CN206860149U - A kind of plunger lift pumping equipment - Google Patents

A kind of plunger lift pumping equipment Download PDF

Info

Publication number
CN206860149U
CN206860149U CN201720660676.2U CN201720660676U CN206860149U CN 206860149 U CN206860149 U CN 206860149U CN 201720660676 U CN201720660676 U CN 201720660676U CN 206860149 U CN206860149 U CN 206860149U
Authority
CN
China
Prior art keywords
plunger
sleeve
oil pipe
sliding sleeve
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720660676.2U
Other languages
Chinese (zh)
Inventor
王林
黄其
李楠
徐庆祥
白石
马田力
吴英新
李相珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Bohai Drilling Engineering Co Ltd
Original Assignee
CNPC Bohai Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Bohai Drilling Engineering Co Ltd filed Critical CNPC Bohai Drilling Engineering Co Ltd
Priority to CN201720660676.2U priority Critical patent/CN206860149U/en
Application granted granted Critical
Publication of CN206860149U publication Critical patent/CN206860149U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model discloses a kind of plunger lift pumping equipment, including ground installation and underground tool string, underground tool string includes oil pipe, middle ball seat, horn mouth, plunger, elastomeric sleeve is provided with the middle part of oil pipe, elastomeric sleeve includes body, top connection and lower contact, the inner chamber of body is provided with sliding sleeve, the side wall of body is provided with stomata, sliding sleeve is limited and moved up and down in body by top connection and lower contact, make stomata repeat switch, the arc elastic plectrum that the installation of sliding sleeve inwall is changed by diameter after transverse shear stress, arc top are provided with wear-resisting projection;Plunger is cylindric, axially sets multiple grooves being parallel to each other around plunger sidewall circumferential surface, and groove rises and occlusion or separation occurs under the elastic force effect of elastic plectrum with abrasion resistant convex, drives sliding sleeve to up and down motion.Using the plunger in oil pipe during use, in well under the promotion of gas, the water in shaft bottom, ground is given rise to.Simple in construction, easy to operate, cost is cheap, is a kind of new equipment of mining operation.

Description

A kind of plunger lift pumping equipment
Technical field
It the utility model is related to a kind of device of oil-gas field development application, especially a kind of plunger lift pumping equipment, profit With the plunger in oil pipe, in well under the promotion of gas, the water in shaft bottom is given rise to ground.
Background technology
At present the lifting technology of Oil/gas Well include rod pumping pump, electric pump, screw pump, hydraulic pump, gaslift, foams drain, The modes such as pumping, for High water cut gas well, majority uses foams drain, but effect is undesirable when stratum is aqueous high, uses Gas lift liquid drainage is costly, and back pressure height is produced to stratum, and discharge opeing effect is undesirable, needs kill-job to play flowline using other pumps, Length duty cycle be present, have the shortcomings that pollution to stratum.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of plunger lift pumping equipment, solves gas lift liquid drainage Can not the mode such as tripping in sucker rod pump, electric pump discharge opeing problem.
In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model is:A kind of plunger lift pumping equipment, Including ground installation and underground tool string, underground tool string includes the oil pipe being arranged in sleeve pipe, the centre being connected on oil pipe Ball seat and horn mouth, and the plunger moved up and down along tube inner wall, are provided with elastomeric sleeve, elastomeric sleeve in the middle part of oil pipe Above middle ball seat and there is a certain distance;Elastomeric sleeve includes the body using via design, positioned at body both ends Top connection and lower contact, the internal diameter of upper and lower joint is less than the internal diameter of body, and top connection is connected by screw socket respectively with lower contact Onto oil pipe, the inner chamber of body is provided with sliding sleeve, and the side wall of body is provided with stomata, and stomata can be closed by sliding sleeve, and the external diameter of sliding sleeve omits Less than body internal diameter but be greater than the internal diameter of upper and lower joint, limited and moved up and down in body by top connection and lower contact, Make stomata repeat switch, connection or isolation tubing wall interior or exterior space, the installation of sliding sleeve inwall is occurred by diameter after transverse shear stress The arc elastic plectrum of change, arc top are provided with wear-resisting projection, and wear-resisting projection is in circular arc;Inside oil pipe freely up and down Mobile plunger is cylindric, axially sets multiple grooves being parallel to each other around plunger sidewall circumferential surface, and groove exists The elastic force effect of elastic plectrum is lower and abrasion resistant convex rises and occlusion or separation occurs, when plunger moves through elastomeric sleeve from the top down When, groove is engaged wear-resisting projection, drives sliding sleeve to move downward, and stomata is closed, and oil pipe is not connected with sleeve pipe;Plunger is from bottom to top When moving through elastomeric sleeve, groove is engaged wear-resisting projection, drives sliding sleeve to move upwards, and stomata is opened, and makes oil pipe oil pipe and set The empty connection of pipe ring.
Underground tool string is fixed in the christmas tree big four of cannula tip and sealed by boll-weevil hanger;Ground installation Including the small four-way of christmas tree, small four-way side is connected with outlet line, and top is connected with catcher and plunger buffer room, outlet Tubing gauge and tubing valve are installed on line, has sleeve pipe inlet/outlet pipeline in the outlet of oil sets annular space, is pressed on sleeve pipe Power table and sleeve valve.
The oil pipe specification of multistage in well is identical, and the internal diameter of middle ball seat is less than the external diameter of plunger, middle ball seat to ground The internal diameter of other instruments and oil pipe between equipment plunger buffer room is slightly larger than the external diameter of plunger, and plunger can be in middle ball seat and post Freely up and down moved between plug surge chamber.
The elastomeric sleeve is located at the top of liquid level in sleeve pipe, and to liquid level distance between 100-300m, horn mouth is located at The bottom of liquid level in sleeve pipe, to liquid level distance between 200-300m.
The beneficial effects of the utility model are:Simple in construction, easy to operate, cost is cheap, is a kind of the new of mining operation Device.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model plunger lift pumping equipment.
Fig. 2 is the structural representation of elastomeric sleeve of the present utility model.
Fig. 3 is the structural representation of plunger of the present utility model.
Fig. 4 is plunger of the present utility model from well head whereabouts schematic diagram.
Fig. 5 is that closing well of the present utility model recovers schematic diagram.
Fig. 6, which is that the plunger of the present utility model that drives a well is up, passes through elastomeric sleeve schematic diagram.
In figure:7 plungers, 9 elastomeric sleeves, 10 middle ball seats, 11 gas-bearing formations, liquid level in 12 sleeve pipes, liquid level in 13 oil pipes, 14 is slow Rush device, 15 sleeve pipe inlet/outlet pipelines, 17 casing pressure tables, 18 outlet lines, 19 oil pipe gates, 20 tubing gauges, 22 oil pipes, 23 sleeve pipes, 24 horn mouths, 26 sleeve gates, 27 tubing hangers, 28 christmas tree big fours, the small four-way of 29 christmas trees.
Embodiment
The utility model is described in further detail with reference to the accompanying drawings and detailed description, but the utility model will The scope of protection is asked to be not limited to the scope of embodiment statement.Ground installation of the present utility model is identical with prior art , prior art is may be referred to, so no longer describing, the difference of the utility model and prior art is downhole tool string structure Difference, it is detailed below:
As Figure 1-3, plunger lift pumping equipment of the present utility model, including ground installation and underground tool string, well Lower tool string is including the oil pipe 22 being arranged in sleeve pipe 23, the middle ball seat 10 and horn mouth 24 being connected on oil pipe 22, and The plunger 7 moved up and down along the inwall of oil pipe 22, the middle part of oil pipe 22 is provided with elastomeric sleeve 9, elastomeric sleeve 9 is located at intermediate The top of seat 10 simultaneously has a certain distance;Elastomeric sleeve 9 includes the body 2 using via design, is connect on the both ends of body 2 First 1 and lower contact 1-1, the internal diameter of upper and lower joint are less than the internal diameter of body 2, and top connection 1 and lower contact 1-1 pass through screw socket respectively It is connected on oil pipe 22, the inner chamber of body 2 is provided with sliding sleeve 3, and the side wall of body 2 is provided with stomata 5, and stomata 5 can be closed by sliding sleeve 3, The external diameter of sliding sleeve 3 is slightly less than the internal diameter of body 2 but is greater than the internal diameter of upper and lower joint, is limited by top connection 1 and lower contact 1-1 And moved up and down in body 2, make the repeat switch of stomata 5, connection or isolation tubing wall interior or exterior space, the installation of the inwall of sliding sleeve 3 The arc elastic plectrum 4 to be changed by diameter after transverse shear stress, arc top are provided with wear-resisting raised 6, wear-resisting raised 6 and are in Circular arc;The plunger 7 freely up and down moved inside oil pipe 22 is cylindric, is axially set around plunger sidewall circumferential surface Multiple grooves 8 being parallel to each other are put, groove 8 is under the elastic force effect of elastic plectrum 4 and wear-resisting raised 6 occur occlusion or separation, When plunger 7 moves through elastomeric sleeve 9 from the top down, groove 8 is engaged wear-resisting raised 6, drives sliding sleeve 3 to move downward, stomata 5 Close, oil pipe 22 is not connected with sleeve pipe 23;When plunger 7 moves through elastomeric sleeve 9 from bottom to top, groove 8 is engaged abrasion resistant convex 6 are played, drives sliding sleeve 3 to move upwards, stomata 5 is opened, and oil pipe oil pipe 22 is connected with the annular space of sleeve pipe 23.
Underground tool string is fixed in the christmas tree big four 28 at the top of sleeve pipe 23 and sealed by boll-weevil hanger 27;Ground Face equipment includes the small four-way 29 of christmas tree, and small four-way side is connected with outlet line 18, top and catcher 25 and plunger buffer Room 14 is connected, and tubing gauge 20 and tubing valve 19 are provided with outlet line, has sleeve pipe in the outlet of oil sets annular space Inlet/outlet pipeline 15, pressure gauge 17 and sleeve valve 26 on sleeve pipe.
The specification of oil pipe 22 of multistage in well is identical, and the internal diameter of middle ball seat 10 is less than the external diameter of plunger 7, middle ball seat 10 It is slightly larger than the external diameter of plunger 7 to other instruments between ground installation plunger buffer room 14 and the internal diameter of oil pipe 22, plunger 7 can be Freely up and down moved between middle ball seat 10 and plunger buffer room.
The elastomeric sleeve 9 is located at the top of liquid level 12 in sleeve pipe, to liquid level distance between 100-300m, horn mouth 24 The bottom of liquid level 12 in sleeve pipe, to liquid level distance between 200-300m.
Plunger lift pumping equipment is connected and used as follows:
Step 1, as shown in figure 1, equipment is installed;First, pit shaft is filled with equilibrium strata pressure with clear water or well killing fluid, Liquid level is kept in well head;
Secondly, by downhole tools such as horn mouth 24, middle ball seat 10, elastomeric sleeves 9, pass sequentially through oil pipe 22 and connect, in Between preferred distance between ball seat 10 and elastomeric sleeve 9 between 300-600 rice, connect underground tool string, root in sequence According to Horizon Prognosis pressure and level, the predetermined depth of elastomeric sleeve 9 in calculating instrument string, and G.I.H, under it is fashionable, really It is (ensuring that oil pipe does not connect with oil jacket annular space) in the closed position to recognize elastomeric sleeve.
Then, christmas tree and fastening screw are installed, side installation tubing gauge 20, lock on the small four-way of well head christmas tree Door 19 and outlet line 18, outlet line 18 are connected with the open flow flow in gas production flow or well site, the small four-way 29 of christmas tree Top installation catcher 25, plunger damper 14 (plunger 7 is now placed in plunger damper 14), the side of christmas tree big four 28 Installation set hook gauge 17.
Step 2, gaslift induced flow;Using the gas lift liquid drainage technique of routine, nitrogen or natural gas from sleeve pipe and oil pipe Annular space is injected, and the water in well is discharged to ground, and is vented well head pressure, closes tubing valve 19 and sleeve valve afterwards 26。
Step 3, starter;In terrestrial operation catcher 25, plunger 7 is discharged, the plunger 7 in plunger damper 14 is in weight Moved downward under power effect along oil pipe 22, when plunger 7 is by elastomeric sleeve 9, groove 8 is engaged the resistance to of the top of elastic plectrum 4 Mill projection 6, under effect of inertia, driving sliding sleeve 3 to move down and close stomata 5, elastomeric sleeve 9 isolates oil pipe 22 and sleeve pipe 23, When sliding sleeve 3 reaches lower contact 1-1, stop movement, wear-resisting raised 6 jump out from groove 8, and plunger 7 leaves elastomeric sleeve 9, continue Under fall on intermediate seat.As shown in Figure 4.
Step 4, wellbore pressure is recovered;After closing tubing valve 19, the water and natural gas on stratum, under strata pressure driving Into pit shaft, borehole pressure progressively recovers, and stratum water gradually floods plunger 7 and elastomeric sleeve 9.As shown in Figure 5.
Step 5, plunger draining;When borehole pressure reaches ground control settings, ground control valve is opened, in oil pipe Pressure is reduced rapidly, and pressure difference is formed in plunger face, using the pressure difference formed between oil pipe and sleeve pipe, liquid and plunger is upward Lifting.When plunger 7 enters elastomeric sleeve 9, groove 8 is engaged wear-resisting raised the 6 of the top of elastic plectrum 4, under effect of inertia, band Dynamic sliding sleeve 3, which moves up, opens stomata 5, the connection oil pipe 22 of elastomeric sleeve 9 and sleeve pipe 23, and the gas in sleeve pipe enters oil pipe, increases The pressure of plunger base, plunger and liquid thereon accelerate and reach ground, when sliding sleeve 3 reaches top connection 1, stop moving Dynamic, wear-resisting raised 6 jump out from groove 8, and plunger 7 leaves the water column on elastomeric sleeve 9 and top together, is acted in gas push Under, continue to move to well head, as shown in Figure 6.The water of the bottom of plunger 7 falls on shaft bottom simultaneously, after plunger 7 reaches ground, in inertia Plunger damper 14 is rushed under effect and is stopped wherein.
It is to be seen arrive ground not water outlet after, close tubing valve 19, repeat step 3 to 5, thus by switching oil pipe repeatedly Valve 19, plunger 7 is allowed constantly to be moved up and down in device to realize gas well discharge opeing.
In summary, content of the present utility model is not limited in the above embodiments, in same area it is insighted it Scholar can easily propose other embodiments within technological guidance's thought of the present utility model, but this embodiment is all wrapped Include within the scope of the utility model.

Claims (4)

1. a kind of plunger lift pumping equipment, including ground installation and underground tool string, underground tool string includes being arranged on sleeve pipe (23) oil pipe (22) in, the middle ball seat (10) and horn mouth (24) being connected on oil pipe (22), and along oil pipe (22) The plunger (7) that inwall moves up and down, it is characterised in that be provided with elastomeric sleeve (9), elastomeric sleeve (9) in the middle part of oil pipe (22) Positioned at middle ball seat (10) top and there is a certain distance;Elastomeric sleeve (9) includes the body (2) using via design, position Top connection (1) and lower contact (1-1) in body (2) both ends, the internal diameter of upper and lower joint are less than the internal diameter of body (2), top connection (1) it is connected to respectively by screw socket on oil pipe (22) with lower contact (1-1), the inner chamber of body (2) is provided with sliding sleeve (3), body (2) Side wall be provided with stomata (5), stomata (5) can be closed by sliding sleeve (3), and the external diameter of sliding sleeve (3) is slightly less than the internal diameter of body (2) still More than the internal diameter of upper and lower joint, move up and down by top connection (1) and lower contact (1-1) limitation and in body (2), make stomata (5) repeat switch, connection or isolation tubing wall interior or exterior space, the installation of sliding sleeve (3) inwall are occurred by diameter after transverse shear stress The arc elastic plectrum (4) of change, arc top are provided with wear-resisting raised (6), and wear-resisting projection (6) is in circular arc;In oil pipe (22) the internal plunger (7) freely up and down moved is cylindric, axially sets multiple phases around plunger sidewall circumferential surface Mutually parallel groove (8), groove (8) is under the elastic force effect of elastic plectrum (4) and occlusion or separation occur for wear-resisting raised (6), When plunger (7) moves through elastomeric sleeve (9) from the top down, groove (8) occlusion is wear-resisting raised (6), drives sliding sleeve (3) downward Motion, stomata (5) are closed, and oil pipe (22) is not connected with sleeve pipe (23);Plunger (7) moves through elastomeric sleeve from bottom to top (9) when, groove (8) occlusion is wear-resisting raised (6), drives sliding sleeve (3) to move upwards, and stomata (5) is opened, make oil pipe oil pipe (22) and Sleeve pipe (23) annular space connects.
2. plunger lift pumping equipment according to claim 1, it is characterised in that underground tool string passes through boll-weevil hanger (27) it is fixed on the christmas tree big four (28) at the top of sleeve pipe (23) Nei and seals;Ground installation includes the small four-way of christmas tree (29), small four-way side is connected with outlet line (18), and top is connected with catcher (25) and plunger buffer room (14), outlet Tubing gauge (20) and tubing valve (19) are installed on line, have sleeve pipe inlet/outlet pipeline in the outlet of oil sets annular space (15), pressure gauge (17) and sleeve valve (26) on sleeve pipe.
3. plunger lift pumping equipment according to claim 2, it is characterised in that oil pipe (22) specification phase of the multistage in well Together, the internal diameter of middle ball seat (10) be less than plunger (7) external diameter, middle ball seat (10) to ground installation plunger buffer room (14) it Between other instruments and oil pipe (22) internal diameter be slightly larger than plunger (7) external diameter, plunger (7) can be in middle ball seat (10) and plunger Freely up and down moved between surge chamber.
4. plunger lift pumping equipment according to claim 1, it is characterised in that the elastomeric sleeve (9) is located at sleeve pipe The top of interior liquid level (12), to liquid level distance between 100-300m, horn mouth (24) is located at the bottom of liquid level (12) in sleeve pipe, To liquid level distance between 200-300m.
CN201720660676.2U 2017-06-08 2017-06-08 A kind of plunger lift pumping equipment Expired - Fee Related CN206860149U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720660676.2U CN206860149U (en) 2017-06-08 2017-06-08 A kind of plunger lift pumping equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720660676.2U CN206860149U (en) 2017-06-08 2017-06-08 A kind of plunger lift pumping equipment

Publications (1)

Publication Number Publication Date
CN206860149U true CN206860149U (en) 2018-01-09

Family

ID=60830758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720660676.2U Expired - Fee Related CN206860149U (en) 2017-06-08 2017-06-08 A kind of plunger lift pumping equipment

Country Status (1)

Country Link
CN (1) CN206860149U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313750A (en) * 2017-06-08 2017-11-03 中国石油集团渤海钻探工程有限公司 A kind of plunger lift pumping equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313750A (en) * 2017-06-08 2017-11-03 中国石油集团渤海钻探工程有限公司 A kind of plunger lift pumping equipment
CN107313750B (en) * 2017-06-08 2023-08-11 中国石油天然气集团有限公司 Plunger gas lift drain

Similar Documents

Publication Publication Date Title
CN201671623U (en) Pipe column for leakage finding and separate mining of horizontal well
CN102979495A (en) Multi-cluster current limiting fracturing string of open hole horizontal well and fracturing method thereof
CN206071845U (en) Eccentric wear prevention oil well pump
CN106050199A (en) Synthetic drainage and gas production device and method
CN204311987U (en) Slip type downhole buffer of tubing plug
CN104963634B (en) Method for tripping sucker rod
CN104563947B (en) Downhole blowout prevention pipe column for oil well
CN202165053U (en) Novel hydraulic control underground sliding sleeve switch valve
CN206860149U (en) A kind of plunger lift pumping equipment
CN107313750A (en) A kind of plunger lift pumping equipment
CN105715234A (en) Self-blowing mechanical-production integrated pipe column
CN201214997Y (en) Metal seal double tube christmas tree wellhead device
CN204754881U (en) Double -barrelled gas well flow string parallels
CN202493239U (en) Blowout preventer
CN204703836U (en) Downhole blowout prevention pipe column for oil well
CN202970640U (en) Reservoir protection tubular pillar of pressure self-adaptive anchoring packer
CN204041041U (en) Oil well liquid increasing device
CN205012973U (en) Machine pump drainage liquid gas production device
CN211448593U (en) Suitable for CO2Huff-puff injection-production integrated wellhead device
CN101109375A (en) Two-stage down-hole pipe pump oil extracting device
CN204113210U (en) Full well section does not have bridging plug half range cementing tool
CN207583343U (en) The safe blowout hookup of oil field well oil pipe Operating Pressure
CN203347704U (en) Well washing and oil draining device for pumping well
CN202544815U (en) Exhaust string for deep-drawing process well
CN203394451U (en) Leakage-sealing water-plugging oil production pipe column for thickened oil horizontal well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20211108

Address after: 100007 No. 9 North Main Street, Dongcheng District, Beijing, Dongzhimen

Patentee after: CHINA NATIONAL PETROLEUM Corp.

Patentee after: CNPC Bohai Drilling Engineering Co.,Ltd.

Address before: China Petroleum Tianjin building Bohai Drilling Engineering Co., Ltd., No. 83, Second Street, economic and Technological Development Zone, Binhai New Area, Tianjin, 300457

Patentee before: CNPC Bohai Drilling Engineering Co.,Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180109

CF01 Termination of patent right due to non-payment of annual fee