CN206861498U - A kind of biomass boiler central heating system - Google Patents

A kind of biomass boiler central heating system Download PDF

Info

Publication number
CN206861498U
CN206861498U CN201720474691.8U CN201720474691U CN206861498U CN 206861498 U CN206861498 U CN 206861498U CN 201720474691 U CN201720474691 U CN 201720474691U CN 206861498 U CN206861498 U CN 206861498U
Authority
CN
China
Prior art keywords
boiler
steam
unit
gasification furnace
control valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720474691.8U
Other languages
Chinese (zh)
Inventor
董燕萍
刘光华
王新强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DONGGUAN BAIDA NEW ENERGY Co Ltd
Original Assignee
DONGGUAN BAIDA NEW ENERGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DONGGUAN BAIDA NEW ENERGY Co Ltd filed Critical DONGGUAN BAIDA NEW ENERGY Co Ltd
Priority to CN201720474691.8U priority Critical patent/CN206861498U/en
Application granted granted Critical
Publication of CN206861498U publication Critical patent/CN206861498U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Gasification And Melting Of Waste (AREA)
  • Solid-Fuel Combustion (AREA)
  • Control Of Steam Boilers And Waste-Gas Boilers (AREA)

Abstract

The purpose of this utility model is to propose a kind of biomass boiler central heating system that can accurately control steam flow and flow, so as to meet multi-user's demand, realizes commercial operation, improves efficiency of energy utilization.Biomass boiler central heating system of the present utility model includes:Gasification furnace, the gasification furnace are provided with gasifier control system device;Boiler, it is connected with gasification furnace, the boiler is provided with the boiler controller for being used for controlling boiler wind speed adjustment;At least two steam use unit, and each steam is connected using unit by the steam output circuit of independent pipeline and boiler;It is critical that being equipped with electric control valve in every independent pipeline, the electric control valve, boiler controller, gasifier control system device communicate with a central controller connect respectively.The utility model is realized using gasification furnace, boiler to supply steam to multi-user simultaneously, and working automation degree is higher, control is simpler, security is higher, is provided the foundation for commercial operation.

Description

A kind of biomass boiler central heating system
Technical field
The utility model belongs to field of new energy technologies, and in particular to a kind of biomass boiler central heating system.
Background technology
Biomass boiler, such as gasification furnace is said, starting extensive use as a kind of new energy, but it is most main at present The application mode wanted is the heat supply or supply to sole user, when number of users is more, is just difficult to control source of the gas or heat The distribution flow in source, therefore, it is difficult to be commercialized.And if an only user, the scale of heat supply or supply is difficult to scale up, the energy The efficiency utilized is also just ranging in low level always.
The content of the invention
The purpose of this utility model, which is that proposition is a kind of, can accurately control the biomass boiler of steam flow and flow to concentrate Heating system, so as to meet multi-user's demand, commercial operation is realized, improves efficiency of energy utilization.
Biomass boiler central heating system of the present utility model includes:Gasification furnace, for biomass material to be converted into Combustion gas, the gasification furnace, which is provided with, to be used to control gasification furnace air intake, emptying, the gasifier control system device of charging;Boiler, with gasification furnace phase Even, steam is produced using the combustion gas, the boiler is provided with the boiler controller for being used for controlling boiler wind speed adjustment;At least two steam Vapour uses unit, and each steam is connected using unit by the steam output circuit of independent pipeline and boiler;It is critical that Be equipped with electric control valve in every independent pipeline, the electric control valve, boiler controller, gasifier control system device respectively with The communication connection of one central controller.
The operation principle of above-mentioned biomass boiler central heating system is as follows:
Central controller detects state of each steam using the electric control valve of unit, and according to the state of all electric control valves Calculate total steam demand amount, then according to total steam demand amount come control the air intake of the air distribution of boiler and gasification furnace, Charging etc., and start gasification furnace output combustion gas emptying when total steam demand amount is zero, so as to stop continuing to boiler furnace Supply combustion gas.Above-mentioned control process avoid the unordered work of gasification furnace, boiler and caused by steam, combustion gas wastes and gasification The waste of fuel of stove, and improve the security of gasification furnace and boiler.
Further, the water inlet of the boiler is connected with storage tank, and the steam outlet of boiler passes through waste heat recovery pipe Road is connected with storage tank, and the waste heat recovery pipeline is provided with waste heat electric control valve, the waste heat electric control valve and central controller Communication connection.In regular supply steam, waste heat electric control valve is closed;When all steam need not using unit During steam(When i.e. all steam are turned off using the electric control valve of unit), central controller while boiler combustion is stopped, Open waste heat electric control valve so that remaining steam is transported in storage tank by waste heat recovery pipeline in boiler, avoids boiler Air pressure is too high;Steam will heat when running into the water in storage tank to water, and be converted into hot water, and so later boiler is again During startup, it is possible to directly using the water by preheating, reduce the waste of the energy.
Further, each steam is equipped with steam-flow meter and the taximeter being connected with steam-flow meter using unit, Each steam is communicated using the taximeter of unit with the steam and connected respectively using the electric control valve of unit.Each steam uses single Position can be using taximeter come the steam service condition of Real Time Observation oneself unit, and can be according to the charging of taximeter Situation and actual steam demand control the aperture of electric control valve.
Further, the taximeter is provided with memory cell, and such Charging Detail Record unit can realize the storage of pre-payment and pre- The real-time update of payment, so as to electric control valve corresponding to the automatic closing when pre-payment is finished.
Further, the central controller is communicated using the taximeter of unit with each steam connect respectively, center control Device processed can be easy to automatic steam control and disbursement and sattlement with each steam of remote monitoring using the paying dues of unit, steam behaviour in service.
Biomass boiler central heating system of the present utility model is by setting electric control valve, steam-flow meter and taximeter Deng, realize using gasification furnace, boiler come simultaneously to multi-user supply steam, and cause whole heating system working automation Degree is higher, control is simpler, security is higher, so as to be provided the foundation for commercial operation.
Brief description of the drawings
Fig. 1 is the schematic diagram of biomass boiler central heating system of the present utility model.
Embodiment
Below against accompanying drawing, by the description to embodiment, to specific embodiment of the present utility model as involved by The shape of each component, construction, the mutual alignment and annexation between each several part, the effect of each several part and operation principle etc. make It is further to describe in detail.
Embodiment 1:
As illustrated, the biomass boiler central heating system of the present embodiment includes:Gasification furnace, for by biomass material Combustion gas is converted into, the gasification furnace, which is provided with, to be used to control gasification furnace air intake, emptying, the gasifier control system device of charging;Boiler, with gas Change stove to be connected, produce steam using the combustion gas, the boiler is provided with the boiler controller for being used for controlling boiler wind speed adjustment;Two Steam uses unit, and each steam is connected using unit by the steam output circuit of independent pipeline and boiler;Wherein, often Electric control valve and steam-flow meter are equipped with independent pipeline described in bar, each steam is all provided with and its steam flow using unit Count the taximeter of connection;Each steam uses electric control valve, steam-flow meter, taximeter and boiler controller, the gas of unit Change furnace controller and communicate connection with a central controller respectively.
The water inlet of boiler is connected with storage tank, and the steam outlet of boiler passes through waste heat recovery pipeline and storage tank phase Even, the waste heat recovery pipeline is provided with waste heat electric control valve, and the waste heat electric control valve connects with central controller communication.
In the present embodiment, central controller PC, related software is so combined, it is possible to achieve each steam is used single Position carries out Energy Management Contract.
The operation principle of above-mentioned biomass boiler central heating system is as follows:
Central controller detects state of each steam using the electric control valve of unit, and according to the state of all electric control valves Calculate total steam demand amount, then according to total steam demand amount come control the air intake of the air intake of boiler and gasification furnace, Charging etc., and start the emptying of gasification furnace when total steam demand amount is zero, continue to produce so as to stop steam, avoid pot Furnace gas presses through height.Central controller can be easy to steam control with each steam of remote monitoring using the paying dues of unit, steam behaviour in service System and disbursement and sattlement.Above-mentioned control process avoid the unordered work of gasification furnace, boiler and caused by steam, combustion gas waste and The waste of fuel of gasification furnace, and improve the security of gasification furnace and boiler.
Each steam using unit can using taximeter come the steam service condition of Real Time Observation oneself unit, and The aperture of electric control valve can controlled according to the charging case and actual steam demand of taximeter.In addition, taximeter is set There is memory cell, such Charging Detail Record unit can realize the storage of pre-payment and the real-time update of pre-payment, so as in advanced charge Electric control valve corresponding to automatic closing when complete.
In regular supply steam, waste heat electric control valve is closed;When all steam need not using unit During steam(When i.e. all steam are turned off using the electric control valve of unit), central controller while boiler combustion is stopped, Open waste heat electric control valve so that remaining steam is transported in storage tank by waste heat recovery pipeline in boiler, avoids boiler Air pressure inside is too high;Steam will heat when running into the water in storage tank to water, and be converted into hot water, so later boiler During restarting, it is possible to directly using the water by preheating, reduce the waste of the energy.
Software design patterns in above-mentioned control process may be referred to charge management system, gasifier control system system and boiler implosion System, this is prior art, therefore here is omitted.

Claims (5)

1. a kind of biomass boiler central heating system, including:
Gasification furnace, for biomass material to be converted into combustion gas, the gasification furnace be provided be used to controlling gasification furnace air intake, emptying, The gasifier control system device of charging;
Boiler, it is connected with gasification furnace, produces steam using the combustion gas, the boiler is provided with the pot for being used for controlling boiler wind speed adjustment Furnace controller;
At least two steam use unit, and each steam passes through the steam output circuit of independent pipeline and boiler using unit Connection;
Characterized in that, it is equipped with electric control valve, the electric control valve, boiler controller, gas in every independent pipeline Change furnace controller and communicate connection with a central controller respectively.
2. biomass boiler central heating system according to claim 1, it is characterised in that the water inlet of the boiler connects Storage tank is connected to, the steam outlet of boiler is connected by waste heat recovery pipeline with storage tank, and the waste heat recovery pipeline is provided with Waste heat electric control valve, the waste heat electric control valve connect with central controller communication.
3. biomass boiler central heating system according to claim 1 or 2, it is characterised in that each steam uses unit Be equipped with steam-flow meter and the taximeter being connected with steam-flow meter, each steam using unit electric control valve respectively with this Steam is connected using the taximeter communication of unit.
4. biomass boiler central heating system according to claim 3, it is characterised in that the taximeter is provided with storage Unit.
5. biomass boiler central heating system according to claim 4, it is characterised in that the central controller difference Communicated and connected using the taximeter of unit with each steam.
CN201720474691.8U 2017-05-02 2017-05-02 A kind of biomass boiler central heating system Expired - Fee Related CN206861498U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720474691.8U CN206861498U (en) 2017-05-02 2017-05-02 A kind of biomass boiler central heating system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720474691.8U CN206861498U (en) 2017-05-02 2017-05-02 A kind of biomass boiler central heating system

Publications (1)

Publication Number Publication Date
CN206861498U true CN206861498U (en) 2018-01-09

Family

ID=60822365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720474691.8U Expired - Fee Related CN206861498U (en) 2017-05-02 2017-05-02 A kind of biomass boiler central heating system

Country Status (1)

Country Link
CN (1) CN206861498U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111057584A (en) * 2019-12-27 2020-04-24 长沙万利节能科技有限公司 System and method for controlling steam production of biomass gasification furnace combined boiler

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111057584A (en) * 2019-12-27 2020-04-24 长沙万利节能科技有限公司 System and method for controlling steam production of biomass gasification furnace combined boiler

Similar Documents

Publication Publication Date Title
CN102519067A (en) Heating energy saving device with additional back pressure generator for extraction condensing unit and heating energy saving method
CN104390260B (en) A kind of biomass heating steam generator system
CN206861498U (en) A kind of biomass boiler central heating system
CN202540459U (en) Waste steam waste heat recovery device of gas brickyard
CN104654385B (en) Waste heat recycling device
CN106196258A (en) Heating water and saving energy system and control method thereof
CN103090359A (en) Electric-heating steam accumulator
CN102519274A (en) Intelligent waste heat recovery and utilization system for boiler
CN202868825U (en) Waste heat recovering thermal power plant energy storage system
CN207881280U (en) Heat pump monoblock type Cooling and Heat Source computer room
CN106382745A (en) Automatic and energy-saving boiler device
CN102581945B (en) Exhaust steam afterheat recycling device for aerated brick field
CN207179607U (en) A kind of residual heat integrative of steel plant utilizes electricity generation system
CN202012982U (en) Life hot water system with multiple heat sources which are complementary
CN202361356U (en) Electric heating steam heat storage device
CN202581247U (en) Waste heat utilization system for natural gas burner
CN202449878U (en) Methanol and waste water heat recovery system in trade mark material production
CN209431389U (en) A kind of waste incineration and generating electricity heat energy recycling system of air compressor
CN209386263U (en) A kind of solid heat reservoir of auxiliary heating
CN206929010U (en) Gas turbine inlet air heater and Combined-cycle Gas Turbine Unit
CN206386911U (en) A kind of chemical water heating system
CN209763246U (en) Flue gas waste heat utilization heating system
CN208983651U (en) A kind of solar energy heating water system
CN203489248U (en) Thermal power plant boiler flue gas waste heat energy-saving system
CN206889029U (en) A kind of thermoelectricity decoupling fired power generating unit depth peak regulation system of no cold source energy

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180109

Termination date: 20210502