CN206706903U - A kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device - Google Patents

A kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device Download PDF

Info

Publication number
CN206706903U
CN206706903U CN201720453427.6U CN201720453427U CN206706903U CN 206706903 U CN206706903 U CN 206706903U CN 201720453427 U CN201720453427 U CN 201720453427U CN 206706903 U CN206706903 U CN 206706903U
Authority
CN
China
Prior art keywords
tubule
conservancy diversion
head
water conservancy
transverse tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720453427.6U
Other languages
Chinese (zh)
Inventor
罗荣辉
温和平
饶荣军
刘贵
陈云龙
刘志科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuxi Dahongshan Mining Co Ltd
Original Assignee
Yuxi Dahongshan Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuxi Dahongshan Mining Co Ltd filed Critical Yuxi Dahongshan Mining Co Ltd
Priority to CN201720453427.6U priority Critical patent/CN206706903U/en
Application granted granted Critical
Publication of CN206706903U publication Critical patent/CN206706903U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The utility model discloses a kind of ring water for being easy to head-tank downstream pipe to overhaul to keep in guiding device, including keeping in transverse tube, head-tank connecting tube, temporary longitudinal tubule (L tubule), first water conservancy diversion transverse tube, first water conservancy diversion longitudinal tubule (L tubule), second water conservancy diversion transverse tube, second water conservancy diversion longitudinal tubule (L tubule), tapping pipe, middle part on described temporary transverse tube is connected by the delivery port of head-tank connecting tube and head-tank, one end of described temporary transverse tube is connected with the lower end of temporary longitudinal tubule (L tubule), the other end is provided with blind plate plug, one end of the first described water conservancy diversion transverse tube is connected with the upper end of temporary longitudinal tubule (L tubule), the other end is connected with the upper end of the first water conservancy diversion longitudinal tubule (L tubule), one end of the second described water conservancy diversion transverse tube is connected with the lower end of the first water conservancy diversion longitudinal tubule (L tubule), the other end is connected with the upper end of the second water conservancy diversion longitudinal tubule (L tubule), described tapping pipe is located at the bottom of temporary transverse tube, described tapping pipe is provided with sluicing tube valve.

Description

A kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device
Technical field
The utility model belongs to supply channel service technique field, and in particular to one kind is easy to head-tank downstream pipe to examine The ring water repaiied keeps in guiding device.
Background technology
Factories and miness ring water system is the important system recycled as industrial enterprise's water resource, whole system ring water use efficiency Height, and judge the important evidence of industrial enterprise's energy consumption index.And working as needs under the head-tank to ring water system When play pipe road is overhauled, because leakage current phenomenon occurs in the flowing water Valve of existing head-tank mostly after closing, cause Normal service is influenceed, so in actual mechanical process, typically first needs all to empty to enter again by the ring water in head-tank Row maintenance, ring water is transmitted back to head-tank again by water pump again after maintenance, such way one is operation be present not The problem of facilitating, but waste time and energy, the energy, manpower consumption are big, and especially the capacity of head-tank reaches 3000m3, very not It is convenient.
Therefore, research and development one kind is easy to head-tank downstream pipe to overhaul, simple to operate, ring water easy to use keeps in water conservancy diversion Device is the key to solve the above problems.
Utility model content
The purpose of this utility model is that providing a kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in water conservancy diversion dress Put.
The purpose of this utility model is achieved in that including temporary transverse tube, head-tank connecting tube, temporary longitudinal tubule (L tubule), the One water conservancy diversion transverse tube, the first water conservancy diversion longitudinal tubule (L tubule), the second water conservancy diversion transverse tube, the second water conservancy diversion longitudinal tubule (L tubule), tapping pipe, on described temporary transverse tube in Portion is connected by the delivery port of head-tank connecting tube and head-tank, under one end of described temporary transverse tube and temporary longitudinal tubule (L tubule) End connection, the other end are provided with blind plate plug, and one end of the first described water conservancy diversion transverse tube is connected with the upper end of temporary longitudinal tubule (L tubule), the other end It is connected with the upper end of the first water conservancy diversion longitudinal tubule (L tubule), one end of the second described water conservancy diversion transverse tube is connected with the lower end of the first water conservancy diversion longitudinal tubule (L tubule), separately One end is connected with the upper end of the second water conservancy diversion longitudinal tubule (L tubule), and described tapping pipe is located at the bottom of temporary transverse tube, and described tapping pipe is provided with Sluicing tube valve.
The beneficial effects of the utility model:When being overhauled to head-tank downstream pipe, temporary transverse tube, temporary longitudinal tubule (L tubule) can The ring water of leakage current is kept in, prevents leakage current ring water from influenceing normal service;The utility model avoids prior art and overhauled , it is necessary to which the shortcomings that ring water in head-tank is emptied, reduces the phenomenon of the wasting of resources in journey;Meanwhile the utility model can Ensure the stability of liquid level in head-tank;Tapping pipe can be discharged easily to keeping in transverse tube, keeping in the residual water in longitudinal tubule (L tubule) Reclaimed to cistern is unified, avoid wasting;The utility model also has the advantages of simple in construction, easy to use.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
In figure:1- keeps in transverse tube, 2- head-tank connecting tubes, and 3- keeps in longitudinal tubule (L tubule), 4- the first water conservancy diversion transverse tubes, the water conservancy diversion of 5- first Longitudinal tubule (L tubule), 6- the second water conservancy diversion transverse tubes, 7- the second water conservancy diversion longitudinal tubule (L tubule)s, 8- tapping pipes, 9- sluicing tube valves.
Embodiment
The utility model is further described below in conjunction with the accompanying drawings, but the utility model is not subject in any way Limitation, any conversion or replacement made based on the utility model training centre, belongs to the scope of protection of the utility model.
The utility model includes temporary transverse tube 1, head-tank connecting tube 2, temporary longitudinal tubule (L tubule) 3, the first water conservancy diversion as shown in Figure 1 Transverse tube 4, the first water conservancy diversion longitudinal tubule (L tubule) 5, the second water conservancy diversion transverse tube 6, the second water conservancy diversion longitudinal tubule (L tubule) 7, tapping pipe 8, on described temporary transverse tube 1 in Portion is connected by head-tank connecting tube 2 with the delivery port of head-tank, one end of described temporary transverse tube 1 and temporary longitudinal tubule (L tubule) 3 Lower end connection, the other end is provided with blind plate plug, and one end of the first described water conservancy diversion transverse tube 4 is connected with the upper end of temporary longitudinal tubule (L tubule) 3, The other end is connected with the upper end of the first water conservancy diversion longitudinal tubule (L tubule) 5, under one end of the second described water conservancy diversion transverse tube 6 and the first water conservancy diversion longitudinal tubule (L tubule) 5 End connection, the other end are connected with the upper end of the second water conservancy diversion longitudinal tubule (L tubule) 7, and described tapping pipe 8 is located at the bottom of temporary transverse tube 1, described Tapping pipe 8 be provided with sluicing tube valve 9.
The caliber of described temporary transverse tube 1 is 920 ~ 940mm.
Described head-tank connecting tube 2, temporary longitudinal tubule (L tubule) 3, the first water conservancy diversion transverse tube 4, the first water conservancy diversion longitudinal tubule (L tubule) 5, the second water conservancy diversion Transverse tube 6, the caliber of the second water conservancy diversion longitudinal tubule (L tubule) 7 are 720 ~ 740mm.
The height of described temporary longitudinal tubule (L tubule) 3 is 1000 ~ 2000mm.
The capacity of described head-tank is 2800 ~ 3200m3
The lower end of the second described water conservancy diversion longitudinal tubule (L tubule) 7 is collector nozzle.
Described collector nozzle is connected with head-tank downstream pipe.
Described tapping pipe 8 is connected with tank.
Utility model works principle and the course of work:When needing to overhaul head-tank downstream pipe, first Head-tank flowing water Valve is closed, then opens sluicing tube valve 9 by the unified recovery of remaining ring water discharge in the present apparatus, then close Close sluicing tube valve 9, you can start to overhaul;During maintenance, the ring water of head-tank flowing water Valve leakage current connects through head-tank Adapter 2 is flowed into temporary transverse tube 1, and after being filled in temporary transverse tube 1, ring water enters temporary longitudinal tubule (L tubule) 3;After maintenance, open Head-tank flowing water Valve, you can normal water supply.
The advantages of the utility model:When being overhauled to head-tank downstream pipe, temporary transverse tube, temporary longitudinal tubule (L tubule) can be to leakages The ring water of stream is kept in, and prevents leakage current ring water from influenceing normal service;The utility model is avoided in prior art maintenance process, The shortcomings that needing to empty in the ring water in head-tank, reduce the phenomenon of the wasting of resources;Meanwhile the utility model can ensure height The stability of liquid level in the pond of position;Tapping pipe easily can be expelled to water storage to keeping in transverse tube, keeping in the residual water in longitudinal tubule (L tubule) Pond is unified to reclaim, and avoids wasting;The utility model also has the advantages of simple in construction, easy to use.

Claims (8)

1. a kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device, it is characterized in that:Including keeping in transverse tube (1), head-tank connecting tube(2), temporary longitudinal tubule (L tubule)(3), the first water conservancy diversion transverse tube(4), the first water conservancy diversion longitudinal tubule (L tubule)(5), the second water conservancy diversion it is horizontal Pipe(6), the second water conservancy diversion longitudinal tubule (L tubule)(7), tapping pipe(8), described temporary transverse tube(1)On middle part pass through head-tank connecting tube (2)It is connected with the delivery port of head-tank, described temporary transverse tube(1)One end and temporary longitudinal tubule (L tubule)(3)Lower end connection, it is another End is provided with blind plate plug, the first described water conservancy diversion transverse tube(4)One end and temporary longitudinal tubule (L tubule)(3)Upper end connection, the other end and the One water conservancy diversion longitudinal tubule (L tubule)(5)Upper end connection, the second described water conservancy diversion transverse tube(6)One end and the first water conservancy diversion longitudinal tubule (L tubule)(5)Lower end connect Connect, the other end and the second water conservancy diversion longitudinal tubule (L tubule)(7)Upper end connection, described tapping pipe(8)Located at temporary transverse tube(1)Bottom, institute The tapping pipe stated(8)Provided with sluicing tube valve(9).
2. the ring water according to claim 1 for being easy to head-tank downstream pipe to overhaul keeps in guiding device, it is characterized in that: Described temporary transverse tube(1)Caliber be 920 ~ 940mm.
3. the ring water according to claim 1 for being easy to head-tank downstream pipe to overhaul keeps in guiding device, it is characterized in that: Described head-tank connecting tube(2), temporary longitudinal tubule (L tubule)(3), the first water conservancy diversion transverse tube(4), the first water conservancy diversion longitudinal tubule (L tubule)(5), the second water conservancy diversion Transverse tube(6), the second water conservancy diversion longitudinal tubule (L tubule)(7)Caliber be 720 ~ 740mm.
4. the ring water according to claim 1 for being easy to head-tank downstream pipe to overhaul keeps in guiding device, it is characterized in that: Described temporary longitudinal tubule (L tubule)(3)Height be 1000 ~ 2000mm.
5. the ring water according to claim 1 for being easy to head-tank downstream pipe to overhaul keeps in guiding device, it is characterized in that: The capacity of described head-tank is 2800 ~ 3200m3
6. the ring water according to claim 1 for being easy to head-tank downstream pipe to overhaul keeps in guiding device, it is characterized in that: The second described water conservancy diversion longitudinal tubule (L tubule)(7)Lower end be collector nozzle.
7. the ring water according to claim 6 for being easy to head-tank downstream pipe to overhaul keeps in guiding device, it is characterized in that: Described collector nozzle is connected with head-tank downstream pipe.
8. the ring water according to claim 1 for being easy to head-tank downstream pipe to overhaul keeps in guiding device, it is characterized in that: Described tapping pipe(8)It is connected with tank.
CN201720453427.6U 2017-04-27 2017-04-27 A kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device Active CN206706903U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720453427.6U CN206706903U (en) 2017-04-27 2017-04-27 A kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720453427.6U CN206706903U (en) 2017-04-27 2017-04-27 A kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device

Publications (1)

Publication Number Publication Date
CN206706903U true CN206706903U (en) 2017-12-05

Family

ID=60459356

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720453427.6U Active CN206706903U (en) 2017-04-27 2017-04-27 A kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device

Country Status (1)

Country Link
CN (1) CN206706903U (en)

Similar Documents

Publication Publication Date Title
CN206752426U (en) A kind of Novel flush storage station water system
CN202329389U (en) Solid-liquid separation device used for circulating fluidized bed heat exchanger
CN105298510A (en) Pipe replacing and slurry discharging device for slurry shield and slurry discharging mode
CN205135644U (en) Slurry shield tube replacement arranges thick liquid device
CN206706903U (en) A kind of ring water for being easy to head-tank downstream pipe to overhaul keeps in guiding device
CN207048738U (en) A kind of ground coal bed gas well mining device
CN201368610Y (en) Siphon-type emptying device for water-supply pipeline and drainage pipeline of solar water heater
CN202195608U (en) Solar pipeline evacuation anti-freezing device
CN107939592A (en) New energy hydroelectric generation tower
CN109422230A (en) A kind of filling pipeline of alcohol-based fuel
CN209162937U (en) A kind of reservoir multipurpose supplies water and water draw-off
CN207622272U (en) A kind of gas heater drainage antifreezing device
CN209685716U (en) The simple collection and purification storing and conveying device of biogas
CN208633131U (en) Building foundation pit precipitation recycling device
CN202355882U (en) Improved structure for by-pass filtration device of circulating water
CN208295553U (en) A kind of single pump hydraulic pressure pipe-line transportation system with a variety of transport models
CN201155490Y (en) High pressure gas flushing pump tube device
CN205841126U (en) A kind of mountain area energy-conservation gravitation water-feeding system
CN205516653U (en) Steam and water separator
CN213728371U (en) Garbage can cleaning station
CN214574540U (en) Sewage lifting device
CN203348698U (en) Built-in float ball valve
CN202047441U (en) Full-automatic water storage device
CN203113495U (en) Drainage device used for oxygen steaming tank
CN207209946U (en) A kind of filling pipeline of alcohol-based fuel