CN206707692U - A kind of large-scale gas drilling kill-job analogue means - Google Patents

A kind of large-scale gas drilling kill-job analogue means Download PDF

Info

Publication number
CN206707692U
CN206707692U CN201621213538.1U CN201621213538U CN206707692U CN 206707692 U CN206707692 U CN 206707692U CN 201621213538 U CN201621213538 U CN 201621213538U CN 206707692 U CN206707692 U CN 206707692U
Authority
CN
China
Prior art keywords
pressure sensor
gas
transparent glass
glass tube
kill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621213538.1U
Other languages
Chinese (zh)
Inventor
李鹏杰
魏纳
林振凯
陈光凌
成川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Petroleum University
Original Assignee
Southwest Petroleum University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Petroleum University filed Critical Southwest Petroleum University
Priority to CN201621213538.1U priority Critical patent/CN206707692U/en
Application granted granted Critical
Publication of CN206707692U publication Critical patent/CN206707692U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)
  • Examining Or Testing Airtightness (AREA)

Abstract

It the utility model is related to a kind of large-scale gas drilling kill-job analogue means, including gas cylinder, choke valve, pressure gauge, flowmeter, pressure sensor, organic transparent glass tube, blue plastic core pipe, aerial drainage valve, leak conduit, pump, video camera.Clear water is pumped into blue plastic core pipe, simulation kill-job mud is pumped into process, throttle valve adjustment clear water flow simulates drilling fluid injection rate, gas cylinder is used to simulate control stratum gas production with choke valve, pressure gauge, flowmeter, organic clear glass bottom of the tube and top are equipped with pressure sensor in pit shaft symmetrical side, two video cameras are attached separately to the upper of transparent organic transparent glass tube, for recording gas liquid two-phase flow situation of change in whole experiment process pit shaft.The utility model can more true simulation gas drilling Well Killing Process, it is simple in construction, it is easy to operate, be easy to observe, provide reliable laboratory reference for real gas drilling well kill-job operation, be easy to preferred arrangement and method for construction.

Description

A kind of large-scale gas drilling kill-job analogue means
Technical field
Gas drilling field is the utility model is related to, relates more specifically to a kind of large-scale gas drilling kill-job analogue means.
Background technology
Gas drilling number accounts for the 30% of world's Land petroleum drilling well total amount, has power auger compared with conventional liq drilling well Speed is fast, overcomes leakage, finds the advantages that oil-gas Layer, protection reservoir in time, and domestic and international drilling practice shows that gas drilling is only with its Special drilling technology, compared with conventional drilling, it can reduce by 2/3 drill bit consumption, improve 4~14 times of rate of penetration, and can save Drilling fluid expense, shorten well construction period.But after gas drilling is boring chance high pressure high yield gas reservoir, if well head is not complete Well-control equipment, be unsatisfactory for the conditions such as non-snubbing service operation, then must carry out kill-job operation so that follow-up completion is constructed, gas Body drilling well has relatively big difference with conventional mud drilling well overflow kill-job, and the original intention that gas drilling opens payzone is protection reservoir, now Using mud lubrication, mud density is too high may cause kill-job after the completion of bottom pressure be far above strata pressure, grievous injury storage Layer, mud density is too low and kill-job may be caused to fail, so the control of wellhead back pressure is particularly important.In protection reservoir base Suitable mud density is set on plinth, slush pump provides suitable discharge capacity, coordinates appropriate wellhead back pressure to control so that pit shaft ring Fluid column is smoothly established in sky, and the kill-job mud of injection is not blown out by air-flow, gas-bearing formation pushed down within the most fast time, while to the greatest extent may be used Can injury of the ground reduction to reservoir.At present, without a gas drilling kill-job laboratory apparatus, therefore, there is provided herein a kind of big Type gas drilling kill-job analogue means, this experimental provision either size or function all can more true simulation gas drillings Well Killing Process, it is easy to observe, flow pattern, bottom pressure, gas production etc. in the reacting gas drilling well Well Killing Process of clear and definite The change of parameter, reliable laboratory reference is provided for real gas drilling well kill-job operation, is easy to preferred arrangement and method for construction.
The content of the invention
The technical problem that the utility model solves is to provide a kind of large-scale gas drilling kill-job analogue means, can be more True simulation gas drilling Well Killing Process, is easy to observe, flow pattern in the reacting gas drilling well Well Killing Process of clear and definite, The Parameters variations such as bottom pressure, gas production, reliable laboratory reference is provided for real gas drilling well kill-job operation, is easy to preferably apply Work scheme.
Technical scheme is used by the utility model:
A kind of large-scale gas drilling kill-job analogue means, mainly by gas cylinder, choke valve, pressure gauge, flowmeter, pressure Sensor, organic transparent glass tube, blue plastic core pipe, aerial drainage valve, leak conduit, pump, image mechanism into.Wherein:Clear water Be connected successively with choke valve B, pressure gauge C, flowmeter B and blue plastic core pipe by pump, gas cylinder successively with throttle valve A, pressure Power Table A, flowmeter A are connected with transparent glass tube, and eduction valve is connected with the top of pressure gauge B, organic transparent glass tube successively.Shooting Machine A, video camera B are attached separately at the top 1/2 of organic transparent glass tube center at center and bottom 1/2, in organic transparent glass Glass bottom of the tube and top are equipped with pressure sensor A, pressure sensor B, pressure sensor C, pressure sensor in pit shaft symmetrical side D, the real-time pressure at two can be read, for simulating bottom pressure and well head pressure in actual condition;Leak conduit and aerial drainage Valve is connected at the top of organic transparent glass tube, and the things such as kill-job failure, blowout, well kick can be simulated by the aperture for adjusting eduction valve Therefore operating mode.
The utility model can more true simulation gas drilling Well Killing Process, it is simple in construction, it is easy to operate, be easy to see Survey, the Parameters variation such as flow pattern, bottom pressure, gas production in the reacting gas drilling well Well Killing Process of clear and definite, for reality Gas drilling kill-job operation provides reliable laboratory reference, is easy to preferred arrangement and method for construction.
Brief description of the drawings
Fig. 1 is a kind of schematic diagram of large-scale gas drilling kill-job analogue means of the utility model.
In Fig. 1:1. gas cylinder, 2. throttle valve As, 3. pressure gauge A, 4. flowmeter A, 5. organic transparent glass tubes, 6. is blue Color plastic core pipe, 7. pressure gauge B, 8. eduction valves, 9. leak conduits, 10. pressure sensor A, 11. pressure sensor B, 12. press Force snesor C, 13. pressure sensor D, 14. video camera A, 15. video camera B, 16. flowmeter B, 17. pressure gauge C, 18. throttle Valve B, 19. pumps.
Embodiment
The utility model is described further below in conjunction with the accompanying drawings.
A kind of large-scale gas drilling kill-job analogue means of the present utility model as shown in Figure 1 is by gas cylinder 1, choke valve A2, pressure gauge A3, flowmeter A4, organic transparent glass tube 5, blue plastic core pipe 6, pressure gauge B7, eduction valve 8, leak conduit 9th, pressure sensor A10, pressure sensor B11, pressure sensor C12, pressure sensor D13, video camera A14, video camera B15, flowmeter B16, pressure gauge C17, choke valve B18 and pump 19 form.With organic transparent glass tube 5 come simulation wellbore hole sleeve pipe, Blue plastic core pipe 6 simulates drill string, and clear water is pumped into by pump 19 through the pipeline equipped with choke valve B18, pressure gauge C17, flowmeter B16 Simulation kill-job mud is pumped into blue plastic core pipe 6 and is pumped into process, can be used for simulation different through choke valve B18 regulation clear water flows Drilling fluid injection rate under operating mode;The gas simulated formation aerogenesis that gas cylinder 1 provides, it is connected with organic transparent glass tube 5 Pipeline on be sequentially arranged with throttle valve A 2, pressure gauge A3, flowmeter A4 be used for simulate control stratum gas production, by choke valve A2 regulation and pressure gauge A3 and flowmeter A4 registrations reaction, this device can be used to simulate the kill-job operating mode of different gas production; The leak conduit 9 and aerial drainage valve 8 for being connected to organic top of transparent glass tube 5 can simulate the things such as kill-job failure, blowout, well kick Therefore operating mode, in organic bottom of transparent glass tube 5 and top in pit shaft symmetrical side equipped with pressure sensor A10, pressure sensor B11, pressure sensor C12, pressure sensor D13, can be read the real-time pressure at two, and pressure is equivalent in actual condition at two Bottom pressure and well head pressure, video camera A14, video camera B15 be attached separately to the top 1/2 of transparent organic transparent glass tube 5 Center at place center and bottom 1/2, for recording in whole experiment process gas-liquid in the situation of change of liquid level and pit shaft Two-phase flow situation of change, the device accurately can really simulate gas drilling Well Killing Process, make for real gas drilling well kill-job Industry provides reliable laboratory reference, is easy to preferred arrangement and method for construction.

Claims (1)

  1. A kind of 1. large-scale gas drilling kill-job analogue means, mainly by gas cylinder (1), throttle valve A (2), pressure gauge A (3), stream Gauge A (4), organic transparent glass tube (5), blue plastic core pipe (6), pressure gauge B (7), eduction valve (8), leak conduit (9), Pressure sensor A (10), pressure sensor B (11), pressure sensor C (12), pressure sensor D (13), video camera A (14), Video camera B (15), flowmeter B (16), pressure gauge C (17), choke valve B (18), pump (19) composition, it is characterised in that:High pressure gas Bottle (1) is connected with throttle valve A (2), pressure gauge A (3), flowmeter A (4) and transparent glass tube (5) successively, and eduction valve (8) is successively It is connected with the top of pressure gauge B (7), organic transparent glass tube (5);Clear water is by pump (19) through being equipped with choke valve B (18), pressure gauge C (17), flowmeter B (16) pipeline is pumped into blue plastic core pipe (6), and choke valve B (18) can adjust clear water flow, high pressure gas Throttle valve A (2), pressure gauge A (3), flowmeter A (4) are sequentially arranged with the pipeline that bottle (1) is connected with organic transparent glass tube (5), Leak conduit (9) and eduction valve (8) are connected at the top of organic transparent glass tube (5), organic transparent glass tube (5) bottom and top In pit shaft symmetrical side equipped with pressure sensor A (10), pressure sensor B (11), pressure sensor C (12), pressure sensor D (13), video camera A (14), video camera B (15) are attached separately to center and bottom 1/2 at the top 1/2 of organic transparent glass tube (5) Place center.
CN201621213538.1U 2016-11-10 2016-11-10 A kind of large-scale gas drilling kill-job analogue means Expired - Fee Related CN206707692U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621213538.1U CN206707692U (en) 2016-11-10 2016-11-10 A kind of large-scale gas drilling kill-job analogue means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621213538.1U CN206707692U (en) 2016-11-10 2016-11-10 A kind of large-scale gas drilling kill-job analogue means

Publications (1)

Publication Number Publication Date
CN206707692U true CN206707692U (en) 2017-12-05

Family

ID=60471375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621213538.1U Expired - Fee Related CN206707692U (en) 2016-11-10 2016-11-10 A kind of large-scale gas drilling kill-job analogue means

Country Status (1)

Country Link
CN (1) CN206707692U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222926A (en) * 2018-01-03 2018-06-29 中国石油大学(华东) Relief well kill-job analogue experiment installation and method
CN108952697A (en) * 2018-07-04 2018-12-07 中国石油天然气集团有限公司 Push back method Experimental mimic system and analogy method
CN109630047A (en) * 2018-12-07 2019-04-16 中国石油大学(华东) Five steps for no safe pressure window fractured reservoir kill-job push back method and equipment
CN110185442A (en) * 2019-06-05 2019-08-30 中海石油(中国)有限公司 Displacement method kill-job experimental provision and method
CN110207749A (en) * 2019-06-05 2019-09-06 中海石油(中国)有限公司 Top well killing method kill-job imitative experimental appliance
CN110593817A (en) * 2019-10-12 2019-12-20 中国石油天然气股份有限公司西南油气田分公司工程技术研究院 Wellhead operation visualization device and method
CN110853475A (en) * 2019-11-25 2020-02-28 中国海洋石油集团有限公司 Deep sea drilling process pit shaft oil gas invasion simulation test device
CN111878058A (en) * 2020-07-28 2020-11-03 中海石油(中国)有限公司 Device and method for simulating gas migration of shaft in well killing process by using pressure recovery method
CN112145170A (en) * 2020-09-29 2020-12-29 中海石油(中国)有限公司 Oil-gas well blowout experiment simulation device and operation method
CN114566072A (en) * 2022-02-25 2022-05-31 中国海洋石油集团有限公司 Blowout emergency drilling simulation system

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222926A (en) * 2018-01-03 2018-06-29 中国石油大学(华东) Relief well kill-job analogue experiment installation and method
CN108952697A (en) * 2018-07-04 2018-12-07 中国石油天然气集团有限公司 Push back method Experimental mimic system and analogy method
CN109630047A (en) * 2018-12-07 2019-04-16 中国石油大学(华东) Five steps for no safe pressure window fractured reservoir kill-job push back method and equipment
CN110207749B (en) * 2019-06-05 2022-01-04 中海石油(中国)有限公司 Well killing simulation experiment device adopting top well killing method
CN110207749A (en) * 2019-06-05 2019-09-06 中海石油(中国)有限公司 Top well killing method kill-job imitative experimental appliance
CN110185442A (en) * 2019-06-05 2019-08-30 中海石油(中国)有限公司 Displacement method kill-job experimental provision and method
CN110593817A (en) * 2019-10-12 2019-12-20 中国石油天然气股份有限公司西南油气田分公司工程技术研究院 Wellhead operation visualization device and method
CN110853475A (en) * 2019-11-25 2020-02-28 中国海洋石油集团有限公司 Deep sea drilling process pit shaft oil gas invasion simulation test device
CN111878058A (en) * 2020-07-28 2020-11-03 中海石油(中国)有限公司 Device and method for simulating gas migration of shaft in well killing process by using pressure recovery method
CN112145170A (en) * 2020-09-29 2020-12-29 中海石油(中国)有限公司 Oil-gas well blowout experiment simulation device and operation method
CN112145170B (en) * 2020-09-29 2023-08-15 中海石油(中国)有限公司 Oil-gas well blowout experiment simulation device and operation method
CN114566072A (en) * 2022-02-25 2022-05-31 中国海洋石油集团有限公司 Blowout emergency drilling simulation system
CN114566072B (en) * 2022-02-25 2024-04-19 中国海洋石油集团有限公司 Blowout emergency drilling simulation system

Similar Documents

Publication Publication Date Title
CN206707692U (en) A kind of large-scale gas drilling kill-job analogue means
CN103531076B (en) A set of drilling condition simulation system and workflow thereof
WO2018184397A1 (en) Integrated evaluation, testing and simulation apparatus for wellbore sand-control blocking and unblocking, and method
CN110924906B (en) Gas lift well liquid discharge simulation test device
CN104453802B (en) Coal bed gas pit shaft gas-liquid two-phase flow analogue means that many coal seams were adopted jointly
CN206035473U (en) Fracturing fluid returns row crack analogue means
CN205654336U (en) Fractured reservoir complex operating condition simulation experiment device
CN105672927B (en) A kind of well killing method after gas drilling blowout
CN105735981A (en) Fractured stratum complex working condition simulation experiment device
CN103967460A (en) Novel oil pool edge water intrusion visualized simulation device with well pattern influence considered
CN109577954A (en) Drilling-measuring-fixing-completing integrated fine pressure control drilling and well completion operation method
CN205477589U (en) Visual simulation experiment device of water pumping gas production in gas well pit shaft of coal seam
CN202081890U (en) All-service gas lifting stratum testing tubular column
CN113338915B (en) Method for judging whether gas well accumulates liquid and predicting liquid accumulation height
CN107780879A (en) A kind of reverse inlet well well formation device and method
CN104632195B (en) Gas lift flow aiding horizontal well water exploration pipe column and method
CN106223888B (en) Sealing liquid rope coring drill
CN113062733A (en) Segmented horizontal well water control three-dimensional simulation experiment device and experiment method thereof
CN206329294U (en) One kind simulation nitrogen horizontal well drilling formation water output experimental provision
CN107939444A (en) A kind of casing programme and installation and application that chamber is made for salt hole air reserved storeroom
CN219176314U (en) Stratum inclination adjustable gas drive analogue means for oil gas field development indoor experiment
CN203097879U (en) Inflow dynamic two-dimensional visible simulation device of horizontal well and straight well
CN115653536B (en) Circulating pressure control method and system for liquid rubber plug packing production layer in drilling process
CN104835405A (en) Experiment method for simulating well killing during overflow period
CN204716213U (en) Pressure fluctuation meter drives self-balancing piston pump pumping equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171205

Termination date: 20181110

CF01 Termination of patent right due to non-payment of annual fee