CN206881424U CN201720681197.9U CN201720681197U CN206881424U CN 206881424 U CN206881424 U CN 206881424U CN 201720681197 U CN201720681197 U CN 201720681197U CN 206881424 U CN206881424 U CN 206881424U
Authority
CN
China
Prior art keywords
tower body
spray
cleaning device
chamber
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720681197.9U
Other languages
Chinese (zh)
Inventor
邓智泳
赵广健
邓发利
杨昌良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU XINGUANGHE ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Original Assignee
GUANGZHOU XINGUANGHE ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU XINGUANGHE ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd filed Critical GUANGZHOU XINGUANGHE ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Priority to CN201720681197.9U priority Critical patent/CN206881424U/en
Application granted granted Critical
Publication of CN206881424U publication Critical patent/CN206881424U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of spray cleaning device is the utility model is related to, including:Tower body, with accommodating chamber, the tower body interior edge bottom is sequentially provided with cyclone structure layer and packing layer so that the accommodating chamber is divided into first chamber, second chamber and the 3rd chamber to top, the bottom of the tower body is provided with the air inlet and delivery port connected with the first chamber, and the top of the tower body is provided with the gas outlet with the 3rd chamber;And spraying mechanism, including the first spray assemblies and the second spray assemblies, first spray assemblies are located between the gas outlet and described filler layer and towards the bottom of the tower body, and second spray assemblies are located between described filler layer and cyclone structure layer and towards the top of the tower body.The spray cleaning device efficient stable, good purification, and filler laying dust can be cleared up automatically, prevent packing layer weight increase in use, internal structure of crushing.

Description

Spray cleaning device
Technical field
Waste gas purification field is the utility model is related to, more particularly to a kind of spray cleaning device.
Background technology
Waste gas purification is primarily referred to as such as dust particle, flue gas flue dust, different of industrial waste gas caused by industrial site The work that taste gas, toxic and harmful gas are administered.Common waste gas purification has factory's fume and exhaust gas purifying, workshop dust to give up Gas purification, organic waste-gas purification, the purification of waste gas peculiar smell, acid-base waste gas purifying, purification of chemical waste gas etc..At present, waste gas purification is grasped Work is typically carried out by spray cleaning device.
But traditional spray cleaning device filler easily accumulates dust, it is necessary to frequently take out cleaning, if cleaning is not in time Packing layer avalanche can be caused, damages device.
Utility model content
Based on this, it is necessary to a kind of the problem of easily accumulating dust for above-mentioned spray cleaning device filler, there is provided filler It is not easy to accumulate the spray cleaning device of dust.
Specific technical scheme is as follows:
A kind of spray cleaning device, including:
Tower body, has accommodating chamber, and the tower body interior edge bottom to top is sequentially provided with cyclone structure layer and packing layer to incite somebody to action The accommodating chamber is divided into first chamber, second chamber and the 3rd chamber, and the bottom of the tower body is provided with and the first chamber The air inlet and delivery port of connection, the top of the tower body are provided with the gas outlet with the 3rd chamber;And
Spraying mechanism, including the first spray assemblies and the second spray assemblies, first spray assemblies are located at the outlet Between mouth and described filler layer and towards the bottom of the tower body, second spray assemblies are located at described filler layer and the rotation Between flow structure layer and towards the top of the tower body.
Waste gas can be entered in tower body by the air inlet of bottom and be passed through successively during spray cleaning device work of the present utility model Cross first chamber, second chamber and the 3rd chamber and reach gas outlet.First, the partial particulate thing in waste gas is attached to cyclone structure On layer, and the centrifugal action through cyclone structure layer is thrown to tower body inwall, then drops down onto tower body bottom and is discharged through delivery port, can be preliminary The dust granules thing contained in removing exhaust gas is removed, reduces the dust accumulation of packing layer.Afterwards waste gas by packing layer with spray liquid Fully contact, so as to further remove the pollutant remained in removing exhaust gas.First spray assemblies and the second spray assemblies are respectively from two Spray liquid spray is arrived packing layer by side, on the one hand waste gas can be made more fully to be contacted with spray liquid, improves washing, purifying effect, separately On the one hand the washable grit being adhered in packing layer, reach the effect of automatic cleaning filler, make filler be not easy to accumulate dust, nothing Cleaning need to be frequently taken out, it is time saving and energy saving.
In one of the embodiments, be additionally provided with dehydration layer in the tower body, the dehydration layer be located at the gas outlet with Between first spray assemblies.
In one of the embodiments, the spraying mechanism also includes the 3rd spray assemblies, and the 3rd spray assemblies are set Between second spray assemblies and the cyclone structure layer and towards the bottom of the tower body.
In one of the embodiments, the spraying mechanism also includes the 4th spray assemblies, and the 4th spray assemblies are set In the cyclone structure layer away from the side at the top of the tower body and towards the bottom of the tower body.
In one of the embodiments, the bottom of the tower body is provided with the reservoir connected with the delivery port.
In one of the embodiments, the spray cleaning device also includes fluid circulation mechanism, the fluid circulator Structure includes connecting tube and circulating pump, and described connecting tube one end connects with the reservoir, and the other end connects with the spraying mechanism, The circulating pump is in the connecting tube.
In one of the embodiments, the bottom surface of the tower body has spaced distance to form waste with the reservoir Clean-up port.
In one of the embodiments, the reservoir is provided with support column, and the support column is away from the reservoir One end is connected with the tower body.
In one of the embodiments, described filler layer is filled with multiaspect cavity filling, Pall ring filler and/or cascade ring Filler.
In one of the embodiments, the tower body is provided with multiple observation windows.
Brief description of the drawings
Fig. 1 is the structural representation of the spray cleaning device of an embodiment.
Embodiment
For the ease of understanding the utility model, the utility model is more fully retouched below with reference to relevant drawings State.Preferred embodiment of the present utility model is given in accompanying drawing.But the utility model can come in fact in many different forms It is existing, however it is not limited to embodiment described herein.On the contrary, the purpose for providing these embodiments is made to public affairs of the present utility model Open the understanding more thorough and comprehensive of content.
It should be noted that when element is referred to as " being installed on " another element, it can be directly on another element Or there may also be element placed in the middle.When an element is considered as " connection " another element, it can directly be connected To another element or it may be simultaneously present centering elements.When an element is considered as " connection " another element, it can To be directly to another element or may be simultaneously present centering elements.
Unless otherwise defined, all of technologies and scientific terms used here by the article is led with belonging to technology of the present utility model The implication that the technical staff in domain is generally understood that is identical.It is simply in term used in the description of the present utility model herein The purpose of description specific embodiment, it is not intended that in limitation the utility model.Term as used herein "and/or" includes The arbitrary and all combination of one or more related Listed Items.
As shown in figure 1, a kind of spray cleaning device 100 in the preferred embodiment of the utility model, including the He of tower body 110 Spraying mechanism 120.Tower body 110 has accommodating chamber, and the interior edge bottom of tower body 110 to top is sequentially provided with cyclone structure layer 111 and filled out The bed of material 112 by above-mentioned accommodating chamber to be divided into first chamber 101, the chamber 103 of second chamber 102 and the 3rd.The bottom of tower body 110 Provided with the air inlet 104 and delivery port 105 connected with first chamber 101, the top of tower body 110 is provided with to be connected with the 3rd chamber 103 Logical gas outlet 106.
Spraying mechanism 120 includes the first spray assemblies 121 and the second spray assemblies 122, and the first spray assemblies 121 are located at out Packing layer 112 and eddy flow are located between gas port 106 and packing layer 112 and towards the bottom of tower body 110, the second spray assemblies 122 Between structure sheaf 111 and towards the top of tower body 110.
Waste gas can be entered in tower body by the air inlet 104 of bottom when the spray cleaning device 100 of present embodiment works Successively gas outlet 106 is reached by first chamber 101, the chamber 103 of second chamber 102 and the 3rd.First, the part in waste gas Grain thing is attached on cyclone structure layer 111, and the centrifugal action through cyclone structure layer 111 is thrown to the inwall of tower body 110, then drops down onto The bottom of tower body 110 is discharged through delivery port 105, can tentatively remove the dust granules thing contained in removing exhaust gas, reduces the ash of packing layer 112 Dirt accumulates.Afterwards waste gas by packing layer 112 fully to be contacted with spray liquid, so as to further go the pollution that is remained in removing exhaust gas Thing.First spray assemblies 121 and the second spray assemblies 122 are sprayed to packing layer 112 from both sides by spray liquid respectively, on the one hand may be used Waste gas is more fully contacted with spray liquid, improve washing, purifying effect, it is on the other hand washable to be adhered in packing layer 112 Grit, reach the effect of automatic cleaning filler, make filler be not easy to accumulate dust, it is time saving and energy saving without frequently taking out cleaning.
Alternatively, packing layer 112 is filled with multiaspect cavity filling, Pall ring filler and/or ladder ring packing, has air-flow The features such as resistance is small, liquid distribution is uniform, cyclone structure layer 111 are spiral board, have the characteristics that simple in construction, efficiency high, can To understand, not limited to this, can select as needed.
In one embodiment, dehydration layer 113 is additionally provided with tower body 110, dehydration layer 113 is located at gas outlet 106 and first Between spray assemblies 121.Dehydration layer 113 plays a part of to separate gas-liquid, follow-up so as to avoid influenceing for reducing the humidity of waste gas Corollary equipment.Alternatively, be dehydrated layer 113 be corrugated plating material, it will be understood that not limited to this or other can be with demisting Material.
In one embodiment, spraying mechanism 120 also includes the 3rd spray assemblies 123, and the 3rd spray assemblies 123 are located at the Between two spray assemblies 122 and cyclone structure layer 111 and towards the bottom of tower body 110 so that waste gas can more fully with spray Liquid contact is drenched, while makes that there is more spray liquid on cyclone structure layer 111, so as to which the particulate matter in waste gas is easier to be attached to Cyclone structure layer 111.
Further, spraying mechanism 120 also includes the 4th spray assemblies 124, and the 4th spray assemblies 124 are located at cyclone structure Layer 111, so as to carry out primary wash to waste gas, reduces useless away from the side at the top of tower body 110 and towards the bottom of tower body 110 The quantity of particulate matter in gas.
In one embodiment, the bottom of tower body 110 is provided with the reservoir 130 connected with delivery port 105, is sprayed for accepting Leaching mechanism 120 spray liquid sprayed and the waste residue to drop.
Alternatively, the bottom surface of tower body 110 has spaced distance to form waste clean-up port 131 with reservoir 130, so as to In observing water quality situation and waste residue accumulation in reservoir 130, while operating personnel are facilitated to be cleared up by the waste clean-up port 131 Waste residue in reservoir 130, improve cleaning efficiency.
Further, reservoir 130 is provided with support column 132, support column 132 one end and tower body away from reservoir 130 110 connections, for Auxiliary support tower body 110, make device more stable.Reservoir 130 is additionally provided with drainpipe 133 and overflow pipe 134, it is convenient for draining and prevents that water level is too high.
In one embodiment, spray cleaning device 100 also includes fluid circulation mechanism 140, and fluid circulation mechanism 140 wraps Connecting tube 141 and circulating pump 142 are included, the one end of connecting tube 141 connects with reservoir 130, and the other end connects with spraying mechanism 120, Circulating pump 142 is in connecting tube 141.In this way, spray liquid can be recycled by fluid circulation mechanism 140, so as to reduce spray The consumption of liquid is drenched, reduces cost.
Further, fluid circulation mechanism 140 also includes liquid reserve tank 143, and the one end of liquid reserve tank 143 connects with reservoir 130, The other end connects with connecting tube 141, so as to which connecting tube 141 is connected by liquid reserve tank 143 with reservoir 130.Alternatively, liquid reserve tank Screen pack 1431 is provided with 143, for preventing the waste residue in reservoir 130 from blocking circulating pump 142.It is additionally provided with liquid reserve tank 143 Float switch (not shown), the water level of reservoir 130 is can control by float switch.
Alternatively, tower body 110 is provided with multiple observation windows 114, in order to check machine operation and conveniently enter dimension Shield maintenance.In one embodiment, first chamber 101 and second chamber 102 are respectively equipped with an observation window 114, the 3rd chamber 103, which are dehydrated the two chambers that layer 113 is separated into, is respectively equipped with an observation window 114, so as to easily observe tower body 110 not With the running situation of position, and pointedly carry out Maintenance and Repair.
The efficient stable of spray cleaning device 100 of the present embodiment, floor space is small, both can be used alone, also can be with other Gas purifying equipment supports the use, applied widely (such as organic waste deposit workshop, sludge fermentation workshop, hardware workshop, The industrial waste gases such as organic solvent workshop processing).Also there is the function of laying dust in automatic cleaning tower body 110 simultaneously, it is effectively clear Except filler laying dust, the weight increase in use of packing layer 112, internal structure of crushing are prevented.In addition waste clean-up port is passed through 131, water quality situation and waste residue accumulation in reservoir 130 can be easily observed, facilitates operating personnel to be cleared up by the waste The waste residues that mouth 131 is cleared up in reservoirs 130, improve cleaning efficiency.
Each technical characteristic of embodiment described above can be combined arbitrarily, to make description succinct, not to above-mentioned reality Apply all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, the scope that this specification is recorded all is considered to be.
Embodiment described above only expresses several embodiments of the present utility model, and its description is more specific and detailed, But therefore it can not be interpreted as the limitation to utility model patent scope.It should be pointed out that the common skill for this area For art personnel, without departing from the concept of the premise utility, various modifications and improvements can be made, these are belonged to The scope of protection of the utility model.Therefore, the protection domain of the utility model patent should be determined by the appended claims.

Claims (10)

  1. A kind of 1. spray cleaning device, it is characterised in that including:
    Tower body, has accommodating chamber, and the tower body interior edge bottom to top is sequentially provided with cyclone structure layer and packing layer with by described in Accommodating chamber is divided into first chamber, second chamber and the 3rd chamber, and the bottom of the tower body is provided with to be connected with the first chamber Air inlet and delivery port, the top of the tower body is provided with the gas outlet with the 3rd chamber;And
    Spraying mechanism, including the first spray assemblies and the second spray assemblies, first spray assemblies located at the gas outlet with Between described filler layer and towards the bottom of the tower body, second spray assemblies are located at described filler layer and the eddy flow knot Between structure layer and towards the top of the tower body.
  2. 2. spray cleaning device according to claim 1, it is characterised in that dehydration layer is additionally provided with the tower body, it is described Layer is dehydrated between the gas outlet and first spray assemblies.
  3. 3. spray cleaning device according to claim 2, it is characterised in that the spraying mechanism also includes the 3rd spray group Part, the 3rd spray assemblies are located between second spray assemblies and the cyclone structure layer and towards the bottom of the tower body Portion.
  4. 4. spray cleaning device according to claim 3, it is characterised in that the spraying mechanism also includes the 4th spray group Part, the 4th spray assemblies are located at the cyclone structure layer away from the side at the top of the tower body and towards the bottom of the tower body Portion.
  5. 5. the spray cleaning device according to any one of Claims 1 to 4, it is characterised in that the bottom of the tower body is provided with The reservoir connected with the delivery port.
  6. 6. spray cleaning device according to claim 5, it is characterised in that the spray cleaning device also follows including liquid Ring mechanism, the fluid circulation mechanism include connecting tube and circulating pump, and described connecting tube one end connects with the reservoir, another End connects with the spraying mechanism, and the circulating pump is in the connecting tube.
  7. 7. spray cleaning device according to claim 5, it is characterised in that the bottom surface of the tower body has with the reservoir Spaced distance is to form waste clean-up port.
  8. 8. spray cleaning device according to claim 5, it is characterised in that the reservoir is provided with support column, described The one end of support column away from the reservoir is connected with the tower body.
  9. 9. the spray cleaning device according to any one of Claims 1 to 4, it is characterised in that described filler layer is filled with more Face cavity filling, Pall ring filler and/or ladder ring packing.
  10. 10. the spray cleaning device according to any one of Claims 1 to 4, it is characterised in that the tower body is provided with multiple Observation window.
CN201720681197.9U 2017-06-12 2017-06-12 Spray cleaning device Active CN206881424U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720681197.9U CN206881424U (en) 2017-06-12 2017-06-12 Spray cleaning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720681197.9U CN206881424U (en) 2017-06-12 2017-06-12 Spray cleaning device

Publications (1)

Publication Number Publication Date
CN206881424U true CN206881424U (en) 2018-01-16

Family

ID=61317736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720681197.9U Active CN206881424U (en) 2017-06-12 2017-06-12 Spray cleaning device

Country Status (1)

Country Link
CN (1) CN206881424U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110917804A (en) * 2019-11-08 2020-03-27 青岛海丽达实验室设备有限公司 Spray tower capable of realizing multidimensional spraying treatment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110917804A (en) * 2019-11-08 2020-03-27 青岛海丽达实验室设备有限公司 Spray tower capable of realizing multidimensional spraying treatment

Similar Documents

Publication Publication Date Title
CN104307293B (en) A kind of water curtain combination dust arrester
CN208287764U (en) A kind of chemical emission processing unit that absorbing liquid recycles
CN108744799A (en) A kind of chemical emission spray washing treating column
CN106310855A (en) Deodorization tower device capable of realizing dusty and oily damp and hot gas temperature regulation
CN206881424U (en) Spray cleaning device
CN206252977U (en) Foamed cleaning dedusting cooling system
CN206587552U (en) A kind of Self-excitation wet-type cleaning dust machine
CN202926262U (en) Coal powder dust catcher
CN206956639U (en) A kind of airborne dust filtration system of sweeper
CN104645752B (en) A kind of negative pressure exhausting water-washing type air purification equipment
CN207324416U (en) A kind of mine dedusting and purifying device
CN105862640A (en) Circulation water-air pavement washing device and washing method thereof
CN218834061U (en) Novel washing formula exhaust-gas treatment equipment
CN205308039U (en) Wet dust collector
KR20180116608A (en) Fine dust collector using water spray
CN109647108A (en) A kind of high effect dust cleaner
CN202315699U (en) Multifunctional tower treatment device
CN201701833U (en) Industrial dust recovery device
CN214233293U (en) Spray tower for exhaust-gas treatment
CN211513969U (en) Industrial waste gas treatment equipment system
CN109335926B (en) Elevator with garbage recycling device
KR101404201B1 (en) Apparatus for eliminating paint dust preventing paint absorption
CN109099492B (en) Range hood with automatic cleaning function
CN212440589U (en) High-efficient scrubbing tower
CN216304532U (en) A system of decontaminating for sweeping machine suction pipe way and sweeping machine thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant