CN206873316U - A kind of device of reinforced steel concrete pier stud - Google Patents
A kind of device of reinforced steel concrete pier stud Download PDFInfo
- Publication number
- CN206873316U CN206873316U CN201720713220.8U CN201720713220U CN206873316U CN 206873316 U CN206873316 U CN 206873316U CN 201720713220 U CN201720713220 U CN 201720713220U CN 206873316 U CN206873316 U CN 206873316U
- Authority
- CN
- China
- Prior art keywords
- frp cloth
- bottom plate
- ground tackle
- tension ground
- anchor hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of device of reinforced steel concrete pier stud.The device includes two bottom plates, two tension ground tackles, tensioning screw rod and FRP cloth;Bottom plate wraps up direction both ends inverted arc angle along FRP cloth;Bottom plate opens up bottom plate anchor hole and installation anchor hole respectively perpendicular to FRP cloth parcel direction both ends;Tension ground tackle upper and lower ends respectively open up two tension ground tackle anchor holes perpendicular to FRP cloth direction;Tension ground tackle opens up two screws respectively along parallel to FRP cloth parcel direction;FRP cloth both ends are wrapped in 2 ~ 3 circle on bottom plate, and FRP cloth surround Reinforced Concrete Pier Column Reinforcing opening position one week;The installation anchor hole at the tension ground tackle anchor hole alignment bottom plate both ends at tension ground tackle both ends, crab-bolt is through tension ground tackle anchor hole and installs anchor hole;Tensioning screw rod is arranged in the screw of tension ground tackle respectively;Anchoring is bonded on two bottom plates with FRP cloth.The bottom plate chooses flat board or arc plate.Present apparatus consolidation effect is good, and simple structure is easy to operate.
Description
Technical field
The utility model belongs to the structural strengthening such as science of bridge building, architectural engineering field, and more particularly to a kind of reinforced steel mixes
The device of solidifying knoll post.
Background technology
Fibre reinforced composites FRP(Fiber Reinforced Plastic)Good mechanical performance, chemical property are steady
It is fixed, have high-strength, lightweight, it is corrosion-resistant, play the characteristics such as mould is high, proportion is small, its thermal coefficient of expansion is close with concrete, is answered extensively
Reinforcing for concrete structure.Common constraint of the FRP material to concrete component belongs to " passive bound ", only in concrete
Fully under expansion, FRP material just starts to play effect of contraction, a certain degree of Stress resort, the high-strength performance of FRP material be present
It is not in full use.Pre-stress FRP cloth reinforcement technique is a kind of active reinforcement means, utilizes FRP high-strength characteristic so that
The concrete column of hoop constraint has the initiative three dimension stress state, improves the bearing capacity, shock resistance, consumption of performance of concrete column confined
Can ability, ductile performance.
At present, the stretching and anchoring device of pre-stress FRP cloth reinforced concrete pier stud is mostly permanent, and anchorage is not reproducible
Utilize, cost is higher.And anchorage is exposed at pier stud surface, architectural appearance is not only influenceed, and the structure that easily comes into the picture adds
Consolidate, so as to psychologically be thrown doubt upon to the safety of structure.In addition, in conventional tension ground tackle FRP cloth be wrapped in intermediate plate or
On person's roller bearing, by tighten both ends tensioning screw rod apply prestressing force, when FRP cloth is wider or prestressing force is larger, intermediate plate or
Roller bearing flexural deformation is larger so that FRP cloth discontinuity and prestress application deficiency.
The content of the invention
The purpose of this utility model is to provide a kind of device of reinforced steel concrete pier stud.
What the utility model was realized in:A kind of device of reinforced steel concrete pier stud, including two bottom plates, two
Tension ground tackle, tensioning screw rod and FRP cloth;Bottom plate wraps up direction both ends inverted arc angle along FRP cloth;Bottom plate is perpendicular to FRP cloth parcel side
Open up bottom plate anchor hole and installation anchor hole respectively to both ends;Tension ground tackle upper and lower ends respectively open up two perpendicular to FRP cloth direction
Individual tension ground tackle anchor hole;Tension ground tackle opens up two screws respectively along parallel to FRP cloth parcel direction;FRP cloth both ends are wound
2 ~ 3 circle on bottom plate, FRP cloth surround Reinforced Concrete Pier Column Reinforcing opening position one week;The tension ground tackle anchor at tension ground tackle both ends
The installation anchor hole at keyhole alignment bottom plate both ends, crab-bolt is through tension ground tackle anchor hole and installs anchor hole;Tensioning screw rod is distinguished
It is arranged in the screw of tension ground tackle;Anchoring is bonded on two bottom plates with FRP cloth.
The bottom plate chooses flat board or arc plate.
The utility model contrasts with prior art, and advantage is:(1)Using bracing means of the present utility model to FRP
After cloth stretch-draw anchor, tension ground tackle can be removed conveniently, reuse, and save material, cost-effective, environmental protection and energy saving.(2)After reinforcing
Pier stud cosmetic variation it is little, do not influence after reinforcing the sight built and using function.(3)Stretch-draw anchor dress of the present utility model
Simple structure is put, it is easy to operate, it is cost-effective.
Brief description of the drawings
Fig. 1 is that the device of reinforced steel concrete square column in the utility model embodiment carries out the overall installation of stretch-draw anchor
Figure.
Fig. 2 is the final use state diagram of the device of reinforced steel concrete square column in the utility model embodiment.
Fig. 3 is that the device of reinforced steel concrete square column in the utility model embodiment carries out the plan of stretch-draw anchor.
Fig. 4 is the final use state plan of the device of reinforced steel concrete square column in the utility model embodiment.
Fig. 5 is the structural representation of the bottom plate used in the utility model embodiment.
Fig. 6 is the structural representation of the tension ground tackle used in the utility model embodiment.
Fig. 7 is the structural representation for the FRP cloth that bottom plate and tension ground tackle are connected in the utility model embodiment.
Marked in figure:1- bottom plates;11- bottom plate anchor holes;12- installs anchor hole;13- crab-bolts;2- tension ground tackles;21-
Draw anchorage anchor hole;22- screws;3- tensioning screw rods;4-FRP cloth;5- reinforced concrete square columns;6- anchoring FRP cloths.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
Embodiment:
As shown in Fig. 1 ~ 7, the present embodiment is using reinforced concrete square columns as object is reinforced, using pre-stress FRP cloth to reinforcing bar
Concrete square column is reinforced, and FRP cloth width is 150mm.It is specific as follows:
A kind of device of reinforced steel concrete square column, including two bottom plates, 1, two tension ground tackle 2, the and of tensioning screw rod 3
FRP cloth 4.
Bottom plate 1 wraps up direction both ends inverted arc angle along FRP cloth 4, in case it scratches FRP cloth 4.Bottom plate 1 wraps perpendicular to FRP cloth 4
Wrap up in direction both ends and open up bottom plate anchor hole 11 and installation anchor hole 12 respectively.
The upper and lower ends of tension ground tackle 2 respectively open up two tension ground tackle anchor holes 21 perpendicular to the direction of FRP cloth 4.Tension ground tackle 2
Two screws 22 are opened up respectively along direction is wrapped up parallel to FRP cloth 4.
The surface of bottom plate 1 uniformly applies glue, and the both ends of FRP cloth 4 wind 2 circles after applying glue on bottom plate, make 4 liang of FRP cloth
End fixation is pasted onto on bottom plate 1.After colloid solidification, FRP cloth 4 reinforces opening position one week around reinforced concrete square columns 5.Tensioning
The tension ground tackle anchor hole 21 at the both ends of anchorage 2 is directed at the installation anchor hole 12 at the both ends of bottom plate 1, and crab-bolt 13 passes through tension ground tackle crab-bolt
Hole 21 and installation anchor hole 12, make bottom plate 1 be fixedly connected with tension ground tackle 2.Tensioning screw rod 3 is arranged in tension ground tackle 2 respectively
In screw 22.
The bottom plate 1 chooses the flat board being close to reinforced concrete square columns surface.
Specific reinforcing step is as follows:
(1)It is determined that the reinforcing position being reinforced on reinforced concrete square columns 5;It need to carry out in advance should in the ejection of its surface with the line of ink marker
The position range of power FRP cloth parcel, is polished surface, filling-up hole, then will be reinforced reinforced concrete square columns 5 with sander
Four corners carry out polishing chamfering, finally wrap up scope to the FRP cloth for being reinforced the surface of reinforced concrete square columns 5 and uniformly brush one
Layer epoxy adhesive layer.
(2)Determine the cutting length of FRP cloth 4 and cutting.Square Reinforced Concrete at cutting length=parcel location of FRP cloth 4
The girth of post 5 adds 2 times of the girth of bottom plate 1.
(3)The surface of bottom plate 1 uniformly applies glue, and 2 circles are wound on bottom plate 1 after the both ends gluing of FRP cloth 4.Make 4 liang of FRP cloth
End fixation is pasted onto on bottom plate 1.After colloid solidification, the tension ground tackle anchor hole 21 at the both ends of tension ground tackle 2 is directed at the both ends of bottom plate 1
Anchor hole 12 is installed, crab-bolt 13 fixes bottom plate 1 and tension ground tackle 2 through tension ground tackle anchor hole 21 and installation anchor hole 12
Connection.
(4)The FRP cloth 4 for connecting bottom plate 1 and tension ground tackle 2 that step (3) is obtained is looped around reinforced concrete square columns 5
Reinforcing opening position one week, synchronously tighten tensioning screw rod 3, prestressing force applied to FRP cloth 4.
(5)After the prestressing force for putting on FRP cloth 4 reaches predeterminated level.Glue is filled into the surface of FRP cloth 4, and makes it
Fully infiltration, wait and paste adhesive curing.
(6)Drilled at the bottom plate anchor hole 11 at the both ends of bottom plate 1 to reinforced concrete square columns 5, thereafter by plastic expansion plug
Knocked in glue hammer in hole.Insert setscrew and be screwed into reinforced concrete square columns 5.Bottom plate 1 is fixed on into institute's reinforced steel to mix
On solidifying earthwork post 5.
(7)After the stickup adhesive curing applied in FRP cloth 4, unscrew the crab-bolt 13 between tension ground tackle 2 and bottom plate 1, unload
Tension ground tackle 2 and tensioning screw rod 3.Drill to reinforced concrete square columns 5 at installation anchor hole 12, thereafter use plastic expansion plug
Glue hammer is knocked in hole, is inserted setscrew and is screwed into reinforced concrete square columns 5.
(8)The bond-anchorage FRP cloth 4 on two bottom plates 1, ensure to apply the bond-anchorage length of prestressed FRP cloth 4
Degree.
Note:If the object that the present embodiment is reinforced is Reinforced Concrete Circular Cylinder, bottom plate chooses the arc being close to periphery
Plate, and omit step(1)In to four corners of square column carry out polish chamfering operation, remaining step all same.
Specific embodiment described herein is only to the utility model spirit explanation for example.Belonging to the utility model
Those skilled in the art can be made some modifications or supplement to described specific embodiment or be substituted using similar mode,
But without departing from spirit of the present utility model or surmount scope defined in appended claims.
Claims (1)
1. a kind of device of reinforced steel concrete pier stud, it is characterised in that the device includes two bottom plates (1), two tensioning anchors
Have (2), tensioning screw rod (3) and FRP cloth (4);Bottom plate (1) wraps up direction both ends inverted arc angle along FRP cloth (4);Bottom plate (1) perpendicular to
FRP cloth (4) parcel direction both ends open up bottom plate anchor hole (11) and installation anchor hole (12) respectively;Tension ground tackle (2) up and down two
End respectively opens up two tension ground tackle anchor holes (21) perpendicular to FRP cloth (4) direction;Tension ground tackle (2) is along parallel to FRP cloth (4)
Parcel direction opens up two screws (22) respectively;Winding 2 ~ 3 is enclosed on bottom plate (1) after the gluing of FRP cloth (4) both ends, FRP cloth (4)
It surround Reinforced Concrete Pier Column Reinforcing opening position one week;Tension ground tackle anchor hole (21) the alignment bottom plate at tension ground tackle (2) both ends
(1) the installation anchor hole (12) at both ends, crab-bolt (13) is through tension ground tackle anchor hole (21) and installs anchor hole (12);Tensioning spiral shell
Bar (3) is arranged in the screw (22) of tension ground tackle (2) respectively;Anchoring is bonded on two bottom plates (1) with FRP cloth (6);
The bottom plate (1) chooses flat board or arc plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720713220.8U CN206873316U (en) | 2017-06-19 | 2017-06-19 | A kind of device of reinforced steel concrete pier stud |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720713220.8U CN206873316U (en) | 2017-06-19 | 2017-06-19 | A kind of device of reinforced steel concrete pier stud |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206873316U true CN206873316U (en) | 2018-01-12 |
Family
ID=61334303
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720713220.8U Expired - Fee Related CN206873316U (en) | 2017-06-19 | 2017-06-19 | A kind of device of reinforced steel concrete pier stud |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206873316U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108252228A (en) * | 2018-02-09 | 2018-07-06 | 桂林理工大学 | A kind of prestressed fiber cloth reinforced device for reinforced steel concrete pier stud |
-
2017
- 2017-06-19 CN CN201720713220.8U patent/CN206873316U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108252228A (en) * | 2018-02-09 | 2018-07-06 | 桂林理工大学 | A kind of prestressed fiber cloth reinforced device for reinforced steel concrete pier stud |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107059665A (en) | A kind of method of utilization pre-stress FRP cloth reinforced steel concrete pier stud | |
CN107059663A (en) | A kind of device of utilization pre-stress FRP cloth reinforced steel concrete pier stud | |
CN103195255B (en) | Construction method for prestressed carbon-fiber reinforced plastic (CFRP) reinforced concrete beam | |
CN102121316B (en) | Construction method for reinforcing circular structures by pre-tensioned high-strength fiber cloth | |
CN106522577A (en) | Construction method of prestress carbon fiber cloth reinforced reinforced-concrete square pillar | |
CN101748900B (en) | Reinforcement method of reinforced concrete beam column node | |
CN201581645U (en) | Device for applying prestress on loop-type composite fiber cloth | |
CN102425311B (en) | Concrete structure reinforcing method based on near surface mounted prestressed FRP (Fiber Reinforced Polymer) | |
CN1936206A (en) | Steel-continuous-fiber composite-rib reinforced concrete earthquake-resisting structure | |
CN105781141B (en) | A kind of fiber knitted net enhancing cement base composite board reinforced for concrete flexural member and preparation method thereof | |
CN105888277B (en) | Prestressed carbon cloth reinforced armored concrete column construction method | |
CN101122177A (en) | Usage method of prestressed thin fiber board in concrete architecture | |
CN107794849A (en) | Using the construction method of the prestressed fiber cloth reinforced post of detachable tension ground tackle | |
CN107905126B (en) | Detachable prestressed fiber cloth tensioning and anchoring device | |
CN206873316U (en) | A kind of device of reinforced steel concrete pier stud | |
CN107268459B (en) | Construction method for prestressed fiber cloth reinforced concrete pier column | |
CN102261166A (en) | Fiber reinforced polymer (FRP) sheet anchor device and anchoring method thereof | |
CN108252228A (en) | A kind of prestressed fiber cloth reinforced device for reinforced steel concrete pier stud | |
CN201588411U (en) | Strengthening device of beam column node of reinforced concrete | |
CN109115106A (en) | Anchoring body producing device and anchoring interface strain piece method of attaching in model test | |
CN208183557U (en) | A kind of prestressed fiber cloth reinforced device | |
CN107059664A (en) | Pre-stressed fiber cloth rotary self-locking formula stretching and anchoring device | |
CN205421038U (en) | A integrated configuration for combination strengthening T roof beam | |
CN108487086A (en) | A kind of construction method using prestressed fiber cloth reinforced Reinforced Concrete Pier Column | |
CN205577465U (en) | Utilize device of FRP reinforcing concrete shear force wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180112 Termination date: 20190619 |