CN206860188U - A kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction - Google Patents

A kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction Download PDF

Info

Publication number
CN206860188U
CN206860188U CN201720450208.2U CN201720450208U CN206860188U CN 206860188 U CN206860188 U CN 206860188U CN 201720450208 U CN201720450208 U CN 201720450208U CN 206860188 U CN206860188 U CN 206860188U
Authority
CN
China
Prior art keywords
chute
delivery chute
mining method
appts
bottom board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720450208.2U
Other languages
Chinese (zh)
Inventor
聂振宇
谢泽福
李欢
黄锋光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Xiamen Engineering Co Ltd
Original Assignee
CCCC First Highway Xiamen Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Xiamen Engineering Co Ltd filed Critical CCCC First Highway Xiamen Engineering Co Ltd
Application granted granted Critical
Publication of CN206860188U publication Critical patent/CN206860188U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction, it includes:First delivery chute, the second delivery chute, the rotating shaft unit for connecting the first delivery chute and the second delivery chute, with the sector located at the first delivery chute and the second delivery chute junction, wherein, rotating shaft unit includes rotary shaft, the first chute connecting bottom board and the second chute connecting bottom board, first chute connecting bottom board and the second chute connecting bottom board are connected in rotary shaft, and can be rotated respectively relative to rotary shaft.The utility model device is applied to the concrete conveyance of various Urban Underground Tunneling by mining method construction, either powdered or damp shape gunite concrete, or stream modeling shape concrete, it can be easily delivered to by the device from ground in tunnel very much, its practicality and economy are very strong, and especially suitable underground is grown up Tunneling by mining method.

Description

A kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction
Technical field
It the utility model is related to a kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction, and in particular to a kind of The concrete (powdered, damp shape and stream mould shape) of various labels is conveyed by concrete conveyance chute, it is with strong applicability.
Background technology
In recent years, the fast development of Chinese national economy, Traffic Jam Problem in Cities are also on the rise, and domestic each city is all Subterranean tunnel project is built large-scale, alleviates traffic pressure.In Urban Underground Tunneling by mining method work progress, vertical shaft conduct The unique passage that tunnel contacts with ground, carries the transport of personnel, machinery, material, dregs.Traditional Tunneling by mining method concrete Supply mode is simple, i.e., in a certain side wall installation pipe of concrete of vertical shaft, concrete is delivered into well by ground by the pipe of concrete Bottom, then delivered to by concrete delivery truck in tunnel at operation.But there is operation phase in vertical shaft in this method in operation process Mutually the problem of interference:When there is concrete work in tunnel, due to the operation back and forth of tank car, the straddle truck by vertical shaft can not be transported OK, the transport of dregs and material is influenceed, other processes stop substantially in tunnel, greatly govern construction speed.
Utility model content
The purpose of this utility model is for more than background technology deficiency, there is provided a kind of operating efficiency height, is avoided completely Vertical shaft operation, security risk is small, puts into the advantages that economical rationality, only relies on the dress that chute completes subterranean tunnel concrete conveyance Put.
The technical solution of the utility model is as follows:
A kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction, it is characterised in that including:
The first delivery chute (1) in transfer passage between ground and tunnel, the second conveying in tunnel Chute (6), the rotating shaft unit (2) for connecting the first delivery chute (1) and the second delivery chute (6), and located at the first conveying Chute (1) and the sector (3) of the second delivery chute (6) junction, wherein,
Rotating shaft unit (2) includes rotary shaft (2-1), the first chute connecting bottom board (2-2) and the second chute connecting bottom board (2- 3), wherein the first chute connecting bottom board (2-2) and the second chute connecting bottom board (2-3) are connected in rotary shaft (2-1), and Difference can rotate relative to rotary shaft (2-1);And first delivery chute (1) and the first chute connecting bottom board (2-2) connection;Second Delivery chute (6) and the connection of the first chute connecting bottom board (2-3);
In preferred embodiment of the present utility model, the two of the first delivery chute (1) and the second delivery chute (6) junction Side is respectively equipped with an at least sector (3).
In preferred embodiment of the present utility model, the center of circle angle of sector (3) is 90-270 degree.Preferably 135 Degree.
In preferred embodiment of the present utility model, the side of sector (3) and the rear side of the first delivery chute (1) The full seam welding of wall, do not welded between opposite side and the second delivery chute (6).
In preferred embodiment of the present utility model, in addition to the second delivery chute dynamic positioning device.
In preferred embodiment of the present utility model, the second described delivery chute dynamic positioning device is bottle gouard moved by hands, Its one end is fixed on tunnel steel arch frame, and the other end is fixed on the second delivery chute (6).
In preferred embodiment of the present utility model, in addition to feed hopper (5), described feed hopper (5) outlet connection the The import of one delivery chute (1).
In preferred embodiment of the present utility model, the first delivery chute and the second delivery chute use thick 1cm, Q235 Steel plate processing, welding are made;
In preferred embodiment of the present utility model, rotating shaft unit (2) is using diameter 2cm, 20cm length, Q335 steel and thickness The processing of 1cm, Q235 steel plate, welding are made;
In preferred embodiment of the present utility model, sector (3) is made of thick 1cm, Q235 steel;
In preferred embodiment of the present utility model, bottle gouard moved by hands (4) can commercially be bought, and be adapted to, without special It is required that.
In preferred embodiment of the present utility model, feed hopper (5) is made of the processing of thick 6mm, Q235 steel, welding.
The utility model device groundwork mechanism and effect
, can phase between the first delivery chute (1) and the second delivery chute (6) because the utility model uses said structure To rotation;Second delivery chute (6) can be lifted by chain block, in the range of certain angle around rotating shaft unit (2) certainly By rotating, the second delivery chute (6) tail height is adjusted, meets the requirement for height of different concrete delivery trucks.In tunnel During without concrete work, the second delivery chute (6) afterbody can be promoted to tunnel vault, be not take up tunnel space, be easy to it His vehicle normal pass.If surface condition allows, mixing station discharging opening can be directly connected in tunnel by chute, saved Go ground concrete to transport this link, have further raising for concrete quality.
The utility model is only with delivery chute (1), rotating shaft unit (2), sector (3), chain block (4) and charging Struggle against (5), its installation and debugging process is very simple, is not related to labyrinth;
The conveying of concrete is completed using chute, avoids vertical shaft operation, it is higher without any interference, operating efficiency.
Seen from the above description, the appts. for transferring ready-mixed concrete of the utility model Urban Underground Tunneling by mining method construction, has The advantages that operating efficiency is high, security risk is small, input economical rationality.The utility model has further the advantage that:
(1) geological conditions is fully combined, is found a new way by excavating transfer passage, delivery chute is buried, has prevented well and erected Cross-operation interference in well, greatly improve the construction speed in tunnel;
(2) only commander 1 need to be set, respectively configures intercom 1 with in-cavity construction personnel, enter by unified command signal Row concrete work, there is the characteristics of contact is close, and operation acts in agreement;
(3) concrete (powdered, damp shape and stream mould shape) of various labels is applicable, adaptability is stronger;
(4) smaller by external environment influence during operation, daytime, night, rainwater and less than 6 grades strong wind weathers can be carried out. And transfer passage need not take excessive surface area, input-output ratio is high.
Brief description of the drawings
Fig. 1 is the utility model the first delivery chute vertical section (A) and cross-sectional view (B);
Fig. 2 is the utility model the second delivery chute vertical section (A) and cross-sectional view (B);
Fig. 3 is the utility model rotating shaft unit structural representation;
Fig. 4 is the utility model sector structural representation;
Fig. 5 is the structural representation of the utility model feed hopper;
Fig. 6 is that the utility model concrete is delivered to operating diagram and its partial enlargement in tunnel from ground;
In Fig. 6, arrow represents direction of rotation.
In figure
The delivery chutes of 1- first
2- rotating shaft units
3- sectors
4- chain blocks
5- feed hoppers
The delivery chutes of 6- second
7- ground
8- tunnels
9- transfer passages
Embodiment
Referring to Fig. 1 to Fig. 6.
The utility model includes:First delivery chute 1, the second delivery chute 6, rotating shaft unit 2, sector 3, pull calabash Reed 4 and feed hopper (5).
Wherein, referring to Fig. 1, the both ends open of the first delivery chute 1, centre closing, the cross section of center section be it is square, its End is inclined-plane 1-1,
Referring to Fig. 2, the both ends open of the second delivery chute 6, center section top is open, and front end also is provided with inclined-plane 6-1.
Referring to Fig. 3, rotating shaft unit 2 includes rotary shaft 2-1, and the first chute connecting bottom board 2-2 and the connection of the second chute Bottom plate 2-3, wherein the first chute connecting bottom board 2-2 and the second chute connecting bottom board 2-3 are connected on rotary shaft 2-1, and Difference can rotate relative to rotary shaft 2-1.In other embodiments or the first chute connecting bottom board 2-2 and second One of chute connecting bottom board 2-3 fixes relative to rotary shaft 2-1, and another can rotate relative to rotary shaft 2-1.
Referring to Fig. 4, sector 3 has two panels, is respectively arranged on the both sides of the first delivery chute 1 and the junction of the second chute 6.
It is of the present utility model to assemble and using as follows referring to Fig. 6
Manually excavating a transfer passage 9 in the side of tunnel 8 or surface, (passage arises from ground, finally tunnel spandrel model Enclose), the first delivery chute 1 is installed, concrete backfill transfer passage 9 is used after installation, avoids that ground settlement occurs.First is defeated The chute 6 of chute 1 and second is sent to be made of the processing of thick 1cm, Q235 steel plate, welding, cross dimensions, according to the need of site operation Specifically to determine.The end of first delivery chute 1 enters in tunnel 8.
Rotating shaft unit 2 is installed afterwards, the first chute connecting bottom board 2-2 of rotating shaft unit 2 is fixed to the first delivery chute 1 Port of export bottom, the second chute connecting bottom board 2-3 be fixed to the second delivery chute 6 entrance point bottom.
The center of circle angle of sector 3 specifically determines according to the lifting and falling head of live second delivery chute, typically For 135 ° or so.The a sides of sector 3 and the full seam welding of afterbody side wall of the first delivery chute 1, it is ensured that blade is in the second conveying Chute 6 will not and then rotate when rotating, all the time in stationary state.It is not required to weld between blade b sides and the second delivery chute 6, Ensure that the second delivery chute 6 is active.Sector 3 is processed into using thick 1cm, Q235 steel.
The one end of chain block 4 is fixed on tunnel steel arch frame, it is ensured that has good stress, the other end is fixed on the second conveying On chute 6.Feed hopper 5 is connected to the entrance point of the first delivery chute 1.
After installing rotating shaft unit 2, sector 3, chute, chain block 4 and feed hopper 5, debugged.Afterwards, Concrete is delivered in ground tunnel by the first delivery chute 1 from ground, because different concrete transportation heights are different, profit The second delivery chute tail height is adjusted with chain block 4, conveying operation in concrete conveyance to transport vehicle, will be completed.In tunnel When in road without concrete work, the second delivery chute afterbody can be promoted to tunnel vault, be not take up tunnel space, be easy to it His vehicle normal pass.
A specific embodiment of the present utility model is above are only, but design concept of the present utility model is not limited to This, all changes for carrying out unsubstantiality to the utility model using this design, all should belong to infringement scope of protection of the utility model Behavior.

Claims (7)

  1. A kind of 1. appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction, it is characterised in that including:
    The first delivery chute (1) in transfer passage between ground and tunnel, the second delivery chute in tunnel (6), the rotating shaft unit (2) for the first delivery chute of connection (1) and the second delivery chute (6), and located at the first delivery chute (1) and the second delivery chute (6) junction sector (3), wherein,
    Rotating shaft unit (2) includes rotary shaft (2-1), the first chute connecting bottom board (2-2) and the second chute connecting bottom board (2-3), Wherein the first chute connecting bottom board (2-2) and the second chute connecting bottom board (2-3) are connected in rotary shaft (2-1), and point It can not rotated relative to rotary shaft (2-1);And first delivery chute (1) and the first chute connecting bottom board (2-2) connection;Second is defeated Chute (6) and the first chute connecting bottom board (2-3) is sent to connect.
  2. A kind of 2. appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction as claimed in claim 1, it is characterised in that The both sides of the first delivery chute (1) and the second delivery chute (6) junction are respectively equipped with an at least sector (3).
  3. A kind of 3. appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction as claimed in claim 1, it is characterised in that The center of circle angle of sector (3) is 90-270 degree.
  4. A kind of 4. appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction as claimed in claim 1, it is characterised in that The side of sector (3) and the full seam welding of afterbody side wall of the first delivery chute (1), opposite side and the second delivery chute (6) Between do not weld.
  5. 5. a kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction as described in any one of Claims 1-4, its It is characterised by, in addition to the second delivery chute dynamic positioning device.
  6. A kind of 6. appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction as claimed in claim 5, it is characterised in that The second described delivery chute dynamic positioning device is bottle gouard moved by hands, and its one end is fixed on tunnel steel arch frame, and the other end is fixed On the second delivery chute (6).
  7. 7. a kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction as described in any one of Claims 1-4, its It is characterised by, in addition to feed hopper (5), the import of described feed hopper (5) outlet the first delivery chute of connection (1).
CN201720450208.2U 2017-03-16 2017-04-26 A kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction Expired - Fee Related CN206860188U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201720256558 2017-03-16
CN2017202565585 2017-03-16

Publications (1)

Publication Number Publication Date
CN206860188U true CN206860188U (en) 2018-01-09

Family

ID=59773765

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201710281320.2A Active CN107143348B (en) 2017-03-16 2017-04-26 Concrete conveying device and method for tunnel construction by urban underground mining method
CN201720450208.2U Expired - Fee Related CN206860188U (en) 2017-03-16 2017-04-26 A kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201710281320.2A Active CN107143348B (en) 2017-03-16 2017-04-26 Concrete conveying device and method for tunnel construction by urban underground mining method

Country Status (1)

Country Link
CN (2) CN107143348B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107143348B (en) * 2017-03-16 2023-08-11 中交一公局厦门工程有限公司 Concrete conveying device and method for tunnel construction by urban underground mining method
CN107575256B (en) * 2017-11-07 2024-09-03 中国建筑土木建设有限公司 Material conveying system for shallow buried section of tunnel and shallow buried section earth surface reinforcing method
CN114955395A (en) * 2022-07-14 2022-08-30 中铁工程服务有限公司 Conveying device and method

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06293417A (en) * 1993-04-07 1994-10-21 Taisei Corp Transporting device for granular body
JP2001090488A (en) * 1999-09-20 2001-04-03 Shimizu Corp Construction method and equipment for tunnel
JP5243357B2 (en) * 2009-06-24 2013-07-24 株式会社フジタ Concrete spraying equipment
CN102352758A (en) * 2011-09-22 2012-02-15 河北省第四建筑工程公司 Construction method for automobile adit and slant chute
CN203768873U (en) * 2014-02-14 2014-08-13 河南水利建筑工程有限公司 Adjustable belt distributor
CN106337416B (en) * 2015-05-25 2018-06-19 中国建筑第八工程局有限公司 The vertically delivery pipe bottom end buffer unit of the downward delivering concrete of structure ultra-deep
CN105312254A (en) * 2015-11-13 2016-02-10 四川雅安雅泉茶业有限公司 Adjustable type multifunctional tea color selector
CN205330672U (en) * 2016-01-28 2016-06-22 中国水利水电第十四工程局有限公司 Buffer of shaft concrete elephant trunk export
CN205636745U (en) * 2016-05-13 2016-10-12 苏州国贸嘉和建筑工程有限公司 Material feeding unit under concrete
CN106049501B (en) * 2016-05-30 2018-05-25 中建五局第三建设有限公司 Construction method for conveying concrete downwards with large drop
CN107143348B (en) * 2017-03-16 2023-08-11 中交一公局厦门工程有限公司 Concrete conveying device and method for tunnel construction by urban underground mining method

Also Published As

Publication number Publication date
CN107143348B (en) 2023-08-11
CN107143348A (en) 2017-09-08

Similar Documents

Publication Publication Date Title
CN206860188U (en) A kind of appts. for transferring ready-mixed concrete of Urban Underground Tunneling by mining method construction
WO2016095538A1 (en) Double-roadway combined speedy tunnelling and waste rock removal system and method
CN103244148A (en) Coal mine wet method guniting process
CN205400737U (en) Demolish main drive arrangement in hole of shield structure machine
CN202266260U (en) Technical equipment for separating coal from gangue and backfilling gangue
CN101660414B (en) Method for conveying coal in end slope laneway in open pit coal mine
CN203856209U (en) Long-distance gentle-slope concrete conveying device
CN103754589A (en) Method and system for transporting bulk materials through high-fall continuous shafts
CN203382232U (en) Large ultra-long single-arm material discharging and distributing machine
CN202594413U (en) Balancing mechanism of novel bucket-wheel stacker reclaimer
CN206409240U (en) A kind of track traffic bored tunnel electric railcar transports corollary system
CN205972995U (en) Underground material conveying system
CN207775933U (en) A kind of pipe gallery temporary plugging wall construction
CN202730556U (en) Rail rotary table for underground transportation
CN203111972U (en) Underground scraper plate type scattered material feeding machine
CN205503143U (en) Primary waste rock is broken system in pit
CN202745931U (en) Underground backfilling and conveying system for ground gangue of coal mine
CN207122323U (en) A kind of coal mine underground mobile lotion prepares and conveying device
CN201116472Y (en) Multiple mine car type secondary transporter
CN206765103U (en) A kind of underground project dug underground concrete mixing plant
CN206439068U (en) A kind of piping shaft transportation system
CN211573528U (en) Be used for coal seam tunnel to combine to dig quick transportation supporting device
CN206857981U (en) A kind of gantry slag bucket device that automatic clinker-removing is completed by self gravitation effect
CN206035498U (en) Contact passageway between upper and lower tunnel
CN217206473U (en) Automatic feeding device for tunnel quick grouting

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180109

CF01 Termination of patent right due to non-payment of annual fee