CN206807023U - A kind of secondary ladder of battery utilizes system - Google Patents

A kind of secondary ladder of battery utilizes system Download PDF

Info

Publication number
CN206807023U
CN206807023U CN201720267340.XU CN201720267340U CN206807023U CN 206807023 U CN206807023 U CN 206807023U CN 201720267340 U CN201720267340 U CN 201720267340U CN 206807023 U CN206807023 U CN 206807023U
Authority
CN
China
Prior art keywords
battery
ladder
bag
energy
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720267340.XU
Other languages
Chinese (zh)
Inventor
陈霞
吕大伟
管凤强
王芳
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Fengguang Tianfu Technology Co Ltd
Original Assignee
Beijing Fengguang Tianfu Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Fengguang Tianfu Technology Co Ltd filed Critical Beijing Fengguang Tianfu Technology Co Ltd
Priority to CN201720267340.XU priority Critical patent/CN206807023U/en
Application granted granted Critical
Publication of CN206807023U publication Critical patent/CN206807023U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The utility model provides a kind of secondary ladder of battery and utilizes system, including:New-energy automobile system, it is cell power systems automobile, is charged by network system to its cells bag;Battery recycling system, the retired battery to get off of new-energy automobile system are sent to battery recycling system;Battery ladder utilizes system, to battery recycling system processing after battery bag carry out postsearch screening, in battery bag monomer carry out it is secondary form new battery bag in groups, provide energy storage release for grid-connected power generation system;Grid-connected power generation system, it can independently generate electricity by way of merging two or more grid systems;Network system, it is power network Transfer pipe in power system.The utility model effectively solves field of new energy generation itself and intermittent electric power be present, and load mismatches with generating dutation, dispatches the problems such as difficult, at the same also cracked the growing retired battery of swift and violent new-energy automobile scrap, the problem that cost recovery is high.

Description

A kind of secondary ladder of battery utilizes system
Technical field
The utility model belongs in power system, and chemical energy storage utilizes field, in particular to a kind of secondary ladder of battery Utilize system.
Background technology
Clearly, by the end of the year 2014, China exists for domestic generation of electricity by new energy in recent years and new-energy automobile speedup The first in the world is sure to occupy in wind-power electricity generation and solar power generation installed capacity.State Council issues《Energy development strategy action plan (2014-2020)》, solar power generation is clearly accelerated development, the year two thousand twenty photovoltaic installed capacity target is 100GW.There is scholarly forecast " 13 " planning photovoltaic installation target is expected to by 100GW final adjustments before be 200GW.
The ring of light that new energy power station is quickly expanded mask behind its technology development relatively lag behind, power station energy waste it is serious The problem of, such as domestic photovoltaic plant and wind-power electricity generation abandon light, abandon wind rate and remain high, if these problems do not take perfect solution Decision-making slightly all will cause the huge electricity charge to waste to operation user.
For " abandoning light to ration the power supply " problem, there are two kinds of solutions:Firstth, electric power Transmission Corridor is built.But electric power is sent outside logical The construction period in road is long, generally requires the time of 3 years;Secondth, chemical energy storage is developed, the power station energy-storage system construction period is non- It is often short, it can put into operation within 3~6 months, but input cost is huge.In view of importance of the energy storage to regenerative resource, national governments are Through bringing up to the status being mutually equal with regenerative resource to the attention degree that energy storage technology develops.The new lithium battery of another aspect Hold at high price, and cause power station chemical energy storage system cost very high, so as to constrain its popularization in photovoltaic art.With Exemplified by 100MW photovoltaic plants, battery energy storage system average price is not less than 3000 yuan/KWh, if matching somebody with somebody according to installed capacity 10% Energy-storage system, the index request of 2 hours of energy storage are put, it is necessary to which 20MWh energy-storage system, investment amount are 60,000,000.
The utility model possesses generation of electricity by new energy echelon and utilizes battery energy storage system total solution, and its composite price is about 6,000,000 yuan of investment is only needed effectively to solve generation of electricity by new energy power station for 10%, the 100MW photovoltaic plants of new lithium battery system Abandon light and abandon wind problem, be embodied as the purpose of client's " increasing income ".
On the other hand, Zhong Guan-cun energy storage industrial technology alliance June in this year issue《Energy storage industrial research white paper 2015》 Prediction, to the year two thousand twenty, Chinese energy storage market capacity can reach 67GW.In addition, the fast development with electric automobile market, it will Continue the second-hand lithium battery of shutout magnanimity, it is contemplated that to the year two thousand twenty, 10GWh retired electrokinetic cell scale can be had more than, battery returns Receive and recycle problem to have increased to national policy aspect.
The new energy field feature of table 1 and present situation
The utility model innovatively proposes the retired secondary ladder of electrokinetic cell to get off of new-energy automobile to recycle Field of new energy generation, solve, because intermittent electric power, load are asynchronous with generating electricity existing for generation of electricity by new energy, to cause largely to abandon Wind, abandon light belt to investor's massive losses the problem of.Also solves the retired battery capacity damage got off of new-energy automobile simultaneously Mistake is less big, cheap, but scraps the problem of cost recovery is high;Effectively solve field of new energy generation itself and intermittence be present Generate electricity, load mismatches with generating dutation, dispatches the problems such as difficult;Growing swift and violent new-energy automobile is also cracked simultaneously The problem that retired battery is scrapped, cost recovery is high.The method can crack simultaneously has new-energy automobile and generation of electricity by new energy two is big The problem of new energy field, the two is together in series with network system, one energy closed loop platform of form, there is extremely strong innovation Property.The utility model has that theory is advanced, technological innovation, advanced, the characteristics of scheme novelty, meets at present and WeiLai Technology and warp Ji development trend.Compared to accelerate power channel construction, water-storage, set up new chemical energy storage have obvious price advantage and Operable space, there is huge economic and social benefit.
Utility model content
The problem of existing for prior art and new energy itself present situation, the utility model provide a kind of secondary ladder of battery Utilize system.The utility model has extremely strong novelty.With using energy source theory is advanced, scheme is novel, principle is simple, is System is succinct, solves the problems, such as that new-energy automobile and generation of electricity by new energy have significant effect and shown.Had based on system of the present utility model There is the construction period short, less investment, income is fast, can voluntarily run or receive management and running, stable and reliable in work, compatible strong, peace Dress flexibly, quick, rapid dynamic response speed the features such as.The income of generation of electricity by new energy and new-energy automobile can effectively be lifted.Entirely The secondary ladder of battery has that stable, reliable, intelligence degree is high using system, and new energy truly can be achieved again Utilize.A kind of secondary ladder of battery of the utility model is matched using system and method to generation of electricity by new energy power station simultaneously, simultaneous Capacitive is strong, and improvement cost is low, after setting up can completely with grid dispatching center seamless the advantages that interacting.The utility model is mainly applied In some large-sized photovoltaic power stations, wind-power electricity generation and some have the field of the intermittent feature that generates electricity, have great market prospects and Social effect.
The purpose of this utility model is realized using following technical proposals:
A kind of secondary ladder of battery utilizes system, it is characterised in that including:New-energy automobile system, it is battery power system System automobile, its cells bag is given to charge by network system;Battery recycling system, the retired battery to get off of new-energy automobile system It is sent to battery recycling system;Battery ladder utilizes system, and postsearch screening is carried out to the battery bag after the processing of battery recycling system, Monomer progress is secondary in battery bag forms new battery bag in groups, and energy storage release is provided for grid-connected power generation system;New energy is sent out Electric system, it can independently generate electricity by way of merging two or more grid systems;Network system, it is power network Transfer pipe in power system.
Battery ladder includes battery screening unit using system, battery matches secondary group production cell, battery charging and discharging management Unit, it is secondary in groups after battery bag and battery management unit with active equalization, wherein battery screening unit, battery matching two Secondary group production cell, it is secondary in groups after battery bag be sequentially connected, battery charging and discharging administrative unit be connected to it is secondary in groups after electricity Chi Bao, the battery management unit with active equalization are controlled to whole battery ladder using system.
Battery screening unit, which possesses, to be carried out secondary identification to each battery cell contained in battery bag, differentiates, classification Function.
Battery match secondary group production cell realize the battery cell after the screening of battery screening unit carry out it is secondary into Group.
Battery charging and discharging administrative unit includes the three phase full bridge converter unit based on electronic power switch composition, wherein electric power Electronic switch is insulated gate bipolar transistor IGBT.
Battery management unit with active equalization is the key control unit that battery ladder utilizes system, and it manages and controlled Whole battery ladder is flowed on demand using the energy of system, receives dispatch command energy storage release.
Battery recycling system includes battery information collecting unit and battery sorting unit.
Battery information collecting unit includes a set of communication system, passes through the battery management unit on communication system and battery bag Communication, read information.
Battery sorting unit can recognize battery type, state, Ran Houzai automatically by reading the beacon information in battery bag Classified, in groups.
Grid-connected power generation system, it is photovoltaic generating system and/or wind generator system.
Compared with the prior art, the beneficial effects of the utility model are:
1st, a kind of secondary ladder of battery of the utility model utilizes system, have it is with strong points, can effectively solve because of new energy The retired number of batteries that automobile fast development is brought is huge;Handled compared to directly scrapping, it is necessary to consume the huge energy, enterprise's needs The technical method of huge scraping expense is paid, there is obvious economic sexual clorminance and social benefit.Directly scrap, disassemble with existing Processing mode compare, have green, environmental protection, the huge technical advantage of cycling and reutilization.
2nd, a kind of secondary ladder of battery of the utility model utilizes system, have it is with strong points, can effectively solve photovoltaic plant Have that intermittent electric power, energy output pulsation big, generating peak and power load are asynchronous, and scheduling is difficult with wind-power electricity generation itself The problem of.Compared with the existing way directly abandoned light, abandon wind brings huge economic losses to investor and operator, have obvious Economy and technical advantage.
3rd, the utility model is used from the method for building energy circulation platform, connects main flow generation of electricity by new energy and electricity consumption neck Domain, and the respective independent operation of existing new energy field, the at a loss what to do of the problem of independent face exists to itself are compared, and have theory Innovative, technological innovation.
4th, region-wide property battery letter can be achieved using internet cloud platform is based in the utility model battery information acquisition system Typing is ceased, information sharing, for back battery sorting flow larger range of screening space is provided, realizes battery sorting efficiency most Bigization.With contain much information, fast, the advantage of operation readiness.
5th, the utility model battery charging and discharging management system is mainly complete by the three-phase formed based on high-speed power electronic switch Bridge converter unit, wherein electronic power switch are the insulated gate bipolar transistor IGBT based on main flow, have working stability can Lean on, the advantages that switching speed is fast, own loss is low, and power density is big, long lifespan, fast dynamic response.
6th, battery management unit of the utility model with active equalization, there is battery cell in monitoring battery system in real time State, the active equalization between internal each battery cell can be carried out in real time, is realized in discharge and recharge, energy storage and release can efficiency maximum Change, the maximized effect of battery bag population size, compared with existing passive balancing technique, there is energy-conservation, efficient, battery capacity profit With the advantage that rate is high, electric energy release is long, service life is grown.
7th, battery management unit of the utility model with active equalization, its own band remote monitoring system, can pass through in real time High in the clouds uploads of battery state, can be monitored by a distant place, controlled, so as to realize that system high reliability works.
8th, battery management unit of the utility model with active equalization, itself there are powerful communication interaction capabilities, can be with The real-time slitless connection of electric power system dispatching department, it is easy to system fading margin, scheduling.
9th, the secondary ladder of the utility model battery is intrinsic with respect to solving new energy itself with new energy-storage battery using system Problem, there is effect that is cost-effective, turning waste into wealth, new-energy automobile, two big field of generation of electricity by new energy are really passed through power network System interconnection is got up, and forms energy efficient flowing ring.
Brief description of the drawings
Fig. 1 is that a kind of secondary ladder of battery utilizes system schematic.
Fig. 2 is that a kind of secondary ladder of battery utilizes fundamental diagram.
Embodiment
Specific embodiment of the present utility model is described in further detail below in conjunction with the accompanying drawings.
As shown in figure 1, new-energy automobile is charged by network system to electrokinetic cell bag, power is provided for new-energy automobile Source;The retired battery to get off of new-energy automobile is handled by the secondary ladder of battery using system, becomes cost-effective Energy-storage system, energy of the receiving as needed in grid-connected power generation system, steady and support generation of electricity by new energy power swing, Also the energy previously stored can be discharged as needed, and energy is released to network system by grid-connected power generation system.So as to whole system It is together in series by the secondary ladder of battery using new-energy automobile, generation of electricity by new energy, network system, so as to realize whole platform Energy-controllable, safe and reliable regulation, scheduling.
Handled by the secondary ladder of battery using system, the recovery of puzzlement new energy car battery, scrap cost is high asks Topic is thoroughly solved, while by optimizing again in groups, the retired battery bag got off is applied in field of new energy generation, i.e., With relatively low energy storage input cost, solves the existing intermittent electric power of photovoltaic plant itself, output-power fluctuation is big, scheduling is tired Difficult, output electric energy and the nonsynchronous problem of power load, by with relatively low price, solving photovoltaic plant itself and inherently asking Topic, ensure that as photovoltaic plant O&M maximum revenue.
A kind of secondary ladder of battery utilizes System Working Principle such as Fig. 2, includes new-energy automobile system 1, battery recycling system System 2, battery ladder utilize system 3, grid-connected power generation system 4, network system 5.The retired power to get off of new-energy automobile system 1 Battery, battery recycling system 2 is sent to, carries out postsearch screening, screen, the secondary cell after the processing of battery recycling system 2, sent Utilize system 3 to battery ladder, carry out it is secondary in groups and according to the actual requirements, composition different capabilities, the battery of voltage class Bag, mixes the battery management unit of active equalization, management of charging and discharging unit, battery ladder is then utilized system 3, applied new Energy electricity generation system 4, such as solar energy power generating, field of wind power generation, solve new energy self generating have it is intermittent, no The problem of stable, finally electric energy of the secondary ladder of battery using the grid-connected power generation system submitting of system is had additional, progress can Control, schedulable, smoothly it is transported to network system 5.Realize that the retired secondary power battery to get off of new-energy automobile passes through this reality The processing of system is utilized with a kind of new secondary ladder of battery, turns waste into wealth, is successfully applied in field of new energy generation, is solved The problem of field of new energy generation itself is present.Each system composition secondary cell ladder reutilization system platform described above, it is real Existing new-energy automobile and generation of electricity by new energy energy are by the way that power network is orderly, controllable, smooth transfer.The system connect new-energy automobile and Two big field of generation of electricity by new energy, efficient, green can solve the problems, such as that two big fields are present.
New-energy automobile system 1 is the dynamical system based on electrochemical lithium cells, predominantly in the market main flow is home-use new Energy car, new energy commercial affairs car, new energy minibus, new energy tourist bus car, new energy school bus, new energy public transport Car etc..
The retired dynamic lithium battery to get off of new-energy automobile system 1 is directly sent to battery recycling system 2, battery recycling system It is responsible for carrying out the information gathering and typing of lithium battery, then carries out preliminary sifting sort.
Battery recycling system 2 includes battery information collecting unit 21 and battery sorting unit 22, the two composition battery recycling System.Battery information collecting unit 21, for collecting and recording the retired battery user got off, battery bag supplier, battery make With the time limit, battery cell information, and cloud server is uploaded to by internet high in the clouds.Battery cell packet contains:Battery bag Burst mode, battery cell positive electrode type, battery cell electric parameter.Battery information collecting unit 21, also comprising a set of The general communication system being consistent with market mainstream battery management system (BMS) supplier communication protocol, passes through itself and battery bag On battery management system communication, read and export the discharge and recharge number of the battery bag life cycle, overcharge, cross put number, therefore Hinder number, battery excess temperature record.After battery information collecting unit 21 is to the retired battery bag information gathering got off, carry out The sign of Quick Response Code, so as to next step battery bag or battery cell classification, pick.Battery sorting unit 22 is by reading electricity The Quick Response Code that pond is wrapped, battery type, state can be recognized automatically, is then classified again, in groups.
Battery ladder includes battery screening unit 31 using system 3, battery matches secondary group production cell 32, battery charging and discharging Administrative unit 33, it is secondary in groups after battery bag 34, the battery management unit 35 with active equalization.Battery screening unit 31 is responsible for The retired battery of battery recycling unit 2 is carried out conformity classification, then the battery after battery screening unit 31 is handled It is sent to battery and matches secondary group production cell 32, it is secondary again in groups carries out battery cell;Then it is secondary in groups after battery unit According to actual user's demand, carry out again be assembled into different capabilities, voltage class battery bag, formed it is secondary in groups after electricity Pond bag 34, then it is secondary in groups after battery bag 34 be installed in addition with the battery management unit 35 with active equalization, by band actively it is equal The battery management unit 35 of weighing apparatus carries out monitoring in real time and as needed to each monomer in secondary groups of battery bag in real time Weighing apparatus;Finally again by configuring battery charging and discharging administrative unit 33, discharge and recharge is carried out to battery bag 34, and carry out in real time by 35 Monitoring, equalizaing charge, electric discharge, realize secondary cell it is groups of after recycling function.
Battery screening unit 31 is realized carries out postsearch screening to the battery bag after the processing of battery recycling system, and this link is main The battery bag close to identical category, status information carries out the electric performance test of battery cell, screening.By to its multiple charge and discharge Electricity process, calculate its effectively usable capacity, each piece of battery cell voltage, discharge current, temperature information carry out it is secondary identification, Differentiate, classification.The link is mainly realized monomer capacity in battery bag is low, service life is short or electric discharge/energy storage capacity is weak Monomer Selection comes out, and is replaced with performance and the close battery of residual monomer, so as to realize that the secondary ladder of whole battery bag utilizes The maximized purpose of efficiency.Battery screening unit 31 is a set of battery status detecting system hardware and software, battery bag discharge and recharge Management system hardware and software forms, and detection hardware, which includes, wherein described in battery screening unit 31 possesses 12 tunnel current detectings, 12 The sampling plate of road voltage detecting function, based on high speed numerical processor control panel, on the sampling plate there is Hall type electric current to pass Sensor, Hall type voltage sensor;The control panel has high speed digital controller, 12 bit AD sample chips of high accuracy.
Battery matches secondary group production cell 32, realizes and the battery cell after battery screening unit 31 is screened is carried out two It is secondary in groups, it is described it is secondary in groups mainly to after screening battery cell carry out it is secondary be connected in series and be connected in parallel, by swash Flush weld, and short circuit copper bar carry out the high-temperature soldering of terminal, electrical connection, in groups into more Large Copacity and the battery pack of voltage class, It is easy to the later stage to combine bag.By it is secondary in groups after battery pack can ensure that whole volume, life-span, energy storage, discharge capability reach Efficiency maximizes, and mainly matches secondary group system platform by battery, realizes battery cell and battery bag equilibrium assignment again.
Battery charging and discharging administrative unit 33, it is secondary in groups after battery bag 34, the battery management unit 35 with active equalization, Three forms one, and cooperation uses, and realizes the function that the secondary ladder of battery utilizes.Battery charging and discharging administrative unit 33 is A set of energy can with the energy management unit of two-way flow, i.e., its can by battery bag to new energy resources system 4 release can, can also Charged by new energy 4 to battery bag.Battery charging and discharging administrative unit includes the three-phase based on high-speed power electronic switch composition Full-bridge converter unit, wherein electronic power switch are the insulated gate bipolar transistor IGBT based on main flow, have working stability Reliably, the advantages that switching speed is fast, own loss is low, and power density is big, long lifespan, fast dynamic response.Battery charging and discharging management Unit 33 is controlled by the battery management unit with active equalization.It is secondary in groups after battery bag 34 be according to being actually needed, voluntarily Certain capacity is built into groups, and there is certain energy storage and release the energy-storage system of energy ability.This in groups after battery bag 34 battery Battery cell capacitance grade contained by system is close, magnitude of voltage approaches, and the ability of release current approaches.Cell tube with active equalization Reason unit 35 is the key control unit that battery ladder utilizes system 3, and it manages and controls whole battery ladder using system 3 Energy flows on demand, receive distal end and dispatch command energy storage and release can so that effectively stabilize power load and generating peak when Domain sex differernce.Battery management unit 35 with active equalization is mainly made up of a set of hardware platform and software platform.Hardware platform It is main include with current acquisition, voltage acquisition, the collection plate of battery temperature acquisition function, with monitoring and control in real time Control panel and the matrix type electronic switch balancing energy plate with balancing energy function.The collection plate consists predominantly of Hall Type current sensor chip, Hall type voltage sensor chip, wide scope, High Accuracy Thermocouple Temperature sensor;The control panel master High speed numerical processor, high-precision adc are included, the balancing energy plate is mainly included by high speed P-channel and N ditches The matrix type electronic switch of logical metal-oxide semiconductor (MOS) effect transistor composition, realizes balancing energy function, have speed it is fast, The characteristics of energy consumption is low.Battery status detection, capacity check, temperature detection, execution remote dispatching instruction after responsible realization in groups. Software platform is responsible for realizing that control algolithm is built, system protection, communication.Battery management unit with active equalization, have real-time The state of battery cell in battery system is monitored, the active equalization between internal each battery cell can be carried out in real time, realized in charge and discharge When electric, energy storage and release can efficiency maximize, the maximized effect of battery bag population size, compared with existing passive balancing technique, With energy-conservation, efficient, battery capacity utilization rate is high, electric energy release is long, the advantage of service life length.Cell tube with active equalization Unit is managed, its own band remote monitoring system, can be monitored, controlled by a distant place in real time by high in the clouds uploads of battery state System, so as to realize that system high reliability works, itself there are powerful communication interaction capabilities, can be real with electric power system dispatching department When slitless connection, be easy to system fading margin, scheduling.
Grid-connected power generation system, mainly it is made up of photovoltaic generating system 41 and/or wind generator system 42;Photovoltaic generation system System refers mainly to the large-sized photovoltaic power station by photovoltaic module, Inverter Station and primary substation composition, and what can independently be generated electricity by way of merging two or more grid systems is new Energy resource system.Wind generator system refers mainly to the large-scale wind powered generation syst by blower fan, current transformer and primary substation composition; The new energy resources system that can independently generate electricity by way of merging two or more grid systems.
Network system 5, it is power network Transfer pipe in power system, general voltage class is 10KV and/or 35KV power networks system System.
The secondary ladder of battery is carried out new-energy automobile and two big field of generation of electricity by new energy using the whole system of system Interconnection, the closed loop platform of an energy flow is formed, is utilized each other.The system make full use of new-energy automobile it is retired get off it is dynamic Power battery, remain the larger remaining capacity and life-span the characteristics of, by the processing of Tthe utility model system, reuse in new energy Source power field, can effectively solve field of new energy generation generating peak and the nonsynchronous problem of load peak, suitable for photovoltaic Electric generating station system and wind generator system.

Claims (10)

1. a kind of secondary ladder of battery utilizes system, it is characterised in that including:
New-energy automobile system, it is cell power systems automobile, is charged by network system to its cells bag;
Battery recycling system, the retired battery to get off of new-energy automobile system are sent to battery recycling system;
Battery ladder utilizes system, postsearch screening is carried out to the battery bag after the processing of battery recycling system, monomer in battery bag Carry out it is secondary form new battery bag in groups, provide energy storage release for grid-connected power generation system;
Grid-connected power generation system, it can independently generate electricity by way of merging two or more grid systems;
Network system, it is power network Transfer pipe in power system.
2. a kind of secondary ladder of battery as claimed in claim 1 utilizes system, it is characterised in that battery ladder utilizes system bag Include battery screening unit, battery matches secondary group production cell, battery charging and discharging administrative unit, it is secondary in groups after battery bag and band The battery management unit of active equalization, wherein battery screening unit, battery match secondary group production cell, it is secondary in groups after battery Bag is sequentially connected, battery charging and discharging administrative unit be connected to it is secondary in groups after battery bag, the battery management list with active equalization Member is controlled to whole battery ladder using system.
3. a kind of secondary ladder of battery as claimed in claim 2 utilizes system, it is characterised in that battery screening unit possesses pair Contained each battery cell carries out secondary identification, differentiated, the function of classification in battery bag.
4. a kind of secondary ladder of battery as claimed in claim 2 utilizes system, it is characterised in that battery matching is secondary single in groups Member is realized the battery cell progress after the screening of battery screening unit is secondary in groups.
5. a kind of secondary ladder of battery as claimed in claim 2 utilizes system, it is characterised in that battery charging and discharging administrative unit Including the three phase full bridge converter unit formed based on electronic power switch, wherein electronic power switch is insulated gate bipolar crystal Pipe IGBT.
6. a kind of secondary ladder of battery as claimed in claim 2 utilizes system, it is characterised in that the cell tube with active equalization Reason unit is the key control unit that battery ladder utilizes system, and it manages and controls energy of the whole battery ladder using system Flow on demand, receive dispatch command energy storage release.
7. a kind of secondary ladder of battery as claimed in claim 1 utilizes system, it is characterised in that battery recycling system includes electricity Pond information acquisition unit and battery sorting unit.
8. a kind of secondary ladder of battery as claimed in claim 7 utilizes system, it is characterised in that battery information collecting unit bag A set of communication system is included, is communicated by the battery management unit on communication system and battery bag, reads information.
9. a kind of secondary ladder of battery as claimed in claim 7 utilizes system, it is characterised in that battery sorting unit passes through reading The beacon information that power taking pond is wrapped, battery type, state can be recognized automatically, is then classified again, in groups.
10. a kind of secondary ladder of battery as claimed in claim 1 utilizes system, it is characterised in that grid-connected power generation system, is Photovoltaic generating system and/or wind generator system.
CN201720267340.XU 2017-03-20 2017-03-20 A kind of secondary ladder of battery utilizes system Expired - Fee Related CN206807023U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720267340.XU CN206807023U (en) 2017-03-20 2017-03-20 A kind of secondary ladder of battery utilizes system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720267340.XU CN206807023U (en) 2017-03-20 2017-03-20 A kind of secondary ladder of battery utilizes system

Publications (1)

Publication Number Publication Date
CN206807023U true CN206807023U (en) 2017-12-26

Family

ID=60730593

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720267340.XU Expired - Fee Related CN206807023U (en) 2017-03-20 2017-03-20 A kind of secondary ladder of battery utilizes system

Country Status (1)

Country Link
CN (1) CN206807023U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110401189A (en) * 2019-07-24 2019-11-01 华翔翔能电气股份有限公司 The layering grouping collaboration Optimization Scheduling of retired power battery group

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110401189A (en) * 2019-07-24 2019-11-01 华翔翔能电气股份有限公司 The layering grouping collaboration Optimization Scheduling of retired power battery group
CN110401189B (en) * 2019-07-24 2021-01-15 华翔翔能科技股份有限公司 Layered grouping cooperative optimization scheduling method for retired power battery group

Similar Documents

Publication Publication Date Title
CN106655233A (en) Secondary step utilization system of batteries
CN105449740B (en) A kind of energy-storage lithium battery active equalization control system and control method
CN204720998U (en) A kind of 1MWh container type energy-storage system
CN104319768B (en) A kind of micro-capacitance sensor is powered and method for supervising
CN202586481U (en) Micro electrical network intelligent balanced charging and power supply system
CN103441520A (en) Micro-grid distribution type new energy storage system
Zeng et al. Notice of Retraction: Research of the Problems of Renewable Energy Orderly Combined to the Grid in Smart Grid
CN203406664U (en) Micro-grid distributed new energy storing device
CN202798010U (en) Micro-grid distributed power supply layering coordination control system
CN104935075B (en) Distributed power supply access user bidirectional metering, monitoring and energy efficiency management system and distributed power supply access user bidirectional metering, monitoring and energy efficiency management method
CN206807023U (en) A kind of secondary ladder of battery utilizes system
CN110212561A (en) A kind of distributed battery energy-storage system of centralized dispatching
Nian et al. A method for optimal sizing of stand-alone hybrid PV/wind/battery system
CN203398816U (en) Power battery group equalization device
CN106671816B (en) A kind of electric car based on voltage stability index is wireless charge-discharge system and method
CN206673622U (en) A kind of battery ladder utilizes system
Bai Research on the application of renewable energy in DC data center
Zhou et al. Research on liquid metal energy storage battery equalization management system in power PSS
CN113285523A (en) Multi-station fusion data center optimization method and system based on data migration
CN207166214U (en) A kind of wind light mutual complementing energy-conservation conversion system based on controller
CN106655416A (en) Battery stepped utilization system
CN112886624A (en) Planning and designing system and method for energy storage device of three-station-in-one transformer substation
CN112491087A (en) Wind-solar-storage independent micro-grid economic optimization method based on demand side response
CN107069868A (en) A kind of retired battery energy storage managing device of balance charge/discharge
CN114784789B (en) Iron tower basic station new forms of energy storage teletransmission electrical power generating system

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171226

Termination date: 20190320

CF01 Termination of patent right due to non-payment of annual fee