenient to operate, improve operating efficiency.Rig walking path is accurate, is not in rig injury operating personnel leg, pin in operating process Security incident.During drilling operation, building block maintains a certain distance with ground, and pore-forming is penetrating, and will not destroy the finished products such as floor.
In one alternate embodiment, as shown in Fig. 2 the vertically movable mechanism 4 includes upwardly extending from connecting plate 41 Vertical rack 42, be also arranged with adapter sleeve 43 in the vertical rack 42, have in the adapter sleeve 43 with it is described vertical The second gear (not shown) that rack 42 engages, the second gear axis extend vertically movable crank 45.Shake vertical move Shake 45, rig can move up and down.
In one alternate embodiment, horizontal slide rail 35 is additionally provided with the top of drill fixing support, longitudinal slide rail 31 can be slided It is arranged on dynamicly in horizontal slide rail 35.The both sides of the width of the drill fixing support 1 are provided with horizontal tooth bar (not show Go out), the 3rd gear 36 engaged with the horizontal tooth bar is provided with longitudinal slide rail 31, the axis of the 3rd gear 36 prolongs Stretch out transverse shifting crank 37.Although the 3rd gear 36 in Fig. 3 is arranged on the end of longitudinal slide rail 31, it is only exemplary , the position of the 3rd gear 36 is determined according to the position of horizontal tooth bar.It can be used among two longitudinal slide rails 31 in Fig. 3 normal Rule connected mode is fixed as one.When shaking transverse shifting crank 37, longitudinal slide rail 31 can be moved transversely slide rail 35.Pin To different building blocks, its required boring sites in curing may not also be with rig in a fore-and-aft plane, and now can operation is laterally Mobile crank 37, then transversely slide rail 35 moves longitudinal slide rail 31 so that drilling-machine shifter to correct position.
In one alternate embodiment, the building block positioning for determining building block placement location is provided with the building block fixed mount Block 22, the side of building block are bonded with the locating piece 22, then show that building block is in place.
In one alternate embodiment, the building block fixed mount 2 connects as one with the drill fixing support 1.Building block is consolidated Determine frame 2 and can be bolted with drill fixing support 1 to be integrated.And so that the bottom surface of building block fixed mount 2 has with ground A certain distance, so when drilling through building block, drill bit will not contact with ground, prevent from boring bad floor or cause bit damage.It is special Not, the bottom surface of building block fixed mount 2 and ground distance 150mm.
In one alternate embodiment, rig 5 is fixed on adapter sleeve 43 by installation card.Specifically, adapter sleeve 43 To the rig installing plate 46 that extends sideways out, there is installation card 47 in the end of rig installing plate 46, rig 5 is consolidated by installation card 47 It is scheduled on rig installing plate 46, blending bolt fastening.
Building block drilling transposition of the present utility model has following technique effect:
1) building block, rig fixation, will not cause damage of the building block in boring procedure, and hole quality is good.
2) convenient operation, improves drilling efficiency, drills normal operations worker's day about 70 meters.
3) size is accurate, and perpendicularity deviation is small, and general building block hole perpendicularity deviation is no more than 1mm, supreme hypodermis building block Faulting of slab ends phenomenon, no obstructed phenomenon of hole.
4) horizontal, longitudinal, the vertical displacement of rig can be adjusted so that rig walking path is accurate, in operating process, no The security incident of rig injury operating personnel occurs.
5) during drilling operation, building block and ground keep certain distance, have both ensured that pore-forming was penetrating, will not destroy again floor etc. into Product.
Preferred embodiment of the present utility model is the foregoing is only, is not limited to the utility model, for this area Technical staff for, the utility model can have various modifications and variations.It is all within the spirit and principles of the utility model, Any modification, equivalent substitution and improvements made etc., should be included within the scope of protection of the utility model.

Claims (10)

  1. The transposition 1. a kind of building block drills, it is characterised in that including:
    Building block fixed mount, for fixing building block;
    Drill fixing support, the neighbouring building block fixed mount are arranged;
    Vertically movable mechanism, the vertically movable mechanism is arranged on the drill fixing support, and the vertically movable mechanism exists It is horizontally slidable on the drill fixing support;
    Rig, the rig is arranged in vertically movable mechanism, and can vertically be slided in the vertically movable mechanism, described Rig is used to drill to building block fixed on the building block fixed mount.
  2. The transposition 2. building block according to claim 1 drills, it is characterised in that be provided with the drill fixing support along vertical To the longitudinal slide rail of extension, slide plate is provided with the longitudinal slide rail, the slide plate is connected with the vertically movable mechanism, institute State slide plate and be provided with the longitudinal rack extended longitudinally, be provided with what is engaged with the longitudinal rack on the drill fixing support First gear, the axis of the first gear, which extends, vertically moves crank, with the shake for vertically moving crank, the slide plate edge Longitudinal direction is moved in longitudinal slide rail, to drive the vertically movable mechanism longitudinally to slide.
  3. The transposition 3. building block according to claim 2 drills, it is characterised in that the vertically movable mechanism includes connecting plate, The connecting plate is arranged on the slide plate, has been upwardly extended vertical rack from connecting plate, has also been arranged in the vertical rack There is adapter sleeve, there is the second gear engaged with the vertical rack, the axis extension of the second gear in the adapter sleeve Go out vertically movable crank, the rig is arranged on the adapter sleeve, and with the shake of vertically movable crank, the rig is vertically Slide.
  4. The transposition 4. building block according to claim 2 drills, it is characterised in that be additionally provided with horizontal stroke on the drill fixing support To slide rail, the longitudinal slide rail is installed in horizontal slide rail, has the transverse teeth extended transversely on the drill fixing support Bar, the 3rd gear engaged with the horizontal tooth bar, the axis extension of the 3rd gear are provided with the longitudinal slide rail Go out transverse shifting crank, with the shake of transverse shifting crank, the longitudinal slide rail is laterally slided in horizontal slide rail.
  5. The transposition 5. building block according to claim 1 drills, it is characterised in that on the width of the building block fixed mount Grip block is provided with, for clamping the building block.
  6. The transposition 6. building block according to claim 5 drills, it is characterised in that be additionally provided with the building block fixed mount really Determine the building block locating piece of building block placement location.
  7. The transposition 7. building block according to claim 1 drills, it is characterised in that the building block fixed mount is fixed with the rig Frame connects as one.
  8. The transposition 8. building block according to claim 1 drills, it is characterised in that between the bottom surface and ground of the building block fixed mount Every setpoint distance.
  9. The transposition 9. building block according to claim 2 drills, it is characterised in that the longitudinal slide rail is that two or more pieces is parallel Track.
  10. The transposition 10. building block according to claim 3 drills, it is characterised in that the adapter sleeve is to the rig that extends sideways out Installing plate, has installation card in the end of rig installing plate, and rig is fixed on rig installing plate by installation card.
CN201720594140.5U 2017-05-25 2017-05-25 A kind of building block drilling transposition Active CN206937660U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720594140.5U CN206937660U (en) 2017-05-25 2017-05-25 A kind of building block drilling transposition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720594140.5U CN206937660U (en) 2017-05-25 2017-05-25 A kind of building block drilling transposition

Publications (1)

Publication Number Publication Date
CN206937660U true CN206937660U (en) 2018-01-30

Family

ID=61363280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720594140.5U Active CN206937660U (en) 2017-05-25 2017-05-25 A kind of building block drilling transposition

Country Status (1)

Country Link
CN (1) CN206937660U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112917722A (en) * 2021-01-30 2021-06-08 北京城建七建设工程有限公司 Adjusting steel frame of water drill perforator
CN114454353A (en) * 2022-03-22 2022-05-10 杭州龙华环境集成系统有限公司 Pipe group construction process of efficient intelligent cold source system of central air conditioner

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112917722A (en) * 2021-01-30 2021-06-08 北京城建七建设工程有限公司 Adjusting steel frame of water drill perforator
CN112917722B (en) * 2021-01-30 2022-06-17 北京城建七建设工程有限公司 Adjusting steel frame of water drill perforator
CN114454353A (en) * 2022-03-22 2022-05-10 杭州龙华环境集成系统有限公司 Pipe group construction process of efficient intelligent cold source system of central air conditioner
CN114454353B (en) * 2022-03-22 2024-05-10 杭州龙华环境集成系统有限公司 Pipe group construction process of efficient intelligent cold source system of central air conditioner

Similar Documents

Publication Publication Date Title
CN206937660U (en) A kind of building block drilling transposition
CN205593782U (en) Indoor outer dual -purpose pavement material gets core machine
CN207386690U (en) A kind of intelligent numerical control cutting mechanics device
CN106141246B (en) Special drilling machine for heightening highway guardrail
CN103866660B (en) A kind of rope saw cutting equipment of miniature high-speed non-fragment orbit
EP2243579A2 (en) Drilling module for creating multiple boreholes in a component and mobile drilling device unit for attachment to a vehicle, in particular with such a drilling module
CN111516115A (en) Hollow slab beam double-side walking type chiseling device
CN110394887A (en) Cutting machine and air entrained concrete production equipment
CA1045902A (en) Mobile track tamping and track position correction machine
CN209907531U (en) A support for rainwater pipeline construction
CN209937344U (en) Lateral drilling device for cement concrete pavement slab
RU2158796C2 (en) Tie-tamping outfit
CN109722958B (en) Rail panel supporting device with transverse synchronous movement and ultra-high stepless adjusting mechanism
EP1186372B1 (en) Portal milling machine
CN208528136U (en) A kind of two-way Double head horizontal hole-drilling system of H profile steel column
CN108278086B (en) A kind of positioning drilling platform for urban track traffic
CN109570549A (en) A kind of positioning formula steel member drilling equipment
CN206425795U (en) A kind of self tapping bores all-in-one certainly
US20090145324A1 (en) Movable crawler system for railroad equipment
CN108274545A (en) A kind of double bit drilling devices for timber drilling
CN211524720U (en) Quick adjusting and fixing device for water drill drilling
JP2010228308A (en) Boring device of concrete flooring
CN110000418A (en) Square plate digs side device
CN104802320B (en) Miniature multi-function cutting machine
KR200481447Y1 (en) Drill Movable on Board a Rail for Forming Hole

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant