CN206881486U - Flue gas pre-washing device before a kind of desulfuration absorbing tower - Google Patents

Flue gas pre-washing device before a kind of desulfuration absorbing tower Download PDF

Info

Publication number
CN206881486U
CN206881486U CN201720741180.8U CN201720741180U CN206881486U CN 206881486 U CN206881486 U CN 206881486U CN 201720741180 U CN201720741180 U CN 201720741180U CN 206881486 U CN206881486 U CN 206881486U
Authority
CN
China
Prior art keywords
absorbing tower
desulfuration absorbing
flue gas
flue
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720741180.8U
Other languages
Chinese (zh)
Inventor
陶明
王少亮
余福胜
何育东
牛拥军
雷鸣
李兴华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Xire Boiler Environmental Protection Engineering Co Ltd
Original Assignee
Xian Xire Boiler Environmental Protection Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Xire Boiler Environmental Protection Engineering Co Ltd filed Critical Xian Xire Boiler Environmental Protection Engineering Co Ltd
Priority to CN201720741180.8U priority Critical patent/CN206881486U/en
Application granted granted Critical
Publication of CN206881486U publication Critical patent/CN206881486U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses flue gas pre-washing device before a kind of desulfuration absorbing tower, detergent circulator including flue before desulfuration absorbing tower and for supplying cleaning solution needed for flue gas washing, flue is connected with the smoke inlet of desulfuration absorbing tower before desulfuration absorbing tower, if the direction that flue interior edge flue gas circulates before desulfuration absorbing tower is sequentially provided with dried layer and pre-washes spraying layer and rectification synergy coating, the nozzle that the outlet of detergent circulator is pre-washed with each layer in spraying layer is connected, and the device can effectively improve the pollutant removing ability of desulfuration absorbing tower.

Description

Flue gas pre-washing device before a kind of desulfuration absorbing tower
Technical field
It the utility model is related to a kind of wash mill, and in particular to flue gas pre-washing device before a kind of desulfuration absorbing tower.
Background technology
As China constantly releases more strict atmosphere pollutants emission standardses, coal unit is both needed to complete ultralow at present Discharge transformation, is less than 35mg/m to reach sulfur dioxide concentration3, dust concentration is less than 5mg/m3, nitrous oxides concentration is less than 50mg/m3Minimum discharge standard.Conventional limestone gypsum wet flue gas desulfurizing absorptive tower flue gas is entered by absorption tower entrance at present Enter, by demister by smoke stack emission after spraying layer removes pollutant.Absorption tower will realize pollutant minimum discharge, generally Desulfuration efficiency will reach more than 99%, and absorption tower collaboration efficiency of dust collection reaches more than 80%, and conventional desulfurization absorption tower is difficult at present Reach so efficient pollutant removing ability, it is necessary to carry out corresponding transformation to meet minimum discharge needs, but prior art In there is no a kind of effective device for improving desulfuration absorbing tower pollutant removing ability.
Utility model content
A kind of the shortcomings that the purpose of this utility model is to overcome above-mentioned prior art, there is provided flue gas before desulfuration absorbing tower Pre-washing device, the device can effectively improve the pollutant removing ability of desulfuration absorbing tower.
To reach above-mentioned purpose, flue gas pre-washing device includes desulfurization and absorbed before desulfuration absorbing tower described in the utility model Flue and the detergent circulator for supplying cleaning solution needed for flue gas washing before tower, flue is inhaled with desulfurization before desulfuration absorbing tower The smoke inlet for receiving tower is connected, if the direction that flue interior edge flue gas circulates before desulfuration absorbing tower is sequentially provided with dried layer and pre-washes spray Drenching layer and rectification synergy coating, the nozzle that the outlet of detergent circulator is pre-washed with each layer in spraying layer are connected.
Flue is in horizontal distribution before the desulfuration absorbing tower.
Also include sprayed slurry collection bucket and pre-wash slurry tank, the bottom of flue goes out provided with cleaning solution before desulfuration absorbing tower Mouthful, spraying layer is respectively pre-washed described in cleaning solution outlet face, sprayed slurry collection bucket is connected with cleaning solution outlet, sprayed Slurries collection bucket is connected with pre-washing slurry tank, pre-washes the scrubbed liquid circulating pump in outlet of slurry tank side and each layer prewashing The nozzle washed in spraying layer is connected.
Also include sprayed slurry collection bucket, the bottom of flue exports provided with cleaning solution before desulfuration absorbing tower, cleaning solution outlet Face respectively pre-washes spraying layer, and the top of sprayed slurry collection bucket is connected with cleaning solution outlet, sprayed slurry collection bucket Bottom be connected with the slurry pool of desulfuration absorbing tower bottom, the slurry pool of desulfuration absorbing tower bottom by detergent circulator with The nozzle that each layer is pre-washed in spraying layer is connected.
The L-shaped distribution of flue before desulfuration absorbing tower.
Also include pre-washing slurry tank, flue includes vertical duct and horizontal pipeline before desulfuration absorbing tower, vertical duct Lower end is connected with one end of horizontal pipeline, and the other end of horizontal pipeline is connected with the smoke inlet of desulfuration absorbing tower, prewashing Wash spraying layer and rectification synergy coating is located in vertical duct, the bottom of the one end being connected on horizontal pipeline with vertical duct is recessed Shape structure, the outlet at bottom of the concave structure are connected with pre-washing slurry tank, and the outlet for pre-washing slurry tank passes through washing The nozzle that liquid circulating pump is pre-washed with each layer in spraying layer is connected.
Flue includes vertical duct and horizontal pipeline, the lower end of vertical duct and one end of horizontal pipeline before desulfuration absorbing tower It is connected, the other end of horizontal pipeline is connected with the smoke inlet of desulfuration absorbing tower, pre-washes spraying layer and rectification synergy coating In vertical duct, the bottom of the one end being connected on horizontal pipeline with vertical duct is concave structure, the concave structure Outlet at bottom be connected with the slurry pool of desulfuration absorbing tower bottom, the slurry pool of desulfuration absorbing tower bottom is circulated by cleaning solution The nozzle that pump is pre-washed with each layer in spraying layer is connected.
The number of plies for pre-washing spraying layer is 1-3 layers.
The number of plies for pre-washing spraying layer is 1-3 times of detergent circulator quantity.
The utility model has the advantages that:
For flue gas pre-washing device in concrete operations, detergent circulator is defeated before desulfuration absorbing tower described in the utility model The cleaning solution gone out sprays into before desulfuration absorbing tower in flue through respectively pre-washing in spraying layer, the washing to flue gas is realized, after washing The rectified synergy coating of flue gas strengthens the removing of pollutant in flue gas and carries out gas-liquid separation, and the flue gas after gas-liquid separation enters de- Sulphur is further processed in absorption tower, is greatly lowered into SO in the flue gas of desulfuration absorbing tower2And the pollutant such as dust is dense Degree, so as to effectively improve the pollutant removing ability of desulfuration absorbing tower, simple in construction, easy to operate, practicality is extremely strong.
Brief description of the drawings
Fig. 1 is the structural representation of embodiment one in the utility model;
Fig. 2 is the structural representation of embodiment two in the utility model;
Fig. 3 is the structural representation of embodiment three in the utility model;
Fig. 4 is the structural representation of example IV in the utility model.
Wherein, 1 for pre-wash spraying layer, 2 be rectification synergy coating, 3 be sprayed slurry collection bucket, 4 be cleaning solution circulation Pump, 5 is pre-wash slurry tank, 6 are desulfuration absorbing tower.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings:
With reference to figure 1, flue gas pre-washing device includes cigarette before desulfuration absorbing tower before desulfuration absorbing tower described in the utility model Road and the detergent circulator 4 for supplying cleaning solution needed for flue gas washing, flue and desulfuration absorbing tower 6 before desulfuration absorbing tower Smoke inlet be connected, if the direction that flue interior edge flue gas circulates before desulfuration absorbing tower is sequentially provided with dried layer and pre-washes spraying layer 1 and rectification synergy coating 2, the outlet of detergent circulator 4 pre-wash the nozzle in spraying layer 1 with each layer and be connected.
The number of plies for pre-washing spraying layer 1 is 1-3 layers, and the number of plies for pre-washing spraying layer 1 is the quantity of detergent circulator 4 1-3 times.
Pre-wash spraying layer 1 to be made up of spraying layer main pipe, spray branch pipe and nozzle, spraying layer main pipe is arranged in outside flue Top or sidepiece, spray branch pipe be arranged in inside flue, nozzle along spray branch pipe arrangement, arrangement of nozzles spacing be apart from nozzle 1 meter of place sprays slurries coverage rate and is not less than 100%.
Rectification synergy coating 2 is two row's bank of staggered pipes formulas, and Bundle material is PP plastics, carbon steel pipe outer wall anti-corrosion or steel alloy, Two comb interfasciculars are away from 50-500 millimeters, and pipeline enclosure per comb beam is away from for 50-500 millimeters, a diameter of 50-200 millis of pipeline Rice.
Pre-wash slurry tank 5 and be provided with agitator, densitometer, pH meter, liquid level gauge and gypsum excavationg pump, pre-wash slurry tank 5 slurry pH value is slightly above absorption tower stock tank;Lime stone slurry, which can be fed directly into, to be pre-washed in slurry tank 5.
Embodiment one
Flue is in horizontal distribution before the desulfuration absorbing tower, and the utility model also includes sprayed slurry collection bucket 3 and prewashing Wash slurry tank 5, the bottom of flue is exported provided with cleaning solution before desulfuration absorbing tower, and spray is respectively pre-washed described in cleaning solution outlet face Layer 1, sprayed slurry collection bucket 3 are connected with cleaning solution outlet, and sprayed slurry collection bucket 3 is connected with pre-washing slurry tank 5 Logical, the scrubbed liquid circulating pump 4 in outlet for pre-washing the side of slurry tank 5 pre-washes the nozzle in spraying layer 1 with each layer and is connected.
Embodiment two
Flue is in horizontal distribution before the desulfuration absorbing tower, and the utility model also includes sprayed slurry collection bucket 3, and desulfurization is inhaled The bottom of flue exports provided with cleaning solution before receipts tower, and cleaning solution outlet face respectively pre-washes spraying layer 1, sprayed slurry collection bucket 3 The outlet of top and the cleaning solution be connected, the slurry pool phase of the bottom and the bottom of desulfuration absorbing tower 6 of sprayed slurry collection bucket 3 Connection, the slurry pool of the bottom of desulfuration absorbing tower 6 pre-wash the nozzle in spraying layer 1 with each layer by detergent circulator 4 and are connected It is logical.
Embodiment three
The L-shaped distribution of flue before desulfuration absorbing tower, the utility model also includes pre-washing slurry tank 5, before desulfuration absorbing tower Flue includes vertical duct and horizontal pipeline, and the lower end of vertical duct is connected with one end of horizontal pipeline, horizontal pipeline it is another One end is connected with the smoke inlet of desulfuration absorbing tower 6, pre-washes spraying layer 1 and rectification synergy coating 2 is located in vertical duct, horizontal The bottom of the one end being connected on to pipeline with vertical duct is concave structure, and the outlet at bottom of the concave structure is with pre-washing Slurry tank 5 is connected, and pre-wash slurry tank 5 exports the nozzle pre-washed by detergent circulator 4 and each layer in spraying layer 1 It is connected.
Example IV
Flue includes vertical duct and horizontal pipeline, the lower end of vertical duct and one end of horizontal pipeline before desulfuration absorbing tower It is connected, the other end of horizontal pipeline is connected with the smoke inlet of desulfuration absorbing tower 6, pre-washes spraying layer 1 and rectification synergy Layer 2 is in the vertical duct, and the bottom of the one end being connected on horizontal pipeline with vertical duct is concave structure, the spill knot The outlet at bottom of structure is connected with the slurry pool of the bottom of desulfuration absorbing tower 6, and the slurry pool of the bottom of desulfuration absorbing tower 6 passes through cleaning solution Circulating pump 4 pre-washes the nozzle in spraying layer 1 with each layer and is connected.
Specific work process of the present utility model is:
The washing slurries that detergent circulator 4 exports are ejected into before desulfuration absorbing tower in flue through respectively pre-washing spraying layer 1, The washing to flue gas in flue before desulfuration absorbing tower is realized, the rectified synergy coating 2 of the flue gas after washing strengthens the removing of pollutant And gas-liquid separation is carried out, the flue gas separated is entered further to be handled into desulfuration absorbing tower 6, so as to substantially reduce entrance SO in the flue gas of desulfuration absorbing tower 62And the pollutant concentration such as dust, becoming more meticulous to remove for pollutant in desulfuration absorbing tower 6 provides Preferable boundary condition.

Claims (9)

1. flue gas pre-washing device before a kind of desulfuration absorbing tower, it is characterised in that including flue before desulfuration absorbing tower and be used for The detergent circulator (4) of cleaning solution needed for flue gas washing is supplied, the flue gas of flue and desulfuration absorbing tower (6) before desulfuration absorbing tower Entrance is connected, if before desulfuration absorbing tower flue interior edge flue gas circulate direction be sequentially provided with dried layer pre-wash spraying layer (1) and Rectification synergy coating (2), the nozzle that outlet and each layer of detergent circulator (4) are pre-washed in spraying layer (1) are connected.
2. flue gas pre-washing device before desulfuration absorbing tower according to claim 1, it is characterised in that the desulfuration absorbing tower Preceding flue is in horizontal distribution.
3. flue gas pre-washing device before desulfuration absorbing tower according to claim 2, it is characterised in that also including sprayed slurry Collection bucket (3) and slurry tank (5) is pre-washed, the bottom of flue exports provided with cleaning solution before desulfuration absorbing tower, and cleaning solution exports just Spraying layer (1) is respectively pre-washed to described, sprayed slurry collection bucket (3) is connected with cleaning solution outlet, and sprayed slurry is collected Bucket (3) is connected with pre-washing slurry tank (5), pre-washes the scrubbed liquid circulating pump (4) in outlet of slurry tank (5) side and each layer The nozzle pre-washed in spraying layer (1) is connected.
4. flue gas pre-washing device before desulfuration absorbing tower according to claim 2, it is characterised in that also including sprayed slurry Collection bucket (3), the bottom of flue exports provided with cleaning solution before desulfuration absorbing tower, and cleaning solution outlet face respectively pre-washes spraying layer (1), the top of sprayed slurry collection bucket (3) is connected with cleaning solution outlet, and the bottom of sprayed slurry collection bucket (3) is with taking off The slurry pool of sulphur absorption tower (6) bottom is connected, the slurry pool of desulfuration absorbing tower (6) bottom by detergent circulator (4) with The nozzle that each layer is pre-washed in spraying layer (1) is connected.
5. flue gas pre-washing device before desulfuration absorbing tower according to claim 1, it is characterised in that cigarette before desulfuration absorbing tower The L-shaped distribution in road.
6. flue gas pre-washing device before desulfuration absorbing tower according to claim 5, it is characterised in that also include pre-washing slurry Liquid case (5), flue includes vertical duct and horizontal pipeline, the lower end of vertical duct and one end of horizontal pipeline before desulfuration absorbing tower It is connected, the other end of horizontal pipeline is connected with the smoke inlet of desulfuration absorbing tower (6), pre-washes spraying layer (1) and rectification Synergy coating (2) is located in vertical duct, and the bottom of the one end being connected on horizontal pipeline with vertical duct is concave structure, described The outlet at bottom of concave structure is connected with pre-washing slurry tank (5), and the outlet for pre-washing slurry tank (5) is circulated by cleaning solution Pump (4) pre-washes the nozzle in spraying layer (1) with each layer and is connected.
7. flue gas pre-washing device before desulfuration absorbing tower according to claim 5, it is characterised in that cigarette before desulfuration absorbing tower Road includes vertical duct and horizontal pipeline, and the lower end of vertical duct is connected with one end of horizontal pipeline, horizontal pipeline it is another End is connected with the smoke inlet of desulfuration absorbing tower (6), pre-washes spraying layer (1) and rectification synergy coating (2) is located at vertical duct Interior, the bottom of the one end being connected on horizontal pipeline with vertical duct is concave structure, the outlet at bottom of the concave structure with The slurry pool of desulfuration absorbing tower (6) bottom is connected, and the slurry pool of desulfuration absorbing tower (6) bottom passes through detergent circulator (4) The nozzle in spraying layer (1) is pre-washed with each layer to be connected.
8. flue gas pre-washing device before desulfuration absorbing tower according to claim 1, it is characterised in that described to pre-wash spray The number of plies of layer (1) is 1-3 layers.
9. flue gas pre-washing device before desulfuration absorbing tower according to claim 1, it is characterised in that pre-wash spraying layer (1) the number of plies is 1-3 times of detergent circulator (4) quantity.
CN201720741180.8U 2017-06-23 2017-06-23 Flue gas pre-washing device before a kind of desulfuration absorbing tower Active CN206881486U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720741180.8U CN206881486U (en) 2017-06-23 2017-06-23 Flue gas pre-washing device before a kind of desulfuration absorbing tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720741180.8U CN206881486U (en) 2017-06-23 2017-06-23 Flue gas pre-washing device before a kind of desulfuration absorbing tower

Publications (1)

Publication Number Publication Date
CN206881486U true CN206881486U (en) 2018-01-16

Family

ID=61316643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720741180.8U Active CN206881486U (en) 2017-06-23 2017-06-23 Flue gas pre-washing device before a kind of desulfuration absorbing tower

Country Status (1)

Country Link
CN (1) CN206881486U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108579316A (en) * 2018-07-05 2018-09-28 山东三融环保工程有限公司 A kind of flue gas for wet desulfuration tower disappears white plumage governing system
CN113413747A (en) * 2021-07-13 2021-09-21 盘锦富添石油化工发展有限公司 Desulfurizing tower and desulfurizing method for producing tar resin

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108579316A (en) * 2018-07-05 2018-09-28 山东三融环保工程有限公司 A kind of flue gas for wet desulfuration tower disappears white plumage governing system
CN113413747A (en) * 2021-07-13 2021-09-21 盘锦富添石油化工发展有限公司 Desulfurizing tower and desulfurizing method for producing tar resin

Similar Documents

Publication Publication Date Title
CN205055807U (en) Coke oven low -sulfur tail gas desulfurization dust collector
CN204522737U (en) A kind of mixed-flow wet process of FGD dedusting near-zero release integration absorption tower
CN104826476A (en) Industrial flue gas desulfurization/denitrification/dedusting integrated technique and device
CN204933240U (en) Double tower Two-way Cycle Wet Limestone Desulfurization treatment system
CN108686490A (en) A kind of fuel gas desulfurization gas wash tower and desulfurization and dust-removal method
CN107261808A (en) A kind of double ultra-clean desulfurized dust collection columns of spray of the double turbulent flows of single cycle
CN206881486U (en) Flue gas pre-washing device before a kind of desulfuration absorbing tower
CN106823742A (en) A kind of desulfurization and dust-removal method of double circulation desulphurization and dust-removing device and flue gas
CN103007728A (en) Operating method of annular pipe rotational flow wet process flue gas desulfurization tower
CN105148699B (en) A kind of single column oxidation sweetening denitrification apparatus and its desulfurization denitration method
CN105617847A (en) Novel rotational flow coupling deep desulfurization intensifying module
CN108744941A (en) A kind of the spray column desulphurization system and method for high-order arrangement
CN207187488U (en) A kind of double ultra-clean desulfurized dust collection columns of spray of the double turbulent flows of single cycle
CN107158921A (en) A kind of ultra-clean exhaust system of coal burning flue gas desulfurization dedusting
CN205517232U (en) Energy -conserving desulfurization dust removal minimum discharge integrated device
CN201978629U (en) Flue gas prewashing device of desulfurization absorption tower
CN208493789U (en) A kind of industrial waste-gas purifier
CN207694591U (en) Two-way Cycle wet process of FGD dust pelletizing system
CN108686492A (en) Flue-gas dust-removing and desulfurization tower and dust-collecting sulfur-removing method
CN210905500U (en) Cyclone dust removal membrane type separation device for treating tail gas of fertilizer granulation high tower
CN202715350U (en) Wet desulfurization adsorption tower with multi-effect turbulence system
CN205948656U (en) Two -way rectification drain device of two pH spray desulfurization tower
CN108686493A (en) Flue-gas dust-removing and desulfurization tower and dust-removing and desulfurization process
CN106178912A (en) Double pH spray desulfurizing tower biphase rectification drainage sets
CN208340471U (en) A kind of three-level desulfurizer of flue

Legal Events

Date Code Title Description
GR01 Patent grant