CN206752810U - Installation of ceiling component - Google Patents
Installation of ceiling component Download PDFInfo
- Publication number
- CN206752810U CN206752810U CN201720500158.4U CN201720500158U CN206752810U CN 206752810 U CN206752810 U CN 206752810U CN 201720500158 U CN201720500158 U CN 201720500158U CN 206752810 U CN206752810 U CN 206752810U
- Authority
- CN
- China
- Prior art keywords
- keel
- ceiling
- suction base
- installation
- magnet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Toys (AREA)
Abstract
Installation of ceiling component, it is related to ceiling decoration technical field, it includes being used to hang suction base, for the keel below ceiling and for connection suspension suction base and the connector of keel installed in furred ceiling back;Suction base is hung in list structure and is arranged at intervals with multiple lock parts, lock part includes being symmetricly set on two spacing hook plates for hanging suction base upper surface, and the first magnet is provided with lock part;The bottom surface of keel offers chute;Connector includes the connecting rod of spaced multiple sliding blocks and each sliding block of connection, the spacing of adjacent sliders is consistent with the spacing for hanging adjacent lock portion on suction base on connector, sliding block is provided with upper block tongue and lower block tongue, upper block tongue is arranged in chute, the both ends of chute are detachably provided with baffle plate, lower block tongue is embedded with the second magnet, and spacing hook plate smocking is stayed block tongue.The utility model can make the installation of furred ceiling quite convenient, without squeezing into the screw of substantial amounts on keel, greatly shorten the time needed for installation furred ceiling.
Description
Technical field
Ceiling decoration technical field is the utility model is related to, especially a kind of installation of ceiling component.
Background technology
Indoors in fitment process, people often install ceiling structure, on the one hand can be used for the crossbeam for covering roof,
Pipeline, circuit etc., on the other hand can also design model, play effect attractive in appearance.Existing installation of ceiling technology is by hanging
More main joists are fixed on the lower section of ceiling by hook, and false keel is then fixed on main joist, need to beat in this process
The setscrew for entering substantial amounts is used for ensureing the stability connected between keel(Such as main joist of suspended ceiling is using 20 × 40 wood dragons
During bone, it need to be fixed with φ 8 × 80 setscrew with original structure floor, when false keel uses 20 × 40 rough ground, with main joist
Between connection also need to rationally be fixed using self threading pin, also to be fixed per every about 800mm by the false keel of wall in addition
One setscrew), screw special is finally reused by plasterboard(That is ceiling board)It is fixed on keel, whole construction procedure is non-
Often cumbersome, installation effectiveness is low.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of installation of ceiling component, makes the installation of furred ceiling quite just
Victory, without squeezing into the screw of substantial amounts on keel, greatly shorten the time needed for installation furred ceiling.
In order to solve the above-mentioned technical problem, the utility model adopts the following technical scheme that:A kind of installation of ceiling component, including
For hanging suction base, for the keel below ceiling and for connection suspension suction base and dragon installed in furred ceiling back
The connector of bone;
The extension suction base is in list structure and is arranged at intervals with multiple lock parts, and the lock part includes being symmetricly set on extension
Two spacing hook plates of suction base upper surface, the first magnet is additionally provided with the lock part;
The bottom surface of the keel offers the chute for mounting connector, and the top surface of the keel, which is provided with, is used for fixed hang
The screwed hole of hook or suspension rod, the bottom of the screwed hole are fixed with for preventing screwed hole from being punched or the downwardly projecting change in bottom hole portion
The metal caul of shape;
The connector includes spaced multiple sliding blocks and connects the connecting rod of each sliding block, adjacent on the connector
The spacing of sliding block is consistent with the spacing in adjacent lock portion on the extension suction base, and the sliding block is provided with upper block tongue and lower block tongue, described
Upper block tongue is arranged in chute so that the sliding block can move along chute, and the chute is provided with and dropped out downwards for anti-limited slip block
Anticreep flange, the both ends of the chute are detachably provided with the baffle plate deviate from for anti-limited slip block from chute both ends, under described
Block tongue is embedded with the second magnet, and the spacing hook plate smocking is stayed block tongue, due between first magnet and the second magnet
Magnetic attraction effect so that the lock part can link closely sliding block;
Pull down the baffle plate, pushed against along the chute or pull sliding block, now connector movement, when the sliding block with
When lock part misplaces, the lower block tongue spins off from spacing hook plate, so as to directly remove ceiling board.
Further, the lock part is provided with the first electric conductor, and the lower block tongue is correspondingly provided with the second electric conductor, the dragon
The power line for connecting the second electric conductor is laid with bone, when the lock part is in the first magnet and the magnetic attraction of the second magnet
Effect is trapped when tangling lower block tongue, and first electric conductor and the second conductive body contact are so that the function of conducting electric current can be realized.
Further, the sliding block positioned at the connector both ends is provided with elastomeric element, one end of the elastomeric element
Prop up sliding block, the other end props up baffle plate.
Further, the elastomeric element includes spring and the briquetting for pushing against spring, and one end of the spring connects
Sliding block, other end connection briquetting are connect, the briquetting props up baffle plate.
Further, the circular hole for being easy to driver bit to head into is offered on the outer face of the briquetting.
Preferably, first magnet is embedded on the top surface for hanging suction base, and second magnet is embedded at the bottom of lower block tongue
On face.
It is highly preferred that the extension suction base is made of PVC material.
It is highly preferred that the extension suction base is threadedly coupled with ceiling board;The keel are threadedly coupled with metope;The baffle plate with
Keel are threadedly coupled.
Installation of ceiling component provided by the utility model hangs suction base, under ceiling by being installed at the back side of ceiling board
Side's installation keel, then suction base is hung as the part of transition by connector and got up with keel mounting, so that by furred ceiling
Plate is installed to the lower section of ceiling, during installation, makes extension suction base company of touching in the state of lock part and sliding block stagger
Fitting, ceiling board is then translated, ceiling board just can be fixed when lock part fastens sliding block, due to need to only pacify below ceiling
Using components such as a number of screws during keel, and false keel need not be installed, therefore substantially reduce the set-up time, tear open
First baffle plate is removed when unloading, pushes against or pull sliding block, ceiling board can easily be removed by sliding block is misplaced with lock part, entirely be torn open
Dress process is very convenient, in addition, the component allows furred ceiling face integrally to customize, more adapts to current integrated building interior decoration
Need.
Brief description of the drawings
Fig. 1 is the overall structure schematic cross-sectional view of the utility model embodiment;
Fig. 2 is that the schematic diagram that suction base is arranged on ceiling board is hung in embodiment;
Fig. 3 is the schematic diagram that extension suction base set hangs on connector in embodiment;
Fig. 4 is schematic diagram when lock part misplaces with sliding block in embodiment;
Fig. 5 is the partial enlarged drawing at A positions in Fig. 4;
Fig. 6 is the elevational schematic view of the keel and connector in embodiment below ceiling.
Reference is:
1 --- hangs suction base 1a --- lock part 1a1 --- spacing hook plate
2 --- keel 2a --- chute 3 --- connectors
3a --- sliding block 3a1 --- upper block tongue 3a2 --- lower block tongues
4a --- the first magnet 4b --- the second magnet 5 --- baffle plates
6 --- elastomeric element 6a --- spring 6b --- briquettings
6b1 --- circular hole 7 --- ceiling board.
Embodiment
For the ease of the understanding of those skilled in the art, the utility model is made with reference to embodiment and accompanying drawing further
Explanation, the content that embodiment refers to not to restriction of the present utility model.
In description of the present utility model, it is to be understood that term " on ", " under ", "front", "rear", "left", "right",
The orientation or position relationship of the instruction such as " vertical ", " level ", " top ", " bottom ", " interior ", " outer " be based on orientation shown in the drawings or
Position relationship, it is for only for ease of description the utility model and simplifies description, rather than indicates or imply signified device or member
Part must have specific orientation, with specific azimuth configuration and operation, therefore it is not intended that to limitation of the present utility model.
, it is necessary to which explanation, unless otherwise prescribed and is limited, term " installation ", " phase in description of the present utility model
Even ", " connection " should be interpreted broadly, for example, it may be mechanical connection or the company of electrical connection or two element internals
It is logical, can be joined directly together, can also be indirectly connected by intermediary, for the ordinary skill in the art, can
To understand the concrete meaning of the term as the case may be.
As shown in figures 1 to 6, a kind of installation of ceiling component, including for the extension suction base 1 installed in furred ceiling back, for pacifying
Keel 2 below ceiling and the connector 3 for connection suspension suction base 1 and keel 2;Suction base 1 is hung in list structure and
Multiple lock part 1a are arranged at intervals with, lock part 1a includes being symmetricly set on two spacing hook plate 1a1 for hanging the upper surface of suction base 1,
The first magnet 4a is additionally provided with lock part 1a;The bottom surface of keel 2 offers the chute 2a for mounting connector 3, the top of keel 2
Face is provided with the screwed hole for being used for fixing suspension hook or suspension rod(Not shown in accompanying drawing), the bottom of screwed hole is fixed with for preventing screw thread
Hole is punched or the metal caul of the downwardly projecting deformation in bottom hole portion(Not shown in accompanying drawing);Connector 3 includes spaced more
Individual sliding block 3a and each sliding block 3a of connection connecting rod 3b, on connector 3 adjacent sliders 3a spacing with it is described hang it is adjacent on suction base 1
Lock part 1a spacing is consistent, and sliding block 3a is provided with upper block tongue 3a1 and lower block tongue 3a2, upper block tongue 3a1 are arranged in chute 2a and caused
Sliding block 3a can move along chute 2a, and chute 2a, which is provided with, is used for the anticreep flange that anti-limited slip block 3a is dropped out downwards, and the two of chute 2a
End is detachably provided with the baffle plate 5 deviate from for anti-limited slip block 3a from chute 2a both ends, and lower block tongue 3a2 is embedded with the second magnet
4b, spacing hook plate 1a1 smockings are stayed block tongue 3a2, due to the magnetic attraction effect between the first magnet 4a and the second magnet 4b, are made
Lock part 1a can link closely sliding block 3a.
The installation of ceiling component that above-mentioned embodiment provides hangs suction base 1, in ceiling by being installed at the back side of ceiling board
Lower section installation keel 2, then suction base 1 is hung as the part of transition by connector 3 and mounts with keel 2, from
And ceiling board is installed to the lower section of ceiling, during installation, make what extension suction base 1 staggered in lock part 1a and sliding block 3a
Connector 3 is touched under state, then translates ceiling board, ceiling board just can be fixed when lock part 1a fastens sliding block 3a, due to
Using components such as a number of screws when need to only install keel 2 below ceiling, and false keel need not be installed, therefore greatly
It is big to shorten the set-up time, first baffle plate 5 is removed during dismounting, sliding block 3a is pushed against or pulled along chute 2a, makes sliding block 3a and locking
1a dislocation in portion can easily remove ceiling board 7, and whole disassembly process is very convenient, in addition, the component make it that furred ceiling face can be with
Overall customization, more adapt to the needs of current integrated building interior decoration;In addition, the metal caul that the bottom of screwed hole is fixed can be kept away
Bottom hole portion is punched or the situation of downwardly projecting deformation when exempting from drivescrew, ensure that the chute 2a of keel bottom surface will not be by
Influence.
Further, it is possible to the first electric conductor is set in lock part 1a(Not shown in accompanying drawing), it is correspondingly arranged in lower block tongue 3a2
Second electric conductor(Not shown in accompanying drawing), the power line for connecting the second electric conductor is laid with keel 2, when lock part 1a exists
The effect of first magnet 4a and the second magnet 4b magnetic attraction is trapped when tangling lower block tongue 3a2, the first electric conductor and the second electric conductor
Contact so as to which the function of conducting electric current can be realized, using this function can in ceiling board 7 installation fluorescent tube, by conductor wire by lamp
Pipe is electrically connected with the first electric conductor, and when ceiling board 7 tangles connector 3, the first electric conductor and the second electric conductor will
By current lead-through, so as to so that fluorescent tube normal luminous.
Further, as shown in Fig. 3-5, elastomeric element 6, bullet can be set on the sliding block 3a positioned at the both ends of connector 3
Property part 6 one end prop up sliding block 3a, the other end props up baffle plate 5, sliding after ensureing to pull down baffle plate 5 and pushing against sliding block 3a
Block 3a can easily return to initial position so that can be still installed on accurate position during the ceiling board more renewed.
It should be noted that in the present embodiment, elastomeric element 6 has enough compression strokes to meet sliding block 3a and lock
Stopping seat 1a misplaces.
As a kind of preferable structure, elastomeric element 6 includes spring 6a and the briquetting 6b for pushing against spring 6a, spring 6a
One end connection sliding block 3a, other end connection briquetting 6b, briquetting 6b is propped up baffle plate 5, after briquetting 6b is set, operator can be facilitated
Member directly pushes against briquetting 6b, compresses spring 6a, and then promotes sliding block 3a so that connector 3 is subjected to displacement in chute 2a.Also
Can open up the circular hole 6b1 for being easy to driver bit to head on briquetting 6b outer face, such operating personnel can use with
The screwdriver that body carries pushes against sliding block 3a, avoids directly being supported with hand push, not only increases security, moreover it is possible to connector 3 is existed
The distance moved in chute 2a becomes much larger, and then enables sliding block 3a and lock part 1a more thoroughly to produce dislocation.
In the present embodiment, preferably, the first magnet 4a is embedded on the top surface for hanging suction base 1, and the second magnet 4b is embedding
It is located on lower block tongue 3a2 bottom surface, so that lower block tongue 3a2 is when being caught in lock part 1a, the first magnet 4a and the second magnet
4b possesses larger magneticaction area, and then can make block tongue 3a2 under the more firm pinnings of lock part 1a.In addition, this reality
The extension suction base 1 applied in example is made of PVC material, light, waterproof and dampproof, good flame retardation effect, and cost is low.Inhaled in addition, hanging
Seat 1 is threadedly coupled with ceiling board, and keel 2 are threadedly coupled with metope, and baffle plate 5 is threadedly coupled with keel 2, and its installation effect is stable,
It is easy to disassemble.
Above-described embodiment is the preferable implementation of the utility model, and in addition, the utility model can be with other sides
Formula is realized, any on the premise of the technical program design is not departed from obviously to replace in protection model of the present utility model
Within enclosing.
In order to allow those of ordinary skill in the art more easily understand the utility model relative to prior art improvement it
Place, some accompanying drawings of the present utility model and description have been simplified, and for the sake of clarity, present specification is omitted one
A little other elements, those of ordinary skill in the art should be aware that these elements omitted also may make up in of the present utility model
Hold.
Claims (8)
- A kind of 1. installation of ceiling component, it is characterised in that:Including for installed in ceiling board(7)The extension suction base at the back side(1), be used for Keel below ceiling(2)And for connection suspension suction base(1)With keel(2)Connector(3);The extension suction base(1)In list structure and it is arranged at intervals with multiple lock parts(1a), the lock part(1a)Including symmetrical It is arranged on extension suction base(1)Two spacing hook plates of upper surface(1a1), the lock part(1a)Inside it is additionally provided with the first magnet(4a);The keel(2)Bottom surface offer for mounting connector(3)Chute(2a), the keel(2)Top surface be provided with For fixing the screwed hole of suspension hook or suspension rod, the bottom of the screwed hole is fixed with for preventing screwed hole from being punched or bottom hole portion The metal caul of downwardly projecting deformation;The connector(3)Including spaced multiple sliding blocks(3a)And each sliding block of connection(3a)Connecting rod(3b), it is described Connector(3)Upper adjacent sliders(3a)Spacing and the extension suction base(1)Upper adjacent lock portion(1a)Spacing it is consistent, the cunning Block(3a)Provided with upper block tongue(3a1)With lower block tongue(3a2), the upper block tongue(3a1)It is arranged in chute(2a)In cause the cunning Block(3a)Can be along chute(2a)It is mobile, the chute(2a)It is provided with and is used for anti-limited slip block(3a)The anticreep flange dropped out downwards, The chute(2a)Both ends be detachably provided with for anti-limited slip block(3a)From chute(2a)The baffle plate of both ends abjection(5), institute State lower block tongue(3a2)It is embedded with the second magnet(4b), the spacing hook plate(1a1)Smocking is stayed block tongue(3a2), due to described First magnet(4a)With the second magnet(4b)Between magnetic attraction effect, the lock part(1a)Can be linked closely sliding block(3a);Pull down the baffle plate(5), along the chute(2a)Pushing and pressing pull sliding block(3a), the now connector(3)It is mobile, when The sliding block(3a)With lock part(1a)During dislocation, the lower block tongue(3a2)From spacing hook plate(1a1)In spin off, so as to Ceiling board can directly be removed(7).
- 2. installation of ceiling component according to claim 1, it is characterised in that:The lock part(1a)It is conductive provided with first Body, the lower block tongue(3a2)It is correspondingly provided with the second electric conductor, the keel(2)On be laid with for connecting second electric conductor Power line, when the lock part(1a)In the first magnet(4a)With the second magnet(4b)Magnetic attraction effect trap and tangle lower block tongue (3a2)When, first electric conductor and the second conductive body contact are so that the function of conducting electric current can be realized.
- 3. installation of ceiling component according to claim 1, it is characterised in that:Positioned at the connector(3)The sliding block at both ends (3a)It is provided with elastomeric element(6), the elastomeric element(6)One end prop up sliding block(3a), the other end prop up baffle plate(5).
- 4. installation of ceiling component according to claim 3, it is characterised in that:The elastomeric element(6)Including spring(6a) With for pushing against spring(6a)Briquetting(6b), the spring(6a)One end connection sliding block(3a), the other end connection briquetting (6b), the briquetting(6b)Prop up baffle plate(5).
- 5. installation of ceiling component according to claim 4, it is characterised in that:The briquetting(6b)Outer face on offer It is easy to the circular hole that driver bit heads into(6b1).
- 6. installation of ceiling component according to claim 5, it is characterised in that:First magnet(4a)It is embedded and hangs suction base (1)Top surface on, second magnet(4b)It is embedded in lower block tongue(3a2)Bottom surface on.
- 7. installation of ceiling component according to claim 6, it is characterised in that:The extension suction base(1)Using PVC material system Into.
- 8. installation of ceiling component according to claim 7, it is characterised in that:The extension suction base(1)Connect with ceiling board screw thread Connect;The keel(2)It is threadedly coupled with metope;The baffle plate(5)With keel(2)Threaded connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720500158.4U CN206752810U (en) | 2017-05-08 | 2017-05-08 | Installation of ceiling component |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720500158.4U CN206752810U (en) | 2017-05-08 | 2017-05-08 | Installation of ceiling component |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206752810U true CN206752810U (en) | 2017-12-15 |
Family
ID=60616728
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720500158.4U Expired - Fee Related CN206752810U (en) | 2017-05-08 | 2017-05-08 | Installation of ceiling component |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206752810U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108360726A (en) * | 2018-04-03 | 2018-08-03 | 苏州美瑞德建筑装饰有限公司 | Big scale of construction mirror face stainless steel suspended ceiling mounting structure |
CN109594703A (en) * | 2018-12-26 | 2019-04-09 | 浙江添锦建筑装饰工程有限公司 | A kind of Fast Installation ceiling structure |
CN110241964A (en) * | 2019-06-27 | 2019-09-17 | 苏州美瑞德建筑装饰有限公司 | A kind of auxiliary mounting structure of various dimensions suspended ceiling modeling |
CN110424618A (en) * | 2019-07-30 | 2019-11-08 | 北新集团建材股份有限公司 | A kind of assembled ceiling structure and its installation method |
CN115262849A (en) * | 2022-08-12 | 2022-11-01 | 广州市第一装修有限公司 | Decorative plate mounting structure and mounting method of wood grain gypsum ceiling |
CN115450443A (en) * | 2022-09-01 | 2022-12-09 | 孙芸菁 | Assembled building steel structure |
-
2017
- 2017-05-08 CN CN201720500158.4U patent/CN206752810U/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108360726A (en) * | 2018-04-03 | 2018-08-03 | 苏州美瑞德建筑装饰有限公司 | Big scale of construction mirror face stainless steel suspended ceiling mounting structure |
CN108360726B (en) * | 2018-04-03 | 2023-08-15 | 苏州美瑞德建筑装饰有限公司 | Stainless steel ceiling mounting structure with substantial mirror surface |
CN109594703A (en) * | 2018-12-26 | 2019-04-09 | 浙江添锦建筑装饰工程有限公司 | A kind of Fast Installation ceiling structure |
CN109594703B (en) * | 2018-12-26 | 2020-09-22 | 浙江添锦建筑装饰工程有限公司 | Install furred ceiling structure fast |
CN110241964A (en) * | 2019-06-27 | 2019-09-17 | 苏州美瑞德建筑装饰有限公司 | A kind of auxiliary mounting structure of various dimensions suspended ceiling modeling |
CN110424618A (en) * | 2019-07-30 | 2019-11-08 | 北新集团建材股份有限公司 | A kind of assembled ceiling structure and its installation method |
CN115262849A (en) * | 2022-08-12 | 2022-11-01 | 广州市第一装修有限公司 | Decorative plate mounting structure and mounting method of wood grain gypsum ceiling |
CN115262849B (en) * | 2022-08-12 | 2023-08-18 | 广州市第一装修有限公司 | Decoration plate mounting structure and method for wood grain gypsum ceiling |
CN115450443A (en) * | 2022-09-01 | 2022-12-09 | 孙芸菁 | Assembled building steel structure |
CN115450443B (en) * | 2022-09-01 | 2023-12-08 | 浙江恒搏钢结构有限公司 | Assembled building steel construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206752810U (en) | Installation of ceiling component | |
CN106988469B (en) | Integrated ceiling system | |
CN106939680B (en) | The decorated wall surface of replacement easy to disassemble | |
CN206752933U (en) | Decorative panel is detachably connected component | |
KR20140001178U (en) | Light installtion apparatus | |
CN208782310U (en) | A kind of small distribution case suspension mechanism | |
CN109138214A (en) | Prefabricated laminated wood wall construction and log cabin structure | |
CN205579746U (en) | Wall spare, air conditioner wall hanging plate and air conditioner are hung to air conditioner | |
CN209658838U (en) | A kind of attachment device suitable for illuminating bus slot | |
CN105494308A (en) | Bird-preventing device | |
CN205781887U (en) | Computer display wall hanging rack | |
CN101775866B (en) | Suspended ceiling | |
KR100672800B1 (en) | Electric terminal box for ceiling of apartment house | |
CN209484245U (en) | A kind of extension wall flat television bracket with stretching hook | |
CN208572639U (en) | A kind of new structure of intelligent switch panel | |
CN209114704U (en) | Integrated furred ceiling suspended structure | |
CN208460537U (en) | Reactor assemblies | |
CN208817222U (en) | A kind of fillet lamp with magnetic and buckle structure | |
CN207251060U (en) | A kind of anti-misoperation apparatus of drawer-type switch cabinet | |
CN205296535U (en) | Integrated furred ceiling card formula fossil fragments mounting structure | |
CN205744554U (en) | The fan lamp of accidental falling auto-power-off device is installed | |
CN205811473U (en) | Entrance line support | |
CN205807137U (en) | The surface frame structure of LED panel lamp | |
CN205713456U (en) | Net piece formula protection rail | |
CN203718333U (en) | Television hanging arm provided with safety lock mechanism |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171215 Termination date: 20200508 |
|
CF01 | Termination of patent right due to non-payment of annual fee |