CN206784638U - Include the prefabricated overlapped shear wall of steel plate - Google Patents

Include the prefabricated overlapped shear wall of steel plate Download PDF

Info

Publication number
CN206784638U
CN206784638U CN201720083843.1U CN201720083843U CN206784638U CN 206784638 U CN206784638 U CN 206784638U CN 201720083843 U CN201720083843 U CN 201720083843U CN 206784638 U CN206784638 U CN 206784638U
Authority
CN
China
Prior art keywords
concrete
steel plate
prefabricated
peg
circular hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720083843.1U
Other languages
Chinese (zh)
Inventor
李检保
汪晏
鲁正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN201720083843.1U priority Critical patent/CN206784638U/en
Application granted granted Critical
Publication of CN206784638U publication Critical patent/CN206784638U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A kind of prefabricated overlapped shear wall for including steel plate is the utility model is related to, is made up of concrete prefabricated board, steel plate, peg and cast-in-place concrete.Concrete prefabricated board is the concrete slab that thickness is 30mm 50mm, is provided with circular hole at a certain distance thereon.Steel plate is made up of Q235 steel, and thickness is 4mm 10mm, which is provided with the circular hole corresponding with concrete slab.Concrete prefabricated board and steel plate are produced by prefabrication, and both fit together.Peg uses the steel of high intensity, and quantity is consistent with the circular hole quantity on prefabricated plates.Cast-in-place concrete uses commerical ready-mixed concrete, when constructing at the scene, the casting concrete between two pieces of prefabricated plates, and peg is inserted by preformed hole, fasten peg after concrete scleroma.The prefabricated overlapped shear wall for including steel plate, which is arranged on, needs the place of lateral resistant member, in the presence of side force, due to the collective effect of steel plate and concrete, the shear wall has higher intensity, more preferable deformability, and more multi-energy can be consumed under geological process.

Description

Include the prefabricated overlapped shear wall of steel plate
Technical field
Prefabricated overlapped shear wall and steel plate shear force wall are the utility model is related to, it is pre- to make the concrete with steel plate by factory Making sheet improves the efficiency of site operation, belongs to civil engineering work technical field of structures.
Background technology
German composite plate shear wall widely uses in advanced industrial countries such as Europe, and existing scholar's research shows, overlaps Board-like shear wall structure is approximate with full-situ shear wall malformation, and its piece can effectively transmit geological process power, and protect Hold the overall performance of structure space.Using such prefabricated plus cast-in-place construction method, a large amount of templates can be saved, improve production Efficiency, and ensure the quality of works.However, it maintains the shortcomings that traditional cast-in-place concrete shear wall, i.e., larger Tensile region tensile crack can continue to develop under cyclic load, and compressive region concrete local compression destroys.
Combined steel plate concrete shear force wall be one kind in cast-in-place concrete shear wall add steel plate, shaped steel, steel truss or A kind of shear wall of other steel members.Combined steel plate concrete shear force wall has steel using amount small, and bearing capacity is big, displacement performance with it is steady It is qualitative good, the features such as relatively low, result of the test both domestic and external and numerical value analysis shows are required to structure fire-resistant performance and endurance quality, Steel plate is combined into collaborative work with concrete, forming a kind of steel-concrete combination lateral resistant member has larger theory Value and wide actual application prospect.However, it is as site concrete, inevitable substantial amounts of branch masterplate, the precision of construction It is low with efficiency comparison.
Two kinds of above-mentioned shear walls all respectively have advantage and disadvantage, therefore the prefabricated laminated steel plate shear wall knot that the utility model is related to The advantages of stating shear wall is closed, the shortcomings that improving them, it is intended that the product of high quality can be efficiently produced in produce reality.
The content of the invention
In order to solve traditional shear wall in anti-seismic performance and the contradiction of speed of application, while solves the knot of steel plate and concrete Close and protect the uncorroded problem of steel plate.The purpose of this utility model is to propose the prefabricated overlapping shearing for including steel plate Wall.The device is improved on the basis of composite plate shear wall and combined steel plate shearing force wall is played, i.e., both is combined, made Prefabricated steel plate concrete plate can cooperate with cast-in-place concrete, ensure the speed of increase construction while its intensity, subtract Few template usage amount, reaches high-quality, quick, environmentally friendly requirement.
To achieve these goals, the utility model adopts the following technical scheme that.
The utility model proposes a kind of prefabricated overlapped shear wall for including steel plate, by concrete prefabricated board 1, steel plate 2, bolt Nail 3 and cast-in-place concrete 4 form, and concrete prefabricated board 1 is the concrete slab that thickness is 30mm-50mm, is evenly distributed with thereon Circular hole, steel plate 2 are made up of Q235 steel, thickness 4mm-10mm, which is provided with the circular hole corresponding with concrete prefabricated board 1; The steel of the use high intensity of peg 3, quantity are consistent with the circular hole quantity on prefabricated plates.Cast-in-place concrete 4 uses commodity coagulation Soil, the one side of two blocks of steel plates 2 paste setting cast-in-place concrete 4 between 1 two blocks of steel plates 2 of concrete prefabricated board, two pieces of coagulations respectively Native 1, two block of steel plate 2 of prefabricated board and cast-in-place concrete 4 are fastened by peg 3.
In the utility model, the circular hole on the two block concretes prefabricated board 1, the circular hole on two blocks of steel plates 2 and peg 3 Quantity is identical.
In the utility model, peg 3 is through the circular hole on two block concrete prefabricated boards 1, the circular hole on two blocks of steel plates 2 and shows Pouring concrete 4.
In the utility model, concrete prefabricated board 1 and steel plate 2 are produced by prefabrication, and both fit together.
In the utility model, during cast-in-place simultaneously, it should be noted that poured with adjacent members, to ensure that well-formed's is whole Body.
Compared with prior art, advantages of the present invention is as follows:
(1)The utility model adds steel plate on the basis of prefabricated overlapped shear wall, can greatly improve shear wall Anti-seismic performance.
(2)Peg is set up between prefabricated board, steel plate and cast-in-place concrete, the combination of three can be better ensured that.
(3)Steel plate is arranged on the inner side of concrete, can protect it from corroding while using its advantage.
Brief description of the drawings
Fig. 1 is the prefabricated overlapped shear wall elevation that the utility model includes steel plate;
Fig. 2 is the prefabricated overlapped shear wall profile that the utility model includes steel plate;
Label in figure:1 is concrete prefabricated board, and 2 be steel plate, and 3 be peg, and 4 be cast-in-place concrete.
Embodiment
Describe the embodiment of the present invention in detail with reference to Fig. 1 and Fig. 2.
As depicted in figs. 1 and 2, the embodiment of a kind of prefabricated overlapped shear wall for including steel plate of the present utility model, it is led To include concrete prefabricated board 1, steel plate 2, peg 3 and cast-in-place concrete 4.
Concrete prefabricated board 1 is the concrete slab that thickness is 30mm-50mm, is provided with circular hole at a certain distance thereon.Steel plate 2 It is made up of Q235 steel, thickness 4mm-10mm, which is provided with the circular hole corresponding with concrete slab.The He of concrete prefabricated board 1 Steel plate 2 is produced by prefabrication, and both fit together.Peg 3 uses the steel of high intensity, quantity and the circle on prefabricated plates Hole number is consistent.Cast-in-place concrete 4 uses commerical ready-mixed concrete, when constructing at the scene, coagulation is poured between two pieces of prefabricated plates Soil 4, and peg 3 is inserted by preformed hole, fasten peg 3 after concrete scleroma.During cast-in-place, it should be noted that with adjacent structure Part pours simultaneously, to ensure the globality of well-formed.
The prefabricated overlapped shear wall for including steel plate, which is arranged on, needs the place of lateral resistant member, in the effect of side force Under, due to the collective effect of steel plate and concrete, the shear wall has higher intensity, more preferable deformability, and on ground More multi-energy can be consumed under shake effect.

Claims (3)

  1. A kind of 1. prefabricated overlapped shear wall for including steel plate, by concrete prefabricated board(1), steel plate(2), peg(3)Mixed with cast-in-place Solidifying soil(4)Composition, it is characterised in that:Concrete prefabricated board(1)The concrete slab for being 30mm-50mm for thickness, uniformly divide thereon It is furnished with circular hole, steel plate(2)It is made up, thickness 4mm-10mm, which is provided with and concrete prefabricated board of Q235 steel(1)It is corresponding Circular hole;Peg(3)Using the steel of high intensity, quantity is consistent with the circular hole quantity on prefabricated plates;Cast-in-place concrete(4)Adopt With commerical ready-mixed concrete, two blocks of steel plates(2)One side paste concrete prefabricated board respectively(1), two blocks of steel plates(2)Between set it is cast-in-place Concrete(4), two block concrete prefabricated boards(1), two blocks of steel plates(2)And cast-in-place concrete(4)Pass through peg(3)Fastening.
  2. 2. the prefabricated overlapped shear wall according to claim 1 for including steel plate, it is characterised in that:Two block concrete is pre- Making sheet(1)On circular hole, two blocks of steel plates(2)On circular hole and peg(3)Quantity it is identical.
  3. 3. the prefabricated overlapped shear wall according to claim 1 for including steel plate, it is characterised in that:Peg(3)Through two pieces Concrete prefabricated board(1)On circular hole, two blocks of steel plates(2)On circular hole and cast-in-place concrete(4).
CN201720083843.1U 2017-01-23 2017-01-23 Include the prefabricated overlapped shear wall of steel plate Expired - Fee Related CN206784638U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720083843.1U CN206784638U (en) 2017-01-23 2017-01-23 Include the prefabricated overlapped shear wall of steel plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720083843.1U CN206784638U (en) 2017-01-23 2017-01-23 Include the prefabricated overlapped shear wall of steel plate

Publications (1)

Publication Number Publication Date
CN206784638U true CN206784638U (en) 2017-12-22

Family

ID=60704860

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720083843.1U Expired - Fee Related CN206784638U (en) 2017-01-23 2017-01-23 Include the prefabricated overlapped shear wall of steel plate

Country Status (1)

Country Link
CN (1) CN206784638U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108005260A (en) * 2018-01-03 2018-05-08 浙江绿筑集成科技有限公司 A kind of assembling steel plate shear wall and its manufacture method
CN108316515A (en) * 2018-03-23 2018-07-24 广东省建筑科学研究院集团股份有限公司 A kind of prefabricated steel compound shear wall with bolt-type batten plate
CN108643391A (en) * 2018-03-23 2018-10-12 广东省建筑科学研究院集团股份有限公司 A kind of prefabricated steel compound shear wall with groove profile batten plate

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108005260A (en) * 2018-01-03 2018-05-08 浙江绿筑集成科技有限公司 A kind of assembling steel plate shear wall and its manufacture method
CN108316515A (en) * 2018-03-23 2018-07-24 广东省建筑科学研究院集团股份有限公司 A kind of prefabricated steel compound shear wall with bolt-type batten plate
CN108643391A (en) * 2018-03-23 2018-10-12 广东省建筑科学研究院集团股份有限公司 A kind of prefabricated steel compound shear wall with groove profile batten plate
CN108643391B (en) * 2018-03-23 2024-01-12 广东省建筑科学研究院集团股份有限公司 Prefabricated steel plate combined shear wall with grooved batten plates

Similar Documents

Publication Publication Date Title
US10273691B2 (en) Method of constructing a reinforced compound concrete beam containing demolished concrete lumps
CN106522440A (en) Composite floor slab based on polyphenyl granule fiber concrete sandwich insulation and construction method
CN202247707U (en) Vertical external prestress and steel plate combined reinforcing box girder structure
CN206784638U (en) Include the prefabricated overlapped shear wall of steel plate
CN105839813A (en) Assembly type thermal insulation energy saving wall board with groovechannel steel connection piece, and manufacture method thereof
CN108193588A (en) A kind of assembled steel-mixed bondbeam shear connector
CN108708551A (en) A kind of preparation method of TRC permanent formworks beam or column
CN108532810A (en) A kind of recycled concrete superposed composite floor of steel plate-
CN208502068U (en) A kind of partial precast assembly prestress girder with rolled steel section en cased in concrete
CN208219952U (en) A kind of recycled concrete superposed composite floor of steel plate-
CN208088522U (en) A kind of novel fabricated bean column node of imitative joggle
CN110130501A (en) A kind of welding procedure method suitable for combining the cement-based material of concrete structure
CN206205232U (en) Laminated floor slab based on granular polystyrene fibre concrete sandwiched thermal insulating
CN108374516A (en) A kind of profiled sheet-raw bamboo-concrete combined floor and its manufacturing method
CN106638260A (en) Combined box beam structure and manufacturing method thereof
CN107524162A (en) A kind of assembled corrugated sheet steel Combined concrete pipe gallery
CN207469438U (en) A kind of prefabricated open tubular column
CN206693469U (en) A kind of precast floor slab connecting node
CN202745481U (en) Nibbed light high-strength concrete combined-type fence
CN201695550U (en) Closed profiled steel sheet-concrete combined floor
CN103526877B (en) A kind of precast concrete
CN208777519U (en) A kind of high-strength profiled sheet-fiber reinforcement regeneration concrete compoboard
CN108018972A (en) Full precast floor slab and laminated floor slab combining structure, making and assembly method
CN107989391A (en) A kind of combination beam of existed concrete bridge floor and girder steel
CN106836641A (en) Side sticking steel plate formula Combined concrete coupling beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171222

Termination date: 20200123

CF01 Termination of patent right due to non-payment of annual fee