CN206736949U - The tower-crane foundation structure of building surrounding is covered in suitable for multi-layer underground building - Google Patents
The tower-crane foundation structure of building surrounding is covered in suitable for multi-layer underground building Download PDFInfo
- Publication number
- CN206736949U CN206736949U CN201720276657.XU CN201720276657U CN206736949U CN 206736949 U CN206736949 U CN 206736949U CN 201720276657 U CN201720276657 U CN 201720276657U CN 206736949 U CN206736949 U CN 206736949U
- Authority
- CN
- China
- Prior art keywords
- tower
- building
- crane
- tower crane
- underground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Foundations (AREA)
Abstract
It the utility model is related to the tower-crane foundation structure that building surrounding is covered in suitable for multi-layer underground building.Tower-crane foundation structure includes the tower body of building underground structure, tower crane and tower crane;Building underground structure includes more than one layer of hypogee and bottom plate or raft plate, tower crane base pitch and standard knot are sequentially connected composition;Improvement is:Tower crane one-piece casting is on bottom plate or raft plate;Tower body passes through more than one layer of hypogee, and the lower end of the tower crane base pitch of tower body foot is fixed on tower crane.Tower-crane foundation structure of the present utility model avoids increases supporting construction similar to lattice column for construction tower crane, and constructing operation is simple and convenient, and safety guarantee coefficient is big, does not influence underground main structure construction, effectively reduces working measure and takes.
Description
Technical field
The utility model belongs to building engineering technical field, and in particular to the tower crane installation suitable for architectural engineering is applied
Work.
Background technology
In building engineering, in especially present more single buildings of the big scale of construction and integral multi-layered construction of underground structure,
Part tower crane directly can not construct on foundation, be made troubles to tower crane construction and installation use.Currently, have and much apply
Work order position adds lattice column to be supported as tower crane using cast-in-situ bored pile, and lattice column stretches out underground structure top board, tower crane
It is cast on lattice column.Such a tower-crane foundation structure has the following disadvantages:1. lattice pillar tower crane complicated construction technique, into
This is higher, and safety wind is dangerous big;2. in lattice column insertion cast-in-situ bored pile, the difficult control of construction quality, quality directly affects
Tower crane bearing capacity;3. pouring tower crane on lattice column again, equivalent to sky assembling reinforcement is faced, supporting module, coagulation is poured
Soil, difficulty of construction are big.
Utility model content
Farthest to ensure tower crane construction safety, easy for construction and economic, the utility model provides a kind of suitable
The building tower-crane foundation structure of building surrounding is covered in for multi-layer underground building.
Specific technical solution is as follows:
The tower-crane foundation structure of building surrounding, including building underground structure, tower are covered in suitable for multi-layer underground building
Hang basis(1)With the tower body of tower crane;The building underground structure includes more than one layer of hypogee and bottom plate or raft plate 2,
The tower body of tower crane is sequentially connected and formed by base pitch and standard knot 4;Improvement is:
The one-piece casting of tower crane 1 is on bottom plate or raft plate 2;
The tower body passes through more than one layer of hypogee, and the lower end of the tower crane base pitch of tower body bottom is fixed on tower crane
1。
The technical scheme further limited is as follows:
When bottom plate or raft plate 2 are constructed after tower crane 1, steel plate for sealing water 9 is embedded with advance on tower crane 1.
The building underground structure also includes the pile foundation 8 being made up of the pile of more than four, and the tower crane 1 is set
In in pile foundation 8.
Described more than one layer of hypogee includes underground negative one floor plate 5, the minus two floors plate 6 in underground and underground structure top
Plate 7.
Advantageous effects of the present utility model embody in the following areas:
1. the utility model tower crane 1 on the bottom plate or raft plate 2 in hypogee, is avoided as tower crane base of constructing
Plinth and increase the supporting construction similar to lattice column, effectively reduce working measure take.
2. standard section of tower crane 4 passes through hypogee floor and top plate, constructing operation is simple and convenient, and safety guarantee coefficient is big,
Underground main structure construction is not influenceed, and its economic benefit is constructed also above the tower crane of other modes.
Brief description of the drawings
Fig. 1 is the utility model structure diagram.
Fig. 2 is Fig. 1 tower crane profile.
Fig. 3 is the utility model structural representation for having pile foundation.
Fig. 4 is Fig. 3 tower crane profile.
Sequence number in upper figure:Tower crane 1, bottom plate or raft plate 2, bed course 3, standard section of tower crane 4, underground negative one floor plate 5,
Under minus two floors plate 6, underground structure top board 7, pile foundation 8, steel plate for sealing water 9, pre-embedded bolt 10.
Embodiment
Below in conjunction with the accompanying drawings, by embodiment, the utility model is further described.
Embodiment 1
Referring to Fig. 1 and Fig. 2, the tower-crane foundation structure of building surrounding is covered in suitable for multi-layer underground building includes building
The tower body of underground structure, tower crane 1 and tower crane.
Building underground structure includes underground negative one floor plate 5, the minus two floors plate 6 in underground, underground structure top board 7 and bottom plate
Or raft plate 2.The tower body of tower crane is sequentially connected and formed by tower crane base pitch and standard section of tower crane 4.
Improvement is:The one-piece casting of tower crane 1 is on bottom plate or raft plate 2;Tower body through underground structure top board 7,
Under minus two floors plate 6 and underground negative one floor plate 5, the lower end of the tower crane base pitch of tower body foot is fixed on tower crane 1.
Embodiment 2
Referring to Fig. 3 and Fig. 4, when natural characteristic value of foundation bearing capacity is insufficient for tower crane requirement for bearing capacity, then tower of constructing
Before hanging basis 1, four pile foundations 8 of first constructing, for improving the bearing capacity of tower crane 1.Tower crane 1 is arranged in pile foundation 8.
Pile foundation 8 is generally four pile foundations, but is not limited to four.
Claims (4)
1. the tower-crane foundation structure of building surrounding is covered in suitable for multi-layer underground building, including building underground structure, tower crane
Basis(1)With the tower body of tower crane;The building underground structure includes more than one layer of hypogee and bottom plate or raft plate(2),
The tower body of tower crane is by base pitch and standard knot(4)It is sequentially connected composition;It is characterized in that:
The tower crane(1)One-piece casting is located at bottom plate or raft plate(2)On;
The tower body passes through more than one layer of hypogee, and the lower end of the tower crane base pitch of tower body bottom is fixed on tower crane(1).
2. the tower-crane foundation structure according to claim 1 that building surrounding is covered in suitable for multi-layer underground building, it is special
Sign is:When bottom plate or raft plate(2)After tower crane(1)During construction, tower crane(1)On be embedded with steel plate for sealing water in advance(9).
3. the tower-crane foundation structure according to claim 1 that building surrounding is covered in suitable for multi-layer underground building, it is special
Sign is:The building underground structure also includes the pile foundation being made up of the stake of more than four(8), the tower crane(1)
Located at pile foundation(8)On.
4. the tower-crane foundation structure according to claim 1 that building surrounding is covered in suitable for multi-layer underground building, it is special
Sign is:Described more than one layer of hypogee includes underground negative one floor plate(5), the minus two floors plate in underground(6)Tied with underground
Structure top plate(7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720276657.XU CN206736949U (en) | 2017-03-21 | 2017-03-21 | The tower-crane foundation structure of building surrounding is covered in suitable for multi-layer underground building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720276657.XU CN206736949U (en) | 2017-03-21 | 2017-03-21 | The tower-crane foundation structure of building surrounding is covered in suitable for multi-layer underground building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206736949U true CN206736949U (en) | 2017-12-12 |
Family
ID=60556835
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720276657.XU Active CN206736949U (en) | 2017-03-21 | 2017-03-21 | The tower-crane foundation structure of building surrounding is covered in suitable for multi-layer underground building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206736949U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110331735A (en) * | 2019-07-18 | 2019-10-15 | 中建八局第四建设有限公司 | A kind of tower crane mounting structure for coastal region soft layer |
-
2017
- 2017-03-21 CN CN201720276657.XU patent/CN206736949U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110331735A (en) * | 2019-07-18 | 2019-10-15 | 中建八局第四建设有限公司 | A kind of tower crane mounting structure for coastal region soft layer |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110374131A (en) | A kind of cylinder composite truss formula offshore wind turbine foundation and its construction technology | |
CN205152976U (en) | Marine precast concrete cushion cap wind turbine foundation | |
CN201581409U (en) | Combined tower crane foundation of cross beam supported by steel latticework columns in deep foundation pit | |
CN206468008U (en) | Outer wall of basement one side formwork support system | |
CN208251156U (en) | It is a kind of to reduce the grand heavy device of underground structure using building enclosure | |
CN105421477A (en) | Construction method for tower crane foundation | |
CN206736949U (en) | The tower-crane foundation structure of building surrounding is covered in suitable for multi-layer underground building | |
CN206233272U (en) | A kind of anti-floating of underground building structure | |
CN206829461U (en) | After pour teeth groove and be linked and packed formula precast slab | |
CN201495555U (en) | Cap tower-crane foundation of concrete cast-in-place high pile for tower erection at the house center | |
CN202595758U (en) | Batter post foundation structure for overhead transmission line | |
CN208486282U (en) | A kind of vertical layered assembled environment-friendly concrete basis | |
CN206887980U (en) | A kind of integrated bracket basis of antifreeze pile | |
CN208235562U (en) | A kind of static pressure pile structure for Collapsible Loess Stabilized | |
CN103225313A (en) | Connection flange for prestressed reinforced concrete composite foundation | |
CN110593298A (en) | Composite foundation for improving bearing performance of cylindrical foundation by using auxiliary piles and construction method thereof | |
CN203475463U (en) | Offshore wind turbine foundation with concrete caisson and steel pipe frame steel structure combined | |
CN205530324U (en) | Miniature stake of thin -walled cold -formed steel | |
CN213625735U (en) | Basement drainage anti-floating structure | |
CN204959769U (en) | Lower part has stagnant water centrifugation side of strutting stake envelope in clamping orient groove | |
CN108487316A (en) | It is a kind of to reduce underground structure grand heavy device and its construction method using building enclosure | |
CN210827544U (en) | Composite foundation for improving bearing performance of cylindrical foundation by using auxiliary piles | |
CN207846678U (en) | The strong ties of first floor vertical member and basement roof construct | |
CN206385562U (en) | A kind of Novel Communication bar basis | |
CN201501749U (en) | Self-climbing type tower machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||