CN206902911U - A kind of precast concrete with communication power cable - Google Patents

A kind of precast concrete with communication power cable Download PDF

Info

Publication number
CN206902911U
CN206902911U CN201720087490.2U CN201720087490U CN206902911U CN 206902911 U CN206902911 U CN 206902911U CN 201720087490 U CN201720087490 U CN 201720087490U CN 206902911 U CN206902911 U CN 206902911U
Authority
CN
China
Prior art keywords
cable
precast concrete
bus duct
wire casing
branch wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720087490.2U
Other languages
Chinese (zh)
Inventor
段创峰
戴子枢
顾沉颖
何晓
巴雅吉呼
林俊
田江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI UNDERGROUND SPACE ARCHITECTURAL DESIGN & RESEARCH INSTITUTE
Shanghai Urban Construction Information Technology Co., Ltd.
Original Assignee
Shanghai Underground Space Architectural Design & Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Underground Space Architectural Design & Research Institute filed Critical Shanghai Underground Space Architectural Design & Research Institute
Priority to CN201720087490.2U priority Critical patent/CN206902911U/en
Application granted granted Critical
Publication of CN206902911U publication Critical patent/CN206902911U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a kind of precast concrete with communication power cable, including one or more precast concretes, cable concentrator and cable trough are provided with wherein at least one precast concrete, cable concentrator includes shell and hub module, shell is embedded in the surface of precast concrete by pre-buried mode, hub module is set inside the housing, hub module includes multiple power supply interfaces and multiple data communication interfaces, each can be conductive between power supply interface and any other power supply interfaces, each data communication can be realized between data communication interface and any other data communication interfaces;Shell is connected with cable trough inside, and cable trough laid inside has cable, and cable is connected with power supply interface and/or data communication interface.Cable is embedded on prefabricated precast concrete by undamaged mode, is avoided implementing destructive fixation to precast concrete after construction stage or construction, is effectively protected concrete members protective layer.

Description

A kind of precast concrete with communication power cable
Technical field
A kind of precast concrete is the utility model is related to, more specifically to one kind with communication power cable Precast concrete.
Background technology
Precast concrete have good quality, section material saving of labor, reduce situ wet operation, reduce energy consumption, construction is quick, changes The advantages of kind built environment.In civilian infrastructure field, bridge, tunnel, box culvert etc. are original to precast concrete Just there are many ripe application schemes, and under the overall background that assembled architecture is widelyd popularize, precast concrete is even more To being widely applied.Its recoverable amount is constantly increased sharply, and the thing followed is the O&M maintenance work of magnanimity.In order to realize to prefabricated The high maintenance maintenance of concrete component forms a set of structural healthy monitoring system, to structure, it is necessary to set sensor on component Operating environment, external loads, the factor such as mechanical state carry out monitoring in all directions, so as to the performance to precast concrete Assessed.
The sensor and its data telecommunication line cable of existing structural healthy monitoring system are typically to have been constructed in structural elements Cheng Hou, then body structure surface is fixed to by modes such as expansion bolt, hook, wall nails, this mounting means destroys structure appearance The integrality in face, have influence on the life cycle management performance of structure;The attractive in appearance of structure alien invasion is hindered in the laying of a plurality of line;It is in disorder Data communication line lay mode and will also influence the data transmission stability of structural healthy monitoring system itself;Structure is improved to be good for The health monitoring system O&M of itself is with repairing difficulty;The installation steps such as punching, wiring add the workload of system construction.
Utility model content
In view of the above-mentioned problems, with reference to precast concrete manufacture characteristic, the utility model proposes one kind with communication The precast concrete of power cable.The component is by the data communication cable of structural healthy monitoring system and precast concrete structure Part integrates, and just solves the problem of later stage cable laying in the construction phase of precast concrete.
The utility model provides a kind of precast concrete with communication power cable, including one or more pre- Concrete component processed, cable concentrator and cable trough, the cable concentrator are provided with described in wherein at least one on precast concrete Including shell and hub module, the shell is embedded in the surface of the precast concrete by pre-buried mode, described Hub module is arranged on the enclosure, and the hub module includes multiple power supply interfaces and multiple data communication interfaces, its In it is each can be conductive between the power supply interface and any other power supply interfaces, each data communication interface is with appointing Data communication can be realized between one other data communication interfaces;
The shell connects with cable trough inside, and the cable trough laid inside has cable, the cable and institute State power supply interface and/or data communication interface connection.
Further, the cross section of the cable trough is U-shaped, and the cable trough is embedded in the precast concrete Surface, or the cable trough is in a tubular form, and the cable trough is embedded in the inside of the precast concrete.
Further, the cable trough includes a bus duct and multiple wire casings, and the bus duct is in yi word pattern, and longitudinal direction Through the surface of the precast concrete, wherein multiple branch wire casings are connected on the bus duct, and it is described Internal between bus duct and the branch wire casing to connect, described bus slot at least one end is connected with a cable concentrator, and institute State bus duct and connected inside the cable concentrator.
Further, the branch wire casing connects the bus slot opposite end and is connected with a cable concentrator, and the branch Wire casing connects with cable concentrator inside.
Further, face of the branch wire casing from the bus duct on the precast concrete, extend to described total Side where wire casing;
The quantity of the branch wire casing is six, wherein three branch wire casings are arranged on bus slot first side, separately Outer three branch wire casings are arranged on bus slot second side, positioned at bus slot first side the branch wire casing and The branch wire casing positioned at bus slot second side is symmetrically set.
Further, the cable includes bus cable and branch line cable, at least one end and the collection of the bus cable The power supply interface and/or data communication interface connection in line box;
The bus cable is laid in the bus duct, and the branch line cable laying is and described in the branch wire casing The intersection of bus duct and the branch wire casing is provided with a multiple-pass joint, and the multiple-pass joint is used to connect the bus cable With the branch line cable.
Further, the surface of the precast concrete is additionally provided with sensor, and the sensor is located at the branch line Groove connects the bus slot opposite end, the branch line cable that the sensor connection is drawn from the branch wire casing.
Further, the cable can be fixed in the cable trough with flexible material or metal button member.
Further, the quantity of the precast concrete is two, this two T-shaped rows of precast concrete Row, and it is respectively arranged with the cable, the cable concentrator and the cable trough on two precast concretes;
Connected between the hub module on two precast concretes by the cable.
Further, the quantity of the precast concrete is three, this three T-shaped rows of precast concrete Row, precast concrete described in two of which is located along the same line, and be located along the same line two are described prefabricated mixed Native component is coagulated to be arranged in a mutually vertical manner with another precast concrete, and on three precast concretes respectively It is provided with the cable, the cable concentrator and the cable trough;
Connected between the hub module on three precast concretes by the cable.
According to preferred embodiment, the utility model offers the advantage that:
(1) cable of the utility model connection power supply interface and data communication interface can be by structural elements not damaged Mode be embedded on prefabricated precast concrete, avoid implementing precast concrete after construction stage or construction broken Bad property fixation, effectively protects concrete members protective layer, extends the life-span of precast concrete.
(2) the utility model applies the wire casing laying mode of bus duct and branch wire casing, simplifies the laying mode of cable, The stability of cable is improved, and has beautified laying structure.
(3) the utility model multiple can will carry the prefabricated of data communication cable by the connection between hub module Concrete component is combined, so as to realize by single power supply and data-interface the equipment of multiple structural elements is powered with Data communicate, and application mode is very flexible.
The utility model is further illustrated below in conjunction with drawings and Examples.
Brief description of the drawings
Fig. 1 is that the structure of the precast concrete first embodiment described in the utility model with communication power cable is shown It is intended to;
Fig. 2 is that the structure of the precast concrete second embodiment described in the utility model with communication power cable is shown It is intended to;
Fig. 3 is that the structure of the precast concrete 3rd embodiment described in the utility model with communication power cable is shown It is intended to;
Fig. 4 is that the structure of the precast concrete fourth embodiment described in the utility model with communication power cable is shown It is intended to;
Fig. 5 is that the structure of precast concrete the 5th embodiment described in the utility model with communication power cable is shown It is intended to.
Embodiment
Describe to be used to disclose the utility model so that those skilled in the art can realize the utility model below.Retouch below Preferred embodiment in stating is only used as illustrating, it may occur to persons skilled in the art that other obvious modifications.Retouched following The general principle of the present utility model defined in stating can apply to other embodiments, deformation program, improvement project, etc. Tongfang Case and the other technologies scheme without departing from spirit and scope of the present utility model.
First embodiment
As shown in figure 1, a kind of precast concrete with communication power cable, including a precast concrete 1, cable concentrator 3 and cable trough 2 are provided with the precast concrete 1, and cable concentrator 3 includes shell and hub module, and shell leads to The surface that pre-buried mode is embedded in precast concrete 1 is crossed, hub module is set inside the housing, and hub module includes more Individual power supply interface and multiple data communication interfaces, wherein can be conductive between each power supply interface and any other power supply interfaces, It is each to realize data communication between data communication interface and any other data communication interfaces, inside shell and cable trough 2 Connection, and the laid inside of cable trough 2 has cable, cable can be connected with power supply interface and/or data communication interface, pass through cable trough 2 laying, cable can be led to each position of precast concrete 1, be powered for relevant device and communicated with data.
In the present embodiment, the cross section of cable trough 2 is U-shaped, and the cable trough 2 can be embedded in precast concrete 1 Surface, also in the surface casting concrete of cable trough 2 cable trough 2 can be made to be located at the inside of precast concrete 1 afterwards.
In other embodiments, in a tubular form, the cable trough 2 is embedded in the inside of precast concrete 1 to cable trough 2.
In the present embodiment, cable trough 2 includes a bus duct 21 and multiple wire casings 22, and bus duct 21 is in yi word pattern, And longitudinally through the surface of precast concrete 1, multiple wire casings 22, and bus duct are wherein connected on bus duct 21 Internal between 21 and branch wire casing 22 to connect, one end of bus duct 21 is connected with a cable concentrator 3, and bus duct 21 and cable concentrator 3 Inside connection, by using the laying mode of bus duct 21 and branch wire casing 22, simplifies the laying mode of cable, improves cable Stability, and beautified laying structure.
In other embodiments, the both ends of bus duct 21 are connected to a cable concentrator 3, and bus duct 21 and cable concentrator 3 inside connect.
In other embodiments, the opposite end of the connection of branch wire casing 22 bus duct 21 is connected with a cable concentrator 3, and branch wire casing 22 connect with the inside of cable concentrator 3.
In the present embodiment, branch wire casing 22 can extend to bus from the face on the place precast concrete 1 of bus duct 21 Side where groove 21.The quantity of branch wire casing 22 is six, wherein three branch wire casings 22 are arranged on the first side of bus duct 21, separately Outer three branch wire casings 22 are arranged on the second side of bus duct 21, positioned at the branch wire casing 22 of the first side of bus duct 21 and positioned at bus The branch wire casing 22 of second side of groove 21 is symmetrically set.
In other embodiments, the branch wire casing 22 positioned at the first side of bus duct 21 and the second side positioned at bus duct 21 Branch wire casing 22 asymmetric can be set.
In other embodiments, the quantity of branch wire casing 22 can be other numbers.
In the present embodiment, cable can be fixed in cable trough 2 with flexible material, and wherein flexible material can be plastic cement or silicon Glue etc..
In other embodiments, cable can be fixed in cable trough 2 with metal button member.
In the present embodiment, cable can be single core cable, only connect power supply interface or data communication interface, i.e., only undertake confession Electricity or communication function.
In other embodiments, cable can also be multi-core cable, can undertake power supply and communication function simultaneously.
In the present embodiment, cable includes bus cable and branch line cable, at least one end of bus cable with cable concentrator 3 Power supply interface and/or data communication interface connection, bus cable is laid in bus duct 21, and branch line cable laying is in branch wire casing In 22, and the intersection of bus duct 21 and branch wire casing 22 is provided with a multiple-pass joint, and the multiple-pass joint is used to connect Bus Wire Cable and branch line cable.
The equipment for being arranged on the surface of precast concrete 1 can be sensor, and the sensor is located at branch wire casing 22 and connected The opposite end of bus duct 21, and sensor can connect the branch line cable drawn from branch wire casing 22, above-mentioned sensor can be structure Sensor, temperature sensor or humidity sensor etc..
Second embodiment
As shown in Fig. 2 the difference of second embodiment and first embodiment is, the quantity of precast concrete 1 is two It is individual, two precast concretes, the 1 T-shaped arrangement, wherein only underlying precast concrete 1 can be set it is wired Cable, cable concentrator 3 and cable trough 2 etc..
3rd embodiment
As shown in figure 3, the difference of 3rd embodiment and first embodiment is, the quantity of precast concrete 1 is two It is individual, two precast concretes, the 1 T-shaped arrangement, be wherein respectively arranged with two precast concretes 1 cable, Cable concentrator 3 and cable trough 2 etc..
In the present embodiment, the length of two precast concretes 1 can be unequal, wherein concrete above The length of native component 1 is longer than the length of underlying precast concrete 1, therefore precast concrete above The length of 1 bus duct 21 is longer, can now increase the quantity of branch wire casing 22 and cable concentrator 3, and with reference to figure 3, above is pre- The quantity of branch wire casing 22 on concrete component 1 processed is 13, and the quantity of cable concentrator 3 is three, specifically, two cable concentrators 3 are located at the both ends of the bus duct 21, and another cable concentrator 3 is located among precast concrete 1.
In other embodiments, the equal length of two precast concretes 1.
Fourth embodiment
As shown in figure 4, the difference of fourth embodiment and first embodiment is, the quantity of precast concrete 1 is three Individual, three precast concretes, the 1 T-shaped arrangement, two of which precast concrete 1 is located along the same line, the position It is arranged in a mutually vertical manner in two precast concretes 1 on same straight line with another precast concrete 1, and this three Cable, cable concentrator 3 and cable trough 2 etc. are respectively arranged with precast concrete 1.
5th embodiment
As shown in figure 5, the difference of the 5th embodiment and first embodiment is, the quantity of precast concrete 1 is two Individual, two precast concretes 1 are located along the same line, and are respectively arranged with two precast concretes 1 Cable, cable concentrator 3 and cable trough 2 etc..
In summary, precast concrete can use separately as the primary structure member of works, can will be more therefore Individual precast concrete is applied in combination, for example, second, third, the 4th and the 5th shown in embodiment, but not limited to this can also lead to Cross the hub module that cable connects each precast concrete so that the cable included in precast concrete forms series connection Or parallel relationship.
Embodiment described above is merely to illustrate technological thought of the present utility model and feature, and its object is to make ability Technical staff in domain can understand content of the present utility model and implement according to this, it is impossible to only limit this practicality with the present embodiment New the scope of the claims uses, i.e., the equal change or modification that all spirit according to disclosed in the utility model is made, still falls at this In the scope of the claims of utility model.

Claims (10)

1. a kind of precast concrete with communication power cable, it is characterised in that including one or more concretes Native component (1), cable concentrator (3) and cable trough (2) are provided with described in wherein at least one on precast concrete (1), it is described Cable concentrator (3) includes shell and hub module, and the shell is embedded in the precast concrete (1) by pre-buried mode Surface, the hub module is arranged on the enclosure, and the hub module includes multiple power supply interfaces and multiple data Communication interface, wherein each can be conductive between the power supply interface and any other power supply interfaces, each data Data communication can be realized between communication interface and any other data communication interfaces;
Connect inside the shell and the cable trough (2), and the cable trough (2) laid inside has a cable, the cable and The power supply interface and/or data communication interface connection.
2. the precast concrete as claimed in claim 1 with communication power cable, it is characterised in that the cable trough (2) cross section is U-shaped, and the cable trough (2) is embedded in the surface of the precast concrete (1), or the line In a tubular form, and the cable trough (2) is embedded in the inside of the precast concrete (1) to cable groove (2).
3. the precast concrete as claimed in claim 1 with communication power cable, it is characterised in that the cable trough (2) bus duct (21) and multiple wire casings (22) are included, the bus duct (21) is in yi word pattern, and longitudinally through described pre- The surface of concrete component (1) processed, wherein multiple branch wire casings (22) are connected on the bus duct (21), and it is described Internal between bus duct (21) and the branch wire casing (22) to connect, at least one end of the bus duct (21) is connected with described in one Cable concentrator (3), and the bus duct (21) connects with the cable concentrator (3) inside.
4. the precast concrete as claimed in claim 3 with communication power cable, it is characterised in that the branch wire casing (22) opposite end for connecting the bus duct (21) is connected with a cable concentrator (3), and the branch wire casing (22) and described Connected inside cable concentrator (3).
5. the precast concrete as claimed in claim 3 with communication power cable, it is characterised in that the branch wire casing (22) face from the bus duct (21) on the precast concrete (1), extend to where the bus duct (21) Side;
The quantity of the branch wire casing (22) is six, wherein three branch wire casings (22) are arranged on the of the bus duct (21) Side, branch wire casing (22) is arranged on the second side of the bus duct (21) described in the other three, positioned at the bus duct (21) The branch wire casing (22) of first side and the branch wire casing (22) positioned at the second side of the bus duct (21) symmetrically set Put.
6. the precast concrete as claimed in claim 5 with communication power cable, it is characterised in that the cable bag Include bus cable and branch line cable, at least one end of the bus cable and the power supply interface in the cable concentrator (3) and/ Or the data communication interface connection;
The bus cable is laid in the bus duct (21), and the branch line cable laying is interior in the branch wire casing (22), and The intersection of the bus duct (21) and the branch wire casing (22) is provided with a multiple-pass joint, and the multiple-pass joint is used to connect The bus cable and the branch line cable.
7. the precast concrete as claimed in claim 6 with communication power cable, it is characterised in that described prefabricated mixed The surface for coagulating native component (1) is additionally provided with sensor, and the sensor is located at the branch wire casing (22) and connects the bus duct (21) opposite end, the branch line cable that the sensor connection is drawn from the branch wire casing (22).
8. the precast concrete as claimed in claim 6 with communication power cable, it is characterised in that the cable can It is fixed on flexible material or metal button member in the cable trough (2).
9. the precast concrete with communication power cable as described in any one of claim 1 or 8, it is characterised in that The quantity of the precast concrete (1) be two, this two T-shaped arrangements of the precast concrete (1), and this two The cable, the cable concentrator (3) and the cable trough (2) are respectively arranged with the individual precast concrete (1);
Connected between the hub module on two precast concretes (1) by the cable.
10. the precast concrete with communication power cable as described in any one of claim 1 or 8, it is characterised in that The quantity of the precast concrete (1) is three, this three T-shaped arrangements of the precast concrete (1), wherein two The individual precast concrete (1) is located along the same line, two precast concrete structures being located along the same line Part (1) is arranged in a mutually vertical manner with another precast concrete (1), and on this three precast concretes (1) It is respectively arranged with the cable, the cable concentrator (3) and the cable trough (2);
Connected between the hub module on three precast concretes (1) by the cable.
CN201720087490.2U 2017-01-23 2017-01-23 A kind of precast concrete with communication power cable Active CN206902911U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720087490.2U CN206902911U (en) 2017-01-23 2017-01-23 A kind of precast concrete with communication power cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720087490.2U CN206902911U (en) 2017-01-23 2017-01-23 A kind of precast concrete with communication power cable

Publications (1)

Publication Number Publication Date
CN206902911U true CN206902911U (en) 2018-01-19

Family

ID=61295083

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720087490.2U Active CN206902911U (en) 2017-01-23 2017-01-23 A kind of precast concrete with communication power cable

Country Status (1)

Country Link
CN (1) CN206902911U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759849A (en) * 2017-01-23 2017-05-31 上海市地下空间设计研究总院有限公司 A kind of precast concrete with communication power cable

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759849A (en) * 2017-01-23 2017-05-31 上海市地下空间设计研究总院有限公司 A kind of precast concrete with communication power cable

Similar Documents

Publication Publication Date Title
WO2019200726A1 (en) Assembled intelligent node with particle damping bin energy consumption, and method for installing same
CN106786266A (en) Prefabrication and assembly construction steel house cable and wire laying system and its construction method
CN206902911U (en) A kind of precast concrete with communication power cable
CN106223498A (en) Integrated prefabricated heat-insulation wall plate manufacture method and structure, wallboard connecting component
CN105756089A (en) Transverse laminated connection type single compartment precast multiple-compartment assembled comprehensive pipe gallery
CN106703832A (en) Intelligent shield tunnel segment
CN203296259U (en) Light type prefabricated wall body assembly with conductor inlaying and power distribution connection functions
CN106906843A (en) Underground pipe gallery and its construction method
CN206658030U (en) A kind of expansible hanging wire street code
CN111648601A (en) Temperature control system for concrete structure winter grouting and construction method
CN106759849A (en) A kind of precast concrete with communication power cable
CN103526776A (en) Rubber waterstop rigidity layering method and rubber waterstop for immersed tunnel
CN207033460U (en) A kind of intelligent duct pieces of shield tunnel
CN107370097A (en) A kind of prefabricated assembled FRP tendons pervious concrete cable duct bank
CN101783200A (en) Prefabricated multi-core coaxial branch cable
CN207296158U (en) A kind of water proof type building PC insulation stone walling connection structures
CN101707342A (en) Cable head
CN205049991U (en) Cable outdoor termination installation environment system
CN209816906U (en) Prefabricated utility tunnel of straight bolted connection
CN203452335U (en) Water and electricity installation structure for constructional engineering
CN102340088A (en) Integrated wiring harness for photovoltaic power supply system
CN204023788U (en) A kind of external member and body of wall without cold-heat bridge syndeton
CN206625257U (en) Underground pipe gallery
CN107503466A (en) A kind of water proof type building PC insulation stone walling attachment structures
CN211928450U (en) Temperature control system for winter grouting construction of prefabricated concrete structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191009

Address after: 200032 room 249, No. 406, Bang Bang Road, Xuhui District, Shanghai

Co-patentee after: Shanghai Urban Construction Information Technology Co., Ltd.

Patentee after: SHANGHAI UNDERGROUND SPACE ARCHITECTURAL DESIGN & RESEARCH INSTITUTE

Address before: 200032 room 249, No. 406, Bang Bang Road, Xuhui District, Shanghai

Patentee before: SHANGHAI UNDERGROUND SPACE ARCHITECTURAL DESIGN & RESEARCH INSTITUTE

TR01 Transfer of patent right