CN206681484U - A kind of fast assembling temporary construction fence - Google Patents

A kind of fast assembling temporary construction fence Download PDF

Info

Publication number
CN206681484U
CN206681484U CN201720442282.XU CN201720442282U CN206681484U CN 206681484 U CN206681484 U CN 206681484U CN 201720442282 U CN201720442282 U CN 201720442282U CN 206681484 U CN206681484 U CN 206681484U
Authority
CN
China
Prior art keywords
support frame
frame
push rod
connection frame
connecting rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720442282.XU
Other languages
Chinese (zh)
Inventor
梅理
付明明
张健
刘亚松
全有维
王鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN201720442282.XU priority Critical patent/CN206681484U/en
Application granted granted Critical
Publication of CN206681484U publication Critical patent/CN206681484U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Fencing (AREA)

Abstract

The utility model discloses a kind of fast assembling temporary construction fence, it is made up of the connecting rod of at least two groups of support frames and several connection two adjacent groups support frames, support frame as described above includes push rod, is fixed on the supporting leg at the push rod both ends and at least one hollow upper connection frame being rotatably installed on the push rod, the connection frame surrounds it and the tie point of the push rod freely rotates, and adjusts its opening direction;The both ends of the connecting rod respectively penetrate the connection inframe at the top of two adjacent groups support frame, connect two support frames, and two support frames are supportted and stood on the ground.Temporary construction fence structure of the present utility model and making are very simple, it is made up of the support frame and connecting rod of inverted U, assembling is convenient to, fast, when needing to use, by support frame placement spaced apart, again by connecting rod through in the upper connection frame at the top of two support frames, you can complete assembling, realize the functions such as the placing of material region division of job site, warning, easy enclosing.

Description

A kind of fast assembling temporary construction fence
Technical field
A kind of construction instrument is the utility model is related to, specifically a kind of provisional protection of job site, warning, region Dividing tool.
Background technology
In order to avoid the material of construction site, instrument leave about everywhere, it will usually build interim enclosing at the scene, rise To the effect of region division, warning and provisional protection.
Existing temporary construction fence common practice is set up using steel tube fastener, is removed again after use, installation and It is inconvenient to remove, for provisional protection, it is clear that compare waste, add construction cost.
The content of the invention
Goal of the invention:The utility model purpose is in view of the shortcomings of the prior art, there is provided one kind assembling is quick, user Just temporary construction fence.
Technical scheme:Fast assembling temporary construction fence described in the utility model, by least two groups of support frames and several Connect two adjacent groups support frame connecting rod composition, support frame as described above include push rod, be fixed on the push rod both ends supporting leg and At least one hollow upper connection frame being rotatably installed on the push rod, the connection frame surround its connection with the push rod Point freely rotates, and adjusts its opening direction;The both ends of the connecting rod respectively penetrate the connection frame at the top of two adjacent groups support frame It is interior, two support frames are connected, and two support frames are supportted and stood on the ground.
Further preferably technical scheme is the utility model, and a bottom is additionally provided between two supporting legs of support frame as described above Bar, the both ends of the bottom bar are separately fixed at the bottom of two supporting legs, are provided with the bottom bar and the upper company on the push rod The consistent lower connection frame of mount structure is connect, the lower connection frame of two adjacent groups support frame is connected by connecting rod.
Preferably, the quantity of the lower connection frame is consistent with the quantity of the upper connection frame.
Preferably, support frame as described above is more than three groups, and the quantity of the upper connection frame at the top of support frame as described above is two, wherein One connection frame is connected by the support frame of connecting rod and homonymy, another connection support of the frame by another connecting rod and opposite side Frame connects.
Preferably, the bottom of the connection frame is welded with bolt, and the connection frame is rotatably installed in the top by bolt On bar, and pass through nut check.
Beneficial effect:(1)Temporary construction fence structure of the present utility model and making are very simple, by the support frame of inverted U Being formed with connecting rod, assembling is convenient to, fast, when needing to use, by support frame placement spaced apart, then will even Extension bar is through in the upper connection frame at the top of two support frames, you can complete assembling, realize job site placing of material region division, The functions such as warning, easy enclosing;For the ease of the assembling of multigroup support frame, connection frame is rotatably installed on push rod, can be free Regulation angle, by opening towards another group of support frame direction;
(2)Support frame is also provided with bottom bar in the utility model, is provided with bottom bar identical with upper connection mount structure, quantity Lower connection frame, connected again by connecting rod between the lower connection frame of the support frame of adjacent sets, so both can guarantee that support frame Between connection and stand steadiness, and can enhancing protection effect;
(3)Support frame can be more than three groups in the utility model, can freely increase and decrease support frame according to being actually needed Quantity, the enclosing of arbitrary shape is assembled into, built flexible, conveniently.
Brief description of the drawings
Fig. 1 is the structural representation of support frame described in the utility model embodiment;
Fig. 2 is the structural representation of temporary construction fence described in the utility model embodiment;
In figure, 1- push rods, 2- supporting legs, 3- bottom bars, 4- connections frame, 5- connecting rods.
Embodiment
Technical solutions of the utility model are described in detail below by accompanying drawing, but the scope of protection of the utility model It is not limited to the embodiment.
Embodiment:A kind of fast assembling temporary construction fence, by four groups of support frames and several connection two adjacent groups supports The connecting rod 5 of frame forms.
Support frame as described above includes push rod 1, the supporting leg 2 for being fixed on the both ends of push rod 1, the bottom between two supporting legs 2 Bar 3.
Two hollow connection frames 4 are respectively arranged with push rod and bottom bar, the bottom of the connection frame 4 is welded with spiral shell Bolt, the connection frame 4 be rotatably installed on the push rod 1 or bottom bar 3 by bolt, around it with the push rod 1 or bottom bar 3 Tie point freely rotates, and adjusts its opening direction, and pass through nut check.
The upper and lower two connections frame 4 of the homonymy of every group of support frame passes through connecting rod 5 corresponding with adjacent side stand component two respectively Connection frame 4 is connected, and two connection frames 4 of opposite side are connect by the two connections frame 4 corresponding with another adjacent supports frame of connecting rod 5.
As described above, although the utility model has been represented and described with reference to specific preferred embodiment, but it must not It is construed to the limitation to the utility model itself.In the spirit and scope of the present utility model for not departing from appended claims and defining Under the premise of, can various changes can be made in the form and details to it.

Claims (5)

1. a kind of fast assembling temporary construction fence, it is characterised in that by least two groups of support frames and several connections adjacent two The connecting rod composition of group support frame, support frame as described above include push rod, are fixed on the supporting leg at the push rod both ends and are rotatably installed in At least one hollow upper connection frame on the push rod, the connection frame surrounds it and the tie point of the push rod freely turns It is dynamic, adjust its opening direction;The both ends of the connecting rod respectively penetrate the connection inframe at the top of two adjacent groups support frame, connection two Support frame, and two support frames are supportted and stood on the ground.
2. fast assembling temporary construction fence according to claim 1, it is characterised in that two supporting legs of support frame as described above it Between be additionally provided with a bottom bar, the both ends of the bottom bar are separately fixed at the bottom of two supporting legs, are provided with the bottom bar and institute The lower connection frame of upper connection mount structure unanimously on push rod is stated, the lower connection frame of two adjacent groups support frame is connected by connecting rod.
3. fast assembling temporary construction fence according to claim 2, it is characterised in that the quantity of the lower connection frame and institute The quantity for stating connection frame is consistent.
4. the fast assembling temporary construction fence according to any one of claim 1 ~ 3, it is characterised in that support frame as described above three More than group, the quantity of the upper connection frame at the top of support frame as described above is two, and one of connection frame passes through connecting rod and homonymy Support frame is connected, and another connection frame is connected by the support frame of another connecting rod and opposite side.
5. the fast assembling temporary construction fence according to any one of claim 1 ~ 3, it is characterised in that the bottom of the connection frame Portion is welded with bolt, and the connection frame is rotatably installed on the push rod by bolt, and passes through nut check.
CN201720442282.XU 2017-04-25 2017-04-25 A kind of fast assembling temporary construction fence Expired - Fee Related CN206681484U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720442282.XU CN206681484U (en) 2017-04-25 2017-04-25 A kind of fast assembling temporary construction fence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720442282.XU CN206681484U (en) 2017-04-25 2017-04-25 A kind of fast assembling temporary construction fence

Publications (1)

Publication Number Publication Date
CN206681484U true CN206681484U (en) 2017-11-28

Family

ID=60403311

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720442282.XU Expired - Fee Related CN206681484U (en) 2017-04-25 2017-04-25 A kind of fast assembling temporary construction fence

Country Status (1)

Country Link
CN (1) CN206681484U (en)

Similar Documents

Publication Publication Date Title
CN208073095U (en) Mobile falling-proof bracket
CN208718393U (en) A kind of building overlapping plate bracing frame
CN205663284U (en) Electric power transportation hydraulic stretching bracing piece
CN201438607U (en) Steel structure bracket of transformation equipment
CN204157372U (en) Bamboo frame wind-resistant device of greenhouse
CN203865934U (en) Temporary suspension device of pulley lifting mechanism for electric pole
CN206681484U (en) A kind of fast assembling temporary construction fence
CN207046733U (en) A kind of post supporting device for cantilever crane
CN205132955U (en) Hoist and mount operation of electric power industry low latitude is with hoist and mount frame
CN207714760U (en) A kind of quick access frame that stability easy to disassemble is strong
CN207749839U (en) A kind of detachable five feet support jig
CN206769453U (en) A kind of Hydraulic and Hydro-Power Engineering turn ladder
CN205164048U (en) Multistage over -and -under type sports dancing barre of doing exercises
CN203748335U (en) Folding grape planting greenhouse
CN206755920U (en) A kind of suspension type sewage cooling tower
CN208731034U (en) A kind of modified sterilizing cabinet frame work
CN208105278U (en) A kind of foundation pit adjustable support frame
CN208718350U (en) Inner guide type elevating scaffold attached wall support base
CN206864969U (en) Full-insulation distribute-electricity transformer operating platform
CN207296333U (en) A kind of scaffold device for building
CN205666020U (en) Environmental protection profiled steel structure swiftly assembles trilateral bill -board of single -upright -column
CN105594513A (en) Steel structure greenhouse
CN204071350U (en) A kind of extension support for mosquito net
CN104905551A (en) Foldable table
CN211047971U (en) Warmhouse booth aluminum alloy support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171128

CF01 Termination of patent right due to non-payment of annual fee