CN106786266A - Prefabrication and assembly construction steel house cable and wire laying system and its construction method - Google Patents
Prefabrication and assembly construction steel house cable and wire laying system and its construction method Download PDFInfo
- Publication number
- CN106786266A CN106786266A CN201611145896.8A CN201611145896A CN106786266A CN 106786266 A CN106786266 A CN 106786266A CN 201611145896 A CN201611145896 A CN 201611145896A CN 106786266 A CN106786266 A CN 106786266A
- Authority
- CN
- China
- Prior art keywords
- cable
- branch pipe
- wire casing
- prefabrication
- steel house
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G3/00—Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
- H02G3/36—Installations of cables or lines in walls, floors or ceilings
- H02G3/38—Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts
- H02G3/386—Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts in walls
- H02G3/388—Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts in walls in modular walls, e.g. wall panels
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
- H02G1/08—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G3/00—Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
- H02G3/02—Details
- H02G3/04—Protective tubing or conduits, e.g. cable ladders or cable troughs
- H02G3/0431—Wall trunking
Abstract
It is formed in wall in advance for existing cable poling, the inconvenient problem of later stage modification, the larger problem for being unfavorable for saving installing space of radius is laid caused by cable installation in pipe, the invention provides a kind of prefabrication and assembly construction steel house cable and wire laying system and its construction method, the system includes some water power wallboards and some cables, the vertical branch pipe wire casing for cabling is opened up on water power wallboard, cable is fixed by some clip bunchys, clip is bonded in vertical branch pipe wire casing, easy construction, the upper end of cable runs to indoor distribution box in furred ceiling along top board, the lower end of cable is connected with socket or switch respectively.In the later stage in water power wallboard, can be facilitated to change or repair, cable fixes i.e. not cable installation in pipe by some clip bunchys, can reduce and lay radius, saves installing space for cable laying.Additionally, power distribution room is connected with each indoor distribution box respectively with emanant power supply mode, can directly be powered after the completion of every layer of assembly, temporary electricity application can be reduced.
Description
Technical field
Laid the present invention relates to electromechanical construction technology field, more particularly to a kind of prefabrication and assembly construction steel house cable and wire
System and its construction method.
Background technology
For a long time, the electric wiring laying installation of traditional prefabrication and assembly construction house is divided into two parts:Supply main portion
Divide and electric terminal part.
Supply main part refers to electric power, (supporter refers to build to communication trunk line arrangement in house supporter
The part that immobilizes is built, resident family utilizes jointly etc. beam, post, floor and load bearing wall, community installations, equipment in load-carrying members
Part).Electric terminal part refers to the laying installations such as secondary distribution piping part, socket, switch (filling in house obturator
Body refers to building variable part, including interior decoration, internal partition wall, kitchen and toilet facility and privately owned part etc. life pipeline).
The characteristics of coordinating this traditional prefabrication and assembly construction house, from plant produced is designed into, largely the equipment such as electric will match somebody with somebody
Pipe, distribution are embedded in reinforced concrete prefabricated board as the pre-buried part of PC plate, due to the prefabricated component of prefabricated dwelling house
All disposably machined in factory, live perforate, fluting are not allowed, for electric specialty, in the design process
An accurate positioning must be disposed with to equipment and pipeline, this just proposes requirement higher to electrical design:First
Calculating will comprehensively consider the quantity of electrical equipment;Perforate, fluting size and position on the prefabricated boards such as its secondary determination floor, exterior wall
Put;The pre-buried electrical power distribution pipe position in prefabricated component is finally marked.And these positioning will be carried out more with structure discipline
Closely coordinate, it is higher to the fitness requirement between specialty;Even late design change can be damaged to precast wall body.
The content of the invention
It is an object of the invention to provide a kind of prefabrication and assembly construction steel house cable and wire laying system and its construction party
Method, by the way that, in the later stage in water power wallboard, can be facilitated to change or repair, cable is solid by some clip bunchys by cable laying
Fixed, the clip is bonded in the vertical branch pipe wire casing of water power wallboard, compared to existing cable cable installation in pipe, can be reduced and be laid half
Footpath, saves installing space.
In order to solve the above technical problems, the present invention provides following technical scheme:
A kind of prefabrication and assembly construction steel house cable and wire laying system, including some water power wallboards and some cables,
The water power wallboard is distributed in the prefabrication and assembly construction steel house according to indoor need for electricity, is opened on the water power wallboard
If for the vertical branch pipe wire casing of cabling, the cable is fixed by some clip bunchys, and the clip is bonded in described
In vertical branch pipe wire casing, the upper end of the cable runs to indoor distribution box, the lower end of the cable in furred ceiling along top board
It is connected with socket or switch respectively.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the cable is in furred ceiling
Fixed by some clip bunchys, the clip is bonded on the bottom surface of top board.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, on the water power wallboard also
Open up a horizontal branch pipe wire casing perpendicular with the vertical branch pipe wire casing.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the lower end of the cable exists
The vertical branch pipe wire casing is walked after being turned with the intersection of the horizontal branch pipe wire casing along the horizontal branch pipe wire casing.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the cable is in level branch
Fixed by clip bunchy in chase, the clip is bonded in horizontal branch pipe wire casing.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, also including cover plate, the lid
The detachable outside for being arranged at the vertical branch pipe wire casing and horizontal branch pipe wire casing of plate, the cover plate is provided with the switch
And/or socket.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the top board is provided with honeybee
Nest beam, sets reserved threading sleeve pipe in the hole that current supply cable is passed through in the Honeycomb Beam.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the water power wallboard it is upper
End is provided with upper lateral chase, and the upper lateral chase is connected with the vertical branch pipe wire casing, the upper lateral pipe
Wire casing sets plaster decoration line with furred ceiling link position.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, power distribution room is with emanant confession
Electrically it is connected with each indoor distribution box respectively, the service entrance cable between power distribution room and each indoor distribution box passes through cable testing bridge
It is arranged in floor cup prefabricated components, size is directly formed in floor cup prefabricated components the cable testing bridge in advance on demand.
The invention also discloses a kind of construction of prefabrication and assembly construction steel house cable and wire laying system as described above
Method, comprises the following steps:
Step one, there is provided some water power wallboards and some cables;
Step 2, the prefabrication and assembly construction steel house is arranged at according to indoor need for electricity by the water power wallboard
It is interior, the vertical branch pipe wire casing for cabling is opened up on the water power wallboard, the cable is fixed by some clip bunchys,
The clip is bonded in the vertical branch pipe wire casing, and the upper end of the cable runs to indoor distribution in furred ceiling along top board
Case, the lower end of the cable is connected with socket or switch respectively;
Step 3, power distribution room is connected with each indoor distribution box respectively with emanant power supply mode, and power distribution room is indoor with each
Service entrance cable between distribution box is arranged in floor cup prefabricated components by cable testing bridge, and the cable testing bridge is big on demand
It is small to be directly formed in advance in floor cup prefabricated components.
From techniques disclosed above scheme, compared with prior art, beneficial effects of the present invention are as follows:
First, the present invention is provided prefabrication and assembly construction steel house cable and wire laying system and its construction method, in water power
The vertical branch pipe wire casing for cabling is opened up on wallboard, the cable is fixed by some clip bunchys, the clip glues
Tie in the vertical branch pipe wire casing, by by cable laying in the later stage in water power wallboard, can be facilitated to change or repair;Electricity
Cable is fixed by some clip bunchys, and the clip is bonded in the vertical branch pipe wire casing of water power wallboard, is worn compared to existing cable
Pipe lays, and can reduce and lay radius, saves installing space.The clip is bonded in the vertical branch pipe wire casing of water power wallboard,
Bonding mode compares other connected modes, and construction more facilitates convenient.
2nd, the present invention is provided prefabrication and assembly construction steel house cable and wire laying system and its construction method, at one layer
Total ammeter metering room is set, and power distribution room is connected with each indoor distribution box respectively with emanant power supply mode, power distribution room and each family
Cable between interior distribution box is arranged in floor cup prefabricated components by cable testing bridge, cable testing bridge size on demand
Directly it is formed in advance in floor cup prefabricated components.Existing normal cable main line crane span structure is installed in electric shaft, and present invention electricity
Size is directly formed in floor cup prefabricated components cable crane span structure in advance on demand, can complete each layer distributing box for household in factory in advance
Service entrance cable is prefabricated, such that it is able to directly take scene laid by floor, length according to actual needs and pre- allowance carry out it is prefabricated, in
Between be not required to joint, can directly be powered after the completion of every layer of assembly, such that it is able to reduce temporary electricity application.
Brief description of the drawings
Fig. 1 is the structural representation of the prefabrication and assembly construction steel house cable and wire laying system of one embodiment of the invention.
Fig. 2 illustrates for the distribution of vertical branch pipe wire casing and horizontal branch pipe wire casing on water power wallboard in one embodiment of the invention
Figure.
In figure:1- water power wallboard, 2- cables, 3- clips, 4 vertical branch pipe wire casings, 5- top boards, 6- horizontal branch pipees wire casing, 7-
The reserved threading sleeve pipe of cover plate, 8- Honeycomb Beams, 9-, 10- upper laterals chase, 11- lower, transverses chase, 12- gypsum decoratives
Lines, 13- walls inner chamber, 14- skirtings.
Specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.According to following explanation and right
Claim, advantages and features of the invention will become apparent from.Hereinafter this hair will be described in detail by cited embodiment combination accompanying drawing
Bright technology contents and feature.Need to illustrate in addition, accompanying drawing is compared in the form of simplifying very much and accurately using non-
Example, is only used to conveniently, lucidly aid in illustrating the purpose of the embodiment of the present invention.For sake of convenience, described below " on ",
The upper and lower direction of D score and accompanying drawing is consistent, but this can not turn into the limitation of technical solution of the present invention.
Embodiment one
Fig. 1 and Fig. 2 is referred to, present embodiment discloses a kind of prefabrication and assembly construction steel house cable and wire laying system,
Including some water power wallboards 1 and some cables 2 (can turn into inside cable), the water power wallboard 1 is according to indoor electricity consumption
Demand is distributed in the prefabrication and assembly construction steel house, and the vertical branch pipe for cabling 2 is opened up on the water power wallboard 1
Wire casing 4, the cable 2 is fixed by the bunchy of some clips 3, and the clip 3 is bonded in the vertical branch pipe wire casing 4, described
The upper end of cable 2 runs to indoor distribution box (not shown) in furred ceiling along top board, and the upper end of the cable 2 is stretched into furred ceiling
Run to indoor distribution box connection, i.e., the upper end of described cable 2 is stretched into furred ceiling along running to indoor distribution box, institute inside furred ceiling
The lower end for stating cable 2 is connected with socket or switch (not shown) respectively.On the one hand, the present embodiment is laid in by by cable 2
In water power wallboard 1, the later stage can be facilitated to change or repair.On the other hand, cable 2 passes through some 3 one-tenth of clips in the present embodiment
Beam is fixed, and the clip 3 is bonded in the vertical branch pipe wire casing 4 of water power wallboard 1, it is seen that the cable 2 of the present embodiment is used and do not worn
Bright system of laying is managed, it compares the cable installation in pipe mode of existing cable 2, can reduce and lay radius, save installing space.The card
Folder 3 is bonded in the vertical branch pipe wire casing 4 of water power wallboard 1, and bonding mode compares other connected modes so that construction more facilitates
It is convenient.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the cable 2 is in furred ceiling
Fixed by the bunchy of some clips 3, the clip 3 is bonded on the top board 5 i.e. bottom surface of floor of steel structure.Likewise, cable 2
Using the bright system of laying of not poling, it compares the cable installation in pipe mode of existing cable 2, can reduce and lay radius, saves and installs empty
Between;The clip 3 is bonded on the bottom surface of top board 5, and bonding mode compares other connected modes so that construction more facilitates just
It is prompt
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, on the water power wallboard 1 also
Open up a horizontal branch pipe wire casing 6 perpendicular with the vertical branch pipe wire casing 4.The lower end of the cable 2 is in the vertical branch pipe
Wire casing 4 is walked after being turned with the intersection of the horizontal branch pipe wire casing 6 along the horizontal branch pipe wire casing 6.By setting level
The setting of branch pipe wire casing 6, can cause required horizontal level by cable 2.Preferably, lived in above-mentioned prefabrication and assembly construction steel construction
In home telephone cable electrical line setting system, the cable 2 is fixed in horizontal branch pipe wire casing 6 by the bunchy of clip 3, and the clip 3 glues
Tie in horizontal branch pipe wire casing 6, bonding mode compares other connected modes so that construction more facilitates convenient.
Preferably, it is described also including cover plate 7 in above-mentioned prefabrication and assembly construction steel house cable and wire laying system
The detachable outside for being arranged at the vertical branch pipe wire casing 4 and horizontal branch pipe wire casing 6 of cover plate 7.The cover plate 7 is provided with described
Switch and/or socket (not shown).Can not only be protected in vertical branch pipe wire casing 4 and horizontal branch pipe wire casing 6 by setting cover plate 7
Cable 2, be easy to switch or socket installation.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the top board 5 is provided with honeybee
Nest beam 8, sets reserved threading sleeve pipe 9 in the hole that current supply cable 2 is passed through in the Honeycomb Beam 8.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the water power wallboard 1 it is upper
End and lower end are respectively equipped with upper lateral chase 10 and lower, transverse chase 11, the upper lateral chase 10 with it is described
Vertical branch pipe wire casing 4 is connected, and the upper lateral chase 10 sets plaster decoration line 12 with furred ceiling link position.The water
Electric wallboard 1 has wall inner chamber 13, and the side of the water power wallboard 1 is provided with the opening connected with interior wall intracoelomic cavity 13, is available for
Pipeline level is passed through.The outside of the lower, transverse chase 11 is provided with skirting 14.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, in prefabrication and assembly construction steel construction
One layer of house sets total ammeter metering room (not shown), and power distribution room is connected with each indoor distribution box respectively with emanant power supply mode
Connect, the service entrance cable between power distribution room and each indoor distribution box is arranged in floor cup prefabricated components by cable testing bridge,
Size is directly formed in floor cup prefabricated components the cable testing bridge in advance on demand.Compared to existing normal cable crane span structure electric
Install in vertical shaft, and cable testing bridge of the present invention size is directly formed in floor cup prefabricated components in advance on demand, in advance can be
Each layer distributing box for household service entrance cable is completed in factory prefabricated, laid by floor such that it is able to the scene of directly taking, length is by actual
Need and pre- allowance carries out prefabricated, centre is not required to joint, can directly be powered after the completion of every layer of assembly, it is interim such that it is able to reduce
Electricity consumption application.
Embodiment two
Please continue to refer to Fig. 1 and Fig. 2, the present embodiment provides the prefabrication and assembly construction steel house cable electricity described in embodiment one
The construction method of wire routing system, comprises the following steps:
Step one, there is provided some water power wallboards and some cables.
Step 2, the prefabrication and assembly construction steel house is arranged at according to indoor need for electricity by the water power wallboard
It is interior, the vertical branch pipe wire casing 4 for cabling 2 is opened up on the water power wallboard 1, the cable 2 passes through the bunchy of some clips 3
Fixed, the clip 3 is bonded in the vertical branch pipe wire casing 4, and the upper end of the cable 2 is walked in furred ceiling along top board 5
To indoor distribution box, the lower end of the cable 2 is connected with socket or switch respectively.On the one hand, the present embodiment is by by cable 2
It is laid in water power wallboard 1, the later stage can be facilitated to change or repair.On the other hand, cable 2 passes through some cards in the present embodiment
Press from both sides 3 bunchys to fix, the clip 3 is bonded in the vertical branch pipe wire casing 4 of water power wallboard 1, it is seen that the cable 2 of the present embodiment is used
The not bright system of laying of poling, it is compared the cable installation in pipe mode of existing cable 2, can reduce and lay radius, saves installing space.Institute
State clip 3 to be bonded in the vertical branch pipe wire casing 4 of water power wallboard 1, bonding mode compares other connected modes so that construction is more
Facilitate convenient.
Step 3, power distribution room is connected with each indoor distribution box respectively with emanant power supply mode, and power distribution room is indoor with each
Service entrance cable between distribution box is arranged in floor cup prefabricated components by cable testing bridge, and the cable testing bridge is big on demand
It is small to be directly formed in advance in floor cup prefabricated components.Installed in electric shaft compared to existing normal cable crane span structure, and it is of the invention
Size is directly formed in floor cup prefabricated components cable testing bridge in advance on demand, can complete Ge Ceng resident families distribution in factory in advance
Case service entrance cable is prefabricated, such that it is able to directly take scene laid by floor, length according to actual needs and pre- allowance carry out it is prefabricated,
Centre is not required to joint, can directly be powered after the completion of every layer of assembly, such that it is able to reduce temporary electricity application.
In sum, the present invention has the beneficial effect that:
First, the prefabrication and assembly construction steel house cable and wire laying system that the present invention is provided, use is opened up on water power wallboard
In the vertical branch pipe wire casing of cabling, the cable is fixed by some clip bunchys, and the clip is bonded in described vertical
In branch pipe wire casing, by by cable laying in water power wallboard, can facilitate the later stage change or repair;Cable passes through some cards
Folder bunchy is fixed, and the clip is bonded in the vertical branch pipe wire casing of water power wallboard, compared to existing cable cable installation in pipe, can be subtracted
It is small to lay radius, save installing space.The clip is bonded in the vertical branch pipe wire casing of water power wallboard, and bonding mode compares it
His connected mode, construction more facilitates convenient.
2nd, the prefabrication and assembly construction steel house cable and wire laying system that the present invention is provided, total ammeter meter is set at one layer
Between amount, power distribution room is connected with each indoor distribution box respectively with emanant power supply mode, between power distribution room and each indoor distribution box
Cable be arranged in floor cup prefabricated components by cable testing bridge, size is directly formed on building to the cable testing bridge in advance on demand
In layer cup prefabricated component.Existing normal cable main line crane span structure is installed in electric shaft, and cable testing bridge of the present invention is on demand
Size is directly formed in floor cup prefabricated components in advance, can complete each layer distributing box for household service entrance cable in factory in advance pre-
System, such that it is able to directly take it is live laid by floor, length is according to actual needs and pre- allowance carries out prefabricated, and centre is not required to connect
Head, can directly power after the completion of every layer of assembly, such that it is able to reduce temporary electricity application.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair
Any change, modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims
Scope.
Claims (10)
1. a kind of prefabrication and assembly construction steel house cable and wire laying system, it is characterised in that including some water power wallboards and
Some cables, the water power wallboard is distributed in the prefabrication and assembly construction steel house according to indoor need for electricity, the water
The vertical branch pipe wire casing for cabling is opened up on electric wallboard, the cable is fixed by some clip bunchys, the clip
It is bonded in the vertical branch pipe wire casing, the upper end of the cable runs to indoor distribution box in furred ceiling along top board, described
The lower end of cable is connected with socket or switch respectively.
2. prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 1, it is characterised in that the cable
Fixed by some clip bunchys in furred ceiling, the clip is bonded on the bottom surface of top board.
3. prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 1, it is characterised in that the water power
A horizontal branch pipe wire casing perpendicular with the vertical branch pipe wire casing is also opened up on wallboard.
4. prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 3, it is characterised in that the cable
Lower end after the intersection of the vertical branch pipe wire casing and the horizontal branch pipe wire casing is turned along the horizontal branch pipe wire casing
Walking.
5. prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 4, it is characterised in that the cable
Fixed by clip bunchy in horizontal branch pipe wire casing, the clip is bonded in horizontal branch pipe wire casing.
6. prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 3, it is characterised in that also including lid
Plate, the detachable outside for being arranged at the vertical branch pipe wire casing and horizontal branch pipe wire casing of the cover plate, the cover plate is provided with
The switch and/or socket.
7. prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 2, it is characterised in that the top board
Honeycomb Beam is provided with, reserved threading sleeve pipe is set in the hole that current supply cable is passed through in the Honeycomb Beam.
8. prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 1, it is characterised in that the water power
The upper end of wallboard is provided with upper lateral chase, and the upper lateral chase is connected with the vertical branch pipe wire casing, it is described on
Portion's transverse pipe wire casing sets plaster decoration line with furred ceiling link position.
9. the prefabrication and assembly construction steel house cable and wire laying system as described in any one in claim 1-8, its feature
It is that power distribution room is connected with each indoor distribution box respectively with emanant power supply mode, between power distribution room and each indoor distribution box
Service entrance cable be arranged in floor cup prefabricated components by cable testing bridge, size is directly prefabricated on demand for the cable testing bridge
In in floor cup prefabricated components.
10. prefabrication and assembly construction steel house cable and wire laying system in a kind of 1-9 such as claim as described in any one
Construction method, it is characterised in that comprise the following steps:
Step one, there is provided some water power wallboards and some cables;
, be arranged at the water power wallboard in the prefabrication and assembly construction steel house according to indoor need for electricity, institute by step 2
The vertical branch pipe wire casing opened up on water power wallboard for cabling is stated, the cable is fixed by some clip bunchys, described
Clip is bonded in the vertical branch pipe wire casing, and the upper end of the cable runs to indoor distribution box in furred ceiling along top board,
The lower end of the cable is connected with socket or switch respectively;
Step 3, power distribution room is connected with each indoor distribution box respectively with emanant power supply mode, power distribution room and each indoor distribution
Service entrance cable between case is arranged in floor cup prefabricated components by cable testing bridge, and size is straight on demand for the cable testing bridge
Connect pre- being formed in floor cup prefabricated components.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611145896.8A CN106786266B (en) | 2016-12-13 | 2016-12-13 | Prefabrication and assembly construction steel house cable and wire laying system and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611145896.8A CN106786266B (en) | 2016-12-13 | 2016-12-13 | Prefabrication and assembly construction steel house cable and wire laying system and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106786266A true CN106786266A (en) | 2017-05-31 |
CN106786266B CN106786266B (en) | 2018-08-31 |
Family
ID=58876503
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611145896.8A Active CN106786266B (en) | 2016-12-13 | 2016-12-13 | Prefabrication and assembly construction steel house cable and wire laying system and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106786266B (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2019218224A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | House having water pipe and high-voltage wire separate from main structure |
WO2019218179A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | Construction method for house having water pipe and high-voltage wire separate from main structure |
CN110499933A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of house that pipeline is separated with main structure |
CN110499861A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of furred ceiling electricity separation system |
CN110730853A (en) * | 2018-05-16 | 2020-01-24 | 深圳市君盈建筑科技有限公司 | Construction method of house with separated pipeline and main body structure |
CN110945191A (en) * | 2018-05-16 | 2020-03-31 | 广东博智林机器人有限公司 | Construction method of house with separated strong-current electric wire and main body structure |
CN110945198A (en) * | 2018-05-16 | 2020-03-31 | 广东博智林机器人有限公司 | House with separated strong current wire and main body structure |
CN110945197A (en) * | 2018-05-16 | 2020-03-31 | 广东博智林机器人有限公司 | Residence with separated electric wire and main structure |
CN111201358A (en) * | 2018-05-16 | 2020-05-26 | 深圳市君盈建筑科技有限公司 | Residence with water pipe and weak current electric wire separated from main structure |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004064816A (en) * | 2002-07-25 | 2004-02-26 | Aoki Engineering:Kk | Routing method of conduit in building |
CN103061515A (en) * | 2012-12-29 | 2013-04-24 | 陕西省第三建筑工程公司 | Method for perforating and pre-burying polyvinyl chloride (PVC) wiring tubes in concrete hollow block filled walls |
CN204216515U (en) * | 2014-10-18 | 2015-03-18 | 福州万山电力咨询有限公司 | The mounting structure of distribution engineering cable testing bridge |
CN104453085A (en) * | 2014-10-28 | 2015-03-25 | 成都市第四建筑工程公司 | Mounting method of wire box of lightweight aggregate concrete hollow partition board |
CN204651834U (en) * | 2015-06-09 | 2015-09-16 | 上海绿地建设(集团)有限公司 | The pre-buried structure of electric pipeline in a kind of brick wall |
CN204741240U (en) * | 2015-04-07 | 2015-11-04 | 自贡市博雅装饰工程有限公司 | Strong and weak electric winding displacement system |
CN106149880A (en) * | 2015-03-20 | 2016-11-23 | 万平华 | Use the assembling room of new architecture |
CN206313397U (en) * | 2016-12-13 | 2017-07-07 | 上海市建工设计研究总院有限公司 | Prefabrication and assembly construction steel house cable and wire laying system |
-
2016
- 2016-12-13 CN CN201611145896.8A patent/CN106786266B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004064816A (en) * | 2002-07-25 | 2004-02-26 | Aoki Engineering:Kk | Routing method of conduit in building |
CN103061515A (en) * | 2012-12-29 | 2013-04-24 | 陕西省第三建筑工程公司 | Method for perforating and pre-burying polyvinyl chloride (PVC) wiring tubes in concrete hollow block filled walls |
CN204216515U (en) * | 2014-10-18 | 2015-03-18 | 福州万山电力咨询有限公司 | The mounting structure of distribution engineering cable testing bridge |
CN104453085A (en) * | 2014-10-28 | 2015-03-25 | 成都市第四建筑工程公司 | Mounting method of wire box of lightweight aggregate concrete hollow partition board |
CN106149880A (en) * | 2015-03-20 | 2016-11-23 | 万平华 | Use the assembling room of new architecture |
CN204741240U (en) * | 2015-04-07 | 2015-11-04 | 自贡市博雅装饰工程有限公司 | Strong and weak electric winding displacement system |
CN204651834U (en) * | 2015-06-09 | 2015-09-16 | 上海绿地建设(集团)有限公司 | The pre-buried structure of electric pipeline in a kind of brick wall |
CN206313397U (en) * | 2016-12-13 | 2017-07-07 | 上海市建工设计研究总院有限公司 | Prefabrication and assembly construction steel house cable and wire laying system |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2019218224A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | House having water pipe and high-voltage wire separate from main structure |
WO2019218179A1 (en) * | 2018-05-16 | 2019-11-21 | 深圳市君盈建筑科技有限公司 | Construction method for house having water pipe and high-voltage wire separate from main structure |
CN110499933A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of house that pipeline is separated with main structure |
CN110499861A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of furred ceiling electricity separation system |
CN110730853A (en) * | 2018-05-16 | 2020-01-24 | 深圳市君盈建筑科技有限公司 | Construction method of house with separated pipeline and main body structure |
CN110731038A (en) * | 2018-05-16 | 2020-01-24 | 深圳市君盈建筑科技有限公司 | Construction method of house with water pipe, strong electric wire and main body structure separated |
CN110945191A (en) * | 2018-05-16 | 2020-03-31 | 广东博智林机器人有限公司 | Construction method of house with separated strong-current electric wire and main body structure |
CN110945198A (en) * | 2018-05-16 | 2020-03-31 | 广东博智林机器人有限公司 | House with separated strong current wire and main body structure |
CN110945197A (en) * | 2018-05-16 | 2020-03-31 | 广东博智林机器人有限公司 | Residence with separated electric wire and main structure |
CN111201358A (en) * | 2018-05-16 | 2020-05-26 | 深圳市君盈建筑科技有限公司 | Residence with water pipe and weak current electric wire separated from main structure |
CN112106265A (en) * | 2018-05-16 | 2020-12-18 | 东莞市碧桂园房地产开发有限公司 | House with separated water pipe, strong current electric wire and main body structure |
Also Published As
Publication number | Publication date |
---|---|
CN106786266B (en) | 2018-08-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106786266B (en) | Prefabrication and assembly construction steel house cable and wire laying system and its construction method | |
CN206313397U (en) | Prefabrication and assembly construction steel house cable and wire laying system | |
CN109577535A (en) | Assembled architecture PC superimposed sheet and the electromechanical installation built-in process of dry wall combination | |
CN111980233A (en) | Vertical splicing light and thin template structure of assembled inner wall | |
CN203296259U (en) | Light type prefabricated wall body assembly with conductor inlaying and power distribution connection functions | |
CN106906843A (en) | Underground pipe gallery and its construction method | |
CN103326279A (en) | Cable duct bank construction device and method | |
CN216344379U (en) | Pipeline node two-way connecting piece | |
CN206498168U (en) | A kind of distribution system of high-effective multilayer structure low level equipment | |
CN206558992U (en) | Outlet distribution structure under a kind of assembled architecture house indoor distribution box | |
CN210857599U (en) | Pipeline separation waterproof heat preservation integration wall body and building that constitutes thereof | |
CN210621997U (en) | Assembled wall body of pre-buried electric wire | |
CN203339577U (en) | Cable duct construction device | |
CN208094124U (en) | A kind of electrical structure wiring system for assembled architecture | |
CN212935272U (en) | Mounting structure of indoor distribution box and household distribution box of residence | |
JP5537972B2 (en) | Apartment house provided with solar power generation device and method of renovating this apartment house | |
JP2013044187A (en) | Building | |
II | Technical Specifications | |
CN215926561U (en) | Building pipeline separation system | |
CN216195868U (en) | Line box embedded structure and coincide floor | |
CN205976631U (en) | But sled dressization mobility control room | |
CN214900035U (en) | Assembled light wallboard electrical pipeline integrated device | |
CN112027827B (en) | Method for shifting along household power conductor by matching with existing house and additionally installing elevator | |
CN207651821U (en) | First and second unit equipment prefabricated cabins of 35kV with additional maintenance cabin | |
CN210111565U (en) | Wire outlet structure of box transformer substation arranged above basement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 200050 Changning District, Wuyi Road, No. 150, Applicant after: Shanghai construction design and Research Institute Co Ltd Applicant after: Shanghai Mechanized Construction Group Co., Ltd. Address before: 200050 Changning District, Wuyi Road, No. 150, Applicant before: Shanghai Construction Group Design Institute Co., Ltd. Applicant before: Shanghai Mechanized Construction Group Co., Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant |