CN206800207U - The arch rib installation system of bridge - Google Patents

The arch rib installation system of bridge Download PDF

Info

Publication number
CN206800207U
CN206800207U CN201720550352.3U CN201720550352U CN206800207U CN 206800207 U CN206800207 U CN 206800207U CN 201720550352 U CN201720550352 U CN 201720550352U CN 206800207 U CN206800207 U CN 206800207U
Authority
CN
China
Prior art keywords
arch rib
section
saddle
mounting bracket
rib section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720550352.3U
Other languages
Chinese (zh)
Inventor
李远文
彭鑫
黄秋莹
黄木荣
李建明
欧阳静达
陈达文
刘振力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU MUNICIPAL ENGINEERING MACHINERY CONSTRUCTION CO LTD
Original Assignee
GUANGZHOU MUNICIPAL ENGINEERING MACHINERY CONSTRUCTION CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU MUNICIPAL ENGINEERING MACHINERY CONSTRUCTION CO LTD filed Critical GUANGZHOU MUNICIPAL ENGINEERING MACHINERY CONSTRUCTION CO LTD
Priority to CN201720550352.3U priority Critical patent/CN206800207U/en
Application granted granted Critical
Publication of CN206800207U publication Critical patent/CN206800207U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The arch rib installation system of bridge is the utility model is related to, multistage arch rib section is connected into whole arch rib, including transport channel, mounting bracket, saddle, lifting system;Transport channel is used to transport arch rib section, is continuously built along the perspective plane of arch rib;Mounting bracket is arranged in rows builds successively along transport channel, and the upper end of each mounting bracket is respectively provided with top of support, and each top of support is mounted on lifting system, and lifting system is used to lift arch rib section;Each mounting bracket is respectively arranged with a saddle, and saddle is located at the lower section of corresponding lifting system, and saddle is used to arch rib section being supported on link position.The utility model can realize the aerial abutting joint of arch rib section, suitable for large-tonnage, the super-large component construction and installation of large span, large area, the construction for asymmetric, the irregular arch rib that is particularly suitable for use in, belong to bridge construction supplementary structure technical field.

Description

The arch rib installation system of bridge
Technical field
Bridge construction supplementary structure is the utility model is related to, specifically, is related to the arch rib installation system of bridge.
Background technology
At present, domestic, external steel case arch rib is more using construction works such as cable hoisting, crane barge lifting, tower crane liftings Skill, but these existing techniques are not particularly suited for the construction of asymmetric, irregular arch rib.
Utility model content
For technical problem present in prior art, the purpose of this utility model is:There is provided a kind of by multistage arch rib section Be in turn connected into the arch rib installation system of the bridge of section arch rib in the air, suitable for large-tonnage, large span, large area super large Type component construction and installation, the construction of asymmetric, irregular arch rib is particularly suitable for, in security, applicability and economy There is good result Deng many-side.
In order to achieve the above object, the utility model adopts the following technical scheme that:
The arch rib installation system of bridge, multistage arch rib section is connected into whole arch rib, including transport channel, mounting bracket, Saddle, lifting system;Transport channel is used to transport arch rib section, is continuously built along the perspective plane of arch rib;Mounting bracket is arranged in Row is built successively along transport channel, and the upper end of each mounting bracket is respectively provided with top of support, and each top of support is mounted on being lifted System, lifting system are used to lift arch rib section;Each mounting bracket is respectively arranged with a saddle, and saddle is located at corresponding lifting system Lower section, saddle are used to arch rib section being supported on link position.
As a preferred embodiment, transport channel includes track, electric flatbed tricycle, substrate, substrate is prolonged along the perspective plane of arch rib Stretch, track is laid along substrate, and electric flatbed tricycle is along rail running, through the bottom of mounting bracket.
As a preferred embodiment, substrate includes road surface section and trestle section, road surface section is set on land, and trestle section is arranged on water In.
As a preferred embodiment, substrate is located at side riverbank, the other end position of " people " word into " people " font, the both ends of " people " word In opposite side riverbank, the bifurcation of " people " word is positioned at the middle part of whole arch rib.
As a preferred embodiment, mounting bracket is the lattice support connected with girder steel;When lifting arch rib section, respective steel is removed Beam is by arch rib section by recovering to connect by rear.
As a preferred embodiment, saddle is provided with supporting mouth, arch rib section is caught in the supporting mouth of corresponding saddle, the shape of supporting mouth It is consistent with the shape of arch rib section.
As a preferred embodiment, lifting system includes two traversing jack and two lifting jacks;Two liftings are very heavy Top is connected by hoist cable with arch rib section respectively, and two tie points of two hoist cables and arch rib section are mutual on the width of arch rib Stagger, two traversing jack adjust position of two lifting jacks on the width of arch rib.
The arch rib installation method of bridge, using the arch rib installation system of bridge, arch rib is fabricated to multistage arch rib section, lower Arch rib section contraposition installation is carried out by crawler crane, the arch rib section of eminence is aligned in the air by the arch rib installation system of bridge Installation;The installation method of the arch rib section of eminence is:Arch rib section is transported to below corresponding mounting bracket by transport channel, passes through lifting Arch rib section is promoted to higher than saddle is installed after saddle by system, and lifting system adjustment arch rib section is inserted after the posture of installation site Saddle, it is welded and fixed again after the arch rib section newly inserted and the adjacent arch rib section installed are carried out into pre-connection.
As a preferred embodiment, in arch rib section lifting process, the girder steel for the mounting bracket for stopping the lifting of arch rib section is removed, arch The girder steel of dismounting is resetted installation by rib section again after;Hoist cable installation is carried out after whole arch rib installation, finally removes the arch of bridge Rib installation system.
As a preferred embodiment, the three-dimensional space meta of arch rib section is adjusted by two traversing jack and two lifting jacks Put, to control the athletic posture of arch rib section and stress distribution, carry out axis rotation and accurate adjustment in the air to arch rib section, realize The aerial docking of adjacent arch rib section.
Principle of the present utility model is:
The installation of arch rib is using " double trestle transports+superelevation assembled mounting bracket, by intelligence system control by more companies The lifting system of continuous hydraulic jack composition Synchronous lifting, the three-dimensional abutting joint in situ in high-altitude in superelevation assembled lifting bracket Technique ", rope is adjusted away from realizing arch rib rotation, axis centering is accurately positioned by continuous jack.
Substrate and track are set up along steel lagging jack projection line, as the transport channel of arch rib section, mounting bracket is set up in substrate, It is electronic by large-tonnage in top of support setting hydraulic lifting system erection & lift steel arch rib section, transport of the arch rib section in substrate Flat car transports along the track set.
After mounting bracket installation, lifting system and arch rib saddle are installed.Lifting system uses hydraulic continuous lifting thousand Jin top, intelligence system control Hydraulic Hoisting Technique are supported using flexible steel twisted wire and rigid posts, lifter cluster, intelligence system Control, hydraulic pressure lift principle are in place to predetermined altitude installation by the lifting of arch rib section.
In lifting process, the athletic posture and stress distribution of arch rib section can be not only controlled, arch rib section can also be allowed in sky Middle progress axis rotation and accurate adjustment, realize aerial docking, and completion manpower and conventional equipment are difficult to the construction task completed, made The lifting installation process of Large-scale Arch rib section is simple and efficient, securely and reliably.
Generally speaking, the utility model has the following advantages that:
1. it is simple in construction, it is easy to operate, the aerial abutting joint of arch rib section can be achieved.
2. arch rib section is transported using electric flatbed tricycle, securely and reliably.
3. using the lifting system of four jack compositions, three-dimensional regulation can be carried out to the aerial statue of arch rib section, make it Saddle is inserted to approach design orientation, realizes precisely contraposition.
4. using the underlying structure of " people " font, i.e. turnout imports the structure of main channel, and main channel is located at the projection of arch rib On face, electric flatbed tricycle enters main channel by turnout, easy to implement.
5. it is applied widely, it is especially suitable suitable for large-tonnage, the super-large component construction and installation of large span, large area In the construction of asymmetric, irregular arch rib.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the partial enlarged drawing of mounting bracket, saddle, lifting system.
Wherein, 1 is transport channel, and 2 be mounting bracket, and 3 be saddle, and 4 be top of support, and 5 be electric flatbed tricycle, and 6 be traversing Jack, 7 be lifting jack, and 8 be girder steel, and 9 be hoist cable, and 10 be arch rib section, and 11 be arch rib.
Embodiment
It is next below that the utility model is described in more detail.
The arch rib installation system of bridge, multistage arch rib section is connected into whole arch rib, including transport channel, mounting bracket, Saddle, lifting system.With reference to the traffic conditions along Gang Gou factories to job site, the mounting condition of job site, mount scheme, Optimize arch rib design segmentation.
Transport channel is used to transport arch rib section, including track, electric flatbed tricycle, substrate, perspective plane of the substrate along arch rib Extension, track are laid along substrate, and electric flatbed tricycle is along rail running, through the bottom of mounting bracket.Substrate includes road surface Section and trestle section, road surface section are set on land, and trestle section is arranged in water.Substrate is into " people " font, the both ends position of " people " word In side riverbank, the other end of " people " word is located at opposite side riverbank, and the bifurcation of " people " word is located at whole arch rib for building completion Middle part, " people " word is the structure that turnout imports main channel, and main channel is located on the perspective plane of arch rib, and electric flatbed tricycle passes through trouble Road enters main channel, and arch rib section is transported into main channel from the one end on turnout.
Mounting bracket is the lattice support connected with girder steel, need to meet the load-bearing need of arch rib section, saddle, lifting system Ask, while local girder steel is easy to assemble and disassemble, bottom can allow electric flatbed tricycle to pass through.When lifting arch rib section, remove and stop arch rib section The girder steel of rising is by arch rib section by being connected by rear recovery girder steel.Multiple mounting brackets are arranged in rows along transport channel Main channel is built successively, and the upper end of each mounting bracket is respectively provided with top of support, and each top of support is respectively arranged with one group of lifting system, often Individual mounting bracket is respectively arranged with a saddle.
Saddle is used to arch rib section being supported on link position, provided with supporting mouth, posture and position that arch rib section need to be according to design Put and be caught in the supporting mouth of corresponding saddle, the shape of supporting mouth is consistent with the shape of arch rib section, to realize exactitude position, saddle position In the lower section of the lifting system of same mounting bracket, after treating arch rib Duan Yue, correct position is just attached to.
Lifting system is used to lift arch rib section, including two traversing jack and two lifting jacks.Two liftings thousand Jin top is connected by hoist cable with arch rib section respectively, two tie points of two hoist cables and arch rib section phase on the width of arch rib Mutually stagger, two traversing jack adjust position of two lifting jacks on the width of arch rib.Lifting jack can Adjust the height of arch rib section, traversing jack can adjust the position of arch rib section in the direction of the width, the difference in height of two tie points and The corner of the adjustable arch rib section of width position difference, the cooperation of adjacent two lifting system can adjust the gradient of one section of arch rib section, Therefore the regulation of three-dimensional space position can be realized.
The arch rib installation method of bridge, arch rib is fabricated to multistage arch rib section, multistage arch rib is taken from two sides to centre successively If connection, the arch rib section of lower carries out contraposition installation by crawler crane, the arch rib installation system that the arch rib section of eminence passes through bridge Aerial contraposition installation is carried out, hoist cable installation is carried out after whole arch rib installation, finally removes the arch rib installation system of bridge.Bridge two Set up using same method side.
Substrate is laid, land lays road surface section, trestle section is laid in water, and track is laid in substrate and builds installation Frame, builds lifting system and saddle in mounting bracket, and electric flatbed tricycle drives into track.
The installation method of the arch rib section of eminence is:Arch rib section is transported to below corresponding mounting bracket by transport channel, is passed through Arch rib section is promoted to higher than saddle is installed after saddle by lifting system, and lifting system adjusts arch rib section after the posture of installation site Saddle is inserted, the arch rib section newly inserted and the adjacent arch rib section installed are carried out after pre-connection (using bolt and horse plate) again It is welded and fixed.Wherein, in arch rib section lifting process, the girder steel for the mounting bracket for stopping the lifting of arch rib section is removed, arch rib section is led to Later the girder steel of dismounting is resetted into installation again.
The co-operating of two traversing jack and two lifting jacks is controlled by intelligence control system, adjusts arch rib The three-dimensional space position of section, to control the athletic posture of arch rib section and stress distribution, axis rotation is carried out to arch rib section in the air And accurate adjustment, the aerial docking of adjacent arch rib section is realized, completion manpower and existing equipment are difficult to the construction task completed, and make big The lifting installation process of type component is simple and efficient, securely and reliably.
In addition to the mode that the present embodiment refers to, substrate can only include road surface section, can also only include trestle section, these conversion Mode is in the scope of protection of the utility model.
Above-described embodiment is the preferable embodiment of the utility model, but embodiment of the present utility model is not by above-mentioned The limitation of embodiment, it is other it is any without departing from Spirit Essence of the present utility model with made under principle change, modify, replace Generation, combination, simplify, should be equivalent substitute mode, be included within the scope of protection of the utility model.

Claims (7)

1. the arch rib installation system of bridge, multistage arch rib section is connected into whole arch rib, it is characterised in that:Including transport channel, Mounting bracket, saddle, lifting system;Transport channel is used to transport arch rib section, is continuously built along the perspective plane of arch rib;Installation branch Frame is arranged in rows to be built successively along transport channel, and the upper end of each mounting bracket is respectively provided with top of support, and each top of support is pacified Equipped with lifting system, lifting system is used to lift arch rib section;Each mounting bracket is respectively arranged with a saddle, and saddle carries positioned at corresponding The lower section of the system of liter, saddle are used to arch rib section being supported on link position.
2. according to the arch rib installation system of the bridge described in claim 1, it is characterised in that:Transport channel includes track, electronic Flat car, substrate, perspective plane extension of the substrate along arch rib, track lays along substrate, electric flatbed tricycle along rail running, Through the bottom of mounting bracket.
3. according to the arch rib installation system of the bridge described in claim 2, it is characterised in that:Substrate includes road surface section and trestle Section, road surface section are set on land, and trestle section is arranged in water.
4. according to the arch rib installation system of the bridge described in claim 2, it is characterised in that:Substrate is into " people " font, " people " word Both ends be located at side riverbank, the other end of " people " word is located at opposite side riverbank, and the bifurcation of " people " word is positioned at whole arch rib Middle part.
5. according to the arch rib installation system of the bridge described in claim 1, it is characterised in that:Mounting bracket is to be connected with girder steel Lattice support;When lifting arch rib section, corresponding girder steel is removed by arch rib section by recovering to connect by rear.
6. according to the arch rib installation system of the bridge described in claim 1, it is characterised in that:Saddle is provided with supporting mouth, arch rib section It is caught in the supporting mouth of corresponding saddle, the shape of supporting mouth is consistent with the shape of arch rib section.
7. according to the arch rib installation system of the bridge described in claim 1, it is characterised in that:Lifting system includes two traversing thousand Jin top and two lifting jacks;Two lifting jacks are connected by hoist cable with arch rib section respectively, two hoist cables and arch rib section Two tie points mutually stagger on the width of arch rib, two traversing jack adjust two lifting jacks in arch rib Width on position.
CN201720550352.3U 2017-05-17 2017-05-17 The arch rib installation system of bridge Active CN206800207U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720550352.3U CN206800207U (en) 2017-05-17 2017-05-17 The arch rib installation system of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720550352.3U CN206800207U (en) 2017-05-17 2017-05-17 The arch rib installation system of bridge

Publications (1)

Publication Number Publication Date
CN206800207U true CN206800207U (en) 2017-12-26

Family

ID=60741116

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720550352.3U Active CN206800207U (en) 2017-05-17 2017-05-17 The arch rib installation system of bridge

Country Status (1)

Country Link
CN (1) CN206800207U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988224A (en) * 2017-05-17 2017-07-28 广州市市政工程机械施工有限公司 The arch rib installation system and installation method of bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988224A (en) * 2017-05-17 2017-07-28 广州市市政工程机械施工有限公司 The arch rib installation system and installation method of bridge

Similar Documents

Publication Publication Date Title
CN108532465B (en) A kind of construction method of the main bridge of Through Steel case arch bridge
CN101117795A (en) Mounting method for steel case basket arch single-frame segment
CN203977309U (en) A kind of shuttle type culvert linear steel form carrier
CN107938520B (en) Using the method for vertical drag-line construction steel reinforced concrete combination beam
CN208122371U (en) On across the high-speed rail safe guarding shed fast dismounting device of operation line
CN103526699A (en) Method for replacing pipe bridge hanging steel ropes
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN206071141U (en) Transformer substation framework beam
CN109184189A (en) A kind of diameter Silo conical shell silo roof construction method
CN107447973A (en) A kind of unilateral suspension type aerial movement steel platform
CN106988224B (en) The arch rib installation system and installation method of bridge
CN105256728A (en) Cable-stayed bridge warren steel truss cantilever erection method
CN104831632A (en) Upper transverse beam and lower transverse beam construction method for bridge cable bent tower
CN112832368A (en) Quick construction process for cantilever beam at ultrahigh position
CN209081290U (en) Bailey truss pylon and distributing earth anchor CABLEWAY ERECTION SYSTEM that can be traversing
CN206800207U (en) The arch rib installation system of bridge
CN203199913U (en) Assembling and disassembling type hoisting truss
CN108277994B (en) Method for quickly dismantling safety protection shed of overhead high-speed rail operation line
CN207160223U (en) A kind of fulcrum-variable pin joint formula steel girder platform
CN104775572B (en) A kind of railroad platform prefabricated canopy plate of prestressing force
CN206707237U (en) Cable-stayed type top layer construction platform for elevator installation
CN201809032U (en) Self-adjusting stay device with combinable hanger
CN105625732B (en) Superelevation overhanging steel structure truss support free construction method
CN205669313U (en) A kind of Universal adjustable hangs template system
CN205329550U (en) Suspension bridge catwalk system

Legal Events

Date Code Title Description
GR01 Patent grant