CN206784115U - Artificial skiing road - Google Patents

Artificial skiing road Download PDF

Info

Publication number
CN206784115U
CN206784115U CN201720581149.2U CN201720581149U CN206784115U CN 206784115 U CN206784115 U CN 206784115U CN 201720581149 U CN201720581149 U CN 201720581149U CN 206784115 U CN206784115 U CN 206784115U
Authority
CN
China
Prior art keywords
pillar
supporting layer
layer
artificial skiing
road according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720581149.2U
Other languages
Chinese (zh)
Inventor
陈秋平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Bosch Sports Development Co Ltd
Original Assignee
Beijing Bosch Sports Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Bosch Sports Development Co Ltd filed Critical Beijing Bosch Sports Development Co Ltd
Priority to CN201720581149.2U priority Critical patent/CN206784115U/en
Application granted granted Critical
Publication of CN206784115U publication Critical patent/CN206784115U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of artificial skiing road, its drip irrigation device is to include basal layer, the elastic cord breaker on basal layer, the supporting layer on elastic cord breaker and positioned at the stratum granulosum on supporting layer, the fibre bundle set in a row is fixed with the supporting layer, the fibre bundle is located in supporting layer and stratum granulosum.It is poor that the utility model solves common artificial ski trail shock-absorbing capacity, the problem of user's easy tumble injury.

Description

Artificial skiing road
Technical field
A kind of sports equipment is the utility model is related to, in particular, it is related to a kind of artificial skiing road.
Background technology
With economy rapid development, requirement of the people for motion is more various, not snowfall season and do not drop Snow city is also required to ski this stimulation and modish motion, therefore indoor and outdoor artificial skiing road just meets people Skiing demand.
Authorization Notice No. is CN2527323Y Chinese patent, it discloses a kind of removable protective cover for artificial skiing, by substrate and carefully Silk is formed, and filament is made of soft high-abrasive material, and filament forms an angle with substrate, in use, the place mat phase that will be made Interconnection, which is connected together, is paved with trail, and the invention has and simple in construction, the advantage of achievable skiing round-the-clock throughout the year, But the trail of utility model laying is used, elastic poor, the easy tumble injury of slider.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of artificial skiing road, its advantage It is that elastic cord breaker and entablature can increase the shock-absorbing capacity of ski trail.
To achieve the above object, the utility model provides following technical scheme:A kind of artificial skiing road, including basis Layer, the elastic cord breaker on basal layer, the supporting layer on elastic cord breaker and positioned on supporting layer Granulosa, is fixed with the fibre bundle set in a row on the supporting layer, the fibre bundle be located at supporting layer with stratum granulosum.
By using above-mentioned technical proposal, whole ski trail has good elasticity, can reduce the probability of slider's tumble injury, Supporting layer and fibrous layer collective effect support stratum granulosum, the stabilization of stratum granulosum can be kept.
The utility model is further arranged to:The elastic cord breaker is made up of close-packed arrays rubber pillar, the rubber Pillar is fixed on the lower end of the supporting layer.
By using above-mentioned technical proposal, rubber pillar has good toughness and elasticity, can lift whole ski trail Shock-absorbing capacity, especially for the ski trail for having ramp and diving tower, entablature can buffer what kanone person fell from eminence Impulse force, lift the security performance of whole ski trail.
The utility model is further arranged to:The rubber pillar upper and lower surface be arranged in parallel, and is connect with the supporting layer Tactile surface is less than and the surface of basal layer contact.
By using above-mentioned technical proposal, rubber pillar upper surface causes between rubber pillar and basal layer more than lower surface Form some spaces so that rubber pillar easily deforms upon the elasticity so as to lift columns layer, if in addition, ski trail is located at Indoor or building top, the space formed can also play the effect of reducing noise.
The utility model is further arranged to:The supporting layer includes elastic bottom plate and is fixed on the elastic bottom plate The elastic support set in a row.
By using above-mentioned technical proposal, elastic bottom plate and elastic support can further enhance the elasticity of ski trail and buffer Performance, the security performance of whole ski trail is improved, in addition, elastic support can also play a supporting role to stratum granulosum.
The utility model is further arranged to:Expand globulate in the free end of the elastic support.
By using above-mentioned technical proposal, spherical end can increase the contact area with body, can reduce skiing personnel The probability of tumble injury.
The utility model is further arranged to:The elastic support is divided into the high pillar of uniform interphase distribution and low pillar, The height of the high pillar is 1-3cm, a diameter of 0.2-1cm, and the height of the low pillar is 0.5-2.5cm, a diameter of 0.2- 1cm, high pillar described in each two and low branch intercolumniation are 0.5-2cm.
By using above-mentioned technical proposal, pillar height distributes alternately, and can facilitate the turning or brake in taxiing procedures Stop, further, it is also possible to increase skiing experience sense.
The utility model is further arranged to:The fibre bundle is made up of the polyethylene rope of flexibility, the fibre bundle lower end Bunchy, upper end are loose.
By using above-mentioned technical proposal, fibre bundle, high pillar and low pillar support stratum granulosum, the loose fibre in upper end jointly Dimension beam can also catch plastic grain, reduce plastic grain and shed away in use and cause stratum granulosum became uneven The probability that even situation occurs.
The utility model is further arranged to:The stratum granulosum is formed by plastic grain laying.
By using above-mentioned technical proposal, plastic grain surface is smooth in light weight, can increase skiing experience sense.
The utility model is further arranged to:The plastic grain top layer scribbles paraffin layer.
By using above-mentioned technical proposal, can reinforced plastics particle surface slickness, increase skiing experience sense.
In summary, the utility model has the advantages that compared to prior art:The utility model shock-absorbing capacity It is excellent to be applicable to each season to lack the city of snow;The utility model also ensures the safety of user from many aspects, has good Security performance;In addition, the utility model, which is simulated natural trail and set, has good skiing experience sense.
Brief description of the drawings
Fig. 1 is the overall structure figure of embodiment;
Fig. 2 is elastic cord breaker upward view;
Fig. 3 is entablature structure chart.
In figure:1st, basal layer;2nd, elastic cord breaker;21st, rubber pillar;3rd, supporting layer;31st, elastic bottom plate;32nd, high branch Post;33rd, low pillar;34th, fibre bundle;4th, stratum granulosum.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
Referring to Fig. 1, a kind of artificial skiing road, including the basal layer 1 of the bottom, basal layer 1 is that concrete laying forms, Can be that smooth soil layer is corrected on outdoor hillside;Bonded on the basal layer 1 of concrete laying by aqueous acrylamide acid binder There is ski trail place mat, ski trail place mat includes and the elastic cord breaker 2 of the bonding of basal layer 1, the support on elastic cord breaker 2 Layer 3 and paving are sprinkled upon the stratum granulosum 4 on supporting layer.By heating fixed or bonding side between elastic cord breaker 2 and supporting layer 3 Formula connects.
With reference to shown in Fig. 1 and Fig. 2, elastic cord breaker 2 is made up of compact arranged rubber pillar 21, and rubber pillar 21 is upper Lower surface is square, side surface is hexahedron structure that isosceles trapezoid and upper surface are more than lower surface.The height of rubber pillar 21 For 1.5cm, the height of rubber pillar 21 can also be 0.5cm, 1cm, 2cm, and its lower surface is bonded with basal layer 1, and upper surface is glued It is connected on the bottom surface of supporting layer 3.
With reference to shown in Fig. 1 and Fig. 3, supporting layer 3 includes elastic bottom plate 31 made of polyurethane material, elastic bottom plate 31 Thickness is 1cm, and the upper surface of elastic bottom plate 31 hot melt is fixed with equally distributed high pillar 32, and the height of high pillar 32 is 2cm, directly Footpath is 0.5cm, intercolumniation 1cm;The height of high pillar 32 can also be 1cm, 1.5cm, 2cm or 3cm, and diameter can also be 0.2cm, 0.8cm or 1cm, the spacing between the high pillar of each two can also be 0.5cm, 1.5cm or 2cm;The high pillar of each two Bottom pillar 33, low pillar 33 and the upper surface hot-melt adhesive paste of elastic bottom plate 31 are provided between 32, the height of low pillar 33 is 1.5cm, Diameter and intercolumniation are identical with high pillar 32, and the height of this outer bottom pillar 33 can also be 0.5cm, 1cm, 2cm or 2.5cm.It is high Pillar 32 is made with bottom pillar 33 of polyurethane elastomeric materials, and spacing is between adjacent two high pillar 32 and bottom pillar 33 0.5cm, pillar is arranged to the spaced turning facilitated in taxiing procedures of height or brake stops;High pillar 32 and bottom pillar 33 Globulate is expanded in end, and a diameter of 0.7cm, when skiing personnel fall down, spherical end can increase the contact area with body, The probability of tumble injury can be reduced.
Also ordered on elastic bottom plate 31 equipped with the fibre bundle 34 formed by the flexible polyethylene rope that length is 2.5cm, fibre bundle 34 are evenly distributed between high pillar 32 and low pillar 33, and its lower end bunchy, upper end is loose, high pillar 32, the and of low pillar 33 Fibre bundle 34 supports the stratum granulosum 4 on upper strata jointly, stratum granulosum 4 by outside be coated with polyethylene that the particle diameter of paraffin is 0.5mm or Polypropylene plastics particle is formed, and according to different demands, the particle diameter of plastic grain can also be 0.2mm-1mm.High pillar 32, low branch Post 33 and the collective effect of fibre bundle 34 can reduce plastic grain and be shed away in use and cause the thickness of stratum granulosum 4 The probability that uneven situation occurs.
The production method of the embodiment is as follows:
First, concrete foundation layer 1 is laid, then high pillar 32 or bottom pillar 33 are thermally melted on elastic bottom plate 31, or It is integrally formed using grinding tool;Fibre bundle 34 is bound on elastic bottom plate 31, then, rubber pillar 21 is bonded in elastic bottom plate 31 bottom surface, the entablature 2 of shaping is bonded in the upper surface of basal layer 1 with bonding agent, it is left back to spill particle on the upper berth of supporting layer 3 Layer.
Described above is only preferred embodiment of the present utility model, and the scope of protection of the utility model is not limited merely to Above-described embodiment, all technical schemes belonged under the utility model thinking belong to the scope of protection of the utility model.It should refer to Go out, for those skilled in the art, some improvement under the premise of the utility model principle is not departed from and Retouching, these improvements and modifications also should be regarded as the scope of protection of the utility model.

Claims (9)

  1. A kind of 1. artificial skiing road, it is characterised in that:Elastic cord breaker (2) including basal layer (1), on basal layer (1), Supporting layer (3) on elastic cord breaker (2) and positioned at the stratum granulosum (4) on supporting layer (3), the supporting layer (3) fibre bundle (34) set in a row is fixed with, it is interior with stratum granulosum (4) that the fibre bundle (34) is located at supporting layer (3).
  2. 2. artificial skiing road according to claim 1, it is characterised in that:The elastic cord breaker (2) is by close-packed arrays rubber Glue pillar (21) is formed, and the rubber pillar (21) is fixed on the lower end of the supporting layer (3).
  3. 3. artificial skiing road according to claim 2, it is characterised in that:Rubber pillar (21) upper and lower surface is parallel to be set Put, and the surface contacted with the supporting layer (3) is less than and the surface of the basal layer (1) contact.
  4. 4. artificial skiing road according to claim 1, it is characterised in that:The supporting layer (3) includes elastic bottom plate (31) With the elastic support set in a row being fixed on the elastic bottom plate (31).
  5. 5. artificial skiing road according to claim 4, it is characterised in that:Expand balling-up in the free end of the elastic support Shape.
  6. 6. the artificial skiing road according to claim 4 or 5, it is characterised in that:The elastic support is divided into uniform alternate row The high pillar (32) and low pillar (33) of cloth, the height of the high pillar (32) are 1-3cm, a diameter of 0.2-1cm, the low branch The height of post (33) is 0.5-2.5cm, a diameter of 0.2-1cm, and high pillar (32) described in each two and low pillar (33) spacing are 0.5-2cm。
  7. 7. artificial skiing road according to claim 6, it is characterised in that:The fibre bundle (34) is by flexible polyethylene rope Form, fibre bundle (34) lower end bunchy, upper end is loose.
  8. 8. artificial skiing road according to claim 1, it is characterised in that:The stratum granulosum (4) by plastic grain lay and Into.
  9. 9. artificial skiing road according to claim 8, it is characterised in that:The plastic grain top layer scribbles paraffin layer.
CN201720581149.2U 2017-05-23 2017-05-23 Artificial skiing road Active CN206784115U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720581149.2U CN206784115U (en) 2017-05-23 2017-05-23 Artificial skiing road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720581149.2U CN206784115U (en) 2017-05-23 2017-05-23 Artificial skiing road

Publications (1)

Publication Number Publication Date
CN206784115U true CN206784115U (en) 2017-12-22

Family

ID=60711890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720581149.2U Active CN206784115U (en) 2017-05-23 2017-05-23 Artificial skiing road

Country Status (1)

Country Link
CN (1) CN206784115U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110487451A (en) * 2019-08-27 2019-11-22 清华大学深圳研究生院 A kind of Bionic flexible pressure sensor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110487451A (en) * 2019-08-27 2019-11-22 清华大学深圳研究生院 A kind of Bionic flexible pressure sensor

Similar Documents

Publication Publication Date Title
CN100436715C (en) Artificial surface with integrated thermal regulation
CN102172186B (en) Regulation structure for temperature of lawn bed and construction method thereof
CN206204732U (en) Water-permeable brick and its laying structure
CN206784115U (en) Artificial skiing road
CN206607596U (en) Side slope fixes water-collecting irrigation integrated apparatus
CN207512769U (en) A kind of vertical greening retaining wall
CN109680582A (en) A kind of permeable garden path structure
KR20160118023A (en) fabricated panel for planting nature lawn
CN207582236U (en) Football Field Turf
CN207376599U (en) Gu native solid vegetation net and the vegetation blanket using the vegetation net
CN208266626U (en) A kind of TPE elastomer plastic cement race track
CN206916565U (en) Concrete road surface structure
CN208884306U (en) A kind of body-building by scientific methods prevents joint injury and slows down the health walk of muscular fatigue
CN105239490B (en) A kind of anti-skidding shock-absorbing floor tile
CN207575721U (en) A kind of golf hitting mat
CN105200896B (en) A kind of wear-resisting shock-absorbing floor tile
KR101107662B1 (en) Artificial turf building method
CN201738214U (en) Artificial turf
CN206376170U (en) A kind of Novel assembled High-simulation artificial grass level ground
CN201952704U (en) Runway coiled material capable of efficiently discharging water
CN213653101U (en) Sand-filling-free football lawn
CN210177312U (en) Environment-friendly plastic course
CN206279423U (en) Antidetonation floor tile and people's walking along the street