CN206903334U - A kind of high-strength combination formula shaft tower - Google Patents

A kind of high-strength combination formula shaft tower Download PDF

Info

Publication number
CN206903334U
CN206903334U CN201720257390.XU CN201720257390U CN206903334U CN 206903334 U CN206903334 U CN 206903334U CN 201720257390 U CN201720257390 U CN 201720257390U CN 206903334 U CN206903334 U CN 206903334U
Authority
CN
China
Prior art keywords
shaft tower
reinforced
connection
tube
combination formula
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720257390.XU
Other languages
Chinese (zh)
Inventor
钱方良
张斌杰
翟宏伟
禇禹秋
蒋建强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUZHOU FEIJIAN TOWER MANUFACTURING CO LTD
Original Assignee
HUZHOU FEIJIAN TOWER MANUFACTURING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUZHOU FEIJIAN TOWER MANUFACTURING CO LTD filed Critical HUZHOU FEIJIAN TOWER MANUFACTURING CO LTD
Priority to CN201720257390.XU priority Critical patent/CN206903334U/en
Application granted granted Critical
Publication of CN206903334U publication Critical patent/CN206903334U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of high-strength combination formula shaft tower, including at least two segmented shaft tower unit, each shaft tower unit includes four and is used for assembled principal post, connection member is set between adjacent two principal posts, the connection member includes at least more than two the first reinforced pipes for being used to reinforce connection, for fixing the telophragma of the first reinforced pipe and support tube for carrying telophragma, the first reinforced pipe positioned at telophragma the same side, its one end is all connected with telophragma, the other end is connected with the two ends of principal post respectively, the structure can facilitate shaft tower in mountain area to carry out splicing installation after installing in advance, and possess high intensity.

Description

A kind of high-strength combination formula shaft tower
Technical field
The present invention relates to the high-strength combination formula shaft tower of power Transmission equipment, more particularly to conveying extra-high voltage electric power.
Background technology
It is big originally to transport the shaft tower installation difficulty of extra-high voltage electric power, time length.Because shaft tower requirement is installed in no road , it is necessary to which each component for forming shaft tower is first transported into specified location on the mountain ridge, splicing installation is then carried out by worker again. It is big transportation rod tower assembly difficulty to be present in this mode, and each component splicing is cumbersome for installation, and because single component needs worker to exist Height carries out splicing assembling in the air, the problem of being affected for the intensity of whole shaft tower.
Such as a kind of iron tower for ultra-high voltage transmission that patent announcement CN201433592Y is announced, the iron tower for ultra-high voltage transmission can expire The electric clearance requirement of sufficient UHV transmission;Negative shielding angle is formed to wire, is adapted to mountain area to use;Using comprehensive length tower Leg, landform and the vegetation in mountain area are protected, beneficial to environmental protection.But the iron tower component transport difficulty is big, component is cumbersome when installing, simultaneously Because component is that worker is aerial separately installed in height, the intensity after shaft tower installation is caused easily to be affected.
The content of the invention
Technical problems to be solved
The purpose of the present invention is the above mentioned problem present in prior art, and spy provides a kind of high-strength combination formula bar Tower.
Technical scheme
In order to solve the above technical problems, the present invention provides a kind of high-strength combination formula shaft tower, including it is at least two Segmented shaft tower unit, each shaft tower unit include four and are used for assembled principal posts, the company of setting between adjacent two principal posts Relay part, the connection member include at least more than two the first reinforced pipes for being used for reinforcing connection, for fixing the first reinforcement The telophragma of pipe and the support tube for carrying telophragma, the first reinforced pipe positioned at telophragma the same side, its one end all with Telophragma is connected, and the other end is connected with the two ends of principal post respectively.
Further, the both ends of the support tube are connected on two adjacent principal posts, and the support tube includes length Pipe, it is arranged at the ring flange of long tube end, the short tube being connected by ring flange with long tube.
Further, the long tube is stretched out in outside telophragma and is connected again by ring flange with short tube, enables telophragma complete It can ensure the accuracy of connection by adjusting short tube when being carried on long tube, and installing entirely and improve the strong of whole support tube Degree.
Further, the second reinforced pipe is set between adjacent connection member, by what is surrounded between multiple second reinforced pipes Plane and the plane by being surrounded between multiple support tubes are parallel to each other.
Further, the first reinforced tube is set between second reinforced pipe and its principal post closest to side;The phase The second reinforced tube is set between adjacent two second reinforced pipes, both of which plays a part of enhancing structure stability and intensity.
Further, be all respectively arranged to be connected with the first reinforced tube on second reinforced pipe and principal post first is mended Strong plate, also sets up the second stiffening plate for being connected with the second reinforced tube on second reinforced pipe, first stiffening plate with Second stiffening plate is in the same plane.
Further, the telophragma includes being welded in supporting plate on long tube, and the support plate face is to the second reinforced pipe One side on be provided for the fixed plate that is connected with the second reinforced pipe, opposite side sets the limited block being connected with support tube.
Further, the limited block is the two boards in length and breadth of right-angled intersection, and increase supporting plate is indulged when being connected with support tube To and transverse direction on intensity.
Further, the first reinforced pipe both ends open up bayonet socket, welding U-board in the bayonet socket, right on the principal post Reinforcing plate is set in the position of U-board connection, plane is parallel with plane where supporting plate where the reinforcing plate.
Further preferred, the bayonet socket is arranged at the centre position of the first reinforced pipe two ends, and its depth is less than U-board Length, for improving stability when connecting.
Beneficial effects of the present invention:
This shaft tower solves the installation question of extra-high voltage electric power shaft tower, can be by way of being assembled after installing in advance Make shaft tower mountain area installation become it is succinct, quickly, without worker the separately installed shaft tower in mountain area high-altitude each component, and this Tower structure intensity is high, is influenceed beneficial to various natural causes are tackled to caused by shaft tower.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the left view of telophragma;
Fig. 3 is the structural representation of support tube;
Fig. 4 is the structural representation of the first reinforced pipe.
In figure, 1- principal posts, 11- reinforcing plates, 2- connection members, the reinforced pipes of 21- first, 211- bayonet sockets, 22- telophragmas, 221- supporting plates, 222- fixed plates, 223- limited blocks, 23- support tubes, 231- long tubes, 232- ring flanges, 233- short tubes, 24- Two reinforced pipes, the reinforced tubes of 25- first, the reinforced tubes of 26- second, the stiffening plates of 27- first, the stiffening plates of 28- second, 29-U shape plates, 3- Bolt.
Embodiment
Invention is described further below in conjunction with the accompanying drawings:
As shown in Figure 1 and Figure 4, a kind of high-strength combination formula shaft tower, including at least two segmented shaft tower unit, The segmented shaft tower unit includes four and is used for assembled principal posts 1, and the principal post 1 is round steel pipe, adjacent two principal posts 1 it Between be attached by connection member 2.The connection member 2 includes four the first reinforced pipes 21 for being used to reinforce connection, described First reinforced pipe 21 is the round steel pipe that diameter is less than the diameter of principal post 1, and its both ends opens up bayonet socket 211, and the bayonet socket 211 is Strip, its position are located on the center line of the first reinforced pipe 21, then in the interior welds U-board 29 of bayonet socket 211, ensure U-shaped Plate 29 is overlapped with the center line of the first reinforced pipe 21.So will after the welding of U-board 29 and miscellaneous part, just can determine that first plus The place plane of strong pipe 21.The U-board 29 is formed by rectangle steel plate bending, and compared to common rectangle steel plate, it is tied Structure has higher intensity.Throat thickness is more than the steel reinforcing plate 11 of U-board 29 on the principal post 1, for raising and U-board 29 bonding strength.The U-board 29 of described one end of first reinforced pipe 21 is connected with reinforcing plate 11 by bolt 3, the connected mode Worker is not only facilitated to carry out installation fixation, moreover it is possible to ensure to fix by face between the first reinforced pipe 21 and principal post 1, increase both it Between contact area so that total has more preferable stabilized soil pavement.
As shown in figures 1 and 3, the other end of the first reinforced pipe 21 by U-board 29 and is carried on support tube 23 Telophragma 22 is connected by bolt 3, and the both ends of the support tube 23 are respectively welded on two adjacent principal posts 1.The support Pipe 23 includes long tube 231, is arranged at the ring flange 232 of the end of long tube 231, the short tube being connected by ring flange 232 with long tube 231 233.The long tube 231 is round steel pipe, its one end is welded and fixed with principal post 1, other end welding flange 232 and extends Outside disk 22, whole telophragma 22 is set to be carried on completely on long tube 231, to ensure the stability of telophragma 22.The short tube 233 be the round steel pipe with the same diameter of long tube 231, and its one end is welded with principal post 1, and the other end passes through ring flange 232 and long tube 231 connections, this connected mode can correct the position of telophragma 22 by adjusting the connection of short tube 233, whole so as to improve The stability of individual structure and the difficulty for reducing installation.
As shown in Fig. 2 the telophragma 22 includes the supporting plate 221 being welded on long tube 231, the face of supporting plate 221 It is provided for what is be connected with the second reinforced pipe 24 on to the one side for connecting the second reinforced pipe 24 between abutting connection part 2 Fixed plate 222, opposite side set the limited block 223 being made up of the plate of two pieces of cruciform shapes being connected with support tube 23.It is described The place plane of fixed plate 222 is mutually perpendicular to the place plane of supporting plate 221, makes the uniform force of telophragma 22.The limited block 223 Add longitudinal direction when supporting plate 221 is connected with support tube 23 and the intensity in transverse direction.
As shown in figure 1, the plane by being surrounded between four the second reinforced pipes 24 and by being enclosed between four support tubes 23 Into plane be parallel to each other, and because the plane is horizontal plane, the influence of structure wind-engaging power effect can be reduced.It is simultaneously described First reinforced tube 25, adjacent two second reinforced pipes are set between the second reinforced pipe 24 and its principal post 1 closest to side Second reinforced tube 26 is set between 24, is all respectively arranged on second reinforced pipe 24 and principal post 1 and the first reinforced tube 25 First stiffening plate 27 of connection, the second stiffening plate for being connected with the second reinforced tube 26 is also set up on second reinforced pipe 24 28, first stiffening plate 27 with the second stiffening plate 28 is in the same plane be connected to improve when structure stability.Institute It is identical to state material all with the first reinforced pipe 21 of the second reinforced pipe 24, the first reinforced tube 25 and the second reinforced tube 26, structure, but Length dimension is different, and all carries out bolt connection by U-board 29 and other plate bodys.Pass through the second reinforced pipe 24, first The setting of the reinforced tube 26 of reinforced tube 25 and second, connection between connection member 2 is set to possess higher intensity, it is whole so as to improve The strength and stability of individual segmented shaft tower unit.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, some improvements and modifications can also be made, these improvements and modifications Also it should be regarded as protection scope of the present invention.

Claims (10)

1. a kind of high-strength combination formula shaft tower, including at least two segmented shaft tower unit, it is characterised in that:Described point Segmentation shaft tower unit includes four and is used for assembled principal post(1), adjacent two principal posts(1)Between connection member is set(2), it is described Connection member(2)Including at least more than two the first reinforced pipes for being used to reinforce connection(21), for fixing the first reinforced pipe (21)Telophragma(22)And for carrying telophragma(22)Support tube(23), positioned at telophragma(22)The first of the same side Reinforced pipe(21), its one end all with telophragma(22)Connection, the other end respectively with principal post(1)Two ends connection.
A kind of 2. high-strength combination formula shaft tower according to claim 1, it is characterised in that:The support tube(23)Both ends It is connected to two adjacent principal posts(1)On, the support tube(23)Including long tube(231), it is arranged at long tube(231)End Ring flange(232), pass through ring flange(232)With long tube(231)The short tube of connection(233).
A kind of 3. high-strength combination formula shaft tower according to claim 2, it is characterised in that:The long tube(231)Stretch out in Telophragma(22)Pass through ring flange again outside(232)With short tube(233)Connection.
A kind of 4. high-strength combination formula shaft tower according to claim 1, it is characterised in that:Adjacent connection member(2)It Between the second reinforced pipe is set(24), by multiple second reinforced pipes(24)Between the plane that surrounds with by multiple support tubes(23)Between The plane surrounded is parallel to each other.
A kind of 5. high-strength combination formula shaft tower according to claim 4, it is characterised in that:Second reinforced pipe(24)With Its principal post closest to side(1)Between the first reinforced tube is set(25);Adjacent two second reinforced pipes(24)Between set Two reinforced tubes(26).
A kind of 6. high-strength combination formula shaft tower according to claim 5, it is characterised in that:Second reinforced pipe(24)With Principal post(1)On be all respectively arranged to and the first reinforced tube(25)First stiffening plate of connection(27), second reinforced pipe (24)On also set up for and the second reinforced tube(26)Second stiffening plate of connection(28), first stiffening plate(27)With second Stiffening plate(28)It is in the same plane.
A kind of 7. high-strength combination formula shaft tower according to claim 2, it is characterised in that:The telophragma(22)Including weldering It is connected to long tube(231)On supporting plate(221), the supporting plate(221)Towards the second reinforced pipe(24)One side on set use In with the second reinforced pipe(24)The fixed plate of connection(222), opposite side is set and support tube(23)The limited block of connection(223).
A kind of 8. high-strength combination formula shaft tower according to claim 7, it is characterised in that:The limited block(223)By ten Word X-shape two boards combine.
A kind of 9. high-strength combination formula shaft tower according to claim 1, it is characterised in that:First reinforced pipe(21) Both ends open up bayonet socket(211), the bayonet socket(211)Interior welding U-board(29), the principal post(1)On for U-board(29)Connection Position set reinforcing plate(11), the reinforcing plate(11)Place plane and supporting plate(221)Place plane is parallel.
A kind of 10. high-strength combination formula shaft tower according to claim 9, it is characterised in that:The bayonet socket(211)It is arranged at First reinforced pipe(21)The centre position of two ends, its depth are less than U-board(29)Length.
CN201720257390.XU 2017-03-16 2017-03-16 A kind of high-strength combination formula shaft tower Expired - Fee Related CN206903334U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720257390.XU CN206903334U (en) 2017-03-16 2017-03-16 A kind of high-strength combination formula shaft tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720257390.XU CN206903334U (en) 2017-03-16 2017-03-16 A kind of high-strength combination formula shaft tower

Publications (1)

Publication Number Publication Date
CN206903334U true CN206903334U (en) 2018-01-19

Family

ID=61294806

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720257390.XU Expired - Fee Related CN206903334U (en) 2017-03-16 2017-03-16 A kind of high-strength combination formula shaft tower

Country Status (1)

Country Link
CN (1) CN206903334U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106801533A (en) * 2017-03-16 2017-06-06 湖州飞剑杆塔制造有限公司 A kind of high-strength combination formula shaft tower

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106801533A (en) * 2017-03-16 2017-06-06 湖州飞剑杆塔制造有限公司 A kind of high-strength combination formula shaft tower

Similar Documents

Publication Publication Date Title
WO2022213492A1 (en) Frp steel concrete column and steel beam combined joint, and installation method therefor
KR101440434B1 (en) Construction Method for Composite Type Rahmen Bridge
CN206903334U (en) A kind of high-strength combination formula shaft tower
AU2004203023A1 (en) Mine roof-support truss
WO2017118362A1 (en) Telecommunication tower
CN109695473A (en) A kind of railway tunnel built-in groove channel fixing device and fixing means
CN106049719B (en) A kind of self-balancing monoblock type template assembly structure of reinforced concrete shear wall
CN106801533A (en) A kind of high-strength combination formula shaft tower
KR101632911B1 (en) Bridge using end prestressed beam and the construction method therewith
KR20140076005A (en) segment type steel composite girder and its construction methods with intermediate anchorage device
US6627832B2 (en) Modular steel concrete reinforcement system
KR101660888B1 (en) Girder with pressing embed ahchorage apparatus and the girder construction method therewith
CN102011432B (en) Novel polygonal combined steel pipe
KR20230025521A (en) construction method and structure for TG beam form
KR20160068107A (en) Steel beam and prestressed composite girder using the same thing and construction method there of
CN108755960A (en) A kind of high intensity square tube beam-to-column joint structure and its installation method
US9714520B1 (en) Direct anchorage termination for pole reinforcement
KR102465099B1 (en) construction method and structure for TG beam form
KR101646866B1 (en) Tendon fixing system of long span fire resistance deck strained at deck end and construction method of the same
KR101874755B1 (en) Prestressed Steel-Concrete Composite Girder and Method for Fabricating thereof
CN209368701U (en) Girder steel and beams of concrete floorings rigid splicing binding structure
JP2004116124A (en) Foundation structure of steel tower
CN219450400U (en) Butterfly-shaped suspension bridge
CN213980795U (en) Integrated pavement board support can be dismantled in tunnel
EP1777355A2 (en) Beam or truss consisting of two or more reinforced concrete half-members with a new jointing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180119