CN206874852U - Jack concrete filled steel tube stop valve - Google Patents
Jack concrete filled steel tube stop valve Download PDFInfo
- Publication number
- CN206874852U CN206874852U CN201720526801.0U CN201720526801U CN206874852U CN 206874852 U CN206874852 U CN 206874852U CN 201720526801 U CN201720526801 U CN 201720526801U CN 206874852 U CN206874852 U CN 206874852U
- Authority
- CN
- China
- Prior art keywords
- steel plate
- concrete
- pieces
- fixation
- fixation steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model provides a kind of jacking concrete filled steel tube stop valve, including:One block of big steel plate is as movable steel plate, and the steel plate small using two pieces is as fixation steel plate, and in the side of two pieces of fixation steel plates, respectively a piece concrete pump pipe of welding, one end with of concrete pump pipe have the cuff of concrete pump pipe connection.Slightly expanded concrete is continuously pumped into tubular arch and steel pipe column by short tube of the pump pressure by delivery pipe and with stop valve, until concrete is filled in pipe, after filling concrete terminates, it is only necessary to twitch activity steel plate, it is possible to prevent outside concrete effuser.The utility model can be saved manually, and accelerating construction progress is cost-effective, meet the requirement of intensity, rigidity, stability and globality.
Description
Technical field
It the utility model is related to the visual plant device used on town road bridge and house construction engineering, suitable steel pipe column
With tubular arch pumping concrete construction.
Background technology
In town road bridge and house construction engineering are built, steel pipe column or tubular arch slightly expanded concrete i.e. in steel pipe column or
Filling slightly expanded concrete, the composite construction that two kinds of combinations of materials of different nature are integrally formed in tubular arch.The spy of steel
Property be that intensity is high, there is elastoplasticity;Concrete has preferable anti-compression property, but tensile property is poor.The two is combined, and can make coagulation
Soil is in lateral spacing pressured state, and its compression strength can significantly improve, simultaneously because the effect of fill concrete, it is steady to improve tube wall
Qualitative and resistance to overturning, so as to substantially increase the bearing capacity of structure, impact resistance ability, the Confinement effect of steel pipe carries significantly
The high plastic property of concrete so that the weakness of concrete, particularly Brittleness of High Strength Concrete is overcome.Steel pipe is in itself again
Template and support can not be just needed substantially as the template of resistance to side pressure, during construction.
Steel pipe inner concrete filling using from arch springing to vault or from post bottom to capital continuously be pumped jacking pour in down a chimney apply
Work technique, opened exactly in the arch springing side wall of tubular arch or on Steel Pipe Column downside wall one it is more bigger than concrete delivery pipe caliber
Charging aperture, tubular arch across top set steam vent, with the short tube with stop valve by the outlet and charging of concrete pump
Mouth connection, slightly expanded concrete are continuously pumped into tubular arch and steel pipe column by being pumped by delivery pipe, until being filled in pipe mixed
Solidifying soil.Therefore a short tube with stop valve must be designed.
Utility model content
Technical problem to be solved in the utility model is:Using simple several pieces of steel plates, steel pipes, socket building bolt and set
Hoop, is assembled into a simple delivering concrete stop valve.Ensure to destroy under concrete pumping pressure, will not
Unstability and deformation.To consider simultaneously also will not unstability and deformation when carrying.Assembly welding is simple simultaneously, and weight is light and handy, rises
To the effect for preventing concrete from flowing back.
Technical scheme is used by the utility model solves above-mentioned technical problem:The steel plate big using one piece is used as movable steel
Plate, the steel plate small using two pieces weld 4 block welding plates, two pieces of fixations as fixation steel plate between two pieces of small fixation steel plates
Steel plate welds together, and certain hole is stayed between two pieces of small fixation steel plates, may be inserted into big movable steel plate.In two pieces of fixations
Diameter 145mm circular hole is opened on steel plate, internal diameter 125mm concrete pump pipe is respectively welded in the side of two pieces of fixation steel plates,
One end with of concrete pump pipe has the cuff of concrete pump pipe connection.Respectively opened on two pieces of small fixation steel plates two long
320mm, wide 20mm groove, the depth of groove are the thickness of fixation steel plate.Diameter 135mm circular hole and 4 is provided with movable steel plate
Individual diameter 20mm bolt hole.Movable steel plate may be inserted between two pieces of small fixation steel plates, the bolt hole on movable steel plate
The groove being aligned on fixation steel plate, then movable steel plate and fixation steel plate are connected with 4 diameter 18mm socket bolt and nut
Pick up and, when the circular hole of diameter 135mm on movable steel plate is directed at the pump line hole on fixation steel plate, tighten 4 a diameter of 18mm
The nut for socketing bolt, make nut compressing fixation steel plate using the pulling force of bolt, be to socket bolt to move, so as to ensure
Slip will not be produced between movable steel plate and two pieces of fixation steel plates.Now can utilizes concrete stop valve short tube pumped concrete
Soil.After filling concrete terminates, unscrew the nut of 4 bolts, manually movable steel plate pull out distance 135mm with
On, it is possible to the passage of pump line inner concrete is blocked, plays a part of ending concrete, then withdraws pump truck, wait concrete hard
Can be with dismantling concrete stop valve after change.
Compared with prior art, the utility model has the advantage of:Using traditional stop valve, two rows are opened on pump line
Hole, 3 holes are often arranged, after filling concrete terminates, insertion steel carves son in each hole, and this device can not prevent concrete stream completely
Outside outlet pipe, while 6 holes are provided with pump line, concrete easily overflows from 6 holes in pump concrete.And this practicality is new
Type device, a short tube with stop valve, microdilatancy are welded into using simple several blocks of steel plates, several bolts and concrete pump pipe
Concrete is continuously pumped into tubular arch and steel pipe column by short tube of the pump pressure by delivery pipe and with stop valve, until being filled in pipe
Concrete, after filling concrete terminates, it is only necessary to twitch activity steel plate, it is possible to prevent outside concrete effuser.This invention dress
Putting can save manually, and accelerating construction progress is cost-effective.This invention device is used for multiple times by Practical Project, it was demonstrated that can be with
Meet the requirement of intensity, rigidity, stability and globality.
Brief description of the drawings
Fig. 1 structural plan schematic diagrames of the present utility model.
Fig. 2 structural facades schematic diagrames of the present utility model.
Fig. 3 fixation steel plate floor map of the present utility model.
Fig. 4 movable steel plate floor map of the present utility model.
Embodiment
Concrete lift-up construction process:Processing and fabricating stop valve → jacking mouth cleaning → in jacking mouth position installation stop valve
→ connection concrete delivery pump pipe → reinforcing → jacking steel pipe inner concrete → closing stop valve → dismantling concrete delivery pump pipe
→ concrete curing → concrete cuts stop valve → former material steel plate welding closure after reaching design strength.
The utility model is described in further detail below in conjunction with drawing.
Fig. 1 structural plan schematic diagrames of the present utility model.The steel plate big using one piece is small with two pieces as movable steel plate (A)
Steel plate as fixation steel plate (B), 4 block welding plates (C) are welded between two pieces of small fixation steel plates, two pieces of fixation steel plates are welded
It is connected together, certain hole is stayed between two pieces of small fixation steel plates, may be inserted into big movable steel plate.On two pieces of fixation steel plates
Diameter 145mm circular hole is opened, internal diameter 125mm concrete pump pipe, concrete are respectively welded in the side of two pieces of fixation steel plates
One end with of pump line has the cuff of concrete pump pipe connection.Two long 320mm, width are respectively opened on two pieces of small fixation steel plates
20mm groove, the depth of groove are the thickness of fixation steel plate.Diameter 135mm circular hole and 4 diameters are provided with movable steel plate
20mm bolt hole.Movable steel plate may be inserted between two pieces of small fixation steel plates, and the bolt hole alignment on movable steel plate is solid
Determine the groove on steel plate, then movable steel plate has been connected with fixation steel plate with nut with the 4 diameter 18mm bolt (D) that sockets
Come, when the circular hole of diameter 135mm on movable steel plate is directed at the pump line hole on fixation steel plate, tighten 4 a diameter of 18mm drawing
The nut of connecting bolt, make nut compressing fixation steel plate using the pulling force of bolt, be to socket bolt to move, so as to guarantee activity
Slip will not be produced between steel plate and two pieces of fixation steel plates.Now can utilizes concrete stop valve short tube pump concrete.
After filling concrete terminates, unscrew the nut of 4 bolts, manually movable steel plate is pulled out more than distance 135mm, just
The passage of pump line inner concrete can be blocked, plays a part of ending concrete, then withdraws pump truck, waiting can after concrete hardening
With dismantling concrete stop valve.
Fig. 2 structural facades schematic diagrames of the present utility model.The steel plate big using one piece is small with two pieces as movable steel plate (A)
Steel plate as fixation steel plate (B), 4 block welding plates (C) are welded between two pieces of small fixation steel plates, two pieces of fixation steel plates are welded
It is connected together, certain hole is stayed between two pieces of small fixation steel plates, may be inserted into big movable steel plate.On two pieces of fixation steel plates
Diameter 145mm circular hole is opened, internal diameter 125mm concrete pump pipe, concrete are respectively welded in the side of two pieces of fixation steel plates
One end with of pump line has the cuff (E) of concrete pump pipe connection.Be provided with movable steel plate diameter 135mm circular hole and 4
Diameter 20mm bolt hole.Movable steel plate may be inserted between two pieces of small fixation steel plates, as diameter 135mm on movable steel plate
Circular hole alignment fixation steel plate on pump line hole when, tighten the 4 a diameter of 18mm nut for socketing bolt (D), utilize bolt
Pulling force make nut compressing fixation steel plate, be to socket bolt to move, so as to guarantee activity steel plate and two pieces of fixation steel plates it
Between will not produce slip.
Fig. 3 fixation steel plate floor map of the present utility model.The size of fixation steel plate is 400mm × 250mm × 20mm.
Two long 320mm, wide 20mm groove are respectively opened on small fixation steel plate, the depth of groove is the thickness of fixation steel plate.In fixed steel
Diameter 145mm circular hole is provided with plate.
Fig. 4 movable steel plate floor map of the present utility model.The size of movable steel plate is 560mm × 240mm × 20mm.
Diameter 135mm circular hole and 4 diameter 20mm bolt hole (F) are provided with movable steel plate.Movable steel plate may be inserted into two
Between the small fixation steel plate of block, the groove on bolt hole on movable steel plate alignment fixation steel plate, then with 4 diameter 18mm's
Socket bolt and nut to connect movable steel plate and fixation steel plate, when the circular hole alignment of diameter 135mm on movable steel plate is solid
When determining the pump line hole on steel plate, the 4 a diameter of 18mm nut for socketing bolt is tightened, makes nut compressing using the pulling force of bolt
Fixation steel plate, it is to socket bolt to move, so as to which slip will not be produced between guarantee activity steel plate and two pieces of fixation steel plates.
Claims (3)
1. one kind jacking concrete filled steel tube stop valve, it is characterised in that:One block of big steel plate as movable steel plate, two pieces small
Steel plate welds 4 block welding plates between two pieces of small fixation steel plates, two pieces of fixation steel plates is welded on one as fixation steel plate
Rise, stay certain hole between two pieces of small fixation steel plates, insert big movable steel plate.
2. jacking concrete filled steel tube stop valve according to claim 1, it is characterised in that:Opened on two pieces of fixation steel plates
Diameter 145mm circular hole, internal diameter 125mm concrete pump pipe, concrete pump are respectively welded in the side of two pieces of fixation steel plates
One end with of pipe has the cuff of concrete pump pipe connection, and two long 320mm, wide 20mm groove are respectively opened on fixation steel plate, groove
Depth is the thickness of fixation steel plate.
3. jacking concrete filled steel tube stop valve according to claim 1, it is characterised in that:Diameter is provided with movable steel plate
The bolt hole of 135mm circular hole and 4 diameter 20mm, movable steel plate are inserted between two pieces of small fixation steel plates, movable steel plate
On bolt hole alignment fixation steel plate on groove, then with 4 diameter 18mm socket bolt and nut movable steel plate with
Fixation steel plate connects.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720526801.0U CN206874852U (en) | 2017-05-12 | 2017-05-12 | Jack concrete filled steel tube stop valve |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720526801.0U CN206874852U (en) | 2017-05-12 | 2017-05-12 | Jack concrete filled steel tube stop valve |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206874852U true CN206874852U (en) | 2018-01-12 |
Family
ID=61339933
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720526801.0U Active CN206874852U (en) | 2017-05-12 | 2017-05-12 | Jack concrete filled steel tube stop valve |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206874852U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109469329A (en) * | 2018-10-30 | 2019-03-15 | 浙江中南建设集团有限公司 | One kind can have enough to meet the need steel pipe column pumping Lifting Equipment and jacking interface construction method |
CN109505250A (en) * | 2018-12-07 | 2019-03-22 | 中铁局集团厦门建设工程有限公司 | A kind of filling concrete method of steel tube arch rib |
CN114109042A (en) * | 2022-01-12 | 2022-03-01 | 山东三箭建设工程股份有限公司 | Check valve for construction of concrete filled steel tubular column by jacking method and application method thereof |
-
2017
- 2017-05-12 CN CN201720526801.0U patent/CN206874852U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109469329A (en) * | 2018-10-30 | 2019-03-15 | 浙江中南建设集团有限公司 | One kind can have enough to meet the need steel pipe column pumping Lifting Equipment and jacking interface construction method |
CN109469329B (en) * | 2018-10-30 | 2021-04-23 | 浙江中南建设集团有限公司 | Recyclable steel pipe column pumping jacking equipment and jacking interface construction method |
CN109505250A (en) * | 2018-12-07 | 2019-03-22 | 中铁局集团厦门建设工程有限公司 | A kind of filling concrete method of steel tube arch rib |
CN114109042A (en) * | 2022-01-12 | 2022-03-01 | 山东三箭建设工程股份有限公司 | Check valve for construction of concrete filled steel tubular column by jacking method and application method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206874852U (en) | Jack concrete filled steel tube stop valve | |
CN103556624B (en) | Adapter sleeve, to produce and method of attachment containing the prefabricated units of this adapter sleeve and prefabricated units | |
WO2017107960A1 (en) | Connection device for use in vertical uplift resistance load of pre-buried foundation pile | |
CN106351401B (en) | Half assembled super-high strength steel pipe slip casting overlaps rod structure and production method | |
CN106150060A (en) | Based on assembled wall-connecting piece exterior wall scaffold system and construction method | |
CN106988455A (en) | Steel plate concrete shear wall scene splicing node and its construction method | |
CN203905485U (en) | Form for reservation of water service pipe channel in cast-in-place concrete wall | |
CN206426071U (en) | A kind of tunneling shield section of jurisdiction storing unit | |
CN209775994U (en) | High strength sculpture structure | |
CN103882994B (en) | Ring beam steel bar connecting structure and ring beam construction method | |
CN204024068U (en) | A kind of hoisting steel pipe pillar concrete connection control device | |
CN107447975A (en) | Exterior wall scaffold tapered cup nut wall-connecting piece | |
CN207308898U (en) | A kind of coated sand core shooting machine adds sand system | |
CN102650158A (en) | Connecting device used in casting of shear walls in upper and lower layers | |
CN202359553U (en) | Pure mechanical connection structure between piles | |
KR100916672B1 (en) | Mast fixation of construction lift embed anchor and spatial-temporal method | |
CN104153464A (en) | Steel pipe concrete jacking inserting plate type control device and method for connecting steel pipe concrete jacking inserting plate type control device to steel pipe column | |
CN205116685U (en) | Can dismantle shaped steel of encorbelmenting platform of unloading | |
CN202559746U (en) | Continuing device for upper-lower-layer shear wall during pouring | |
CN104099870B (en) | Roller type prefabricated box girder internal mold demoulding device as well as manufacturing, construction and operation method thereof | |
CN206158011U (en) | Strong steel pipe slip casting coincide post structure of half -assembled formula superelevation | |
CN204140090U (en) | A kind of Novel circular steel pipe concrete bracket link | |
CN206707283U (en) | A kind of unidirectional fishbolt fixed form root device of built-in type | |
CN206346188U (en) | A kind of steel reinforcement cage | |
CN206607586U (en) | A kind of self-balancing grouting under pressure steel tube for soil-nail structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |