CN206815165U - Track traffic steel reinforced concrete combines trough girder - Google Patents

Track traffic steel reinforced concrete combines trough girder Download PDF

Info

Publication number
CN206815165U
CN206815165U CN201720510696.1U CN201720510696U CN206815165U CN 206815165 U CN206815165 U CN 206815165U CN 201720510696 U CN201720510696 U CN 201720510696U CN 206815165 U CN206815165 U CN 206815165U
Authority
CN
China
Prior art keywords
steel
girder
track
connector
girder steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720510696.1U
Other languages
Chinese (zh)
Inventor
秦大航
艾凌
李照明
李江
马树田
李盼到
徐亮
许欣
徐艳玲
马利君
高应振
胡松松
刘平
刘一平
王鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing General Municipal Engineering Design and Research Institute Co Ltd filed Critical Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201720510696.1U priority Critical patent/CN206815165U/en
Application granted granted Critical
Publication of CN206815165U publication Critical patent/CN206815165U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses support and connector, steel beam web plate, steel beam web plate stiffening construction, girder steel bottom plate and stiffening construction and girder steel and track structure connecting structure on a kind of track traffic steel reinforced concrete combination trough girder, including concrete top flange, girder steel.Girder steel bottom plate and stiffening construction are connected by connector with girder steel with track structure connecting structure, and girder steel and track structure connecting structure are concrete structure, lay solid concrete roabed plummer or ballast bed thereon;Steel beam web plate is fixed with by connector in girder steel bottom plate and stiffening construction both sides;The upper end of steel beam web plate is fixedly connected with support and connector on girder steel, and concrete top flange and steel beam web plate are connected to become entirety by support and connector on girder steel.Technical problem that loss of weight, span ability that the utility model can solve track traffic steel reinforced concrete combination trough girder are big, comprehensive cost is cheap etc..

Description

Track traffic steel reinforced concrete combines trough girder
Technical field
It the utility model is related to a kind of track traffic facility.More particularly to a kind of track girder technology.
Background technology
With the national economic development and social progress, the trip of big city people is increasingly relied in track traffic, and right Rail line in connection city and suburb, overhead section is inevitable, and the track girder for being used to carry train is overhead The most important component of structure.
Trough girder has the following advantages that:
1) building height is low, Bridge Landscape is good:Trough girder is base-supporting structure, and the more general beam type of building height reduces about 1.3m (by 30m exemplified by), Bridge Landscape effect is good, and is arranged beneficial to track profile.
2) excellent noise reduction effect:When rail traffic vehicles travel on beam channel, its wheel track walking system noise is by both sides master Beam top flange and the barrier of web, reduce influence of the vehicle noise to surrounding environment to a certain extent;And relative box-girder, Beam channel is without casing resonance noise.
3) functionals:Using web top surface as emergency evacuation, access path, cable is used as by the use of web inner side Passage.
4) have a safety feature:There is prevention effect to the derailing situation being likely to occur:Twice abutment wall can ensure that train security row Sail, prevent derailing and overturn accident.
5) comprehensive economy is excellent:Due to saving side shield and escape platform outside conventional beam type, and simplify sound barrier Set, compound material dosage is few, low engineering cost.
Because trough girder has many advantages, such as above-mentioned, it is used widely in urban rail transit in China.But due to Standard channel beam is both designed as prestressed reinforced concrete construction at present, and general span is no more than in 30m, it is difficult to adapt to line crossing road Road, the needs in river, therefore it is excessive that Cast-in-situ Beam need to be set to carry out at node, constrains the mark of line construction to a certain extent Standardization and mechanization, and it is connected the overall landscape effect that also have impact on bridge between Standard Beam and node bridge.
The content of the invention
The purpose of this utility model is to provide a kind of track traffic steel reinforced concrete combination trough girder, to solve track traffic steel reinforced concrete group Technical problem that the loss of weight, the span ability that close trough girder are big, comprehensive cost is cheap etc..
In order to realize foregoing invention purpose, technical scheme is as follows used by the utility model:
Support and connector (2), girder steel on track traffic steel reinforced concrete combination trough girder, including concrete top flange (1), girder steel Web (3), steel beam web plate stiffening construction (4), girder steel bottom plate and stiffening construction (5) and girder steel and track structure connecting structure (6); It is characterized in that:Track girder is undertaken by the girder steel bottom plate and stiffening construction (5) of curved caused tension by connector and girder steel It is connected with track structure connecting structure (6), girder steel and track structure connecting structure (6) are concrete structure, and laying is overall thereon Railway roadbed plummer is ballast bed;Girder steel bottom plate and stiffening construction (5) both sides be fixed with by connector undertake track girder by The steel beam web plate (3) of curved shear stress;The upper end of steel beam web plate (3) is fixedly connected with support and connector (2) on girder steel, on girder steel Concrete top flange (1) and steel beam web plate (3) are connected to become entirety by support and connector (2);Steel beam web plate stiffening construction (4) The steel beam web plate stiffening construction (5) for also serving as track girder cable bearer of inner side is arranged as required to vertically put more energy into or/and level Put more energy into.
Connector is as needed using a kind of type of attachment in WELDING STUDS, PBL shear connectors or welding U-shaped muscle.
Described steel beam web plate (3) is made using general steel plate or setback steel plate.
Bottom plate longitudinal stiffener uses board-like rib or inverted T-shaped rib as needed for described girder steel bottom plate and stiffening construction (5), Transverse stiffener uses inverted T-shaped rib.
The utility model has the following advantages that:
Track traffic steel reinforced concrete combination trough girder uses section top flange of the concrete material as simply supported beam, can give full play to Its compressive property;Steel construction is used in tensile zone, while material tensile property is given full play to, has effectively evaded steel construction Resistance to compression stable problem.Steel reinforced concrete combination groove profile girder span gets over ability and is better than conventional Pre-stress Concrete U-Shaped Beam, can further expand groove The use range of type beam;Equal across footpath steel reinforced concrete combination trough girder is only conventional Pre-stress Concrete U-Shaped Beam weight simultaneously 60%, and prestressed setting is eliminated, reduce difficulty of construction and construction period.Although steel reinforced concrete combination trough girder is more pre- in itself Prestressed concrete groove profile deck-molding, but with cast-in-place node bridge integrate essential, its economy still has some superiority, and meets state Family goes the requirement of production capacity on green and steel.
Brief description of the drawings
Fig. 1 is structure section figure of the present utility model.
Numbered in figure:1st, concrete top flange, 2, support and connector on girder steel, 3, steel beam web plate, 4, steel beam web plate adds Strength constructs, 5, girder steel bottom plate and stiffening construction, 6, girder steel and track structure connecting structure, 7, solid concrete roabed, 8, ballast bed, 9, Cable bearer, 10, line of symmetry.
Embodiment
The utility model is shown in Figure 1.Track traffic steel reinforced concrete combines trough girder, including concrete top flange (1), girder steel Upper support and connector (2), steel beam web plate (3), steel beam web plate stiffening construction (4), girder steel bottom plate and stiffening construction (5) and girder steel With track structure connecting structure (6);Girder steel bottom plate and stiffening construction (5) pass through connector and girder steel and track structure connecting structure (6) connect, girder steel and track structure connecting structure (6) are concrete structure, lay solid concrete roabed plummer or rubble road thereon Bed;Steel beam web plate (3) is fixed with by connector in girder steel bottom plate and stiffening construction (5) both sides;The upper end of steel beam web plate (3) is consolidated Surely support and connector (2) on girder steel are connected, support and connector (2) are by concrete top flange (1) and steel beam web plate on girder steel (3) it is connected to become entirety.
Concrete top flange mainly undertakes track girder by curved caused compression, while still sound barrier, electrical control are strong Deng basis, escape platform when can also also serve as emergency evacuation uses.Conventional concrete or high-strength coagulation can be used as needed Soil;According to execution conditions, may be selected simultaneously prefabricated with girder steel in factory;It is prefabricated in the factory, in-site installation or scene are poured Build.
Support and connector are that contact concrete top flange and steel beam coupling device, connector can be adopted as needed on girder steel With forms such as WELDING STUDS, PBL shear connectors or welding U-shaped muscle.
Steel beam web plate is the main member for undertaking track girder shearing, and general steel plate or setback steel plate can be used to make.
Steel beam web plate stiffening construction is to ensure steel beam web plate by cutting stable and web transverse strength, the main member of rigidity, Track girder cable bearer can be also also served as, it is settable vertical as needed to put more energy into and sash.
Girder steel bottom plate and stiffening construction mainly undertake track girder by curved caused tension, and it is laterally strong to be also to provide bottom plate Degree, the main member of rigidity, bottom plate longitudinal stiffener as needed can use board-like rib or inverted T-shaped rib, and transverse stiffener uses Inverted T-shaped rib.
Girder steel and track structure connecting structure are solid concrete roabed track or ballast bed supporting construction, are concrete knot Structure, connected by WELDING STUDS, PBL shear connectors or welding U-shaped muscle and girder steel bottom plate reinforcing construction.According to execution conditions, may be selected It is simultaneously prefabricated with girder steel in factory;It is prefabricated in the factory, in-site installation or scene are poured.
Method for bridge construction:
Girder steel construction part prefabrication, on-site hoisting are constructed, and are poured after concrete flange plate, need to be taken measures to prevent when pouring Only building materials drop.Substructure cast-in-site is constructed.
Main girder construction technological process:
Factory process girder steel construction part, welding top flange concrete connector, girder steel and track structure connector.
Factory completes girder steel construction part and all connector preservative treatments.
On-site hoisting girder steel construction part.
The live colligation edge of a wing and girder steel and track structure connecting portion reinforcing bar.
Pour into a mould top flange concrete.
Pour into a mould girder steel and track structure connecting portion concrete.
Construction waterproof layer and protective layer, construction track structure, installation expansion joint, cable bearer etc..

Claims (4)

1. support and connector (2), girder steel abdomen on track traffic steel reinforced concrete combination trough girder, including concrete top flange (1), girder steel Plate (3), steel beam web plate stiffening construction (4), girder steel bottom plate and stiffening construction (5) and girder steel and track structure connecting structure (6);Its It is characterised by:Undertake track girder by curved caused tension girder steel bottom plate and stiffening construction (5) by connector and girder steel with Track structure connecting structure (6) connects, and girder steel and track structure connecting structure (6) are concrete structure, lay overall road thereon Bed plummer or ballast bed;It is fixed with by connector in girder steel bottom plate and stiffening construction (5) both sides and undertakes track girder by curved Shear stress steel beam web plate (3);The upper end of steel beam web plate (3) is fixedly connected with support and connector (2) on girder steel, is held on girder steel Concrete top flange (1) and steel beam web plate (3) are connected to become entirety by support and connector (2);In steel beam web plate stiffening construction (4) The steel beam web plate stiffening construction (4) for also serving as track girder cable bearer of side is arranged as required to vertically put more energy into or/and level adds Strength.
2. track traffic steel reinforced concrete as claimed in claim 1 combines trough girder, it is characterised in that connector uses cut as needed A kind of type of attachment in power nail, PBL shear connectors or welding U-shaped muscle.
3. track traffic steel reinforced concrete as claimed in claim 1 combines trough girder, it is characterised in that described steel beam web plate (3) is adopted Made of general steel plate or setback steel plate.
4. track traffic steel reinforced concrete as claimed in claim 1 combines trough girder, it is characterised in that described girder steel bottom plate and puts more energy into Bottom plate longitudinal stiffener uses board-like rib or inverted T-shaped rib to construction (5) as needed, and transverse stiffener uses inverted T-shaped rib.
CN201720510696.1U 2017-05-10 2017-05-10 Track traffic steel reinforced concrete combines trough girder Active CN206815165U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720510696.1U CN206815165U (en) 2017-05-10 2017-05-10 Track traffic steel reinforced concrete combines trough girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720510696.1U CN206815165U (en) 2017-05-10 2017-05-10 Track traffic steel reinforced concrete combines trough girder

Publications (1)

Publication Number Publication Date
CN206815165U true CN206815165U (en) 2017-12-29

Family

ID=60755543

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720510696.1U Active CN206815165U (en) 2017-05-10 2017-05-10 Track traffic steel reinforced concrete combines trough girder

Country Status (1)

Country Link
CN (1) CN206815165U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108374316A (en) * 2018-02-07 2018-08-07 湖南省交通规划勘察设计院有限公司 Medium-and low-speed maglev traffic combination beam element, medium-and low-speed maglev traffic combination beam, rail system and construction method
CN112921784A (en) * 2021-01-27 2021-06-08 中铁大桥勘测设计院集团有限公司 Rail transit steel-concrete composite beam with sound insulation function
CN113272496A (en) * 2018-11-30 2021-08-17 维拉萨米·塔瓦马尼 潘迪 Construction system for double-U-shaped and single-U-shaped reinforced concrete composite structure of bridge
CN114232462A (en) * 2021-12-29 2022-03-25 哈尔滨工业大学 Urban rail transit corrugated steel-concrete U-shaped combination beam and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108374316A (en) * 2018-02-07 2018-08-07 湖南省交通规划勘察设计院有限公司 Medium-and low-speed maglev traffic combination beam element, medium-and low-speed maglev traffic combination beam, rail system and construction method
CN113272496A (en) * 2018-11-30 2021-08-17 维拉萨米·塔瓦马尼 潘迪 Construction system for double-U-shaped and single-U-shaped reinforced concrete composite structure of bridge
CN112921784A (en) * 2021-01-27 2021-06-08 中铁大桥勘测设计院集团有限公司 Rail transit steel-concrete composite beam with sound insulation function
CN114232462A (en) * 2021-12-29 2022-03-25 哈尔滨工业大学 Urban rail transit corrugated steel-concrete U-shaped combination beam and construction method thereof
CN114232462B (en) * 2021-12-29 2024-05-03 哈尔滨工业大学 Urban rail transit corrugated steel-concrete U-shaped composite beam and construction method thereof

Similar Documents

Publication Publication Date Title
CN206815165U (en) Track traffic steel reinforced concrete combines trough girder
CN102926299B (en) Railway elevating and fixing device and railway bridge and culvert construction method adopting railway elevating and fixing device
CN110582609B (en) Construction system and method for combined U-shaped reinforcing beam bridge floor
CN207891661U (en) A kind of medium-and low-speed maglev traffic track beam and rail system
CN104594173B (en) One kind embraces rail magnetic levitation track traffic box beam
US20130264394A1 (en) Pre-stressed concrete track slab of slab-type ballast-less track
CN108867310A (en) The short rib T beam bridge of pretensioning prestressed concrete and its construction method
CN105178164B (en) Prefabrication and lifting fish belly Wavelike steel webplate prestressing with bond combined box beam and its construction method
US4905896A (en) Railroad roadway for high speed rail-mounted vehicles
CN206328642U (en) A kind of board-like track structure of framework in tunnel
CN208293453U (en) In a kind of railway beam plus the anti-fall stone structure of vault hangar tunnel
CN109868721A (en) A kind of integrated precast bridge floor affiliated facility
CN203065950U (en) Railway bridge composed of simply-supported T-shaped beams
CN204849562U (en) Little box girder bridge roof beam
CN105888281A (en) Method for utilizing jacking storey-adding technique to promote integrated function of community
CN201891068U (en) U-shaped prestressed concrete continuous beam bridge
CN105803923B (en) Inter-city passenger rail Simple T-Girders pavement combining structure and combined method
CN106812244A (en) The preparation method of the continuous superposed floor of precast beam, prefabricated PC and superstructure
CN208328660U (en) The U-shaped girder construction of the Two bors d's oeuveres of combined bridge
CN103911948B (en) Be applied to horizontal purlin formula steel work and the construction method thereof of wide concrete rib plate-girder
CN110258633A (en) A kind of Underground Station section of track well with prestressed concrete beam
CN208009170U (en) Plate-type ballastless track on a kind of steel truss girder bridge
CN212337358U (en) Connection structure of evacuation platform in shield zone at interconnection channel
CN109024266B (en) Central separation belt concrete wall type guardrail connecting structure meeting double-bridge settlement difference and construction method
CN211947900U (en) Railway steel structure channel beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant