CN206752894U - A kind of standard regularization stair - Google Patents

A kind of standard regularization stair Download PDF

Info

Publication number
CN206752894U
CN206752894U CN201720525412.6U CN201720525412U CN206752894U CN 206752894 U CN206752894 U CN 206752894U CN 201720525412 U CN201720525412 U CN 201720525412U CN 206752894 U CN206752894 U CN 206752894U
Authority
CN
China
Prior art keywords
time
marking time
vertical rod
socket joint
joint disk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720525412.6U
Other languages
Chinese (zh)
Inventor
李会强
仲继传
刘麦荣
梁泉
宋磊
李振宇
刘伊岚
张艳芳
赵宗礼
王立军
崔荷荷
蔡会迎
陈浩宇
王银军
陈亮
苏帅宜
薛洋
丁杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN SIXTH CONSTRUCTION GROUP CO Ltd
Original Assignee
HENAN SIXTH CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN SIXTH CONSTRUCTION GROUP CO Ltd filed Critical HENAN SIXTH CONSTRUCTION GROUP CO Ltd
Priority to CN201720525412.6U priority Critical patent/CN206752894U/en
Application granted granted Critical
Publication of CN206752894U publication Critical patent/CN206752894U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Steps, Ramps, And Handrails (AREA)

Abstract

The utility model discloses a kind of standard regularization stair, marked time including multilayer and installation frame body, multilayer is marked time in stepped arrangement, marking time for every layer includes pedal and hook, hook is symmetricly set on the both sides of pedal, installation frame body includes mark time positioning vertical rod and fixed connecting rod of marking time, positioning vertical rod equi-spaced apart of marking time is arranged on the both sides that each layer is marked time, positioning vertical rod of marking time is being provided with socket joint disk with each layer contour position of marking time, slot is offered on socket joint disk, fixed connecting rod of marking time is provided between the adjacent positioning vertical rod of marking time of homonymy, that marks time fixed connecting rod is provided at both ends with set tower bolt, set tower bolt is plugged in the slot of socket joint disk, each layer is marked time and hangs over the marking time on fixed connecting rod of corresponding height by both sides respectively.The utility model greatly facilitates the spelling assembly and disassembly of stair, improves efficiency of construction, moreover it is possible to recycles, promotes economizing type building site construction.

Description

A kind of standard regularization stair
Technical field
It the utility model is related to skyscraper stair technical field of safety protection, more particularly to a kind of standard regularization building Ladder.
Background technology
In recent years, project in construction engineering promoting standards, tool, the protection tool and protective articles of regularization energetically, Such product possesses recycling, safe and reliable performance, is to create Civilization Worksite, the necessary bar in green construction economizing type building site Part.In conventional standard regularization stair construction of prevention work, framework is set up using fastener type steel pipe, is stepped on using discarded template laying Step, due to the mutability of itself of marking time, overall perception effect is poor, and damaged template is serious after use, it is impossible to repeats profit With causing waste of material;Other frame intersection node needs to use fastener to fix, and increases and sets up difficulty and workload, reduces Integral construction efficiency.
Utility model content
The purpose of this utility model is to provide a kind of standard regularization stair, can quick-assembling and dismounting, raising applies Work efficiency rate, moreover it is possible to recycle, promote economizing type building site construction.
To achieve the above object, the technical solution adopted in the utility model is:
A kind of standard regularization stair, including multilayer is marked time and installation frame body, described multilayer is marked time in stepped arrangement, Marking time for every layer includes pedal and hook, and described hook is symmetricly set on the both sides of pedal, and described installation frame body includes stepping on Step positioning vertical rod and fixed connecting rod of marking time, described positioning vertical rod equi-spaced apart of marking time are arranged on the both sides that each layer is marked time, marked time Positioning vertical rod is being provided with socket joint disk with each layer contour position of marking time, and offers slot on described socket joint disk, homonymy is adjacent Mark time positioning vertical rod between be provided with fixed connecting rod of marking time, described fixed connecting rod of marking time is provided at both ends with set tower bolt, Set tower bolt is plugged in the slot of socket joint disk, and each layer is marked time respectively by the fixation of marking time for hanging over corresponding height of both sides On connecting rod.
Described positioning vertical rod of marking time corresponds to front end face and the rear end face setting that each layer is marked time respectively, between adjacent two layers are marked time Positioning vertical rod of marking time be respectively arranged with socket joint disk with adjacent two layers contour position of marking time.
The bottom of described positioning vertical rod of marking time is provided with socket joint disk, is provided between the adjacent positioning vertical rod of marking time of homonymy vertical To connecting rod, described longitudinally connected bar is provided at both ends with set tower bolt, and set tower bolt is plugged in the slot of socket joint disk.
Described multilayer mark time both sides mark time positioning vertical rod between be provided with transverse connecting rod, described transverse connecting rod Be provided at both ends with set tower bolt, set tower bolt is plugged in the slot of the socket joint disk for positioning bottom of upright rod of marking time.
The top of described positioning vertical rod of marking time is provided with socket joint disk, and guard rail is provided between the adjacent socket joint disk of homonymy Bar, described guard rail are provided at both ends with set tower bolt, and set tower bolt is plugged on the socket joint disk on positioning vertical rod top of marking time Slot in.
Four orthogonal slots are offered on described socket joint disk.
Described set tower bolt includes the collar and cutting, the described collar be arranged on fixed connecting rod of marking time, transverse connecting rod, The end of longitudinally connected bar and guard rail, described cutting are vertically arranged in the outside of the collar.
Described marking time also includes riser and side plate, and described riser is vertically set on the rear end of pedal upper surface, described Side plate be symmetricly set on the left surface and right flank of pedal, described hook is fixed on side plate.
The rectangular shape of described side plate, the two sides of side plate are separately fixed at upper surface and left surface or the right flank of pedal On.
Multilayer is marked time by setting separate multilayer to mark time and hangs over installation frame body by the utility model using hook On, the spelling assembly and disassembly of stair are greatly facilitated, and improve the recycling rate of waterused marked time;The utility model uses spigot-and-socket bar Part connects installation frame body, not only simple to operate, easy to connect, and saves manpower, effectively increases efficiency of construction, fully meets Create the requirement of Civilization Worksite, green construction economizing type building site.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation that individual layer described in the utility model is marked time;
Fig. 3 is the structural representation of fixed connecting rod described in the utility model of marking time;
Fig. 4 is socket joint disk described in the utility model and the structural representation for covering tower bolt.
Embodiment
As shown in figure 1, standard regularization stair described in the utility model, including multilayer is marked time 1 and installation frame body.Multilayer Mark time 1 structure it is identical, in stepped arrangement in installation frame body.As shown in Fig. 2 every layer is marked time 1 including pedal 2, riser 3rd, side plate 4 and hook 5, riser 3 is vertically set on the rear end of the upper surface of pedal 2, and side plate 4 is symmetricly set on the both sides of pedal 2.This 4 rectangular shape of embodiment latus inframedium, the horizontal plane and vertical plane of side plate 4 be separately fixed at pedal 2 upper surface and left surface or On right flank, hook 5 is fixed on the vertical plane of side plate 4.
Installation frame body of the present utility model includes mark time positioning vertical rod 6 and fixed connecting rod 7 of marking time, positioning vertical rod 6 etc. of marking time Away from be disposed on each layer mark time 1 both sides, each layer 1 contour position of marking time is being provided with socket joint disk 8.Wherein, it is fixed to mark time Position vertical rod 6 and each layer mark time 1 front end face and rear end face is correspondingly arranged, because last layer marks time 1 front end face and next layer is stepped on The rear end face of step 1 be located in same vertical plane, therefore adjacent two layers marking time between 1 of marking time positions vertical rod 6 and stepped on adjacent two layers Walk 1 contour position and be respectively arranged with socket joint disk 8, the outer rim of socket joint disk 8 offers four orthogonal slots 9.Each layer is stepped on Step 1 is provided with fixed connecting rod 7 of marking time between homonymy and adjacent positioning vertical rod 6 of marking time, as shown in figure 3, marking time fixed connect Bar 7 is provided at both ends with set tower bolt 10, and set tower bolt 10 includes the collar 11 and cutting 12, and the collar 11 is arranged on fixed connect of marking time The end of bar 10, cutting 12 are fixed on the outside of the collar 11 vertically, and are plugged in the slot 9 of socket joint disk 8.Each layer is marked time 1 point The marking time on fixed connecting rod 7 of corresponding height, fast and easy installation and removal are not hung over by the hook 5 of both sides.
The utility model is provided with socket joint disk 81 in the bottom for positioning vertical rod 6 of marking time, and each layer marks time 1 positioned at homonymy and adjacent Positioning vertical rod 6 of marking time between be provided with longitudinally connected bar 13, longitudinally connected bar 13 is provided at both ends with set tower bolt 10, sleeve pipe Latch 10 is plugged in the socket joint disk 81 for positioning vertical rod 6 bottom of marking time.In order to further strengthen the steadiness of installation frame body, this reality With it is new multilayer mark time 1 both sides mark time positioning vertical rod 6 between be provided with transverse connecting rod 14, the both ends of transverse connecting rod 14 Set tower bolt 10 is provided with, set tower bolt 10 is plugged in the socket joint disk 81 for positioning vertical rod 6 bottom of marking time.In the present embodiment laterally Connecting rod 14 is arranged between the positioning vertical rod 6 of marking time that the second layer is marked time and layer 5 is marked time.In order to improve the peace of installation frame body Full protection function, the utility model are provided with socket joint disk 82 on the top for positioning vertical rod 6 of marking time, the adjacent socket joint disk 82 of homonymy it Between be provided with guard rail 15, guard rail 15 is provided at both ends with set tower bolt 10, and set tower bolt 10 is plugged on positioning of marking time In the socket joint disk 82 on the top of vertical rod 6, as shown in Figure 4.Choose lower floor in the present embodiment, middle level and upper strata marking time for both sides of marking time it is fixed Position vertical rod 6 upwardly extends, and sets two row's socket joint disks 82 at the different height on positioning vertical rod 6 top of marking time, and installs two layers and prevents Guard rail rod 15, the security that stair use is effectively ensured.
The utility model welds to pedal 2, riser 3, hook 5 and side plate 4 first when building, and is formed multiple only It is vertical to mark time 1, socket joint disk 8 then is fixed at the corresponding height of every positioning vertical rod 6 of marking time according to actual conditions, and will mark time Positioning vertical rod 6 be fixed on each layer mark time 1 both sides, the fixed connecting rod 7 of marking time that homonymy is adjacent to mark time between positioning vertical rod 6 installs Cheng Hou, installation, which is marked time, successively positions the longitudinally connected bar 13 and transverse connecting rod 14 of the bottom of vertical rod 6, and finally installation is marked time to position and stood The guard rail 15 on the top of bar 6, so far forms firm installation frame body, then each layer is marked time and 1 hung successively to fixed connecting rod 7 of marking time On, then stair build completion.Each layer is removed during dismounting first and marks time 1, then removes each rod member successively.The utility model It convenient disassembly, can not only recycle, and improve efficiency of construction, fully meet to create Civilization Worksite, green construction section The about requirement in type building site.

Claims (9)

  1. A kind of 1. standard regularization stair, it is characterised in that:Marked time including multilayer and installation frame body, described multilayer are marked time in rank Ladder type arranges, and marking time for every layer includes pedal and hook, and described hook is symmetricly set on the both sides of pedal, described mounting bracket Body includes mark time positioning vertical rod and fixed connecting rod of marking time, and described positioning vertical rod equi-spaced apart of marking time is arranged on each layer is marked time two Side, positioning vertical rod of marking time are being provided with socket joint disk with each layer contour position of marking time, are offering slot on described socket joint disk, together Fixed connecting rod of marking time is provided between the adjacent positioning vertical rod of marking time in side, described fixed connecting rod of marking time is provided at both ends with sleeve pipe Latch, set tower bolt are plugged in the slot of socket joint disk, and each layer is marked time and hangs over stepping on for corresponding height by both sides respectively On the fixed connecting rod of step.
  2. 2. standard regularization stair as claimed in claim 1, it is characterised in that:Described positioning vertical rod of marking time corresponds to each respectively The front end face marked time of layer and rear end face are set, adjacent two layers mark time between mark time positioning vertical rod marked time with adjacent two layers it is contour Position is respectively arranged with socket joint disk.
  3. 3. standard regularization stair as claimed in claim 2, it is characterised in that:The bottom of described positioning vertical rod of marking time is set There is socket joint disk, be provided with longitudinally connected bar between the adjacent positioning vertical rod of marking time of homonymy, the both ends of described longitudinally connected bar are set There is set tower bolt, set tower bolt is plugged in the slot of socket joint disk.
  4. 4. standard regularization stair as claimed in claim 3, it is characterised in that:Described multilayer is marked time the positioning of marking time of both sides Transverse connecting rod is provided between vertical rod, described transverse connecting rod is provided at both ends with set tower bolt, and set tower bolt is plugged on Mark time in the slot for the socket joint disk for positioning bottom of upright rod.
  5. 5. standard regularization stair as claimed in claim 4, it is characterised in that:The top of described positioning vertical rod of marking time is set There is socket joint disk, guard rail is provided between the adjacent socket joint disk of homonymy, the sleeve pipe that is provided at both ends with of described guard rail is inserted Pin, set tower bolt are plugged in the slot of the socket joint disk on positioning vertical rod top of marking time.
  6. 6. standard regularization stair as claimed in claim 5, it is characterised in that:Four are offered on described socket joint disk mutually Vertical slot.
  7. 7. standard regularization stair as claimed in claim 6, it is characterised in that:Described set tower bolt includes the collar and inserted Bar, the described collar is arranged on the end of fixed connecting rod of marking time, transverse connecting rod, longitudinally connected bar and guard rail, described Cutting is vertically arranged in the outside of the collar.
  8. 8. standard regularization stair as claimed in claim 7, it is characterised in that:Described marking time also includes riser and side plate, Described riser is vertically set on the rear end of pedal upper surface, and described side plate is symmetricly set on the left surface and right flank of pedal On, described hook is fixed on side plate.
  9. 9. standard regularization stair as claimed in claim 8, it is characterised in that:The rectangular shape of described side plate, the two of side plate Face is separately fixed on the upper surface and left surface or right flank of pedal.
CN201720525412.6U 2017-05-12 2017-05-12 A kind of standard regularization stair Expired - Fee Related CN206752894U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720525412.6U CN206752894U (en) 2017-05-12 2017-05-12 A kind of standard regularization stair

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720525412.6U CN206752894U (en) 2017-05-12 2017-05-12 A kind of standard regularization stair

Publications (1)

Publication Number Publication Date
CN206752894U true CN206752894U (en) 2017-12-15

Family

ID=60617960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720525412.6U Expired - Fee Related CN206752894U (en) 2017-05-12 2017-05-12 A kind of standard regularization stair

Country Status (1)

Country Link
CN (1) CN206752894U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356344A (en) * 2018-12-04 2019-02-19 金螳螂精装科技(苏州)有限公司 A kind of full glass staircase structure of non-division formula
CN112854633A (en) * 2021-02-04 2021-05-28 佛山市爱拼科技有限公司 Stair frame capable of being assembled quickly
CN113250488A (en) * 2021-05-18 2021-08-13 国网山东省电力公司潍坊供电公司 Detachable socket stair and installation method
CN114000667A (en) * 2021-11-30 2022-02-01 中国二十二冶集团有限公司 Combined stair for prefabricated building
NO346851B1 (en) * 2022-01-19 2023-01-30 Rolf Wee Transp As STAIRCASE AND PROCEDURE FOR ASSEMBLING THE SAME

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356344A (en) * 2018-12-04 2019-02-19 金螳螂精装科技(苏州)有限公司 A kind of full glass staircase structure of non-division formula
CN112854633A (en) * 2021-02-04 2021-05-28 佛山市爱拼科技有限公司 Stair frame capable of being assembled quickly
CN113250488A (en) * 2021-05-18 2021-08-13 国网山东省电力公司潍坊供电公司 Detachable socket stair and installation method
CN114000667A (en) * 2021-11-30 2022-02-01 中国二十二冶集团有限公司 Combined stair for prefabricated building
CN114000667B (en) * 2021-11-30 2024-05-24 中国二十二冶集团有限公司 Combined stair for assembled building
NO346851B1 (en) * 2022-01-19 2023-01-30 Rolf Wee Transp As STAIRCASE AND PROCEDURE FOR ASSEMBLING THE SAME
WO2023140737A1 (en) * 2022-01-19 2023-07-27 Rolf Wee Transport As Stairway and method for assembling the same

Similar Documents

Publication Publication Date Title
CN206752894U (en) A kind of standard regularization stair
CN103206074B (en) Elevator shaft template construction method, platform and support
CN205477339U (en) A cage ladder that is used for steel construction factory building shingle nail to install
CN204753397U (en) Temporary mounting hanger for steel box bridge
CN203783170U (en) Detachable protective shed
CN205742975U (en) A kind of direct plugging type scaffold
CN210152194U (en) Scaffold for house building construction
CN205894627U (en) Scaffold frame convenient to dismantle installation
CN206233544U (en) Adjustable operation platform
CN204781869U (en) Scaffold suitable for building site
CN205777629U (en) A kind of Fabricated railing
CN204174915U (en) Scaffold
CN204326565U (en) Face frontier defense guardrail
CN104499724B (en) Edge protection fence
CN207538481U (en) A kind of floor height changeable type input and output material platform
CN210636767U (en) Scaffold for constructional engineering
CN203257110U (en) Constructional engineering protection support
CN204571249U (en) The load module of hoist material receiving and hoist material receiving thereof
CN206233532U (en) Operating platform
CN205908001U (en) Operation platform standard module and operation platform
CN206279760U (en) A kind of hydraulic engineering means for fastening scaffolding
CN206205422U (en) A kind of deep basal pit steel inclined ladder
CN205894678U (en) Steel wood convolution stair reinforcement template of marking time
CN105863247A (en) Direct-plug type scaffold with locking block
CN205224556U (en) Scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee