CN206815805U - Direct burial rigid connecting tube - Google Patents

Direct burial rigid connecting tube Download PDF

Info

Publication number
CN206815805U
CN206815805U CN201720659577.2U CN201720659577U CN206815805U CN 206815805 U CN206815805 U CN 206815805U CN 201720659577 U CN201720659577 U CN 201720659577U CN 206815805 U CN206815805 U CN 206815805U
Authority
CN
China
Prior art keywords
wall
connecting piece
bar
vertical rod
connecting tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720659577.2U
Other languages
Chinese (zh)
Inventor
徐子武
袁鹏
罗细驼
易忠东
徐恰皮
魏金平
陈佳烽
雷攀
苏承翔
晏夏明
李可
周剑
金强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Construction Building Iv Ltd LLC
Original Assignee
Jiangxi Construction Building Iv Ltd LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Construction Building Iv Ltd LLC filed Critical Jiangxi Construction Building Iv Ltd LLC
Priority to CN201720659577.2U priority Critical patent/CN206815805U/en
Application granted granted Critical
Publication of CN206815805U publication Critical patent/CN206815805U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of direct burial rigid connecting tube is the utility model is related to, suitable for exterior window, exterior wall more high level and high-rise building.It includes vertical rod, vertical equity bar, transverse horizontal bar;90 degree are connected between the vertical rod, vertical equity bar, transverse horizontal bar three;One end of wall-connecting piece is connected by double fasteners with vertical rod, and the other end of wall-connecting piece, which is stretched into beam, to be fixed.The utility model thoroughly eliminates the exterior wall leakage hidden danger that traditional wall-connecting piece is brought.Because this wall-connecting piece is to be embedded in concrete side bar side, exterior wall and window are not influenceed, seepage point will not be produced.

Description

Direct burial rigid connecting tube
Technical field
A kind of direct burial rigid connecting tube is the utility model is related to, suitable for exterior window, exterior wall more high level and Super High Building.
Background technology
In architectural engineering, outer scaffold wall connector is as external scaffolding support body and constructure body structure to be connected Connect, pulling force and the component of pressure can be transmitted.The rigidity formed using the push-and-pull rods such as steel pipe, fastener or built-in fitting or component is connected The attached wall connection that wall part is realized.Resistance to overturning for strengthening high-rise and Super High external scaffolding, improves its bearing capacity, and The major accident tool such as topple over or cave in is avoided the occurrence of to play a very important role.Traditional wall-connecting piece is embedded on side bar frequently with steel pipe Mouthful, its burial place often conflicts with exterior wall, exterior window, influences the construction speed of the processes such as later stage building wall, window installation And quality, the hole that the later stage blocks also easily produce seepage point.And in traditional wall-connecting piece work progress easily by artificial destruction, tear open Unload;Using traditional wall-connecting piece because the harmony of floor height and external scaffolding step pitch is because of Lou Eryi, wall-connecting piece deviate host node away from From can not be completely secured meet code requirement " connection dot center to host node with a distance from≤300mm ".
The content of the invention
The purpose of this utility model is to provide a kind of direct burial rigid connecting tube, eliminates the exterior wall that traditional wall-connecting piece is brought Hidden leakage defect.
The utility model to achieve these goals, adopts the following technical scheme that:
A kind of direct burial rigid connecting tube, it includes vertical rod, vertical equity bar, transverse horizontal bar;
90 degree are connected between the vertical rod, vertical equity bar, transverse horizontal bar three;
One end of wall-connecting piece is connected by double fasteners with vertical rod, and the other end of wall-connecting piece, which is stretched into structure side bar, to be fixed.
Further, there is circular hole in the end that wall-connecting piece is stretched into structure side bar, additional anchor muscle is through circular hole and consolidates Fixed, the termination of additional anchor muscle free end is hook structure, and hook structure catches on structure side bar reinforcing bar.
Further, double fasteners are right-angle coupler.
Further, the position of wall-connecting piece being set and staggered a steel pipe opening position with vertical rod, side form template is cut, Cut opening position and open up circular reserved opening, circular reserved opening diameter is bigger than diameter of steel tube;
Circular reserved opening is adjusted up and down along vertical rod position, it is ensured that meets that wall-connecting piece steel pipe is not more than apart from host node 30cm。
Further, two pieces of templates that side form template is cut are reinforced with the lumps of wood.
Further, the termination of wall-connecting piece steel pipe is clogging.
The beneficial effects of the utility model:
1st, wall-connecting piece does not conflict with outer-wall building, exterior window installation.Do not influenceed after wall-connecting piece installation later stage building wall, The construction speed and quality of the processes such as window installation.
2nd, it is not easy by artificial damage or dismounting, and will not loosens after wall-connecting piece installation.
3rd, the position of wall-connecting piece tie wall rod member can be adjusted, it is ensured that meet code requirement wall-connecting piece deviate host node≤ 300mm。
4th, wall-connecting piece easy construction, disposably in place, not only labour cost can be saved with accelerating construction progress;And this connects Wall part construction method can be with cost-effective, and the steel pipe reduced in Transducers Embedded in Concrete wastes;Outer walling, outer can additionally be reduced Wall-connecting piece and the secondary expense for changing outrigger are torn down and reconstructed in window installation process and blocks outer wall opening expense.
5th, the exterior wall leakage hidden danger that traditional wall-connecting piece is brought thoroughly is eliminated.Because this wall-connecting piece is to be embedded in concrete side bar Side, exterior wall and window are not influenceed, seepage point will not be produced.
Brief description of the drawings
Fig. 1 is direct burial rigid connecting tube plan of the present utility model;
Fig. 2 is direct burial rigid connecting tube profile of the present utility model;
Fig. 3 is the perforate schematic diagram of connector of the present utility model;
Fig. 4 is additional anchor muscle schematic diagram of the present utility model;
Fig. 5 is template hole to be provided elevation of the present utility model;
Fig. 6 is template hole to be provided profile of the present utility model.
Embodiment
The utility model is described in detail below in conjunction with the accompanying drawings:
A kind of direct burial rigid connecting tube, it includes vertical rod 1, vertical equity bar 2, transverse horizontal bar 3;
90 degree are connected between the vertical rod 1, vertical equity bar 2, the three of transverse horizontal bar 3;
One end of wall-connecting piece 4 is connected by double fasteners 5 with vertical rod 1, and the other end of wall-connecting piece 4 is stretched into structure side bar 6 admittedly It is fixed.
There is circular hole 9 in the end that wall-connecting piece 4 is stretched into structure side bar 6, additional anchor muscle 7 passes through circular hole and fixation, attached The termination for adding the free end of anchor rib 7 is hook structure, and hook structure catches on structure side bar reinforcing bar 8.
Double fasteners 5 are right-angle coupler.
The position of wall-connecting piece 4 is being set and staggered a steel pipe opening position with vertical rod 1, the template of side form 11 cuts, cut Opening position opens up circular reserved opening 12, and the circular diameter of reserved opening 12 is bigger than diameter of steel tube;
Circular reserved opening 12 is adjusted up and down along the position of vertical rod 1, it is ensured that meets that the steel pipe of wall-connecting piece 4 is little apart from host node In 30cm.
Two blocks of template lumps of wood 13 that the template of side form 11 is cut are reinforced.
The termination of the steel pipe of wall-connecting piece 4 is clogging.
Operating process
Determine that position → wall-connecting piece making → side beam steel bar colligation of wall-connecting piece finishes, model sheetinstallat is completed, template Reserved wall-connecting piece drawknot circular hole → positioning, installation wall-connecting piece → pours side bar concrete, dismounting side bar template → fall frame, the company of excision Wall part, repairing wall-connecting piece hole.
Implementation
(One), wall-connecting piece position determination
The arrangement of wall-connecting piece is rationally carried out according to structure, architectural drawing and external scaffolding arrangement and method for construction.
Equipping rules:
1), wall-connecting piece do not influence the construction of exterior wall, exterior window;
2), wall-connecting piece according to arrangement and method for construction using two steps two across arrangement principle, and open cloth, rhombus cloth in each fault Put;
3), ensure connect dot center to host node distance≤300mm;
4), according to this equipping rules, with reference to drawing, draw the wall-connecting piece floor plan and facade layout drawing in every building.
(Two), wall-connecting piece making
According to the length and quantity of required wall-connecting piece, the making of wall-connecting piece is carried out.
1), steel pipe:Φ 48.3*3.6mm steel pipes, length 50cm(15cm in beam is stretched into, vertical rod is outside side bar in outrigger Side 25cm, reserve vertical rod in the stretching of 10cm joints), about Φ 14mm circular holes are burnt at steel tube head 8cm.
2), additional anchor muscle:Anchor rib uses HRB335 level reinforcing bars, a diameter of Φ 12, length 26cm, and termination is set 135 ° of hooks, segment length that crotch is straight are 6cm.
3), fastener:Even wall steel pipe is connected with outrigger vertical rod with two right-angle couplers, and one is played stress, and one is played guarantor Danger effect.
(Three), side beam steel bar colligation finish, model sheetinstallat is completed, and template reserves wall-connecting piece drawknot circular hole.
The position of wall-connecting piece is being set(Stagger a steel pipe position with vertical rod)By side form template, play is opened with a chainsaw, with convenient Later form removal.And circular hole is opened up in position, hole diameter is more bigger 5mm than diameter of steel tube.Circle is reserved Hole can be adjusted up and down along vertical rod position, it is ensured that meet that wall-connecting piece steel pipe is not more than 30cm requirement apart from host node.Then Two pieces of templates that play is opened are reinforced with the lumps of wood.
(Four), positioning, installation wall-connecting piece
By in the reserved circular hole of the wall-connecting piece steel pipe to have completed insertion side form template, beam is stretched at band hole burning end Inside about 15cm, the reinforcing bar made is inserted in steel pipe circular hole, hook is caught on into structure side bar reinforcing bar.Pay attention to installation process In ensure even wall steel pipe be not more than 30cm apart from host node.Steel tube head is blocked with waste paper, prevents concrete grout from flowing into steel pipe.
(Five), pour side bar concrete, remove side bar side form
Casting concrete, and with vibrating head vibration compacting.After concrete reaches some strength, it is ensured that concrete during form removal Corner angle are not damaged, start form removal side bar side form, first remove the lumps of wood on side form, then remove the two pieces of templates opened by play.
(Six), when falling frame, cut off wall-connecting piece steel pipe with cutting machine, hole repaired using conventional cement mortar.
When removing external scaffolding, wall-connecting piece is progressively removed with the dismounting of outrigger, is exposed with the excision of hand electric cutting machine Wall-connecting piece steel pipe on the outside of side bar, cuts flat with side bar, then fills up steel pipe hole with conventional cement mortar.

Claims (6)

  1. A kind of 1. direct burial rigid connecting tube, it is characterised in that:It includes vertical rod(1), vertical equity bar(2), transverse horizontal bar (3);
    The vertical rod(1), vertical equity bar(2), transverse horizontal bar(3)90 degree are connected between three;
    Wall-connecting piece(4)One end pass through double fasteners(5)With vertical rod(1)Connection, wall-connecting piece(4)The other end stretch into structure side bar (6)Interior fixation.
  2. 2. direct burial rigid connecting tube according to claim 1, it is characterised in that:In wall-connecting piece(4)Stretch into structure side bar (6)There is circular hole interior end(9), additional anchor muscle(7)Through circular hole and fixation, additional anchor muscle(7)The termination of free end For hook structure, hook structure catches on structure side bar reinforcing bar(8).
  3. 3. direct burial rigid connecting tube according to claim 1, it is characterised in that:Double fasteners(5)For right-angle coupler.
  4. 4. direct burial rigid connecting tube according to claim 1, it is characterised in that:Wall-connecting piece is being set(4)Position simultaneously With vertical rod(1)Stagger a steel pipe opening position, side form(11)Template is cut, and circular reserved opening is opened up cutting opening position (12), circular reserved opening(12)Diameter is bigger than diameter of steel tube;
    Circular reserved opening(12)Along vertical rod(1)Position is adjusted up and down, it is ensured that meets wall-connecting piece(4)Steel pipe apart from host node not More than 30cm.
  5. 5. direct burial rigid connecting tube according to claim 4, it is characterised in that:Side form(11)Two pieces of moulds that template is cut The plate lumps of wood(13)Reinforce.
  6. 6. direct burial rigid connecting tube according to claim 1, it is characterised in that:Wall-connecting piece(4)The termination of steel pipe blocks Firmly.
CN201720659577.2U 2017-06-08 2017-06-08 Direct burial rigid connecting tube Active CN206815805U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720659577.2U CN206815805U (en) 2017-06-08 2017-06-08 Direct burial rigid connecting tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720659577.2U CN206815805U (en) 2017-06-08 2017-06-08 Direct burial rigid connecting tube

Publications (1)

Publication Number Publication Date
CN206815805U true CN206815805U (en) 2017-12-29

Family

ID=60759238

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720659577.2U Active CN206815805U (en) 2017-06-08 2017-06-08 Direct burial rigid connecting tube

Country Status (1)

Country Link
CN (1) CN206815805U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115126211A (en) * 2022-06-23 2022-09-30 恩施清江大龙潭水电开发有限公司 Scaffold erecting method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115126211A (en) * 2022-06-23 2022-09-30 恩施清江大龙潭水电开发有限公司 Scaffold erecting method

Similar Documents

Publication Publication Date Title
CN105569330B (en) Building outer frame large-section special-shaped column reinforced formwork and construction method thereof
CN105863253B (en) Integral formwork support is asynchronous to pour staircase wall column formwork system and construction method
CN105298120B (en) A kind of template fast-supporting device
CN209482591U (en) Prefabricated molds shell structure column construction structure
CN203856202U (en) Simple pullable sizing device of reserved holes
CN204983662U (en) To drawing screw rod and steel pipe framed bent combination unilateral formwork device
CN206233596U (en) Building block exterior wall constructional column concrete casting device
CN109208790A (en) Circular arc shear wall single side formwork construction method
CN105178591A (en) Small-gap double-shear-wall deformation joint formwork and construction method thereof
CN206815805U (en) Direct burial rigid connecting tube
CN211228607U (en) Integrally formed construction structure of outer wall and bottom plate of cast-in-place concrete structure of structure
CN104153573A (en) Pouring formwork and construction method for V-shaped cylindrical concrete
CN104912209B (en) Bars In Poured Concrete Slab reserved holes of pipes plugging device and processing and plugging construction method
CN208792746U (en) A kind of expansion joint regularization same tool steel plate template
CN207469596U (en) A kind of beam column outer rim is exempted to tear concrete mold open
CN104746791B (en) Semirigid frame-interior fills out regeneration concrete wallboard and manufacture method
CN208267362U (en) A kind of constructing device of deformation joint concrete wall formwork
CN206220132U (en) A kind of base plate and exterior wall junction construction typified form support
CN206319404U (en) A kind of building precast exterior sheathing
CN103410344B (en) A kind of steel concrete wall beam strengthen device and wall beam Enhancement Method
CN102322022B (en) Construction method for concrete of decorative housing of cable stayed bridge
CN214302829U (en) Scaffold wall connecting piece structure of high-impermeability shear wall
CN206385794U (en) Wall connecting piece and connecting system thereof
CN214117507U (en) Convenient ring beam template system is dismantled in installation
CN106193578B (en) It is a kind of that modular system and construction technology are matched somebody with somebody based on groove type quarter bend

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant