CN206668279U CN201621158242.4U CN201621158242U CN206668279U CN 206668279 U CN206668279 U CN 206668279U CN 201621158242 U CN201621158242 U CN 201621158242U CN 206668279 U CN206668279 U CN 206668279U
Authority
CN
China
Prior art keywords
support frame
tunnel
curved
sheet devices
glass mat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621158242.4U
Other languages
Chinese (zh)
Inventor
丁智
张霄
吴云双
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201621158242.4U priority Critical patent/CN206668279U/en
Application granted granted Critical
Publication of CN206668279U publication Critical patent/CN206668279U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses one kind to reinforce existing operation tactics glass fibre section of jurisdiction, that is, is used for the fiberglass pipe sheet devices for reinforcing existing operation tactics.A kind of fiberglass pipe sheet devices for reinforcing existing operation tactics, including the glass fibre pipe ring for being reinforced to tunnel ring and for longitudinally fixed longitudinally connected plate;The glass fibre pipe ring includes supporting the along the circumferential direction assembled support frame of glass mat and 2 support frame fixed seats for being respectively supported at bottom at left and right sides of support frame as described above by multiple arcs;Multiple arcs support glass mat and two support frame fixed seats to be laid on the same cross section in tunnel, connect as one reinforcing glass fibre pipe ring.It is of the present utility model it is a kind of reinforce existing operation tactics fiberglass pipe sheet devices method and step is simple, reasonable in design and construction transport is simple and convenient, input cost is relatively low, and Practical Project operation implementation is strong;Practical value is high and using effect is good.

Description

For reinforcing the fiberglass pipe sheet devices of existing operation tactics
Technical field
The utility model belongs to existing operated subway reinforcement technique field, and existing operated subway is reinforced more particularly, to one kind Tunnel glass fibre section of jurisdiction, that is, it is used for the fiberglass pipe sheet devices for reinforcing existing operation tactics.
Background technology
In recent years, as the development of China's urbanization, construction of subway engineering are carried out in high gear in each big city.Mesh Before, the existing 19 city underground engineerings in China are being built, and about 13 city underground engineerings are planned.However, due to structure master There is the reasons such as space, differential settlement in stress and secondary stress, deformation, lining cutting back and the soil body, significant proportion was both The problem of excessive is deformed with the presence of operation shield tunnel liner.Way station-Huai-Hai area of way station is revived with Shanghai Rail Transit Line No.8 line Between tunneling shield driving to the influence of established tunnel exemplified by, because two tunnels are closely constructed, shield driving makes built tunnel Road deforms, and established tunnel section interface also generates different degrees of deformation.Established tunnel in shield driving coverage Different degrees of opening substantially occurred for flexible interface, and open width maximum reaches 3mm.Built tunnel in the range of shield driving Road rigid interface totally 190, wherein 16 there occurs local opening, at tunnel both ends close to active well position and maximum vertical Respectively there is the tube coupling concrete fragmentation near one of rigid interface damaged at deformation.
Because the lining cutting conference that deformed destroys the attractive in appearance of structure, cause to bind block and adjacent block disengages, joint opens Measure the disease of a variety of durability deficiencies such as excessive, circumferential weld faulting of slab ends, duct piece connector damage, lining cutting steel bar corrosion and structural concrete corrosion Evil occurs, and then destroys the integrality of structure and reduce their durability, so as to which the situation of percolating water in tunnel increases, influences The safety and service life of shield tunnel.If handled not in time lining damages, destruction can be further increased, even Tunnel cave, life threatening and property safety can be caused.
Therefore, in order to control the development that subway tunnel deforms, reinforced mostly using steel pipe sheet at present in engineering, grouting and reinforcing The method being combined is reinforced with aramid fabric.But steel pipe sheet reinforces transport and construction expends a large amount of human resources, long construction period, adds Gu cost is high, it has not been convenient to construct, this body structure of tunnel and shape are had a great influence, and steel pipe sheet anti-corrosive properties are poor, it is fragile.And Due to the characteristics of adding soil layer low-intensity, high-compressibility, high sensitivity and rheological characteristic in soft clay area, grouting and reinforcing construction is not easily-controllable , usually there is running pulp, spillage and situation about starching partially in system, and additional harmful effect is caused to tunnel structure, exacerbates lining cutting disease on the contrary Harmful generation.In order to control the development of tunnel deformation, aramid fabric has been introduced into tunnel reinforcement engineering field, good so as to serve Limitation tunnel deformation development, the maintenance tunnel water proofing impact of performance.
Now, appearing on the market with various good fiber quality materials, glass fiber material is as a kind of the inorganic non-of excellent performance Metal material, gradually praised highly in concrete strengthening engineering.Glass fiber material is a kind of excellent performance without metal material Material, species is various, and advantage is good insulating, heat resistance is strong, corrosion resistance is strong, high mechanical strength, sound absorption properties good, and it is with glass Ball or discarded glass are raw material through high temperature melting, wire drawing, doff, and the technique such as weave cotton cloth is made, per bundle fiber precursor all by Hundreds of even thousand monofilament compositions, there is extensive development prospect.
The content of the invention
Technical problem to be solved in the utility model is in view of the shortcomings of the prior art, there is provided one kind is used to reinforce both There are the fiberglass pipe sheet devices of operation tactics, reasonable in design and easy construction, construction effect are good, can be to lining cutting disease Evil control effectively, and the cycle is short and cost is low.
A kind of fiberglass pipe sheet devices for reinforcing existing operation tactics, including the glass for being reinforced to tunnel ring Glass fiber pipe ring and for longitudinally fixed longitudinally connected plate;The glass fibre pipe ring includes supporting glass fibers by multiple arcs The along the circumferential direction assembled support frame of dimension plate and 2 support frames for being respectively supported at bottom at left and right sides of support frame as described above are consolidated Reservation;Multiple arcs support glass mat and two support frame fixed seats to be laid on the same cross section in tunnel, make Glass fibre pipe ring is reinforced to connect as one.
Preferably, curved support glass mat is made up of the curved panel and arc gusset being fixedly connected, two neighboring It is fastenedly connected by multiple connecting bolts on arc gusset between curved support glass mat, is provided with curved panel Multiple crab-bolt mounting holes, curved panel are fixed on the section of jurisdiction ring in tunnel by crab-bolt through crab-bolt mounting hole.
Preferably, support frame as described above fixed seat is made up of horizontal panel and arc gusset, horizontal panel and arc gusset profit Each fiberglass sheet material is bonded into assembled shaping with epoxy resin, between curved support glass mat and support frame fixed seat It is fastenedly connected by multiple connecting bolts on arc gusset, 2 support frame fixed seats pass through anchor bolt on horizontal panel It is respectively supported at top at left and right sides of tunnel inverted arch.
Preferably, the longitudinally connected plate is made up of curved panel and longitudinal arc gusset, two neighboring fiberglass pipe It is fastenedly connected between ring by multiple connecting bolts on the arc gusset of multiple tracks longitudinal direction.
Preferably, each glass fibre pipe ring includes 1 small curved support glass mat, 4 big curved support glass Fiberboard and 2 support frame fixed seats.
Preferably, each curved support glass mat includes 1 piece of curved panel and 4 pieces of arc gussets;Each support frame Fixed seat includes 1 piece of horizontal panel and 3 pieces of arc gussets.
Preferably, each longitudinally connected plate includes 1 piece of curved panel and 2 pieces of arc gussets.
Preferably, curved support glass mat is on two side walls of the vault of section and left and right are reinforced.
Preferably, curved support glass mat and two support frame as described above fixed seats are laid in existing operated subway tunnel On the same tunnel cross section in road.
Preferably, curved support glass mat and two support frame as described above fixed seats avoid tunnel circumferential weld laying.
Technical scheme is used by the utility model solves its technical problem:
The utility model discloses a kind of glass fibre material section of jurisdiction, its main component is silica, aluminum oxide, oxidation Calcium, boron oxide, magnesia, sodium oxide molybdena etc..Glass fibre selected by the present invention for alkali-free glass fibre (sodium oxide molybdena 0%~ 2%, belong to aluminium borosilicate glass), with quartz sand, aluminum oxide and pyrophyllite, lime stone, dolomite, boric acid, soda ash, saltcake, firefly Stone etc. is that raw material is manufactured into through high temperature melting, wire drawing, doff, the technique such as weave cotton cloth.Glass fibre section of jurisdiction is made first by tank furnace The raw materials such as pyrophillite are just melting into glass solution by fiber elongation method in kiln, exclude to be transported to porous bushing through path after bubble, High speed pulling is proof strength, control filament diameter is between 10-20um into glass precursor.Because fiberglass pipe piece section is big, Toughness and ductility require high, and glass fibre is made from stretching property by force is good, polypropylene fibre with corrosion resistance is combined with glass fibre Sheet material.By glass fibre and polypropylene fibre mixed cotton 1:1.5 shreddings, carding machine are combed, lapping machine lapping, acupuncture unit acupuncture, Semi-finished product felt is wound, and flat-bed press is compressing, cuts into corresponding size.Corresponding arc is rolled into using numerical control plate bending roll, and Add epoxy resin and each piece of fiberglass sheet material is bonded into assembled shaping, as glass fibre section of jurisdiction.Such glass fibre section of jurisdiction With good insulating, heat resistance is strong, corrosion resistance is good, high mechanical strength, and simple production process is convenient, the high spy of production efficiency Point.
Existing operation tunnel is reinforced is spelled using the curved panel, arc gusset and support frame fixed seat that are made by glass fibre The glass fibre pipe ring of composition is filled, ring reinforcing is carried out to existing operation tunnel section of jurisdiction, and it is whole by longitudinally connected hardened synthesis Body carries out the reinforcing of longitudinal direction to tunnel duct piece.
The glass fibre pipe ring is along the circumferential direction spelled including multiple different size of curved support glass mats Fill the support frame formed and 2 support frame fixed seats for being respectively supported at bottom at left and right sides of support frame as described above.Two branch Support fixed seat is respectively supported at top, multiple curved support glass mats at left and right sides of the inverted arch of existing operation tunnel It is laid on the same tunnel cross section of existing operation tunnel with two support frame as described above fixed seats, makes reinforcing glass fibre Pipe ring connects as one, to reach ring entirety stress.
The concrete platform mated formation for rail is provided with the inverted arch of the existing operation tunnel, the concrete platform A gutter is respectively arranged with left and right sides of top.
Support frame as described above fixed seat is made up of horizontal panel and arc gusset, and two support frame as described above fixed seats pass through level Anchor bolt is respectively supported on two tunnel bottom railway roadbeds (in gutter) on panel, multiple curved support glass The width of glass fiberboard is 500mm.
The curved support glass mat is made up of the curved panel and the arc gusset, the two neighboring arc Pass through arched ribs between shape support glass mat and between the curved support glass mat and support frame fixed seat Multiple connecting bolts are fastenedly connected on plate, and each curved support glass mat passes through multiple anchors on curved panel Bolt is fixed on the section of jurisdiction ring in existing operation tunnel, is provided with the curved panel of each curved support glass mat Multiple crab-bolt mounting holes for crab-bolt installation.
The left and right sides arc gusset of each curved support glass mat is provided with multiple supplies the connection respectively The longitudinal bolt mounting hole of bolt installation, ring both sides are provided with multiple respectively for the ring bolt peace of connecting bolt installation Fill hole;The outer arcuate gusset of support frame as described above fixed seat is provided with multiple ring bolts for connecting bolt installation and installed Hole.
The longitudinally connected plate is made up of the curved panel and the arc gusset, the two neighboring fiberglass pipe It is fastenedly connected between ring by multiple connecting bolts on the longitudinally connected plate arc gusset of multiple tracks, the longitudinally connected plate is only set Longitudinal arc gusset, the arc gusset are provided with multiple respectively for the longitudinal bolt mounting hole of connecting bolt installation, institute The width for stating longitudinally connected plate is 500mm.
Technical concept of the present utility model is:
Step 1: utilize the prefabricated reinforced required component of glass fiber material.Each glass fibre pipe ring includes 1 small arc Support glass mat, 4 big curved support glass mat and 2 support frame fixed seats;Each curved support glass fibre Plate includes 1 piece of curved panel and 4 pieces of arc gussets;Each support frame includes 1 piece of horizontal panel and 3 pieces of arc gussets.It is each vertical Include 1 piece of curved panel and 2 pieces of arc gussets to connecting plate.Each arc gusset is provided with multiple supplies the connection respectively The bolt mounting holes of bolt installation, multiple crab-bolts for crab-bolt installation are each provided with the arc or horizontal panel and are pacified Fill hole.
Step 2: section of jurisdiction ring is reinforced.Different reinforcing positions is used according to the form of tunnel duct piece straight joint or the fissure of displacement Carry out that curved support glass mat and support frame fixed seat are installed, installed in section of jurisdiction intrados (avoiding circumferential weld), prevent section of jurisdiction Differential settlement breaks segment bolt.Small curved support glass mat binds block opening position installed in lining cutting, remaining 4 big The mode that curved support glass mat pushes the wrong open loop seam is installed, with lining cutting adjacent block and calibrated bolck position consistency.5 arc branch The arc gusset supportted between glass mat ring is assembled using the connection of galvanizing M18x8.8 grade bolts, from straight on curved panel Footpath 18mm setscrew is fixed with section of jurisdiction.
Also connected between two support frame fixed seats and curved support glass mat using 3 M18x8.8 grade bolts, again (in ditch) is fixed on tunnel bottom railway roadbed using 4 crab-bolts, connects as one reinforcing ring.
Step 3: section of jurisdiction longitudinal reinforcement:According to the installation situation of tunnel gut line, using corresponding 5 blocks of curved support glass The longitudinally connected plate drawknot of 5 glass fibres (avoiding tunnel gut line) of fiberboard middle position, the longitudinally connected plate ring of multiple tracks It is fastenedly connected using multiple connecting bolts on arc gusset with curved support glass mat, longitudinally connected plate curved panel Bonded between lining cutting using brushing epoxy resin before installation, reinforce ring and form entirety with longitudinal reinforcement, may be such that The section of jurisdiction for occurring settling larger position is deposited in energy uniform settlement under the drawknot of adjacent section of jurisdiction, to reduce tunnel duct piece appearance Deform risk that is larger and destroying.
The beneficial effects of the utility model are mainly manifested in:(1), method and step is simple, reasonable in design and construction transport is simple Just, input cost is relatively low for folk prescription, and Practical Project operation implementation is strong;(2), practice of construction process is mainly existing operation tunnel glass Glass fiber pipe ring is reinforced, and the non-deformability in tunnel can be improved by this method, reduces the generation of tunnel internal lining damages, So as to reduce the possibility that accident occurs for tunnel, traffic safety and tunnel service life ensure that;(3), practical value is high and makes It is good with effect, the construction method with stratum slip casting pre-reinforcement is reinforced compared to existing existing operation tunnel steel loop, shortens construction work It is phase, larger to reduce construction cost;(4), glass fibre has good chemical stability, high intensity, high-modulus, in light weight, size Stability is good, polarization is good, fire prevention, insulation the advantages that, the pipe ring reinforcement block being fabricated to is few, transport easy for construction, safety coefficient Height, effectiveness are good, and life of product is long and the operation of subway train will not be impacted;(5) it is, widely applicable, can effectively it fit Tunnel-liner in lining damages danger stratum easily occurs for all existing operation shield tunnel particularly rich water soft stratums etc. Protection and reinforcing, ensured the security of tunnel structure.
Brief description of the drawings
Fig. 1 is method flow block diagram of the present utility model.
Fig. 2 is that ring glass fibre pipe ring reinforces state diagram.
Glass fibre connecting plate in longitudinal direction reinforces state diagram when Fig. 3 is straight joint.
Glass fibre connecting plate in longitudinal direction reinforces state diagram when Fig. 4 is the fissure of displacement.
Fig. 5 is small curved support glass fibre plate structure schematic diagram.
Fig. 6 is big curved support glass fibre plate structure schematic diagram.
Fig. 7 is support frame fixed seat structure schematic diagram.
Fig. 8 is the longitudinally connected plate structure schematic diagram of glass fibre.
Description of reference numerals
1-existing operation tunnel;2-section of jurisdiction;3-rail;4-concrete platform;5-gutter;6-1 --- arcwall face Plate;6-2-ring arc gusset;6-3-longitudinal arc gusset;7-1-support frame fixed seat;7-2-horizontal panel;8-vertical To connecting plate;9-1-ring bolt mounting holes;9-2-longitudinal bolt mounting hole;9-3-crab-bolt mounting hole;
Embodiment
The utility model is further described below in conjunction with the accompanying drawings.
A kind of glass fibre section of jurisdiction as shown in Figure 1 reinforces the construction method technological process of existing operation tactics, institute It is existing operation tunnel to state existing operation tunnel.The glass fibre pipe ring includes multiple different size of curved supports The along the circumferential direction assembled support frame of glass mat and 2 branch for being respectively supported at bottom at left and right sides of support frame as described above Support fixed seat 7.Two support frame as described above fixed seats 7 are respectively supported at top at left and right sides of the inverted arch of existing operation tunnel 1, more The individual curved support glass mat and two support frame as described above fixed seats 7 are laid in the same of existing operation tunnel 1 On tunnel cross section, connect as one reinforcing glass fibre pipe ring, to reach ring entirety stress (to avoid existing fortune Tunnel inside lining circumferential weld is sought to carry out for principle), refer to Fig. 2.
The concrete platform 4 mated formation for rail 3 is provided with the inverted arch of the existing operation tunnel 1, the concrete is put down A gutter 5 is respectively arranged with left and right sides of the top of platform 4, two support frame as described above fixed seats 7 are respectively supported at two institutes State in gutter 5.
Multiple glass fibre pipe rings are fastenedly connected by longitudinally connected plate 8 described in multiple tracks and are integrated, and the longitudinal direction connects Longitudinal length of the fishplate bar 8 along tunnel reinforcement section is laid and its length is not less than the length for reinforcing section, is indulged described in multiple tracks Along the circumferential direction lay to connecting plate 8, carried out using avoiding existing operation tunnel gut line as principle from left to right.
, can be according to the concrete engineering fissure of displacement or the needs of straight joint, to the glass fibre pipe ring and longitudinal direction during actual reinforcing The quantity and installation position of connecting plate 8 adjust accordingly, and refer to Fig. 3 and Fig. 4.
Detailed process is as follows:
1) Construction in Preparatory Stage
Structure manufacture needed for the reinforcing of glass fibre pipe ring:With reference to Fig. 5, Fig. 6, Fig. 7 and Fig. 8, the glass fibre pipe ring bag Include 1 small curved support glass mat, 4 big curved support glass mat and 2 support frame fixed seats 8.It is multiple described Curved support glass mat and the width of support frame fixed seat are 500mm, and small curved support glass mat length will be grown It is equal as shown in Figure 2 in the block that binds, the structure snd size all same of remaining multiple big curved support glass mat, length Point.During actual processing, the size of the fiberglass pipe ring element can be adjusted accordingly according to specific needs.
1 curved support glass mat is by by 1 piece of curved panel 6-1,2 pieces of ring arc gusset 6- 2 and 2 pieces of longitudinal arc gusset 6-3 are formed, the setscrew from diameter 18mm and section of jurisdiction 2 on the curved panel 6-1 It is fixed, wherein the small curved support glass mat has 5 crab-bolt mounting hole 9-3, the big curved support glass fibers Dimension plate has 11 crab-bolt mounting hole 9-3;Spelled between the ring arc gusset 6-2 using the connection of galvanizing M18x8.8 grade bolts Dress, side are respectively provided with 3 bolt hole 9-1, and longitudinal small curved support glass mats of arc gusset 6-3 set 3 bolt hole 9- 2, big curved support glass mat sets 5 bolt hole 9-2.
Multiple arcs panel 6-1 and arc gusset 6-2,6-3 thickness are 20mm, and arc gusset 6-2,6-3 is highly equal For 60mm.Support frame as described above is fixed 7 and is made up of horizontal panel 7-2 and ring arc gusset 6-2, two support frame as described above fixed seats 7 are respectively supported at (gutter 5 on two tunnel bottom railway roadbeds by the upper 4 anchor bolt 9-3 of horizontal panel 7-2 It is interior), side ring arc gusset 6-2 sets 3 18mm bolts hole 9-1 and connected with the adjacent curved support glass mat fastening Connect.
The longitudinally connected plate 8 is made up of the curved panel 6-1 and longitudinal arc gusset 6-3, two neighboring institute State and be fastenedly connected by multiple connecting bolts on the longitudinal arc gusset 6-3 of the longitudinally connected plate 8 of multiple tracks between glass fibre pipe ring, The longitudinally connected plate 8 sets longitudinal arc gusset 6-3, longitudinal arc gusset 6-3 to be provided with 3 and supply the company respectively The longitudinal bolt mounting hole 9-2 of connecting bolt installation, the width of the longitudinally connected plate 8 is 500mm, and its length is not less than described The length of section is reinforced, is typically circumferentially 5 longitudinally connected plates 8.The size and installation position of the longitudinally connected plate are referring to figure 3rd, 4 two kinds of lining cutting situations, can also be adjusted according to Practical Project.
The external diameter of component is consistent with the Tunnel internal diameter of existing operation tunnel 1 needed for the glass fibre pipe ring reinforcing.Structure Part shaping after, polished, degreasing, ensure surface it is clean.Reinforcement material need to be easy to scene according to drawing requirement machine-shaping Installation.
Because daily consolidation time is short, strengthening construction is more difficult in tunnel, while need to be before daily reinforce by stage+module Complete, platform removal carried out after the completion of construction, construction platform need to be fabricated to simple, distachable platform during reinforcing, according to Toward construction experience, tunnel inner platform making, dismounting, install convenient and safety are carried out using door-type scaffold for building.
2) the transport of materials stage in tunnel
Start component installment work, first truck is positioned on track and with iron wedge after it can enter running tunnel Son fixes four wheels, prevents slippery;Then porter is by small curved support glass mat, big curved support glass fibers Tie up plate, support frame fixed seat, longitudinally connected plate, expansion bolt, epoxy resin and construction tool, door-type scaffold for building is carried On to truck and fix;Manually material etc. is transported to work zone by push truck again.
3) scaffold erection stage
After reaching construction area, door-type scaffold is unloaded first, and starts scaffold assembly, after the completion of assembled, is fixed Four casters have reinforced diagonal brace simultaneously.
4) construction lofting positioning stage
Referring to Fig. 2, according to construction lofting position before, anchor hole 9-3 is bored on concrete section of jurisdiction 2 according to setting-out.Meanwhile enter The installation of row ring support frame fixed seat 7.Ring support frame fixed seat 7 is fixed in tunnel bottom railway roadbed using 4 crab-bolts On (in ditch 5).
5) erection stage is reinforced
After Positioning arc plate installs, ring reinforcing is carried out first according to the order of circumferencial direction from left to right successively, is installed Intrados (the avoiding circumferential weld as far as possible) in section of jurisdiction, big curved support glass mat is carried out tightly according to hole above and concrete section of jurisdiction 2 Gu confining bolt 9-1 between expansion anchor 9-3, with ring support frame fixed seat 7, small curved support glass fibre is then attached to Plate, then to the big curved support glass mat of opposite side.The first fastening duct piece of all glass mats of installation process is multiple Crab-bolt 9-3, then fasten multiple bolt 9-1 between adjacent curved support glass mat.Finally make section of jurisdiction and fiberglass pipe It is annular cyclic to entirety.Section of jurisdiction ring is reinforced referring to Fig. 2.
According to the installation situation of tunnel gut line, tunnel inner tube (is avoided using the longitudinally connected drawknot of plate 8 of 5 glass fibres Line), 5 longitudinally connected plate rings are using on multiple connecting bolt 9-2 on longitudinal arc gusset 6-3 and curved support glass mat Longitudinal arc gusset 6-3 is fastenedly connected, using brush before installation between longitudinally connected plate curved panel 6-1 and lining segment 2 Epoxy resin is applied to be bonded.Section of jurisdiction longitudinal reinforcement is referring to Fig. 3, Fig. 4
6) scaffold teardown phase
Power supply is closed after installation completion per ring, packs up power line, dismounting scaffold is positioned at service channel, truck Exit and be positioned over ventilating shaft stair side, check construction tool, site clearing, personnel please be put, prepare to withdraw from the arena.
7) site clearing and examination are withdrawn from the arena the stage
After the completion of reinforcing, recover all facilities, check site clearing situation, without leftover problem, truck and gate-type Scaffold is withdrawn from the arena and checked and accepted.

Claims (10)

1. a kind of it is used to reinforcing the fiberglass pipe sheet devices of existing operation tactics, including for being reinforced to tunnel ring Glass fibre pipe ring and for longitudinally fixed longitudinally connected plate;The glass fibre pipe ring includes supporting glass by multiple arcs The along the circumferential direction assembled support frame of fiberboard and 2 support frames for being respectively supported at bottom at left and right sides of support frame as described above Fixed seat;Multiple arcs support glass mat and two support frame fixed seats to be laid on the same cross section in tunnel, Connect as one reinforcing glass fibre pipe ring.
2. fiberglass pipe sheet devices according to claim 1, it is characterised in that:Curved support glass mat is by fixing The curved panel and arc gusset of connection form, by multiple on arc gusset between two neighboring curved support glass mat Connecting bolt is fastenedly connected, and multiple crab-bolt mounting holes are provided with curved panel, and curved panel passes through crab-bolt by crab-bolt Mounting hole is fixed on the section of jurisdiction ring in tunnel.
3. fiberglass pipe sheet devices according to claim 2, it is characterised in that:Support frame as described above fixed seat is by horizontal plane Each fiberglass sheet material is bonded assembled shaping by plate and arc gusset composition, horizontal panel and arc gusset using epoxy resin, It is fastenedly connected between curved support glass mat and support frame fixed seat by multiple connecting bolts on arc gusset, 2 support frame fixed seats are respectively supported at top at left and right sides of tunnel inverted arch by anchor bolt on horizontal panel.
4. fiberglass pipe sheet devices according to claim 1, it is characterised in that:The longitudinally connected plate is by curved panel Form with longitudinal arc gusset, entered between two neighboring glass fibre pipe ring by multiple connecting bolts on the arc gusset of multiple tracks longitudinal direction Row is fastenedly connected.
5. fiberglass pipe sheet devices according to claim 1, it is characterised in that:Each glass fibre pipe ring includes 1 Small curved support glass mat, 4 big curved support glass mat and 2 support frame fixed seats.
6. fiberglass pipe sheet devices according to claim 5, it is characterised in that:Each curved support glass mat bag Include 1 piece of curved panel and 4 pieces of arc gussets;Each support frame fixed seat includes 1 piece of horizontal panel and 3 pieces of arc gussets.
7. fiberglass pipe sheet devices according to claim 1, it is characterised in that:Each longitudinally connected plate includes 1 piece of arc Shape panel and 2 pieces of arc gussets.
8. fiberglass pipe sheet devices according to claim 1, it is characterised in that:Curved support glass mat is being reinforced On two side walls of vault and left and right of section.
9. fiberglass pipe sheet devices according to claim 8, it is characterised in that:Curved support glass mat and two Support frame as described above fixed seat is laid on the same tunnel cross section of existing operation tactics.
10. fiberglass pipe sheet devices according to claim 9, it is characterised in that:Curved support glass mat and two Individual support frame as described above fixed seat is avoided tunnel circumferential weld and laid.
CN201621158242.4U 2016-10-31 2016-10-31 For reinforcing the fiberglass pipe sheet devices of existing operation tactics Expired - Fee Related CN206668279U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621158242.4U CN206668279U (en) 2016-10-31 2016-10-31 For reinforcing the fiberglass pipe sheet devices of existing operation tactics

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621158242.4U CN206668279U (en) 2016-10-31 2016-10-31 For reinforcing the fiberglass pipe sheet devices of existing operation tactics

Publications (1)

Publication Number Publication Date
CN206668279U true CN206668279U (en) 2017-11-24

Family

ID=60356417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621158242.4U Expired - Fee Related CN206668279U (en) 2016-10-31 2016-10-31 For reinforcing the fiberglass pipe sheet devices of existing operation tactics

Country Status (1)

Country Link
CN (1) CN206668279U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106640123A (en) * 2016-10-31 2017-05-10 浙江大学城市学院 Tunnel reinforcing device based on fiberglass pipe segments and construction method thereof
CN109723464A (en) * 2019-03-07 2019-05-07 衡水奇佳工程材料有限公司 A kind of tunnel reinforcement structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106640123A (en) * 2016-10-31 2017-05-10 浙江大学城市学院 Tunnel reinforcing device based on fiberglass pipe segments and construction method thereof
CN109723464A (en) * 2019-03-07 2019-05-07 衡水奇佳工程材料有限公司 A kind of tunnel reinforcement structure
CN109723464B (en) * 2019-03-07 2024-03-26 衡水奇佳工程材料有限公司 Tunnel reinforced structure

Similar Documents

Publication Publication Date Title
CN106640123A (en) Tunnel reinforcing device based on fiberglass pipe segments and construction method thereof
CN109458196B (en) Environment-friendly durable single-layer lining structure suitable for weak surrounding rock tunnel
CN105926669B (en) A kind of Construction Method of Metro Station
CN103375170B (en) Underground excavation construction deformation control method for three-hole small clear distance tunnel underpass trunk railway
CN104612711B (en) Lining segment structure of city subway up-down section overlapping shield tunnels
CN202560245U (en) Multifunctional trolley with freely retractable arms
CN103032073B (en) Urban subway mudstone stratum connected aisle and shield tunneling parallel construction method
CN101864959A (en) Method for tunneling construction of main structure of underground station
CN105134009B (en) Sill coping concrete structure of frame structure infilled wall and construction method
CN111676819A (en) Jacking construction method for combined type temporary beam continuous reinforced line large-span frame structure bridge
CN112324475A (en) Method for reinforcing shield tunnel lining structure
CN108385512A (en) One kind being based on bolted modular assembly formula Hollow High Pier splicing structure and its practice
CN207047613U (en) A kind of railway roadbed changeover portion support meanss and railway roadbed changeover portion support system
CN206668279U (en) For reinforcing the fiberglass pipe sheet devices of existing operation tactics
CN109372543A (en) Mangnolia officinalis competent structure and construction method are owed in a kind of tunnel-liner
CN108086354A (en) Prefabricated assembled comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof
CN108561156A (en) Separate tunnel changes arch supporting construction and its construction method
CN104632247A (en) Tunnel supporting structural part made of carbon fiber composite and installation method thereof
CN108086353A (en) Hollow wall plate mixed prefabricated assembly type comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof
CN109519193A (en) A kind of Existing Railway Line tunnel set lining structure and its construction method
KR100644778B1 (en) A process for Water-Proof Construction
CN206219897U (en) Medium-and low-speed maglev two-wire excavation location pile foundation combined type support rail beam transition section structure
CN107905368B (en) A kind of assembled beam and assembled column connection structure and construction method
CN103321242A (en) Subsection steel-bar-distribution prestressed concrete continuous wall and construction method thereof
CN220621871U (en) Shield tunnel lining reinforcing structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171124