CN206681080U - A kind of secondary recovery water roofing cooling integrated system - Google Patents

A kind of secondary recovery water roofing cooling integrated system Download PDF

Info

Publication number
CN206681080U
CN206681080U CN201720457121.8U CN201720457121U CN206681080U CN 206681080 U CN206681080 U CN 206681080U CN 201720457121 U CN201720457121 U CN 201720457121U CN 206681080 U CN206681080 U CN 206681080U
Authority
CN
China
Prior art keywords
roofing
water
overboard
integrated system
secondary recovery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720457121.8U
Other languages
Chinese (zh)
Inventor
孙宇
郝建敏
杨辰亮
崔加文
王宁
张喆
陈俍甫
左微成
范月林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Engineering Corp Ltd CSCEC
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China State Construction Engineering Corp Ltd CSCEC
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Engineering Corp Ltd CSCEC, China Construction Sixth Engineering Division Co Ltd filed Critical China State Construction Engineering Corp Ltd CSCEC
Priority to CN201720457121.8U priority Critical patent/CN206681080U/en
Application granted granted Critical
Publication of CN206681080U publication Critical patent/CN206681080U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

A kind of secondary recovery water roofing cooling integrated system, the roofing body of circulation loop is formed including being sequentially communicated, overboard gutter, overboard sedimentation basin, Water drainage filter, cistern, total filter, total force (forcing) pump and weep pipe, wherein described roofing body is the low pitched roof in middle high both sides, the overboard gutter is circumferentially correspondingly arranged at immediately below the eaves of roofing body, length direction of the weep pipe along roofing body is correspondingly arranged on the ridge of roofing body, the weep pipe is rubber tube, it is provided with quincunx hole for water spraying along its length thereon, the aperture of the hole for water spraying is 1~2mm.The utility model solves water resource waste caused by roofing temperature-fall period and the susceptible to plugging problem of shower nozzle.

Description

A kind of secondary recovery water roofing cooling integrated system
Technical field
The realm of building construction is the utility model is related to, particularly a kind of secondary recovery water roofing cooling integrated system.
Background technology
With the needs of expanding economy and urban construction, executive information systems are more and more, and foundation depth is often At least extraction heel row, which is carried out, more than five meters, in this depth bounds in the presence of three meters of underground water needs enters municipal pipeline, water resource wave Municipal ductwork pressure increases while expense.Job site living area, Office Area use Double-layered movable board house mostly at present simultaneously, by Excessive in movable plank house cold bridge, heat bridge, seal is bad, and two laminate rooms temperature during summer use is often too high, uses Person is typically cooled using air-conditioning, but air-conditioning power is excessive, wastes electric energy, not energy-conserving and environment-protective significantly.Also there is user sharp Roofing is cooled after connecing municipal water use with the pipeline with shower nozzle, though reducing the waste of electric energy, causes the big of water resource Amount wastes, if being cooled using foundation ditch waste water, because foundation ditch wastewater solids particle is excessive, easily causes shower nozzle blocking.
Utility model content
The purpose of this utility model is to provide a kind of secondary recovery water roofing cooling integrated system, to solve roofing and cool Water resource waste caused by journey and the susceptible to plugging problem of shower nozzle.
To achieve the above object, the utility model adopts the following technical scheme that:A kind of secondary recovery water roofing cooling synthesis System, including it is sequentially communicated the roofing body to form circulation loop, overboard gutter, overboard sedimentation basin, Water drainage filter, water storage Pond, total filter, total force (forcing) pump and weep pipe, wherein the roofing body is the low pitched roof in middle high both sides, it is described overboard Gutter is circumferentially correspondingly arranged at immediately below the eaves of roofing body, and length direction of the weep pipe along roofing body is correspondingly set On the ridge of roofing body, the weep pipe is rubber tube, is provided with quincunx hole for water spraying, the water spray along its length thereon The aperture in hole is 1~2mm.
Preferably, the end port of the weep pipe blocked by pipeline plug, intake port by 90 ° of elbows with hang down The straight water supply riser connection for being located at room side.
Preferably, the water supply riser is lining plastic steel risers, and is 3 with the caliber ratio of weep pipe:1.
Preferably, the overboard gutter is 3% to slope and the gradient is looked for close to overboard sedimentation basin side.
Preferably, the cistern is steel cistern.
Preferably, total force (forcing) pump is provided with temperature detect switch (TDS), and the temperature detect switch (TDS) is with being located at temperature sensor within doors Electrical connection.
Preferably, in addition to cistern the ground base pit dewatering recovery subsystem connected, the ground base pit dewatering return Receive subsystem include be sequentially communicated by pipeline base pit dewatering gutter, catch pit, base pit dewatering sedimentation basin, base pit dewatering mistake Filter and base pit dewatering force (forcing) pump.
Preferably, it is 3% that slope and the gradient are looked in the base pit dewatering gutter to catch pit.
Preferably, the catch pit also connects with remote recycle-water transfer tube, and the remote recycle-water transfer tube buries It is located in the ground, it is PE bellowss and looks for slope, the gradient 3% to catch pit.
Preferably, the caliber of the remote recycle-water transfer tube is 250~350mm.
Preferably, the overboard sedimentation basin and base pit dewatering sedimentation basin are three-level sedimentation basin and by steel material system Into.
Preferably, the cistern also connects with dust falling system, flushing system and vehicle washing system respectively.
The utility model has the characteristics that and beneficial effect compared with prior art:By the roofing of recovery it is overboard, Face rainwater and base pit dewatering provide water source for the roofing cooling of job site movable plank house so that water used in roofing cooling is two Secondary recycle-water, air conditioning electricity consumption is reduced while saving water resource;Simultaneously roofing is overboard, ground rainwater and base pit dewatering recovery System in set Multi-channel filtering device, it is ensured that storage water it is clean, effectively solve recycle-water solid particle excessively block weep pipe spray The problem in water hole;Movable plank house roofing temperature is effectively reduced by the method for the water drenching on roofing, so as to reduce inner temperature of room, drop Low air conditioning energy consumption;Using compared with air-conditioning temperature-reducing, every movable plank house can save power consumption twice with single, due to job site and Office Area is commonly equipped with air-conditioning quantity more than 200, monthly nearly ten thousand yuan of escapable cost;Roofing is overboard in movable plank house simultaneously Both sides form cascade, reduce movable plank house both sides temperature, so as to further reduce temperature in room, while can be effectively to board house Surrounding carries out depositing dust;The cistern is also respectively with dust falling system, flushing system and facing and building cooling system and connect, multi-purpose water, Saving water resource.
The utility model can be widely applied in roof cooling system.
Brief description of the drawings
The utility model is described in more detail below in conjunction with the accompanying drawings.
Fig. 1 is system diagram of the present utility model.
Fig. 2 is plan of the present utility model.
Reference:1- roofings body, the overboard gutters of 2-, the overboard sedimentation basins of 3-, 4- Water drainage filters,
5- cisterns, 6- total filters, the total force (forcing) pumps of 7-, 8- weep pipes, 9- water supply risers, 10- base pit dewaterings Gutter, 11- catch pits, 12- base pit dewaterings sedimentation basin, 13- base pit dewaterings filter, 14- base pit dewaterings force (forcing) pump, 15- dust falling systems, 16- flushing systems, 17- vehicle washing systems, 18- temperature detect switch (TDS)s, 19- temperature sensors.
Embodiment
Embodiment is shown in Figure 1, a kind of secondary recovery water roofing cooling integrated system, is mainly used in construction site activity The roofing cooling of board house, including be sequentially communicated the roofing body 1 to form circulation loop, overboard gutter 2, overboard sedimentation basin 3, fall Water filter 4, cistern 5, total filter 6, total force (forcing) pump 7 and weep pipe 8, wherein the roofing body 1 is middle high both sides Low pitched roof, the overboard gutter 2 are circumferentially correspondingly arranged at immediately below the eaves of roofing body 1, overboard 2 gutter Brick or concreting, width 200mm, depth 30mm can be used, length direction of the weep pipe 8 along roofing body corresponds to It is located on the ridge of roofing body 1, the weep pipe 8 is diameter 30mm rubber tube, is provided with along its length thereon quincunx Hole for water spraying, the aperture of the hole for water spraying is 1~2mm;The end port of the weep pipe 8 is blocked by pipeline plug, described Pipeline plug is pvc pipe road plug, and water inlet port is connected by 90 ° of elbows with the vertical water supply riser 9 for being located at room side;It is described to give Water standpipe 9 is DN40mm lining plastic steel risers, section's recycling, and is 3 with the caliber ratio of weep pipe 8:1.The overboard row Ditch 2 is 3% to slope and the gradient is looked for close to the overboard side of sedimentation basin 3;The cistern 5 is welded using 5mm steel plates, can Recycling;Total force (forcing) pump is provided with temperature detect switch (TDS) 18, and the temperature detect switch (TDS) and the temperature sensor 19 being located within doors are electric Connection;Also include the ground base pit dewatering recovery subsystem connected with cistern 5, the ground base pit dewatering reclaims subsystem bag Include the base pit dewatering gutter 10 being sequentially communicated by pipeline, catch pit 11, base pit dewatering sedimentation basin 12, base pit dewatering filter 13 and base pit dewatering force (forcing) pump 14;It is 3% that slope and the gradient are looked in the base pit dewatering gutter 10 to catch pit 11;The catch pit 11 also connect with remote recycle-water transfer tube, and the remote recycle-water transfer tube is embedded in underground, its be PE bellowss and Slope, the gradient 3% are looked for catch pit;The caliber of the remote recycle-water transfer tube is 300mm;The overboard sedimentation basin 3 and base Hole precipitation sedimentation basin 12 is three-level sedimentation basin, is welded using 5mm steel plates, is repeated and is utilized;The cistern also divides Do not connected with dust falling system 15, flushing system 16 and vehicle washing system 17;Total force (forcing) pump and base pit dewatering force (forcing) pump are to raise 10 meters of pumps of journey;The total filter, Water drainage filter, base pit dewatering filter are y-type filter, size and the pipeline being connected Diameter is consistent;Catch pit quantity, each three-level sedimentation basin quantity are set according to foundation ditch size and base pit dewatering amount during Specific construction, stored Pool size and quantity.
The course of work of the present utility model:Referring to shown in Fig. 1 and Fig. 2, in use, first ground rainwater or base pit dewatering are drawn Enter in base pit dewatering gutter(According to the concrete condition of job site, can also be introduced into dewatering well), by base pit dewatering gutter Reclaimed water is converged into catch pit, then is conducted into base pit dewatering three-level sedimentation basin, after being precipitated by base pit dewatering three-level sedimentation basin It is delivered in cistern and stores, base pit dewatering filter is set up on its transfer pipeline, with solid particle in this filter water, most Recovered water pump is delivered on the weep pipe of roofing by total force (forcing) pump afterwards, roofing cooling is played in the trickling of weep pipe reclaimed water on roofing Effect, water are dropped in around board house in overboard gutter by roofing, form the overall Water Sproading circulatory system.Ensure roofing temperature While reduction, the water is repeatable to be utilized, and can effectively solve water after overboard, ground rainwater and base pit dewatering recovery problem, recovery Middle solid particle excessively blocks hole for water spraying or shower nozzle problem and movable plank house top layer cooling problem.

Claims (10)

  1. The integrated system 1. a kind of secondary recovery water roofing cools, it is characterised in that:The room of circulation loop is formed including being sequentially communicated Face body(1), overboard gutter(2), overboard sedimentation basin(3), Water drainage filter(4), cistern(5), total filter(6), it is total Force (forcing) pump(7)And weep pipe(8), wherein the roofing body(1)It is the low pitched roof in middle high both sides, the overboard gutter (2)Circumferentially it is correspondingly arranged at roofing body(1)Eaves immediately below, the weep pipe(8)Along the length direction pair of roofing body Roofing body should be located at(1)Ridge on, the weep pipe(8)For rubber tube, quincunx water spray is provided with along its length thereon Hole, the aperture of the hole for water spraying is 1~2mm.
  2. The integrated system 2. secondary recovery water roofing according to claim 1 cools, it is characterised in that:The weep pipe(8) End port blocked by pipeline plug, the port that intakes passes through 90 ° of elbows and the vertical water supply riser for being located at room side(9)Even It is logical.
  3. The integrated system 3. secondary recovery water roofing according to claim 2 cools, it is characterised in that:The water supply riser (9)It is lining plastic steel risers, and and weep pipe(8)Caliber ratio be 3:1.
  4. The integrated system 4. secondary recovery water roofing according to claim 3 cools, it is characterised in that:The overboard gutter (2)To close to overboard sedimentation basin(3)It is 3% that slope and the gradient are looked in side.
  5. 5. the secondary recovery water roofing cooling integrated system according to claim any one of 1-4, it is characterised in that:It is described total Force (forcing) pump(7)It is provided with temperature detect switch (TDS)(18), the temperature detect switch (TDS)(18)With being located at temperature sensor within doors(19)Electrical connection.
  6. The integrated system 6. secondary recovery water roofing according to claim 1 cools, it is characterised in that:Also include and cistern (5)The ground base pit dewatering recovery subsystem of connection, the ground base pit dewatering recovery subsystem include successively connecting by pipeline Logical base pit dewatering gutter(10), catch pit(11), base pit dewatering sedimentation basin(12), base pit dewatering filter(13)And foundation ditch Precipitation force (forcing) pump(14).
  7. The integrated system 7. secondary recovery water roofing according to claim 6 cools, it is characterised in that:The base pit dewatering row Ditch(10)To catch pit(11)It is 3% to look for slope and the gradient.
  8. The integrated system 8. secondary recovery water roofing according to claim 7 cools, it is characterised in that:The catch pit(11) Also with remote recycle-water transfer tube(21)Connection, the remote recycle-water transfer tube(21)Underground is embedded in, it is PE ripples Line pipe and look for slope, the gradient 3% to catch pit.
  9. The integrated system 9. secondary recovery water roofing according to claim 6 cools, it is characterised in that:The overboard sedimentation basin (3)With base pit dewatering sedimentation basin(12)It is three-level sedimentation basin and is made by steel material.
  10. The integrated system 10. secondary recovery water roofing according to claim 1 cools, it is characterised in that:The cistern(5) Also respectively with dust falling system(15), flushing system(16)And vehicle washing system(17)Connection.
CN201720457121.8U 2017-04-27 2017-04-27 A kind of secondary recovery water roofing cooling integrated system Expired - Fee Related CN206681080U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720457121.8U CN206681080U (en) 2017-04-27 2017-04-27 A kind of secondary recovery water roofing cooling integrated system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720457121.8U CN206681080U (en) 2017-04-27 2017-04-27 A kind of secondary recovery water roofing cooling integrated system

Publications (1)

Publication Number Publication Date
CN206681080U true CN206681080U (en) 2017-11-28

Family

ID=60406034

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720457121.8U Expired - Fee Related CN206681080U (en) 2017-04-27 2017-04-27 A kind of secondary recovery water roofing cooling integrated system

Country Status (1)

Country Link
CN (1) CN206681080U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797715A (en) * 2017-04-27 2018-11-13 中建城市建设发展有限公司 A kind of secondary recovery water roofing cooling integrated system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797715A (en) * 2017-04-27 2018-11-13 中建城市建设发展有限公司 A kind of secondary recovery water roofing cooling integrated system

Similar Documents

Publication Publication Date Title
CN101975087B (en) Mine water overall treatment utilizing technology
CN107816082A (en) A kind of sponge roof rainwater collection reutilization system
CN201459905U (en) Urban rainwater drainage system
CN105926676A (en) Comprehensive pipe rack system with sponge urban function
CN201972229U (en) Residential rainwater comprehensive utilization system device
CN206681080U (en) A kind of secondary recovery water roofing cooling integrated system
CN203741704U (en) Rainwater collecting and recycling system for overpass
CN105735406A (en) Public building roof rainwater utilization, collection and storage device
CN209741602U (en) Drainage system for ground
CN206368389U (en) One kind backwash and sewage sucking system
CN204787025U (en) Indoor ventilation system
CN206971571U (en) Bluish-green roof structure applied to sponge urban construction
CN108797715A (en) A kind of secondary recovery water roofing cooling integrated system
CN215594290U (en) Novel zero-power-consumption lawn water storage device for sponge city
CN110410131A (en) A kind of underground thermal pollution to administer and utilization system
CN203795512U (en) Rainwater recycling device
CN209227739U (en) A kind of ground water permeable device based on sponge urban construction
CN209837151U (en) Sewage well rainwater collection device
CN102155036A (en) Engineering rainfall or rainwater recycling system
CN209763366U (en) Wet curtain cooling system based on rainwater is collected
CN209011198U (en) A kind of situ of drilling well rainwater-collecting spraying fire-extinguishing system
CN206457774U (en) Road ice melting snow melting device
CN110260559A (en) The water resource heat pump ecological recycle system of underground containment structures is constructed using excavated-in t4 area
CN205742466U (en) Prestressing force is to adding series rain dirt shunting underground pipe gallery
CN205530448U (en) Rainwater device is collected to overhead road surface inlet for stom water

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171128