CN206903223U - A kind of building construction formwork Multifunctional pull rod device - Google Patents

A kind of building construction formwork Multifunctional pull rod device Download PDF

Info

Publication number
CN206903223U
CN206903223U CN201720826364.4U CN201720826364U CN206903223U CN 206903223 U CN206903223 U CN 206903223U CN 201720826364 U CN201720826364 U CN 201720826364U CN 206903223 U CN206903223 U CN 206903223U
Authority
CN
China
Prior art keywords
master module
pull bar
termination
center
support column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720826364.4U
Other languages
Chinese (zh)
Inventor
牟雪锋
张霞
李倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Hengshengyuan Group Construction Co Ltd
Original Assignee
Qingdao Hengshengyuan Group Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Hengshengyuan Group Construction Co Ltd filed Critical Qingdao Hengshengyuan Group Construction Co Ltd
Priority to CN201720826364.4U priority Critical patent/CN206903223U/en
Application granted granted Critical
Publication of CN206903223U publication Critical patent/CN206903223U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a kind of building construction formwork Multifunctional pull rod device, including pull bar, fixing bolt, support column and plectane;The pull bar is that the center of two parallel steel pole compositions and two steel poles is connected by connecting rod;The termination that two steel poles of master module and pull bar homonymy are each provided with the pull bar or so termination passes perpendicularly through the side center of master module;Connecting plate is connected between the homonymy termination of two steel poles of the pull bar and connecting plate is parallel to master module.The stability when pull bar of two steel poles composition of the present utility model is easy to increase fixed;The master module of the left and right sides is moulding for clamping cement concrete progress;The threaded rod of both sides is rotated to the center of pull bar, so as to promote the master module of both sides master module to be held out against, to middle slip so as to clamp the cement concrete wall stone of moulding fixation;The turning handle person of being easily installed rotates threaded rod;Rubber sleeve is used for the frictional force for increasing turning handle side wall, is easy to user to firmly grasp.

Description

A kind of building construction formwork Multifunctional pull rod device
Technical field
Building relevant device is the utility model is related to, specially a kind of building construction formwork Multifunctional pull rod device.
Background technology
The Screw arbor with nut at both-ends of fixing concrete wall or thin-wall construction template is presently used for, generally homemade smooth bar Screw rod or thin steel strip tie rod, in order to can Reusability, a plastic tube or concrete prefabricated pipe are often covered on round steel screw rod, After to be removed, Screw arbor with nut at both-ends is extracted out, in practice it has proved that, during concreting, sleeve pipe is due to by coagulation on screw rod The repeated impact of soil and cause the different degrees of deformation of sleeve pipe, cause the size between template to change and single drawing The stability of bar is not strong, position skew easily occurs, and general template is easily sticked to coagulation when being dismantled after fixing to clamp On soil, the damage of concrete is easily caused after prying open, influences surface quality.
Utility model content,
The purpose of this utility model is to provide a kind of building construction formwork Multifunctional pull rod device, to solve above-mentioned background The problem of being proposed in technology.
To achieve the above object, the utility model provides following technical scheme:A kind of building construction formwork Multifunctional pull rod Device, including pull bar, fixing bolt, support column and plectane;The pull bar is two parallel steel pole compositions and two steel poles Center is connected by connecting rod;The end of two steel poles of master module and pull bar homonymy is each provided with the pull bar or so termination Head passes perpendicularly through the side center of master module;Be connected between the homonymy termination of two steel poles of the pull bar connecting plate and Connecting plate is parallel to master module;Threaded rod is provided with two pieces of master modules and threaded rod passes perpendicularly through connecting plate, passes through spiral shell Line is connected to connecting plate;The end of the threaded rod being on the outside of two pieces of connecting plate enclosed spaces is connected with turning handle;It is described Master module both ends are to being connected to secondary template;The end of the master module and secondary template is provided with bolt hole;The fixing bolt is same When through the bolt hole at the master module and secondary form stop of docking;The lower wall center of steel pole is affixed on the downside of the pull bar Have the first thread barrel and the first thread barrel perpendicular to pull bar steel pole;One end of the support column is provided with the first threaded connector And first threaded connector and the first thread barrel cooperate and connect;Another termination of the support column is connected with the second thread barrel And second thread barrel and the first threaded connector it is in mating connection;The plectane is horizontally set on the downside of support column;The circle Plate upper surface center is connected with the second threaded connector vertically and the second threaded connector is threadedly coupled header structure with first It is identical.
Preferably, rubber sleeve is covered on the turning handle.
Preferably, the termination of the master module and secondary template is the smooth termination to cooperate and two terminations of secondary template Center Central Symmetry on secondary template.
Preferably, the upper and lower ends of the opposite end face of two pieces of master modules are connected with draw ring.
Preferably, plastic foil is posted on the clamping face of the master module and secondary template.
Compared with prior art, the beneficial effects of the utility model are:The pull bar of two steel pole compositions is easy to increase to fix When stability;The master module of the left and right sides is moulding for clamping cement concrete progress;By the threaded rod of both sides to pull bar Center rotates, so as to promote the master module of both sides master module to be held out against, to middle slip so as to clamp the cement of moulding fixation Concrete wall stone;The turning handle person of being easily installed rotates threaded rod;Rubber sleeve is used for the frictional force for increasing turning handle side wall, is easy to make User firmly grasps;The length of the extended length master module of the wall for the cement concrete that secondary template fixes to clamp as needed;It is fixed Bolt causes master module and secondary template to be fixedly connected;The termination of master module and secondary template for cooperate smooth termination and Center Central Symmetry of two terminations of secondary template on secondary template, keeps when being easy to master module and secondary template to be attached Planarization, it is convenient to clamp;When two steel poles of pull bar are in upper-lower position so that master module is fixed in vertical position When, support column is connected in the first thread barrel by the first threaded connector, support on the ground, strengthens pull bar fixed form When steadiness;According to the height on tie bar space ground, pass through the second thread barrel and the first threaded connector in mating connection Adjunction support column;Plectane is easy to the firm support of support column;Second threaded connector and the second thread barrel are connected, so that Plectane is affixed on the support columns;Draw ring is easy to worker to pull open master module to both sides, is dismantled;The folder of master module and secondary template Plastic foil is posted on tight face, plastic foil is used to prevent from clamping moulding concrete bonding in the end face of master module.
Brief description of the drawings
Fig. 1 is the structural representation of building construction formwork Multifunctional pull rod device of the present utility model;
Fig. 2 is the structural representation of the master module of the building construction formwork Multifunctional pull rod device shown in Fig. 1;
Fig. 3 is the structural representation of the plectane of the building construction formwork Multifunctional pull rod device shown in Fig. 1;
In figure:1- pull bars;2- draw rings;3- connecting plates;4- threaded rods;5- turning handles;6- rubber sleeves;7- master modules;8- pair moulds Plate;9- plectanes;The threaded connectors of 10- second;The thread barrels of 11- second;12- support columns;The threaded connectors of 13- first;14- first Thread barrel;15- fixing bolts;16- bolts hole.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Refer to Fig. 1-3, a kind of embodiment provided by the utility model:A kind of building construction formwork Multifunctional pull rod dress Put, including pull bar 1, fixing bolt 15, support column 12 and plectane 9;Pull bar 1 is two parallel steel pole compositions and two steel poles Center is connected by connecting rod, the stability when pull bar 1 of two steel pole compositions is easy to increase fixed;Pull bar 1 or so is held The termination that master module 7 and two steel poles of homonymy of pull bar 1 are each provided with head passes perpendicularly through the side center of master module 7, left The master module 7 of right both sides is moulding for clamping cement concrete progress;It is connected between the homonymy termination of two steel poles of pull bar 1 Connecting plate 3 and connecting plate 3 is parallel to master module 7;Threaded rod 4 is provided with two pieces of master modules 7 and threaded rod 4 passes perpendicularly through connection Plate 3, connecting plate 3 is connected through a screw thread, the threaded rod 4 of both sides is rotated to the center of pull bar 1, so as to promote both sides Master module 7 holds out against master module 7, so as to clamp the cement concrete wall stone of moulding fixation to middle slip;In two pieces of companies The end of threaded rod 4 on the outside of the enclosed space of fishplate bar 3 is connected with turning handle 5, and the person of being easily installed of turning handle 5 rotates threaded rod 4;Turning handle Rubber sleeve 6 is covered on 5, rubber sleeve 6 is used for the frictional force for increasing the side wall of turning handle 5, is easy to user to firmly grasp;The both ends pair of master module 7 It is connected to secondary template 8, the length of the extended length master module 7 of the wall for the cement concrete that secondary template 8 fixes to clamp as needed; The end of master module 7 and secondary template 8 is provided with bolt hole 16;Master module 7 He of the fixing bolt 15 also cross docking The bolt hole 16 of the secondary end of template 8, fixing bolt 7 cause master module 7 and secondary template 8 to be fixedly connected;Master module 7 and pair The termination of template 8 is the center center pair of the smooth termination to cooperate and two terminations of secondary template 8 on secondary template 8 Claim, planarization is kept when being easy to master module 7 and secondary template 8 to be attached, it is convenient to clamp;In the lower wall of the downside steel pole of pull bar 1 Heart position be connected with the first thread barrel 14 and the first thread barrel 14 perpendicular to pull bar 1 steel pole;One end of support column 12 is provided with First threaded connector 13 and the first threaded connector 13 and the first thread barrel 14, which cooperate, to be connected, when two steel of pull bar 1 Bar is in upper-lower position so that master module 7 in vertical position be fixed when, support column 12 is passed through into the first threaded connector 13 are connected in the first thread barrel 14, and support on the ground, strengthens steadiness during 1 fixed form of pull bar;Support column 12 it is another One termination is connected with the second thread barrel 11 and the second thread barrel 11 and the first threaded connector 13 are in mating connection, according to pull bar 1 Height apart from ground, pass through the second thread barrel 11 in mating connection and the adjunction support column 12 of the first threaded connector 13;Circle Plate 9 is horizontally set on the downside of support column 12, and plectane 9 is easy to the firm support of support column 12;The upper surface center of plectane 9 is vertical It is connected with the second threaded connector 10 and the second threaded connector 10 is identical with the structure of the first threaded connector 13, the second screw thread connects Joint 10 is connected with the second thread barrel 11, so that plectane 9 is fixed on support column 12;Two pieces of phase backsides of master module 7 The upper and lower ends in face are connected with draw ring 2, and draw ring 2 is easy to worker to pull open master module 7 to both sides, dismantled;Master module 7 and pair Plastic foil is posted on the clamping face of template 8, plastic foil is used to prevent from clamping moulding concrete bonding in the end face of master module 7 On.
Specifically used mode:In use, first then pull bar 1 will across on moulding concrete is needed during use The double steel poles of master module 7 on pull bar 1 along pull bar 1, which slide, clamps concrete, then by turning handle 5 by the threaded rod 4 of both sides Rotated to the center of pull bar 1, so as to hold out against master module 7, clamp the cement concrete wall stone of moulding fixation, Ran Hougen According to the length of the extended length master module 7 of the wall for the cement concrete for needing to fix to clamp, pass through the connect band of fixing bolt 15 There are the master module 7 of the docking of bolt hole 16 and the termination of secondary template 8, when two steel poles of pull bar 1 are in upper-lower position so that main Template 7 in vertical position be fixed when, support column 12 is connected to the first thread barrel 14 by the first threaded connector 13 Interior, support on the ground, strengthens steadiness during 1 fixed form of pull bar, and support column 12 is provided at both ends with mutual cooperation Second thread barrel 11 and the first threaded connector 13, it is easy to support column 12 to carry out adjunction according to height of the pull bar 1 apart from ground, and And the lower end of the support column 12 of lower side is connected to justify by the second thread barrel 11 and the second threaded connector 10 of mating connection Plate 9, strengthen the stability of support, when needing to pull down master module 7, threaded rod 4 is turned on to both sides, then will be drawn by draw ring 2 Open master module 7.
It is obvious to a person skilled in the art that the utility model is not limited to the details of above-mentioned one exemplary embodiment, and And in the case of without departing substantially from spirit or essential attributes of the present utility model, it can realize that this practicality is new in other specific forms Type.Therefore, no matter from the point of view of which point, embodiment all should be regarded as exemplary, and is nonrestrictive, this practicality is new The scope of type limits by appended claims rather than described above, it is intended that the equivalency fallen in claim is contained All changes in justice and scope are included in the utility model.Any reference in claim should not be considered as limitation Involved claim.

Claims (4)

1. a kind of building construction formwork Multifunctional pull rod device, including pull bar(1), fixing bolt(15), support column(12)And circle Plate(9), it is characterised in that:The pull bar(1)Center for two parallel steel pole compositions and two steel poles passes through connection Bar connects;The pull bar(1)Left and right is each provided with master module on termination(7)And pull bar(1)The termination of two steel poles of homonymy is vertical Through master module(7)Side center;The pull bar(1)Two steel poles homonymy termination between be connected with connecting plate (3)And connecting plate(3)Parallel to master module(7);Two pieces of master modules(7)On be provided with threaded rod(4)And threaded rod(4)Hang down Direct puncture crosses connecting plate(3), it is connected through a screw thread connecting plate(3);It is described to be in two pieces of connecting plates(3)Spiral shell on the outside of enclosed space Rasp bar(4)End be connected with turning handle(5);The master module(7)Both ends are to being connected to secondary template(8);The master module(7)With Secondary template(8)End be provided with bolt hole(16);The fixing bolt(15)Also cross the master module of docking(7)And pair Template(8)The bolt hole of end(16);The pull bar(1)The lower wall center of downside steel pole is connected with the first thread barrel (14)And first thread barrel(14)Perpendicular to pull bar(1)Steel pole;The support column(12)One end be provided with the first screw thread company Joint(13)And first threaded connector(13)With the first thread barrel(14)Cooperate connection;The support column(12)It is another Termination is connected with the second thread barrel(11)And second thread barrel(11)With the first threaded connector(13)It is in mating connection;The circle Plate(9)It is horizontally set on support column(12)Downside;The plectane(9)Upper surface center is connected with the second screw thread company vertically Joint(10)And second threaded connector(10)With the first threaded connector(13)Structure is identical.
2. building construction formwork Multifunctional pull rod device according to claim 1, it is characterised in that:The turning handle(5)On Cover rubber sleeve(6).
3. building construction formwork Multifunctional pull rod device according to claim 1, it is characterised in that:The master module(7) With secondary template(8)Termination for cooperate smooth termination and secondary template(8)Two terminations on secondary template(8)Center Place-centric is symmetrical.
4. building construction formwork Multifunctional pull rod device according to claim 1, it is characterised in that:Two pieces of master modules (7)The upper and lower ends of opposite end face are connected with draw ring(2).
CN201720826364.4U 2017-07-10 2017-07-10 A kind of building construction formwork Multifunctional pull rod device Expired - Fee Related CN206903223U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720826364.4U CN206903223U (en) 2017-07-10 2017-07-10 A kind of building construction formwork Multifunctional pull rod device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720826364.4U CN206903223U (en) 2017-07-10 2017-07-10 A kind of building construction formwork Multifunctional pull rod device

Publications (1)

Publication Number Publication Date
CN206903223U true CN206903223U (en) 2018-01-19

Family

ID=61293472

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720826364.4U Expired - Fee Related CN206903223U (en) 2017-07-10 2017-07-10 A kind of building construction formwork Multifunctional pull rod device

Country Status (1)

Country Link
CN (1) CN206903223U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108487631A (en) * 2018-04-04 2018-09-04 陈荣楚 A kind of building construction formwork Multifunctional pull rod device
CN111305563A (en) * 2020-04-07 2020-06-19 天庭无人建造(广东)科技有限公司 End piston robot

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108487631A (en) * 2018-04-04 2018-09-04 陈荣楚 A kind of building construction formwork Multifunctional pull rod device
CN111305563A (en) * 2020-04-07 2020-06-19 天庭无人建造(广东)科技有限公司 End piston robot

Similar Documents

Publication Publication Date Title
CN206903223U (en) A kind of building construction formwork Multifunctional pull rod device
CN211114845U (en) Steel structure support frame for building engineering
CN206053324U (en) A kind of curved adjustable securing member of building template list
CN204152202U (en) Column template clamp frame
CN204402030U (en) A kind of oval door opening concrete wall template
CN203420473U (en) Fast-clamping concrete pouring device
CN213174693U (en) Connect stable concatenation formula scaffold frame
CN203230178U (en) Column formwork and column hoop
CN209780238U (en) Structure for fixing templates on two sides of expansion joint
CN204662974U (en) Integrated template taper lock
CN207582935U (en) A kind of civil construction tool-type scaffold wall connecting piece
CN213927498U (en) I-steel wall-through isolation sleeve box
CN212176561U (en) Corner column outer mold connecting tool
CN104863359A (en) Template reinforcement device of reinforced concrete wall pillar part and usage method of same
CN209261222U (en) It is a kind of to splice the building template for securely and being easy to unbutton
CN203514841U (en) Engineering folding bridge ladder
CN207120988U (en) A kind of easily smooth pallet of granule bio-pharmaceuticals
CN206859682U (en) A kind of building template quick-gripping device
CN206722383U (en) Field of civil engineering gang form
CN215760494U (en) Civil engineering construction template reinforcing apparatus
CN206233571U (en) Beam formwork for building bracing means
CN217256244U (en) Municipal administration construction reinforcing bar piling bin
CN204238548U (en) A kind of concrete blinding clamp frame connector and column template clamp frame
CN211334278U (en) Building external wall template for heat preservation convenient to form removal
CN201747044U (en) Drawknot frame structure of scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180119

Termination date: 20180710

CF01 Termination of patent right due to non-payment of annual fee