CN206752792U - A kind of co-layer draining light gauge cold-formed steel shape dense rib type composite floor system - Google Patents
A kind of co-layer draining light gauge cold-formed steel shape dense rib type composite floor system Download PDFInfo
- Publication number
- CN206752792U CN206752792U CN201720196244.0U CN201720196244U CN206752792U CN 206752792 U CN206752792 U CN 206752792U CN 201720196244 U CN201720196244 U CN 201720196244U CN 206752792 U CN206752792 U CN 206752792U
- Authority
- CN
- China
- Prior art keywords
- light
- gauge cold
- formed steel
- steel shape
- light gauge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Building Environments (AREA)
Abstract
The utility model discloses a kind of co-layer draining light gauge cold-formed steel shape dense rib type composite floor system, is related to light gauge cold-formed steel shape building field.Including light gauge cold-formed steel shape, profiled sheet, dewatering horizontal tube, the light polymer of cement base, sanitary apparatus branch pipe, the profiled sheet is laid on the light gauge cold-formed steel shape, the profiled sheet is waveform steel plate, the light gauge cold-formed steel shape is c-type bending steel plate, filling is equipped with the light polymer of cement base on the profiled sheet, among the light polymeric inner of cement base that the dewatering horizontal tube is arranged on profiled sheet, the sanitary apparatus branch pipe is connected with dewatering horizontal tube and stretches out plane on the light polymer of cement base.The utility model is easy for construction, realizes co-layer draining, is easy to repair.
Description
Technical field
It the utility model is related to light gauge cold-formed steel shape building field, and in particular to a kind of co-layer draining light gauge cold-formed steel shape is close
Rib type composite floor system.
Background technology
Existing light gauge cold-formed steel shape building sets two layers of floor, in upper floor to realize co-layer draining in toilet area
The branch drain and dewatering horizontal tube of installation sanitary apparatus in closing space between plate and lower floor's floor, upper strata floor is as waterproof
The basic unit of layer and architectural surface.The drawbacks of such a way be once there are seepage or other problemses in branch drain or dewatering horizontal tube,
In addition to needing to cut architectural surface and waterproof layer, also need to remove upper strata floor, it is difficult to overhaul.
Utility model content
The purpose of this utility model is that solve above-mentioned deficiency, there is provided a kind of co-layer draining light gauge cold-formed steel shape dense rib type group
Close superstructure.
To achieve the above object, technical solution of the present utility model is:A kind of co-layer draining light gauge cold-formed steel shape is close
Rib type composite floor system, including the light polymer of light gauge cold-formed steel shape, profiled sheet, dewatering horizontal tube, cement base, sanitary apparatus branch pipe,
The profiled sheet is laid on the light gauge cold-formed steel shape, and the profiled sheet is waveform steel plate, the cold bending thin wall type
Steel is c-type bending steel plate, is filled on the profiled sheet and is equipped with the light polymer of cement base, the dewatering horizontal tube is arranged in die mould
Among the light polymeric inner of cement base on steel plate, the sanitary apparatus branch pipe is connected with dewatering horizontal tube and stretches out cement base and gently gathers
Plane on compound.
After installing dewatering horizontal tube, sanitary apparatus branch pipe on profiled sheet during making, the light polymer of backfill cement base is extremely
It is required that absolute altitude.
The utility model has the following advantages:It is easy for construction, solve light gauge cold-formed steel shape building and be not suitable for co-layer draining
Problem, co-layer draining is realized, be easy to repair.
Brief description of the drawings:
Fig. 1 is structural representation of the present utility model.
Fig. 2 is sectional side view of the present utility model.
Embodiment
As shown in Figures 1 and 2, a kind of co-layer draining light gauge cold-formed steel shape dense rib type composite floor system, including cold bending thin wall type
The light polymer 4 of steel 1, profiled sheet 2, dewatering horizontal tube 3, cement base, sanitary apparatus branch pipe 5, the profiled sheet 2 are laid on described
On light gauge cold-formed steel shape 1, the profiled sheet 2 is waveform steel plate, and the light gauge cold-formed steel shape 1 is c-type bending steel plate, described
Filling is equipped with the light polymer 4 of cement base on profiled sheet 2, and the cement base that the dewatering horizontal tube 3 is arranged on profiled sheet 2 is light
The bosom of polymer 4, the sanitary apparatus branch pipe 5 are connected with dewatering horizontal tube 3 and stretch out plane on the light polymer 4 of cement base.
After installing dewatering horizontal tube 3, sanitary apparatus branch pipe 5 on profiled sheet 2 during making, the light polymer of cement base is backfilled
4 to requiring absolute altitude.
Claims (1)
- A kind of 1. co-layer draining light gauge cold-formed steel shape dense rib type composite floor system, it is characterised in that:Including light gauge cold-formed steel shape, die mould The light polymer of steel plate, dewatering horizontal tube, cement base, sanitary apparatus branch pipe, the profiled sheet are laid on the light gauge cold-formed steel shape On, the profiled sheet is waveform steel plate, and the light gauge cold-formed steel shape is c-type bending steel plate, is filled on the profiled sheet The light polymer of cement base is equipped with, among the light polymeric inner of cement base that the dewatering horizontal tube is arranged on profiled sheet, institute Sanitary apparatus branch pipe is stated with dewatering horizontal tube to be connected and stretch out plane on the light polymer of cement base.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720196244.0U CN206752792U (en) | 2017-03-02 | 2017-03-02 | A kind of co-layer draining light gauge cold-formed steel shape dense rib type composite floor system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720196244.0U CN206752792U (en) | 2017-03-02 | 2017-03-02 | A kind of co-layer draining light gauge cold-formed steel shape dense rib type composite floor system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206752792U true CN206752792U (en) | 2017-12-15 |
Family
ID=60608788
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720196244.0U Active CN206752792U (en) | 2017-03-02 | 2017-03-02 | A kind of co-layer draining light gauge cold-formed steel shape dense rib type composite floor system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206752792U (en) |
-
2017
- 2017-03-02 CN CN201720196244.0U patent/CN206752792U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203742623U (en) | Water-pressure-resistant composite structure for tunnel | |
CN205276316U (en) | Modular prefabricated piping lane | |
CN206386134U (en) | A kind of Underground Subway Station guarded drainage construction | |
CN202369968U (en) | Assembled water drainage box culvert | |
CN203768951U (en) | Basement deformation crack waterproof device with hydrophobic structure | |
CN206530363U (en) | One kind can the outer drainage system of maintenance type railway tunnel bottom structure | |
CN103806437B (en) | Double-layer vacuum preloading and hydraulic reclamation soft foundation processing method | |
CN205530344U (en) | Utility tunnel is pour to split type no mould | |
CN103669738A (en) | Method for manufacturing double-layer anti-seepage drainage device of roof | |
CN106869169A (en) | Three-dimensional interval construction method for underground comprehensive pipe gallery cabin body | |
CN202466631U (en) | Prefabricated reinforced concrete inspection well and die thereof | |
CN202416379U (en) | Precipitation post-pouring belt capable of stopping dewatering in advance | |
CN208121807U (en) | A kind of matched benzvalene form interface prefabrication type reinforced concrete water collection well of pipe gallery | |
CN206752792U (en) | A kind of co-layer draining light gauge cold-formed steel shape dense rib type composite floor system | |
CN103790181B (en) | Daylight illumination device pier base and manufacturing method thereof | |
CN103835421B (en) | Leakage-proof floor and anti-seepage construction method | |
CN203147066U (en) | Prepared hole waterproof structure of later-poured through-wall pipe | |
CN205617186U (en) | Finished product escape canal of holding concurrently flat stone function of side | |
CN202689323U (en) | Wall plate for increasing shearing force between wall plates | |
CN204059872U (en) | Building waterproof type piping shaft | |
CN202000461U (en) | Novel anti-seepage drainage system | |
CN203200798U (en) | Waterproof structure for basement post-cast strip | |
CN201738429U (en) | Drainage inspection well | |
CN208280410U (en) | Precast concrete entirety ground floor for kitchen and toilet | |
CN201420394Y (en) | Die for making pipeline reserved holes |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |